construction management greg colzani, ccm
TRANSCRIPT
Important
The material in this presentation has been prepared by Jacobs®.
Copyright and other intellectual property rights in this presentation vest exclusively with Jacobs. Apart from any use permitted under applicable copyright legislation, no part of this work may in any form or by any means (electronic, graphic, mechanical, photocopying, recording or otherwise) be reproduced, copied, stored in a retrieval system or transmitted without prior written permission.
Jacobs is a trademark of Jacobs Engineering Group Inc.
Jacobs Engineering Group Inc. All rights reserved.
Disclaimer
September 18, 2019© Copyright
Agenda
3
• Introduction• CM Functions• Managing What’s Different• Keys to Success• Questions
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Safety Minute
• Plan Your Escape– You got there alright– Now????– Do you know the
way out? – What are the
emergency evacuation procedures?
4 Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Construction Management
6
• Construction Management Association of America (CMAA) defines CM as:
“The practice of professional management applied to the planning, design, and construction of projects from inception to completion for the purpose of controlling time, cost, scope, cost and quality.”
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
CM Functions
8
• Project Management• Cost Management• Time Management• Quality Management• Contract Administration• Safety Management• Program Management
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Project Management
9
• Provide project management services including:– Development of CM Plan:– Supervision of project staff and
consultants– Facilitate communication with
Owner and Designer– Monitor project status and
budgets – Submit monthly status report
Description of work performed
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Cost Management
10
• Pre-construction phase– Scope Management– Check estimates– Value analysis/Substitution
Requests– Addenda estimates– Bid analysis
• Construction Phase Activities– Schedule of Values– Progress payments– Change Order Management
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Time Management
11
• Pre-construction Phase Activities– Project schedule / milestone
analysis– Contractor Bid schedule
analysis• Construction Phase Activities
– Schedule Reviews• Baseline Schedules• Monthly Updates• Recovery schedules• Schedule revisions
– Monitoring Schedule Compliance/Schedule analysis
– Time Related Changes/Claims analysis
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Quality Management
12
• Pre-construction Phase Activities– Quality Management Plan– Inspection/Testing Plan
• Construction Phase Activities
– Contractor QC Plan– Inspection– Testing– Hold points/ witness
testing– Reporting/record keeping– Non-Conforming Work
• Wall collapse at Scottish school highlights lack of supervision in modern construction
• Experience suggests that supervision, inspection and testing have diminished over the years for financial reasons.
• A project needs to be properly designed and the design needs to be appropriately checked. The design needs to be translated into construction and the construction needs to be independently supervised. Design alterations need to be referred to the designer and adequate as-built records need to be produced.
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Contract Administration
13
• Pre-construction Phase Activities– Bidder Qualification– Pre-bid Conferences– Bid Evaluation– NTP
• Construction Phase Activities– Pre-construction conference– Owner furnished materials– Communication
• Meetings• Correspondence• E-mail
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
♦ RFI’s♦ Submittals♦ Field orders♦ Change Orders/Claims♦ Document Control♦ Project Close-out
Safety Management
14
• Pre-construction Phase Activities– Owner Commitment To Safety– Bidder Qualification– Pre-bid Conferences– Staffing– Coordination with Compliance Agencies
• Construction Phase Activities– Contractor Safety Plan Review– Coordination with Compliance Agencies– Safety Committee– Safety Audits– Training
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Summary
15
• Managing construction projects has an established Industry Standard of Practice.
– So what is different in underground construction projects?
– How do these differences challenge effective management of these projects?
• Project Management• Cost Management• Time Management• Quality Management• Contract Administration• Safety Management• Program Management
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Limited Access
17
• Full 360o Access • One Way in – One Way Out
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
The picture can't be displayed.
Multiple Activities at Face
18Breakthroughs in Tunneling Short Course – University of Denver September 2019
Construction Management
Highly Specialized Equipment
19Breakthroughs in Tunneling Short Course – University of Denver September 2019
Construction Management
Complex Site Installations
20Breakthroughs in Tunneling Short Course – University of Denver September 2019
Construction Management
Select Examples
22
• Special Contract Clauses and Payment provisions–– Mobilization – Geotechnical Considerations– Allowances
• Schedule
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Mobilization
23
• Commonly 5% of contract value– 4.5% Mobilization
• Proof of Bond• Safety Submittals• Initial Work Plan Submittals
– 0.5% Demobilization• Post-Substantial Completion
Punchlist• Final As-built drawings.
• General Mobilization– 4.5% Mobilization– 0.5% Demobilization
• TBM Mobilization– Initial Submittal/Proof of
purchase order– Design Completion– Factory Demonstration– On-Site Delivery and
Commissioning– X distance of tunneling
• Segment Casting Plant Provisions• Remaining Physical Plant
– Handled as Work in Place• Impacts on Owner Cash Flow
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Geotechnical Considerations
24
• Contractor to make own interpretation of borings and other tests
• Changed Conditions Clauses– Conditions can be exposed
observed in-situ.– Impacts can are easier evaluate
and quantify.
• Geotechnical Data Report• Geotechnical Interpretive Report• Geotechnical Baseline Report –
GBR– Baselines Geotechnical Bid
Assumptions• Differing Site Conditions Clauses
– Often hard to see in-situ or undisturbed.
– Impacts often discrete and cumulative
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Schedule
25Breakthroughs in Tunneling Short Course – University of Denver September 2019
Construction Management
Albers Mills Upshur Confl. New PS
37+76
40+00
45+00
50+00
55+00
60+00
65+00
70+00
75+00
79+36
80+00
85+00
90+00
95+00
100+00
105+00
110+00
115+00
118+25
120+00
125+00
130+00
135+00
140+00
145+00
148+75
150+00
155+00
160+00
165+00
170+00
175+00
180+00
180+50
185+00
190+00
195+00
200+00
205+00
210+00
215+00
220+00
220+65
225+00
230+00
235+00
240+00
245+00
250+00
255+00
260+00
264+86
265+00
266+66
Jun-02 1 1 Jun-021-Jul-02 2 2 1-Jul-02Aug-02 3 3 Aug-02Sep-02 4 4 Sep-02Oct-02 5 5 Oct-02Nov-02 6 6 Nov-02Dec-02 7 7 Dec-02
1-Jan-03 8 8 1-Jan-03Feb-03 9 9 Feb-03Mar-03 10 10 Mar-03Apr-03 11 11 Apr-03
May-03 12 12 May-03Jun-03 13 13 Jun-03
1-Jul-03 14 14 1-Jul-03Aug-03 15 15 Aug-03Sep-03 16 16 Sep-03Oct-03 17 17 Oct-03Nov-03 18 18 Nov-03Dec-03 19 19 Dec-03
1-Jan-04 20 20 1-Jan-04Feb-04 21 21 Feb-04Mar-04 22 22 Mar-04Apr-04 23 23 Apr-04
May-04 24 24 May-04Jun-04 25 25 Jun-04
1-Jul-04 26 26 1-Jul-04Aug-04 27 27 Aug-04Sep-04 28 28 Sep-04Oct-04 29 29 Oct-04Nov-04 30 30 Nov-04Dec-04 31 31 Dec-04
1-Jan-05 32 32 1-Jan-05Feb-05 33 33 Feb-05Mar-05 34 34 Mar-05Apr-05 35 35 Apr-05
May-05 36 36 May-05Jun-05 37 37 Jun-05
SwanClay Alkeny Nicolai Serv
Confluent Shaft
ConstructionNicolaiShaft
Construction
TBM Erection
Contractual Time = 46 m
onths
TBM South on Site
30 Apr 03 (EARLY O
RDER OF DESIG
N)
Notice toCommence01 June 02
Dismantle at Clay Shaft &
Re Assemble TBM at Nicolai
Average 30 ft/day
N
S
Dismantle TBM,Tunnel
Demobilization & Finishing
Water Valve Replacement
CSO Tunnel
One Long Duration Activity –
Tunnel Excavation
Many Short Duration Activities
Schedule
26
• Many concurrent and inter-dependent activities
• Critical Path – combination of many shorter duration activities
• Ability to re-sequence to recover schedule
• Long single activity with fewer concurrent activities
• Critical Path – ties to long single activity
• Very difficult to re-sequence to recover lost schedule
• Tunneling is a cyclical operation –small impacts to cycle and accumulate rapidly
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
28
A tunnel is a hole in the ground with:–An engineer at one end–A lawyer at the other end and–A contractor stuck in the middle
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Construction is easy, until
29
• Construction is easy,there are technical solutions to all technical problems, so……
what causes all of the difficulties in construction?
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management
Partnership
30
• The common thread on all successful projects– Build a “partnership” attitude for
all parties– Work together in a cooperative
manner focusing on the project goals
– Full understanding of “Risk Sharing” responsibilities
– Recognize and respect the needs of the other partners
– Must occur at ALL levels of the projects and within All individuals associated with the projects.
– Partnership must operate within the framework of the contract.Breakthroughs in Tunneling Short Course – University of Denver September 2019
Construction Management
CM Keys to Success
31
• ADEQUATE PLANNING– Plan for Success –– Prepare to manage the tough
issues.• COMMUNICATION
– Open honest, no cold contact.– Clear concise written direction.
• TEAMWORK– All parties are stake holders, no
hidden agendas• KNOWLEDGE
– No replacement for experience.. Don’t let amateurs do the job.
• DOCUMENTATION– Document, document,
document!!!
Breakthroughs in Tunneling Short Course – University of Denver September 2019Construction Management