Page 1: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Construction Arna - Bergen Stian Ekornaas Head of Strategies and Contracts Railway Tender Conference Oslo, 10 May 2017

Page 2: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Construction Arna - Bergen • 2 projects:

‒ Arna – Fløen ‒ Bergen – Fløen

• Approx. 50 employees in Client organisation

• Offices in Arna and the city centre of Bergen

Information is correct as of 10 May 2017, but may be subject to change. 2

Page 3: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Arna – Fløen – Bergen

3

Page 4: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Arna - Fløen • Production from 2014 • Completed 2022 • New parallel tunnel Arna – Fløen (Ulriken tunnel)

‒ TBM ‒ Breakthrough autumn 2017

• Arna station ‒ Start-up August 2017

• UUT 31 Railway-technical contract

Information is correct as of 10 May 2017, but may be subject to change. 4

Page 5: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

TBM - New Ulriken tunnel

Information is correct as of 10 May 2017, but may be subject to change. 5

Page 6: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Arna station 2022

6 Information is correct as of 10 May 2017, but may be subject to change.

Page 7: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

UUT 31 Railway-technical contract - p.1 • Interdisciplinary railway-technical contract

‒ Track/superstructure ‒ Catenary system ‒ Low-voltage system ‒ High-voltage system ‒ Telecommunications

• New tunnel (7,8 km) • Updating old tunnel • Arna station area

Information is correct as of 10 May 2017, but may be subject to change. 7

Page 8: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Information is correct as of 10 May 2017, but may be subject to change. 8

Railway-technical work at Arna station

Page 9: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

UUT 31 Railway-technical contract - p.2 • Tendered autumn 2017 • Contract summer 2018 • Planned start-up 1. quarter 2019 • Completion 3. quarter 2022

• Detailed design delivered by Bane NOR

• Contractor will be responsible for design of the slab track part of

the tunnel (7 km)

• Estimated cost MNOK 500

Information is correct as of 10 May 2017, but may be subject to change. 9

Page 10: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

The New Ulriken Tunnel

Arna Bergen

10 Information is correct as of 10 May 2017, but may be subject to change.

Page 11: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Bergen - Fløen • Double-tracking Bergen – Fløen (1,3 km) • Renewal of existing systems • Project underway for several years • High complexity due to location (city centre), limited space and

old infrastructure • Bane NOR needs to take into consideration several other

projects ‒ Bergen light rail ‒ Freight terminal ‒ Railway projects

• Bane NOR will review the scope of the project • Working on a new project progress plan. This will be settled in

the near future

Information is correct as of 10 May 2017, but may be subject to change. 11

Page 12: Construction Arna - Bergen · Construction Arna - Bergen • 2 projects: ‒Arna – Fløen ‒Bergen – Fløen • Approx. 50 employees in Client organisation • Offices in Arna

Fløen

Information is correct as of 10 May 2017, but may be subject to change. 12