CONSTRUCTION OF PERIMETER FENCE LOCATION : RIVERSIDE POBLACION, KANANGA, LEYTE AREA : 365 SQUARE METERS OWNER : SPS. ENGR. & MRS. DOMINADOR & LUZ M. MIRO REAR: 15.61m Approx. 7 posts, 6 span @ 2.60m/span 11- Layer 6” CHB; .40m x .30m MID-Beam; 7- Layer 4” CHB w/ .10m Concrete Tapping SIDES: LEFT- rear portion: 5.80m Approx. 2 posts, 2 span @ 2.90m/span 11-Layer 4” CHB; .40m x .30m MID-Beam; 3-Layer 4” CHB w// .10m Concrete Tapping. LEFT- front portion: 14.58m Approx. 5 posts, 5 span @ 2.50m/span 15-Layer 4” CHB w// .10m Concrete Tapping. RIGHT- rear portion: 7.39m Approx. 3 posts, 3 span @ 2.46m/span 11-Layer 4” CHB; .40m x .30m MID-Beam; 3-Layer 4” CHB w// .10m Concrete Tapping. RIGHT- front portion: 18.28m Approx. 6 posts, 6 span @ 3.05m/span 13-Layer 4” CHB w// .10m Concrete Tapping. FRONT: LEFT Side/portion: 5.50m Approx. 2 posts, 2 span @ 2.75m/span 5- Layer 4” CHB; 1.00m x ¼ x 1 ½ Steel Railing on top w/ 2 Hor. Bracing RIGHT Side/portion: 3.00m Approx. 1 post, 1 span @ 3.00m/span 5- Layer 4” CHB; 1.00m x ¼ x 1 ½ Steel Railing on top w/ 2 Hor. Bracing

Upload: emmanuel-linguaje-managbanag-ii

Post on 30-Nov-2015

83 views

Category:

Documents


1 download

DESCRIPTION

construction

TRANSCRIPT

Page 1: Construction of Perimeter Fence

CONSTRUCTION OF PERIMETER FENCE

LOCATION : RIVERSIDE POBLACION, KANANGA, LEYTEAREA : 365 SQUARE METERSOWNER : SPS. ENGR. & MRS. DOMINADOR & LUZ M. MIRO

REAR: 15.61m Approx. 7 posts, 6 span @ 2.60m/span11- Layer 6” CHB; .40m x .30m MID-Beam;7- Layer 4” CHB w/ .10m Concrete Tapping

SIDES:LEFT- rear portion: 5.80m Approx. 2 posts, 2 span @ 2.90m/span

11-Layer 4” CHB; .40m x .30m MID-Beam;3-Layer 4” CHB w// .10m Concrete Tapping.

LEFT- front portion: 14.58m Approx. 5 posts, 5 span @ 2.50m/span15-Layer 4” CHB w// .10m Concrete Tapping.

RIGHT- rear portion: 7.39m Approx. 3 posts, 3 span @ 2.46m/span11-Layer 4” CHB; .40m x .30m MID-Beam;3-Layer 4” CHB w// .10m Concrete Tapping.

RIGHT- front portion: 18.28m Approx. 6 posts, 6 span @ 3.05m/span13-Layer 4” CHB w// .10m Concrete Tapping.

FRONT:LEFT Side/portion: 5.50m Approx. 2 posts, 2 span @ 2.75m/span

5- Layer 4” CHB; 1.00m x ¼ x 1 ½ Steel Railing on top w/ 2 Hor. BracingRIGHT Side/portion: 3.00m Approx. 1 post, 1 span @ 3.00m/span

5- Layer 4” CHB; 1.00m x ¼ x 1 ½ Steel Railing on top w/ 2 Hor. BracingFront Curve: 2.00m Approx. 2 Gate Columns/posts, 2 span @ 1.00m/span

5- Layer 4” CHB; 1.00m x ¼ x 1 ½ curve type Steel Railing on top w/ 2 Hor.Bracing

STEEL GATE: 4.00m- 2 units @ 2.00m/unit w/ 0.60m x 1.20m pedestrian gate (Pre- Fabricated on Heavy duty)

Page 2: Construction of Perimeter Fence

BILL OF QUANTITIES

ITEM 1: EXCAVATION & BACKFILLING

A. MATERIALSB. LABOR

45.17 cu.m.- Volume of Excavation @ .90/m3 - ₱ 4,063.3036.14 cu.m.- Volume of Backfill @ .80/m3 - ₱ 2,891.20

__________Total for this Item: ₱ 6, 954.50

ITEM 2: FORMWORKS

A. MATERIALS60 pcs. – 2x3x8 coco lumber @ 64.00/ pc- ₱ 3,840.0040 pcs. – 2x3x10 coco lumber @ 80.00/ pc- ₱ 3,200.0010 shts. – ¼” x4’x8’ Marine Plywood @ 310/ pc- ₱ 3,100.0015 kls. – Assorted CW Nails @ 70.00/ pc- ₱ 1,050.00

B. LABOR 30% material costs - ₱ 3,357.00 __________

Total for this Item: ₱ 14,547.00

ITEM 3: PERIMETER FENCE

A. MATERIALS410 pcs. – 6” CHB @ 18.50/ pc- ₱ 7,585.002,100 pcs. – 4” CHB @ 11.00/ pc- ₱ 23,100.00320 bags – APO Portland Cement @ 230/bag- ₱ 73,600.0025 cu.m – Washed Sand @ 700.00/ cu.m- ₱ 17,500.0015 cu.m – Crushed Gravel @ 900.00/ cu.m- ₱ 13,500.0040 Lghts – 16mm diam. RSB @ 325/Lgth ₱ 13,000.00115 Lghts – 12mm diam. RSB @ 215/Lgth ₱ 24,725.00250 Lghts – 10mm diam. RSB @ 135/Lgth ₱ 33,750.0080 Lghts – 9mm diam. RSB @ 98/Lgth ₱ 7,840.00(46 kls #16 Tie Wire @ 70/Kl) ₱ 3,220.00

B. LABOR 30% material costs - ₱ 65,347.00 __________

Total for this Item: ₱ 283,166.00

Page 3: Construction of Perimeter Fence

ITEM 4: STEEL RAILINGS (PRE- FABRICATED)

A. MATERIALS, LABOR & INSTALLATION 2 units– 1.00 x 2.75 @ 4,000/ unit- ₱ 8,000.001 unit – 1.00 x 3.00 @ 4,200/ unit- ₱ 4,200.00 __________

Total for this Item: ₱ 12,200.00

ITEM 5: STEEL GATES (PRE- FABRICATED)

A. MATERIALS, LABOR & INSTALLATION 2 units– 2.00 x 2.40 m (span) @ 8,500/ unit- ₱ 17,000.001 unit – 0.60 x 1.20 m (span) @ 3,000/ unit- ₱ 3,000.00 __________

Total for this Item: ₱ 20,000.00

R E C A P I T U L A T I O N

ITEM 1.00 EXCAVATION & BACKFILLING ₱ 6,954.50ITEM 2.00 FORMWORKS ₱ 14,547.00ITEM 3.00 PERIMETER FENCE ₱ 283,166.00ITEM 4.00 STEEL RAILINGS ₱ 283,166.00ITEM 5.00 STEEL GATES ₱ 12,200.00

__________

A. TOTAL DIRECT COST: ₱ 336,867.50B. CONTRUCTOR’S PROFIT : 5% of A ₱ 16,843.38C. EQUIPMENT RENTAL : 3% of A ₱ 10,106.03

__________TOTAL PROJECT COST: ₱ 363,816.91ADJUSTED AMOUNT: ₱ 364,000.00