Page 1: CONSTRUCTION METHODOLOGY

CONSTRUCTION SCHEDULE

EEI CORPORATION

Page 2: CONSTRUCTION METHODOLOGY

FENCE LAYOUT5.00m OFFSET FROM

PROPERTY LINE

Site Development Plan

Page 3: CONSTRUCTION METHODOLOGY

Berm and Fence Detail

Page 4: CONSTRUCTION METHODOLOGY

TEMFACIL Layout

Page 5: CONSTRUCTION METHODOLOGY

EEI Office Layout

Page 6: CONSTRUCTION METHODOLOGY

DCI Office Layout

Page 7: CONSTRUCTION METHODOLOGY

TEMFACIL Section

Page 8: CONSTRUCTION METHODOLOGY

FENCE

FENCE (EXISTING)

EXCAVATION ROUTE

LEGEND

Construction Site Layout

Page 9: CONSTRUCTION METHODOLOGY

AREA 1AREA 2

Initial rebar works & formworks to start as excavation progresses towards Area 1 going to Area 3.

REBARWORKS & FORMWORKS

DIRECTION OF EXCAVATION

Foundation Construction

Page 10: CONSTRUCTION METHODOLOGY

Concreting of footings & columns shall be by direct pouring,and backed up by Mobile Crane & Bucket.

READY MIX CONCRETE WILL BE FROM FOUR SOURCE AROUND METRO MANILA. CONCRETE WILL BE PLACED TO THE SITE BY CRANE & BUCKET

& DIRECT POURING FOR FOUNDATION.

14 MONTHS CONCRETING SCHEDULE.

AVERAGE POURING PER WEEK OF 450 CU. M.

Foundation Concreting

Page 11: CONSTRUCTION METHODOLOGY

After pouring of footing, initial rebar works & formworks for column will start at Tower D1 & D2 as construction of footing progresses towards Tower E1 going to Tower E2

REBARWORKS & FORMWORKS

AREA 2

Completion dates of Concreting works: 3-LEVEL BASEMENT/FOUNDATION

COLUMNS:CONCRETE WORKS Upon concreting operation of columns we will use Crane & Bucket system.

Basement Column Construction

AREA 1

Page 12: CONSTRUCTION METHODOLOGY

SOG-A596.175sqm.

APL 8’07

SOG-B596.74sqm.APL 12’07

SOG-C599.05sqm.APL 21’07

SOG-D599.05sqm.APL 25’07

SOG-E571.87sqm.APL 30’07

SOG-F571.87sqm.MAY 2’07

SOG-G600.00sqm.MAY 5’07

SOG

-J

422.08sqm.

MAY 19’07

SOG-H600.00sqm.MAY 9’07

SOG-I481.89sqm.MAY 12’07

SOG-K547.15sqm.MAY 16’07

SOG-L795.10sqm.MAY 23’07 SOG-M

483.60sqm.MAY 26’07

SOG-N795.10sqm.MAY 30’07

SOG-O795.10sqm.JUN 2’07

SOG Construction

Page 13: CONSTRUCTION METHODOLOGY

RW-2 : CA-AAPL 13’07

RW-2 : D-AAPL 21’07

RW-2 : E-AAPL 20’07

RW-2 : D-BAPL 27’07

RW-2 : E-BAPL 28’07

RW-2 : TAMAY 5’07

RW-2 : TAMAY4’07

RW-2 : E-BMAY 12’07

RW-2 : E-CMAY 11’07

RW-2 : CA-BMAY 19’07

BSMNT 2 RetainingWall Construction

Page 14: CONSTRUCTION METHODOLOGY

B1-A596.175sqm.

APL 24’07

B1-B596.74sqm.APL 27 ’07

B1-C599.05sqm.MAY 1’07

B1-D599.05sqm.MAY 5’07

B1-E571.87sqm.MAY 19’07

B1-F571.87sqm.MAY 23’07

B1-G600.00sqm.MAY 26’07

B1-J

422.08sqm.

JUN

9’07

B1-H600.00sqm.MAY 30’07

B1-I481.89sqm.JUN 2’07

B1-K547.15sqm.JUN 6’07

B1-L795.10sqm.JUN 13’07 B1-M

483.60sqm.JUN 16’07

B1-N795.10sqm.JUN 20’07

B1-O795.10sqm.JUN 23’07

BSMNT 1 Slab Construction

Page 15: CONSTRUCTION METHODOLOGY

RW-1 : CA-AMAY 4’07

RW-1 : D-AMAY 12’07

RW-1 : E-AMAY 11’07

RW-1 : D-BMAY 18’07

RW-1 : E-BMAY 19’07

RW-1 : TAMAY 26’07

RW-1 : TAMAY 25’07

RW-1 : E-BJUN 2’07

RW-1 : E-CJUN 1’07

RW-1 : CA-BJUN 9’07

BSMNT 1 RetainingWall Construction

Page 16: CONSTRUCTION METHODOLOGY

LG-A596.175sqm.MAY 22’07

LG-B472.96sqm.MAY 25’07

LG-C171.57sqm.

LG-D241.73sqm.

LG-E178.92sqm.

LG-F494.73sqm.

LG-G241.73sqm.

LG-J

422.08sqm.

JUN

30’07

LG-H237.98sqm.

LG-I125.34sqm. LG-K

404.32sqm.

LG-L506.05sqm.

LG-M466.04sqm.

LG-N795.10sqm.JUL 11’07

SOG-O795.10sqm.JUL 14’07

Lower GRD Slab Construction

Page 17: CONSTRUCTION METHODOLOGY

TOWER D-A889.38sqm.MAY 26’07

TOWER D-B563.57sqm.JUN 13’07

TOWER E-A669.82sqm.JUN 20’07

TOWER D-B663.11sqm.JUN 27’07

TOWER D-C587.29sqm.JUL 77’07

Upper GRD Slab Construction

Page 18: CONSTRUCTION METHODOLOGY

Project Status

Page 19: CONSTRUCTION METHODOLOGY

Project Status