Constellation Program
Program Manager’s Status
Jeff Hanley, Program Manager2 October 2007
2July, 2007
Program Intro
♦ Program established in 2005 with Formulation Authorization Document complete in August 2006
♦ CxP is organized modeled on Apollo “5 box” structure
♦ CxP is hosted at JSC with participation and support from all Agency centers
♦ Aggressive tempo for standing up CxP with Projects, requirements definition, and procurements proceeding concurrently•
Includes establishing frameworks for content implementation •
Ares 1-X flight is scheduled for April ‘09
♦ CxP resources are constrained in the front end - drive focus on management of reserves, cash flow, and schedule
♦ Efforts to “close” the technical baseline and align margins between Orion and Ares elements underway
3July, 2007
Ground OperationsProject
P. Phillips
Ground OperationsProject
P. Phillips
Chief of Staff Technical: D. Neubek
Assistant Manager Integration: B. Ward
Special Assistant Integration-Headquarters: M. Ivins (M)
Assistant for Strategic Communications: J. Rhatigan
Associate Program Manager KSC: T. Talone
Associate Program Manager MSFC: D. Thomas
Special Assistant for Technology Benchmarking: J. Grunsfeld (M)
Manager for Technology Integration: L. Ham
Secretaries: K. Gabel, K. Moser
Crew Exploration Vehicle Project
C. Hatfield
Crew Exploration Vehicle Project
C. Hatfield
Exploration Launch Projects
S. Cook
Exploration Launch Projects
S. Cook
Program Planning &
Control Office C. Stegemoeller
Program Planning &
Control OfficeC. Stegemoeller
Integrated Test &Evaluation Office
W. Arceneaux
Integrated Test &Evaluation Office
W. Arceneaux
Operations Integration Office
R. Castle
Operations Integration Office
R. Castle
Systems Engineering &
Integration OfficeC. Hardcastle
Systems Engineering &
Integration OfficeC. Hardcastle
Safety, Reliability & Quality Assurance
OfficeC. Noriega
Safety, Reliability & Quality Assurance
OfficeC. Noriega
Lunar Surface Systems Project
C. Culbert (M)
Constellation Program
Program ManagerJ. Hanley
Deputy ManagerM. Geyer
ZA
Lunar and Planetary Exploration Office
W. Mendell (M)
Lunar and Planetary Exploration Office
W. Mendell (M) ZA4/KA
ZC ZD ZF ZG
JSC/ZS
ZB
Ares MSFC/JP01 KSC/LXOrion JSC/ZV
A-
ActingM –
MatrixPre-Project
Administrative OfficeS. Castillo
Administrative OfficeS. Castillo
ZA2
EVA SystemsProjectG. Lutz
EVA SystemsProjectG. Lutz
JSC/XA
Mission Operations Project D. Webb
Mission Operations ProjectD. Webb
JSC/DA
Office of the Program Systems Engineer
B. Muirhead (M)
Office of the Program Systems Engineer
B. Muirhead (M) ZA3
Lunar Lander Project
L. Hansen
JSC/ZL
Chief EngineerS. Labbe (M)
Chief EngineerS. Labbe (M)
EA3
Chief Medical OfficerJ. Davis (M)
Chief Medical OfficerJ. Davis (M)
SA
Ares I-XB. Ess
Ares I-XB. Ess ZA
Ares I-YS. GahringAres I-Y
S. Gahring ZA
Chief SMA Officer J. Bye (M)
Chief SMA Officer J. Bye (M)
NA13
4July, 2007
Program Progression
♦ Constellation Program content based on the results of the ESAS study•
Program initiated Fall ’05•
Initiated alignment of Exploration Launch Vehicle and Crew Exploration Vehicle Projects (Scope, Contracts, Resources) along with establishing Mission Operations, Ground Operations and EVA Project activities−
Initial content and budget alignment in Bottom Up Review−
Spring ’06 Budget updated for OMB in September ’06
•
Initiated Season of SRR’s
with initial review in Spring of ’06−
Program SRR conducted November ’06−
Projects’
SRRs conducted December thru April−
Program Baseline Synchronization conducted May 23 2007
•
Full Program PPBE exercise submit on May 9th, 2007−
Update performed to support the OMB submittal on Sept 9
♦ Program and Projects initiating System Definition Reviews
Version 9 - May 11, 2006 Post ICPR5
Scope &Resource Analysis
POP
8/05 9/05 10/05 11/05 12/05 1/06 2/06 3/06 4/06 5/06 6/06 7/06 8/06 9/06 10/06 11/06 12/06 1/07 2/07 3/07 4/07
Requirements
Full Cost Updates
Submitto OMB
CEV Selection
ReleasePBS FY07
ESAS
BUR
CLV SRRCEV SRR
MO SRRGO SRREVA Systems SRR
POP ‘05
POP ‘07(‘09 PBS)
RAC 2
Pre-NAR(in work)
Pre-NARPricing
Post POP Update
Prime Contracts
FY07 Op Plans
PBS FY08
Task ID/Map
CxPO submit
to ESMD
ESMD submit
to PA&E
POP ’06 (‘08 PBS)
RAC 1
ICPRSRR
OMB Passback
FY ’06 Op Plan updates
ITA’s
CARD ver 1
TPR 3/23-24
Initial Program Review
QPR QPR
Program BaselineUpdate (in Work)QPR
J2 Selection
1st Stage Update US SelectionNote: Definitization occurs 60-150 days post selection
“Early” Constellation Program Integration Roadmap
DRAFT as of 04/23/20076
Constellation Program Integration Roadmap “To Date”
Program Approval
Qtrly5/1-3 LaRC
Qtrly1/31-2/2New Orleans
Qtrly7/31-8/2
Program/Project SDR - Under Review
1/23Orion 3/01
MO 3/272/07
GO 5/043/21
EVA 4/303/28
Qtrly10/23-25
DATES UNDER REVIEW
CxP PPAR APMC 10/11KO Briefto SRB5/22
IMSBaseline Release
ExecutionInitialCapability•Ares•Orion•Ground Ops•Mission Ops•EVA Systems
Resources
PBS5/23PMR ’07
IOC Decision5/8-9
2006Aug Sept Oct Nov Dec
2007Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
2008Jan
QtrlyTBD
PPAR 9/5
DPMC9/19
Project SRRs
‘07 PBS
‘08 PBS
‘09 PBS
‘08 ITAOp Plan Dev
PMR ’07 (‘09 PBS PPBE) PMR
SMC N2Update
Agency to OMB
PMR ’08
PPBE Pre-Planning
’09 PBS to Congress
OMB Passback
‘10 PBS
2/13 SDR LCCR
11/12 OperationalCapability SDR
-MO-GO-EVA
2/06
IDAC 3
’09 PBS to Congress
Prep for PNAR
Project Pre-NARs
DPMCAres, OrionMO, EVA7/16
Integrated Stack SDR
7/12 CEV 8/30
9/10 Ares 10/30
11/09PBS
11/06Ares
9/16CxP SRR 1/07
IPAOKO 8/08
Project CMC
Orion5/17
MO6/25
GO8/21
EVA6/28
Ares5/8
ICMC9/13
‘07 PBS
Prep for PAR
You are here
7July, 2007
Current CxP Working Baseline
♦Supports the Nation’s Commitment to the Vision for Space Exploration•
Meets NASA Planning Guidance•
Represents a more mature program formulation based on SRR completed in November 2006
•
Meets the objective of 65% Confidence Level for a March 2015 IOC−
Supports a FY 2013 Initial Operational Capability (IOC) and Full
Operational Capability (FOC) in FY 2014
•
Includes a robust test plan with two human test flights prior to
FOC•
Begins Constellation Lunar Phase development in 2011 to accomplish Human Lunar Return (HLR) as soon as possible−
Human Lunar Return –
June 2019 (internal plan)−
Reserves to support Agency HLR commitment of December 2020 @ 65% CL
•
Has significant program threats relative to program reserves•
Has minimal reserves through FY 2010
8July, 2007
FY2014FY2013FY2012FY2011FY2010 FY2015 FY2017FY2016 FY2018 FY2019 FY2020FY2009
Overview FY08 President’s Budget Baseline vs. PMR ‘07
FY ‘08 President’s Budget
- Ares I
4/15 Sept Sept June
Sept
Dec
March
May
July
Sept
June Dec June
Dec
Human Lunar Return
Ares I-X Orion 1 Orion 2
Orion 3 Orion 5
Orion 4
Orion 6
Orion 7
Orion 8
Orion 9
Orion 10 1211
Ares I-Y
PA-1
Nov
AA-1 PA-2 AA-2 AA-3 AA-4
May May SeptFebAug
= ISS Crew Flight
= ISS Uncrewed Pressurized Cargo Flight
= Lunar Sortie Cooperative Crew Flight
= CEV LAS Pad Abort (PA) or Ascent Abort (AA) Test
= Ares I / Orion Test Flight
= Ares I / Orion Crewed Test Flight
= Ares V Test Flight
= Ares V / LSAM Lunar Sortie Flight
Initial Operational Capability (IOC)
OrionSept
Oct
Ares I
Ground OpsMarch
= Project DDT&E Complete / Schedule Reserve
- Ares VJune June JuneDec
LSAM 1 3 42June
Ares V-Y
- Ares I
- Ares V
Ares I-X Orion 2 3 5
Orion 1March
Sept March
Sept
March
6Sept
Dec June
June
JuneDec
Dec June
Human Lunar Return
15
7March
8Sept
9March
10Sept
11March
12Sept
14March
16Sept
18March
Sept
4
1917
PA-1
9/23
AA-1 PA-2 AA-2 AA-3
May May FebAug
3 4
Sept
Ares I-Y
20
Dec
13
2June
Ares V-Y
Full OperationalCapability (FOC)
OrionJan
July
Ares I
Ground OpsMay
Initial Operational Capability (IOC)
Agency commitment for IOC is Mar 2015
JuneAres V
DecLander
LSAM 1
PMR ‘074/15
Deleted Flights and Tests
Added Flights and Tests
9July, 2007
Cx Program Summary Schedule Initial Capability Content
PMR ’07 Baseline – As of 8/28/07
Flight Plan
FY06 FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16
Ares I Launches
Program Integration
T-NowAres I-X
Phase C
Phase D
= 0% Complete
Phase A/B
Pre Phase A
= 100% Complete
Level I Level II-C Level II-N Level III
SCIP
PDR 1SRR Ares I-Y FRROrion 3
FRRCDR Orion 2
FRRSDR
PPAR PAR
Ares I-Y
Orion 1 Orion 3 Orion 5
Orion 6
Orion 7
Orion 8
Initial Operational Capability
Orion 2 Orion 4
Full Operational Capability
ProjectsGroundOperations
DDT&E
Processing
Processing
Ares I-YORD
MLCDR
MLPDR
HW Needfor Ares I-X
H/W Needfor Ares I-Y
SRR
Orion 1Need
SDR
Orion 3Need
Orion 2Need
Orion 4Need
Orion 1FRR
Orion 4FRR
Mission OperationsORRSRR
Ops
DDT&E
Production / Operations2 3
PDR CDR
Orion 1
SDR
MCC Ready Ares I-Y 4
Production Production
DelAres I-Y 2 3
DelOrion 1 4
OrionSRR SDR PDR
DDT&ECDR DCR
Ares ISRR PDR
2 3Del
Ares I-YDel
Orion 1Production
DelAres I-X
CDRDDT&E
Production Production
DCR
4
SDR
EVA (Suit 1 Config)SRR SARCDRPDRSDR
Production
Del Orion 2
Sched Reserve
3 4
DDT&E
Production
Sched Reserve
Sched Reserve
PDR 2
Suit IDR
Forward WorkSRR SDR
PDR
SAR
10July, 2007
FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20
Flight Plan
Program Integration
Orion Launches
MissionOperations
Ares V Launches
PDR CDR Ares V-Y FRR LSAM 1 FRR LSAM 2 FRR
SCIP
LSAM 1 LSAM 2MCC Ready for Ares V-Y
SRR SDR PDR
LanderSRR PDR CDR
ORRCDR
Cx Program Summary Schedule Lunar Capability Content
PMR ‘07 Baseline – 8/28/07
Ares V-YLSAM 2LSAM 1
14 16 18
L3Human Lunar Return
Orion 9 10 11 12 20
L4
ProjectsGround Operations
CDR
Del Orion 15Del Orion 13Orion Production
Del Orion 15Del Orion 13Ares I
Production
PDR ORDProject ATP
Ares VForward Work
CDRPDRSRR Sched ReserveProject ATP
Del LSAM 2Del Ares V-Y Del LSAM 1Production
Del LSAM 2Del LSAM 1Production
Un-pressurizedRover
CDRPDRSRRATP DCR Sched Reserve
ProductionDel LSAM 2
EVA(Suit 2 Config)
CDR SARPDRSDR
Orion 13 Del
DDT&E
Production
DDT&E
Production
DDT&E
Production
DDT&E
Production
DDT&E
Ops
Production
Project ATP DCR
Del LSAM 1
Production
13 15 17 19
LSAM 1/Orion 13 Processing
LSAM 2/Orion 15 Processing
Ares V-Y Processing
Processing
DCR
Orion 15Del
Sched Reserve
Sched Reserve
Forward Work
Phase C
Phase D
= 0% Complete
Phase A/B
Pre Phase A
= 100% Complete
Level I Level II-C Level II-N Level III
SDR
SRR SDRMCR
11July, 2007 11
Constellation Leverages Unique Skills and Capabilities Throughout NASA and the Aerospace Industry
Dryden♦
Lead Abort Flight Test Integration/Operations
♦
Abort Test Booster procurement
♦
Flight Test Article Development/ Integration
Ames♦
Lead Thermal Protection System ADP
♦
Aero-Aerothermal database
♦
Ares Abort simulations♦
Software and GN&C support
JPL♦
Thermal Protection System support
Johnson♦
Home for Program♦
Home for Projects: Orion, Mission Ops, EVA, Lunar Lander
♦
Lead Crew Module integration♦
Orion Spacecraft Integration♦
GFE projects management♦
Flight Test Program
Kennedy♦
Home for Ground Ops Project
♦
Ground processing♦
Launch operations♦
Recovery operations
Langley♦
Lead Launch Abort System integration
♦
Lead landing system ADP
♦
Ares I-1 vehicle integration
♦
Ares aerodynamics lead
♦
SE&I Support
Marshall♦
Home for Ares Project♦
Ares I and V development and integration lead
Glenn♦
Lead Service Module and Spacecraft Adapter integration
♦
Flight Test Article “Pathfinder” fabrication
♦
Ares I-1 upper stage simulator lead
♦
Ares power, TVC and sensors lead
♦
J-2X altitude/inspace testing♦
SE&I Support
Goddard♦
Communications Support
Stennis♦
Rocket Propulsion Testing for Ares
12July, 2007
Overview
♦ Initial Operational Capability –
September 2013 (internal plan)
♦ Reserves to support Agency IOC commitment of March 2015 at 65% confidence level
♦ Full Operational Capability –
September 2014
♦ Updated Test and Verification Strategy
♦ Ares I –
five segment SRB, J2X US engine
♦ Orion –
606 POD Configuration (carried in Threats List)
♦ Ground Ops –
all launches from LC-39
♦ EVA –
single system suit architecture
♦ Ares V –
ATP 2011
♦ Lander –
ATP 2011
♦ Human Lunar Return – June 2019 (internal plan)
DRAFT as of 04/23/200713
SRB
Constellation Program Integration Roadmap – “Next 18 mths”
Program Approval
Qtrly7/31-8/2 TBD
Qtrly10/23-25 TBD
DATES UNDER REVIEW
2007Jul Aug Sep Oct Nov Dec
2008Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
CxP PPAR APMC 10/11
PPAR 9/5
DPMC9/19
DPMCAres, OrionMO, EVA7/16
ICMC9/13
SRB Findings
SRB Findings
QtrlyTBD
QtrlyTBD
‘07 PBS
‘08 ITAOp Plan Dev
PMRSMC N2
UpdateAgency to OMB
PMR ’08 (‘10 PBS PPBE)PPBE Pre-Planning PMR
’09 PBS to Congress
OMB Passback
CxP SDR - LCCR2/06
IDAC 3 IDAC 4
PMR ’08tbd
PAR Prep
SDRPBStbd
PNARs
APMCTBD
7/12 ORION P+1 Orion P+2
SRB
Integrated Stack SDR
8/30
Int StackSynch11/0810/01
9/10 AresICE
ICE
11/12 MO – GO - EVA
SRB
ICE
Operational Capability SDR
PBS
3/05
2/13
SRB
QtrlyTBD
QtrlyTBD
10/30
APMCTBD
ExecutionInitialCapability•Ares•Orion•Ground Ops•Mission Ops•EVA Systems
Resources‘07 PBS
‘08 PBS
‘09 PBS
‘10 PBS
Project PDR Activity
CxP PPAR APMC TBD
PARTBD
DPMCTBD
TBD
‘09 ITA
ALL DATES UNDER REVIEW
SMC N2Update
Agency to OMB
OMB Passback
DRAFT as of 04/23/200714
“Current” Constellation Program Integration Roadmap
Program Approval
DATES UNDER REVIEW
ExecutionInitialCapability•CLV•CEV•Ground Ops•Mission Ops•EVA Systems
Resources
2007Q3 Q4
FY08Q1 Q2 Q3 Q4
FY09Q1 Q2 Q3 Q4
FY10Q1 Q2 Q3 Q4
FY11Q1 Q2 Q3 Q4
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
LunarCapability•CaLV•Lunar Lander•Surface Systems
CxP PPAR
Agency PMCTBD
(InitialCapability)
IC Project Pre-NARstbd
CxP PAR
Agency PMCTBD
(InitialCapability)
IC Project NARstbd
Agency PMCTBD
Qtrly4/30-5/2
Qtrly7/31-8/2
Qtrly10/23-25
LC Project Pre-NARs (tbd)
Agency PMCTBD
Post SRRProgram Baseline Synch-Up5/23
IDAC 3 IDAC 4 (tbd)
ARES 1-X
Project CDRs
SDRs
Post SDRProgram Baseline Synch-Uptbd
Project SRRsCxP LC SDR
Project Execution (Processes and products)
Pre-Project Activities(Studies/Assessments/Trades)
Pre-ProjectFormulation
CxP LC SRR
Post PDRProgram Baseline Synch-Uptbd
Post CDRProgram Baseline Synch-Uptbd
IDAC 5 (tbd) IDAC 6 (tbd)
LCCR
Project PDRs
IDAC 7 (tbd)
Project SDRs Project PDRs
LC Project Acquisition ProcessLC Project Acquisition Process
Post LC SDRProgram Baseline Synch-Uptbd
Initial Capability Content ExecutionIC Project Acquisition ProcessIC Project Acquisition Process
Life CycleReview (tbd)
Agency PMCTBD
‘07 PBS
‘09 PBS PMR ‘07
’09 PBS to Congress
OMB Passback‘09 ITA FY09 Op Plan
‘08 PBS ‘08 ITA FY08 Op Plan
’10 PBS to Congress‘10 PBS PMR ‘08
OMB Passback‘10 ITA FY10 Op Plan
‘11 PBS PMR ‘09
’11 PBS to Congress
OMB Passback‘11 ITA FY11 Op Plan
‘12 PBS PMR ’10
’12 PBS to Congress
OMB Passback‘12 ITA
PA-1 AA-1
PA-2 AA-2
AA-3 AA-4
15July, 2007
Summary
16July, 2007
Program and Project content is underwayMajor contracts onboard or near completionRequirements formulation heading into SDRAres 1-X flight elements in DDT&EIOC content planning on trackPreparing for LAT results and Lunar projects
Program Manager’s Recommend (PMR ’07):Supports the President’s Vision for Space ExplorationMeets ESMD Program and Resources Planning GuidanceSupports a FY 2013 IOC with significant risk threats Includes a robust test plan with two human test flights prior to FOCHas minimal reserves through FY 2010Represents significant formulation maturity in the last yearHas a confidence level of 65% for IOC in March 2015
Concerns:Operations/production challenges for both IOC and Lunar Sortie phasesThreat of Shuttle transition mitigation against reservesNOA strategy through FY 2010
Summary