construction and survey accuracies for the execution of rockworks
DESCRIPTION
Presentation by Eric Peeters emphasising on best practices when surveying for the Maasvlakte 2 extension of the Port of Rotterdam and related works.TRANSCRIPT
1
Title slide
Construction and Survey Accuracies
for the execution of rockworks
Eric Peeters | 30-09-2014
Dredging and Marine Contractors
2
Chapter title
Best practices from the
“Maasvlakte 2”
Port Expansion Project
Dredging and Marine Contractors
3
Text including image (small)
Personal
─ Eric Peeters
─ BSc in Hydrography
─ Chief Survey Maasvlakte2 and responsible for:
− Survey Test pit
− Survey crane “Condor”
− E-Crane “Blockbuster”
− Daily survey operations Hard sea wall
− Managing MV2 survey department
─ Software test engineer HQ Rotterdam
Introduction
Dredging and Marine Contractors
4
Icons (eight)
Index
Dredging and Marine Contractors
1. Introduction 2. Construction
Aspects 3. Surveying 4. Evaluation of
construction
accuracies and
survey
accuracies
5
Text (small) including image
PUMA
Boskalis 50%
Van Oord 50%
MV2
─ Value 2.9 billion Euro
─ Final completion 2030
PUMA
─ Value 1.1 billion Euro
− Includes Sea defenses
− Includes Reclamation
− Includes Infrastructure (BAVO)
─ Completion 2013
Dredging and Marine Contractors
Project Background
6
Text (small) including image
Contract 1
Dimensions
─ Hard sea defence 3.5 km
─ Beach and dunes 7.3 km
─ Port basins 530 ha
─ Port area 700 ha
─ Quay wall 3.5 km
─ Road 13 km
─ Rail 14 km
Quantities
─ 240 million m3 of sand
─ 7 million tonnes of rock
─ 20,000 concrete blocks (40t/pcs)
Dredging and Marine Contractors
Project Background
7
Text (large) including image
Design – Construction - Survey
Design
─ Contractual specifications / requirements
− Unrealistic, unachievable or unnecessary strict requirements
Construction
─ Practical limits
− Costs
Survey
─ Surveying errors
− Systematical
− Random
Client and contractor to have a better understanding at start of entire process
Dredging and Marine Contractors
1. Introduction Construction and Survey Accuracies for the execution of rockworks
8
Text including image (small)
Innovative design features
Withstand 1/10,000 year storm
─ Wave height 9m
─ Wave direction North, North-West (348°)
─ Duration of 12 hours
Soft sea defence
─ Use of Pleistocene sand
− Steeper foreshore
Hard sea defence
─ Re-use of MV1 materials
− 2 million tones of quarry stone
− 20,000 concrete blocks
Dredging and Marine Contractors
1. Introduction Construction and Survey Accuracies for the execution of rockworks
9
Text large (build up) including image
Hard sea defence
“Stony dune with a reef of blocks”
Dredging and Marine Contractors
1. Introduction Construction and Survey Accuracies for the execution of rockworks
10
Text (large) including image
Vertical accuracy
─ Equipment type
─ Work method
─ Size and grading of rock
─ Ambient hydraulic conditions
Dredging and Marine Contractors
2. Construction aspects Construction and Survey Accuracies for the execution of rockworks
11
Text small (build up) including image
Specialized Equipment
─ Ability to place 40 tons concrete blocks at a distance of 50m within 10cm.
Dredging and Marine Contractors
2. Construction aspects Construction and Survey Accuracies for the execution of rockworks
12
Text (full)
Inaccuracies as a result of the quality of the survey system
Quality of the installation
─ Software, sensors, platform geometry, corrections for draught, heave, roll and pitch
Quality of operation
─ Calibration of the equipment has been executed sufficiently precise and frequent
─ Version control and settings
− Protocols & instructions
─ Pre-define amount of coverage / point density
─ Processing
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
13
Text (full)
Defining accuracy
The survey accuracy can be defined as the extent to which a collection of individual observations actually reflects the true situation
Average level (macro tolerance) Minimum level (micro tolerance)
Large area 400*Dn502 Small area 16*Dn502
Systematic errors
─ Error which produces a systematic offset between observed values and the true values
− E.g. incorrect tidal values, incorrect draught, incorrect speed of sound
Random errors
─ The random error is the difference between the value of an individual observation at one location and moment in time compared to the average value which would result from a long series of observations at the same location
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
14
Text small (build up) including image
Hard sea defence
Progress drawing
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
15
Text small (build up) including image
Hard sea defence
As-Built drawing
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
16
Text small (build up) including image
Testpit
PUMA (2010) vs Verolme (1999)
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
17
Text (large) including image
Above water / Surf zone
Standard method (CUR 154)
─ Use of a semi-spherical foot
− Diameter of half the nominal average stone diameter (D = 0.5 x Dn50)
− 1m x 1m grid
− Reference level ± 10-15% below top
Alternative methods
─ Use of a square plate of 1m2 and 4m2 (± 4 x Dn502)
─ Point measurements
─ Crane Monitoring System
− Bucket or grab
─ Static and mobile laser measurements
− Including airborne systems
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the
execution of rockworks
18
Full image
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
19
Text (large) including image
Under water / Surf zone
Accepted method
─ Multibeam systems
− 6 different types of multibeam
− 101 - 256 beams (3°-1.5°- 0.5°)
− Full coverage
− Lower volume detected
Alternative methods
─ Single beam
− Standard (7°) and narrow beam (3°)
─ Echoscope
− 3D acoustic camera
− 16.000 beams (0.3°x0.3°)
─ Crane Monitoring System
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
20
Full image
Dredging and Marine Contractors
3. Surveying Construction and Survey Accuracies for the execution of rockworks
21
Chapter title
Are there any questions?
Dredging and Marine Contractors
22
Title slide
Thank you for your kind attention
Van Oord | Marine ingenuity
Get inspired at magazine.vanoord.com.
Dredging and Marine Contractors