1 KEY SLIDES AMERICASCBRE
CONSTRUCTION
INDUSTRY DAY
Lafayette
Regional Airport
LITE Center
104 East University Circle
Lafayette, LA 70508
January 30, 2020
2 KEY SLIDES AMERICASCBRE
• OPENING & WELCOME REMARKS
• NEW TERMINAL PROGRAM OVERVIEW
• UPCOMING BUSINESS OPPORTUNITIES
• SBE/DBE PROGRAM OVERVIEW
• Q&A SESSION
• NETWORKING & REFRESHMENTS
• CONCLUSION
INDUSTRY
DAY
AGENDA
3 KEY SLIDES AMERICASCBRE
SCOPE:
• QTA Rental Car Facility
• RTR Cable Relocation
• New FAA RTR Facility
• New Terminal Building • Airside Improvements
• Enabling Parking
• Terminal Civil Work
FUNDING:
• Federal Grants
• State Grants• Self-imposed local tax
LFT NEW
TERMINAL
PROGRAM
OVERVIEW
4 KEY SLIDES AMERICASCBRE
TERMINAL
RENDERINGS
5 KEY SLIDES AMERICASCBRE
TERMINAL
PROGRESS
PHOTOS
6 KEY SLIDES AMERICASCBRE
QTA
PROGRESS
PHOTOS
UPCOMING BUSINESS OPPORTUNITIES
8 KEY SLIDES AMERICASCBRE
UPCOMING BUSINESS OPPORTUNITIES
TAXIWAY
FOXTROT
PHASE II
CONSTRUCTION VALUE: $10.8M – $13.0M
BID DATE: June 2020
DURATION: 365 Days
A/E: RS&H
PMCM: CBRE | Heery
SCOPE INCLUDES:• ~24,000 SY Aircraft Taxiway• ~14,000 SY Asphalt Shoulders• ~4,500 LF Drainage Improvements• Airfield Electrical
CURRENT STATUS:This project is currently in design through May 2020 and is expected to be advertised in June 2020 for competitive bid procurement.
9 KEY SLIDES AMERICASCBRE
UPCOMING BUSINESS OPPORTUNITIES
TAXIWAY
JULIET REPAIRS
CONSTRUCTION VALUE: $1.4M
BID DATE: June 2020
DURATION: 74 Days
A/E: RS&H
PMCM: CBRE | Heery
SCOPE INCLUDES:• Time Sensitive Night Work• Approximately 1,500 Tons of Asphalt Paving
CURRENT STATUS:Project is currently at 90% design. Expected to be bid in June 2020.
10 KEY SLIDES AMERICASCBRE
UPCOMING BUSINESS OPPORTUNITIES
TERMINAL
APRON
CONSTRUCTION VALUE: $10M
BID DATE: March 2020
DURATION: 365 Days
A/E: RS&H
PM: CBRE | Heery
CMAR: Lemoine-Manhattan JV
SCOPE INCLUDES:• ~25,000 SY Concrete Aircraft Parking Apron• ~21,000 SY Asphalt Aircraft Taxilane• ~1,500 LF Drainage Improvements• Airfield Electrical
CURRENT STATUS:Expected to be advertised by the CMAR in March 2020.
11 KEY SLIDES AMERICASCBRE
PROGRAM SCHEDULE OVERVIEW
Terminal Apron ImprovementsTaxiway Foxtrot Phase IITaxiway Juliet
12 KEY SLIDES AMERICASCBRE
LFT AIRPORT –
CAPITAL
IMPROVEMENT
PLAN
(2020-2025
PROJECTIONS)
CIP POTENTIAL PROJECTS:
• ARFF Truck Replacement
• Erosion Slope Rehab Project
• Master Plan Update & Hot Spot Study
• Perimeter Fence Replacement Project
• North General Aviation Improvements
• T-Hangar Apron Overlay Project
• Runway 4L-22R Seal Coat Project
• Taxiway Delta Removal Project
SBE / DBE PROGRAM OVERVIEW
14 KEY SLIDES AMERICASCBRE
DBE PROGRAM:General Program Overview
How to become DBE Certified
Overall DBE Program Goal FY 2019-2021
SBE PROGRAM:General Program Overview
SBE Program Goals
ACDBE PROGRAM:General Program Overview
ACDBE Certification
Expansion of Services Request
QUESTIONS:Rene’ Cotton, DBE Liaison Officer
SBE/DBE
PROGRAM
OVERVIEW
15 KEY SLIDES AMERICASCBRE
LFT CONSTRUCTION INDUSTRY DAY – JANUARY 30, 2020
Taxiway Foxtrot Phase II
Bid Date: June 2020
Taxiway Juliet RepairsBid Date: June 2020
Terminal Apron ProjectBid Date: March 2020
UPCOMING
BIDS
&
AIRPORT