![Page 1: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/1.jpg)
CONSTRUCTION PROGRESS
AS ON 30th APR’18
![Page 2: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/2.jpg)
E - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat
putty work is in progress• Floor Marble laying work is in progress• Main Floor Tiling work is in progress • Toilet Tiling work is in progress• Fire Fighting – Pipe laying & Testing
work is in progress • Water Proofing work is in progress• Plumbing work is in progress
![Page 3: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/3.jpg)
F - BLOCK
STATUS
• 19th floor completed• Internal Painting – Wall & Ceiling painting
work completed• Floor Marble laying completed• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing
work nearing completion• Water Proofing completed• Plumbing work nearing completion• Window fixing work is in progress
![Page 4: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/4.jpg)
F – BLOCK BATHROOM TILING WORK NEARING COMPLETION
![Page 5: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/5.jpg)
F – BLOCK FLOOR TILE WORK NEARING COMPLETION
![Page 6: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/6.jpg)
G - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat
putty and primer work nearingcompletion
• Floor Marble laying work nearing completion
• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing
work nearing completion• Water Proofing work is in progress• Plumbing work nearing completion• Window fixing work is in progress
![Page 7: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/7.jpg)
H - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat Putty &
Primer work nearing completion• Floor Marble laying work nearing
completion• Main Floor Tiling work nearing completion• Toilet Tiling work nearing completion• Fire Fighting – Pipe laying & Testing
work is in progress• Water Proofing work is in progress• Plumbing work is in progress• Window fixing work is in progress
![Page 8: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/8.jpg)
I - BLOCKSTATUS
• 19th floor completed• Internal Painting – Wall & Ceiling painting
work nearing completion• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Windows fixing work completed• Door Frame fixing – Bedroom & Toilet
work completed, Main door frame fixing work nearing completion
• Electrical switch plate fixing workcompleted(Top cover plate fixingwork nearing completion)
• Sanitary fittings work completed• CP fittings work completed
![Page 9: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/9.jpg)
I - BLOCKHALL FRENCH WINDOW LIFT WORK COMPLETED
![Page 10: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/10.jpg)
I - BLOCKELECTRICAL BOARD FIXING
WORK COMPLETEDFIRE FIGHTING FALSE
CEILING WORK COMPLETED
![Page 11: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/11.jpg)
I - BLOCKKITCHEN AREAHALL WINDOW
![Page 12: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/12.jpg)
I – BLOCK BATHROOM FITTINGS WORK COMPLETED
![Page 13: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/13.jpg)
J - BLOCK
STATUS
• 19th floor completed• Internal Painting – Primer work completed,
Wall & Ceiling Painting work is in progress• Floor Marble laying completed • Main floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Window fixing work is in progress• Door Frame Fixing work completed • Electrical switch plate fixing work
completed(Top cover plate fixingwork is in progress)
• Sanitary fittings work nearing completion• CP fittings work is in progress
![Page 14: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/14.jpg)
J - BLOCKFIRE FIGHTING FALSE
CEILING WORK COMPLETED LOBBY AREA
![Page 15: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/15.jpg)
J - BLOCKHALL WASH-BASIN PIPED GAS
![Page 16: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/16.jpg)
J - BLOCKMARBLE LAYING COMPLETEDKITCHEN AREA
![Page 17: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/17.jpg)
J – BLOCK BATHROOM FITTINGS WORK COMPLETED
![Page 18: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/18.jpg)
K - BLOCKSTATUS
• 19th floor completed• Internal Painting – Primer work completed.
Wall & Ceiling Painting work is in progress• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Windows fixing work completed• Door Frame fixing – Bedroom & Toilet
work completed, Main door frame fixing work nearing completion
• Electrical switch plate fixing workcompleted(Except top plate)
• Sanitary fittings work nearing completion• CP fittings work is in progress
![Page 19: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/19.jpg)
K - BLOCKFIRE FIGHTING FALSE
CEILING WORK COMPLETEDLOBBY AREA
![Page 20: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/20.jpg)
K - BLOCKHALL WASH-BASIN PIPED GAS
![Page 21: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/21.jpg)
K - BLOCKMARBLE LAYING COMPLETEDHALL WINDOW
![Page 22: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/22.jpg)
K – BLOCK BATHROOM FITTINGS WORK COMPLETED
![Page 23: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/23.jpg)
L - BLOCK
STATUS
• 19th floor completed• Internal Painting – Wall & Ceiling painting
work nearing completion• Floor Marble laying completed • Main Floor Tiling work completed• Toilet Tiling work completed• Fire Fighting completed• Water Proofing completed• Plumbing completed• Window fixing work completed• Door Frame Fixing work completed• Electrical switch plate fixing work
completed• CP fittings work completed• Sanitary fittings work completed
![Page 24: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/24.jpg)
L - BLOCKFIRE FIGHTING FALSE
CEILING WORK COMPLETED MAIN DOOR
![Page 25: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/25.jpg)
L - BLOCKLIFT LOBBY AREA
![Page 26: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/26.jpg)
L - BLOCK
INTERNAL DOORS
![Page 27: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/27.jpg)
L - BLOCKMARBLE & TILES LAYING WORK COMPLETED
![Page 28: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/28.jpg)
L - BLOCKBATHROOM FITTINGS HALL FRENCH WINDOW
![Page 29: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/29.jpg)
L - BLOCKPIPED GAS HALL WASH-BASIN
![Page 30: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/30.jpg)
L - BLOCK
![Page 31: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/31.jpg)
P - BLOCK
STATUS
• 19th floor completed• Internal Painting – 1st & 2nd coat putty
and primer work is in progress• Floor Marble laying work is in progress • Main Floor Tiling work is in progress• Toilet Tiling work is in progress• Fire Fighting work is in progress • Water Proofing work is in progress• Plumbing work is in progress
![Page 32: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/32.jpg)
PODIUM AREA (J-K-L)
![Page 33: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/33.jpg)
PODIUM WORK IS IN PROGRESS(I-J-L)
![Page 34: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/34.jpg)
L-BLOCK OPEN AREA
![Page 35: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/35.jpg)
SWIMMING POOL
![Page 36: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/36.jpg)
CLUB HOUSE AREA
![Page 37: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/37.jpg)
CLUB HOUSE AREA
![Page 38: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/38.jpg)
CLUB HOUSE AREA
![Page 39: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/39.jpg)
RAIN WATER SUMP WORK IS IN PROGRESS
![Page 40: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/40.jpg)
BASEMENT PARKING AREA
![Page 41: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/41.jpg)
EB - TRANSFORMER FIXING WORK IS IN PROGRESS
![Page 42: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/42.jpg)
SEWAGE TREATMENT PLANT
![Page 43: CONSTRUCTION PROGRESS AS ON 30th APR’18abhinandan.klpprojects.com/PDF/NEW/construction... · AS ON 30th APR’18. E - BLOCK STATUS • 19th floor completed • Internal Painting](https://reader034.vdocuments.mx/reader034/viewer/2022050600/5fa73dacbd61c81df746fd82/html5/thumbnails/43.jpg)