construction of 38,048 modular pre fabricated kitchen...
TRANSCRIPT
CONSTRUCTION OF 38,048
MODULAR PRE FABRICATED KITCHEN
SHEDS IN THE STATE OF MAHARASHTRA.
Head office:
Wing “A”, Raheja Point I, Pt. Jawaharlal
Nehru Road, Vakola, Santacruz(E).
Mumbai 400 055.
CLIENT - Directorate of primary Education Maharashtra state, PUNE
Regional office:
Block No. 11, 19 & 20, B-1,
Guru Ganeh Commercial Complex, Guru
Ganeshnagar,
Kothrud, PUNE- 411 038
Project Management Consultant :
Wadia Techno Engineering Services Ltd.,
Project Brief
• Government of India has launched “Sarva Shiksha Abhiyan” . Implementation is commenced in the year 2004 for the benefits of students taking primary education.
• Mid day Meal is one of the important aspect of the “Sarva Shiksha Abhiyan”
• Food for Mid Day Meal scheme was mostly cooked outside the school premises due to which quality assurance was consistent issue.
• To overcome with this Government of India has decided to provide Kitchen sheds to all eligible primary schools.
• Central Govt. has approved for 38048 kitchen sheds at
RS.60,000/- per number
• Government of Maharashtra has received Rs.
228,28,80,000/- funds for construction of Kitchen Sheds
in the year 2008-2009 Under Mid Day Meal Scheme.
• Government of Maharashtra decided to construct Pre-
fabricated Moduker Kitchen Sheds of 120 sqft area to
eligible primary schools.
• The Government of Maharashtra has entrusted work of
providing Kitchen Sheds all over Maharashtra State to
Directorate of Primary Education (DPEMS).
• The work is being implemented through Project
Management Consultant.
Salient Features of Project • Size of Kitchen shed 3.30 mtr. X 3.30 mtr.
• Plinth Construction in BB / CC Block / UCR Masonry.
• Pedestal blocks in M20 grade concrete for foundation of
post.
• Posts & roof trusses fabricated from rolled steel section.
• Flooring with M15 Plain Cement Concrete.
• 35 mm thick Sandwich panel - walls with aluminum sheet
on either side & insulated with Poly Eurethene Foam.
• Profiled color coated Roof sheets.
• MS Door frame and Sandwich PUF panel door shutter.
• Provision of Ventilation from all four sides.
• Provision of One light point & one plug point.
• The actual construction of a pre-fabricated kitchen shed
on site requires maximum 5 days for complete the
kitchen shed.
• As time require for a kitchen shed is less comparing to
time required for regular RCC or any conventional
method, and costing is less as compared to any other
structure.
• This modular pre-fabricated kitchen shed having wall
panels & door shutter is fire proof material & remaining is
of structural members.
• The kitchen shed structure having durability of 25 years
& is a decent structure.
APPROVED DRAWINGS
APPROVED DRAWINGS
Methodology for work execution
• Actual survey carrying out by PMC for availability of
sufficient space & finalizing of location.
• The copies of survey done by PMC are handing over to
Contractor for execution.
• Contractor start the work with lay out as per location
finalizing in survey.
• The work is completed by contractor under supervision of
PMC.
• Final inspection is done by PMC & inspection report is
prepared.
• Finally completed kitchen shed is handed over to concern
Head Master along with copy of inspection report.
Excavation In Progress
Plinth Construction In Progress
Plinth Construction In Progress
Plinth Construction In Progress
Completed Plinth
Erection Work In Progress
Erection Work In Progress
Completed Kitchen Shed
Completed Kitchen Shed
Inauguration of Completed Kitchen Shed
Handing Over of Completed Kitchen Shed
Kitchen Shed In use
Kitchen Shed In use