CDG Lahore - Consolidated ADP 2012-13
1
Consolidated Annual Development Programme
2012-13
Lahore (City District Government, WASA, LDA and PHA)
CDG Lahore - Consolidated ADP 2012-13
3
TABLE OF CONTENTS
List of Abbreviations ..................................................................................................................................... 5
Preface .......................................................................................................................................................... 7
Consolidated ADP 2012-13, Lahore. ............................................................................................................. 9
Lahore – Summary of Consolidated Annual Development Programme 2012-13-By Entity ................... 11
Lahore – Summary of Consolidated Annual Development Programme 2012-13-By Sector .................. 14
Lahore – Summary of Consolidated Annual Development Programme 2012-13-By Category .............. 16
Lahore – Summary of Consolidated Annual Development Programme 2012-13- By Commencement
period ...................................................................................................................................................... 18
City District Government, Lahore. .............................................................................................................. 21
Summary of Annual Development Programme 2012-13 ....................................................................... 23
Annual Development Programme 2012-13 - by Category ...................................................................... 25
Annual Development Programme 2012-13 - by Sector ......................................................................... 27
Annual Development Programme 2012-13(Other than CCB's Schemes) ............................................... 29
Annual Development Programme 2012-13 - by Scheme ....................................................................... 31
Water and Sanitation Agency-Lahore ......................................................................................................... 79
Summary of Annual Development Programme 2012-13 ....................................................................... 81
Annual Development Programme 2012-13 - by Category ...................................................................... 83
Annual Development Programme 2012-13 - by Sector .......................................................................... 85
Annual Development Program 2012-13 - by Scheme ............................................................................. 87
Lahore Development Authority- ................................................................................................................. 91
TEPA & UD Wing ......................................................................................................................................... 91
Summary of Annual Development Programme 2012-13 ....................................................................... 93
Summary of Annual Development Programme 2012-13. ...................................................................... 95
Annual Development Programme 2012-13 - by Category ...................................................................... 97
Annual Development Programme 2012-13 - by Sector .......................................................................... 99
Annual Development Programme 2012-13 - by Scheme .................................................................... 101
Urban Development Wing ..................................................................................................................... 104
Summary of Annual Development Programme 2012-13 ..................................................................... 104
Annual Development Programme 2012-13 - by Category .................................................................... 106
Annual Development Programme 2012-13 - by Sector ........................................................................ 108
CDG Lahore - Consolidated ADP 2012-13
4
Annual Development Programme2012-13 - by Components .............................................................. 110
Annual Development Programme - 2012-13- by Scheme .................................................................... 112
Parks &Horticulture Authority-PHA .......................................................................................................... 119
Summary of Annual Development Programme 2012-13 ..................................................................... 120
Annual Development Programme 2012-13 - by Category .................................................................... 122
Annual Development Programme 2012-13 - by Sector ........................................................................ 124
Annual DevelopmentProgramme 2012-13 - by Scheme ...................................................................... 126
Glossary of Terms...................................................................................................................................... 127
CDG Lahore - Consolidated ADP 2012-13
5
List of Abbreviations
ADP Annual Development Programme
B.E Budget Estimate
CCB Citizen's Community Board
CDG City District Government
CMAP Chief Minister Accelerated Programme
DLI Disbursement Linked Indicator
EDO Executive District Officer
LDA Lahore Development Authority
LDP Local Development Programme
PCGIP Punjab City Governance improvement Programme
PDSSP Punjab Devolved Social Services Programme
PESRP Punjab Education Sector Reform Programme
PHA Parks & Horticulture Authority
SDA Special Deposit Account
TEPA Traffic Engineering and Transport Planning Agency
U.D Wing Urban Development Wing
WASA Water and Sanitation Agency
CDG Lahore - Consolidated ADP 2012-13
7
Preface
Lahore District is a district in the Punjab province of Pakistan, covering total area of 1,772 square
kilometers. According to the 1998 census, the population was 6,318,745, of which 81.17% were urban. A
2010 government estimate now puts the population at 10,000,000.
Under the administrative structure of 2001, Lahore is declared as a City District with the division into
nine towns. Each town in turn consists of a group of union councils. City District has three tiers: the City
District Government (CDG), the Town Municipal Administration (TMA) and the Union Administration
(UA).
There is Urban Development Wing for planning, designing and development of various projects in
accordance with the functions of the Development Authority. These have been established for the
integrated metropolitan and regional development approach for the continuous process of planning and
development. And the optimum utilization of resources i.e. economical and best utilization of land. TEPA
in Lahore is responsible for the planning, design and development of traffic and transport system i.e.
roads. Similarly, PHA focuses on horticulture under the head of road rehabilitation project.
Government of the Punjab with the financial assistance of World Bank has an initiative of Punjab Cities
Governance Improvement Project (PCGIP). This is for the strengthening of the system to improve
planning, resource management, accountability and capacity building to deal with emergency or eligible
crisis.
A result based approach is linked to the disbursement decision for the achievement of pre-specified
results. These are referred to as Disbursement Linked Indicators (DLIs). They include immediate
outcomes, incremental steps and results contributing to improved efficiency and effectiveness during
and beyond the project. This is for the encouragement of the concerned districts to develop a
consolidated work plan, to achieve consolidated work position at district level and for the preparation of
an intended plan for development spending.
CDG Lahore - Consolidated ADP 2012-13
11
Lahore – Summary of Consolidated Annual Development Programme 2012-13 -By Entity
No.
Entity
No. of Schemes
Budget Estimate 2012-13
(Rs. in millions) %
1 Lahore City District Government (CDG) 472 3,350 10%
2 Water And Sanitary Agency (WASA) 14 696 2%
3 Lahore Development Authority
Traffic Engineering and Transport Planning Agency (TEPA)
55 21,617
Lahore Development Authority(UD Wing) 125 8,903
Total 180 30,520 87%
4 Parks & Horticulture Authority (PHA) 12 398 1%
Total 678 34,966 100%
Lahore ADP Outlay 2012-13
CDG Lahore - Consolidated ADP 2012-13
14
Lahore – Summary of Consolidated Annual Development Programme 2012-13 -By Sector
Sectors
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Education 0 0 0% 108 400 1% 108 400 1%
Special Education 0 0 0% 14 144 0% 14 144 0%
Literacy 0 0 0% 2 3 0% 2 3 0%
Housing Schemes 9 2060 48% 9 81 0% 18 2,142 6%
General Building 0 0 0% 6 134 0% 6 134 0%
Flat and Building 7 387 9% 10 597 2% 17 984 3%
Parking Plaza 0 0 0% 1 501 2% 1 501 1%
Road & Streets 47 1332 31% 268 23754 77% 315 25,087 72%
Transport Planning 1 52 1% 5 179 1% 6 231 1%
Electrical & Mechanical 0 0 0% 1 7 0% 1 7 0%
Health 0 0 0% 8 63 0% 8 63 0%
Sports 0 0 0% 1 36 0% 1 36 0%
Agriculture 0 0 0% 4 6 0% 4 6 0%
Sewerage 1 75 2% 4 178 1% 5 253 1%
Water Supply 3 150 3% 1 30 0% 4 180 1%
Drainage 1 53 1% 1 100 0% 2 153 0%
Parks 4 17 0% 4 140 0% 8 157 0%
Others 3 165 4% 155 4320 14% 158 4,485 13%
Total 76 4,293 100% 602 30,673 100% 678 34,966 100%
11% 12% 89% 88% 100% 100%
Share by Sector in Lahore ADP Outlay 2012-13
CDG Lahore - Consolidated ADP 2012-13
16
Lahore – Summary of Consolidated Annual Development Programme 2012-13 -By Category
Category
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Replacement 20 2,692 - 275 25505 83% 295 28197 81%
Refurbishment 55 1,550 - 197 3025 10% 252 4575 13%
Up-gradation 0 - - 10 109 0% 10 109 0%
Other 1 50 120 2035 7% 121 2085 6%
Total 76 4,293 - 602 30,673 100% 678 34,966 100%
11% 12% 89% 88% 100% 100%
Share of Schemes by Category in Lahore ADP Outlay 2012-13
CDG Lahore - Consolidated ADP 2012-13
18
Lahore – Summary of Consolidated Annual Development Programme 2012-13
- By Commencement period Commencement
period CDG % WASA % TEPA % UD Wing % PHA % Total %
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
New Schemes 0 - - 7 383 55% 4 148 1% 61 3744 42% 4 17 4% 76 4292 12%
Ongoing Schemes 472 3,351 100% 7 313 45% 51 21469 99% 64 5160 58% 8 381 96% 602 30674 88%
Total 472 3,351 100% 14 696 100% 55 21,617 100% 125 8,904 100% 12 398 100% 678 34,966 100%
70% 10% 2% 2% 8% 62% 18% 25% 2% 1% 100% 100%
*Schemes having no information on New or Ongoing are classified as 'Ongoing' schemes in the above table.
Share of Schemes by Commencement in Lahore ADP Outlay 2012-13
CDG Lahore - Consolidated ADP 2012-13
23
City District Government
Summary of Annual Development Programme 2012-13
S. No.
Programme
No. of Schemes
Budget Estimate 2012-13
(Rs. In million)
%
A. Annual Development Programme (other than CCB's) 359 2191.176 65%
B. Annual Development Programme (CCB Schemes) 113 1160.019 35%
Total 472 3,351 100%
CDG ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
25
City District Government
Annual Development Programme 2012-13 - by Category
Category
New %
Ongoing %
Total % No. of
Schemes Rs. in
Million No. of
Schemes Rs. in
Million No. of
Schemes Rs. in
Million
Replacement - - - 213 1427 43% 213 1427 43%
Refurbishment - - - 137 712 21% 137 712 21%
Up-gradation - - - 9 53 2% 9 53 2%
Other 113 1160 35% 113 1160 35%
Total - - - 472 3,351 100% 472 3,351 100%
0% 0% 100% 100% 100% 100%
Share of Schemes by Category in CDG ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
27
City District Government
Annual Development Programme 2012-13 - by Sector
Sectors New
% Ongoing
% Total
% No. of Schemes
Rs. in Million
No. of Schemes
Rs. in Million
No. of Schemes
Rs. in Million
Education - - - 108 400 12% 108 400 12%
Road & Streets - - - 212 1422 42% 212 1422 42%
Health - - - 8 63 2% 8 63 2%
Agriculture - - - 4 6 0% 4 6 0%
Literacy - - - 2 3 0% 2 3 0%
General Building - - - 6 134 4% 6 134 4%
Special Education - - - 14 144 4% 14 144 4%
Electrical & Mechanical
- - - 1 7 0% 1 7 0%
Others* - - - 117 1171 35% 117 1171 35%
Total - - - 472 3,351 100% 472 3,351 100%
0% 0% 100% 100% 100% 100%
* Includes CCB Schemes, CCB Block Allocation, and Transfer Payments.
Share by Sector in CDG ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
29
City District Government Lahore
Annual Development Programme 2012-13(Other than CCB's Schemes)
S.No
Programme
No. of Schemes
Budget Estimate 2012-13
(Rs. In million)
%
A. Annual Development Programme 359 2191.176
Education 108 399.558 18%
Road & Streets 212 1421.898 65%
Health 8 63.379 3%
Agriculture 4 6.061 0%
Literacy 2 3.311 0%
General Building ADP Schemes 6 134.089 6%
Special Education (Tied Grants) 14 144.266 7%
Electrical & Mechanical 1 7.277 0%
Transfer Payments 4 11.337 1%
Total 359 2,191 100%
CCB Schemes in CDG ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
31
City District Government, Lahore Annual Development Programme 2012-13 - by Scheme
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Education
Ongoing ADP Schemes
1 127 154 143 Construction of B-class Rooms, Toilet Block, Boundary Wall & Renovation of Govt. Middle School, Bagarian. Lahore. (2nd Amended)
Approved 36.260 1.500 37.760 30.000 0.000 30.000 21.883 0.000 21.883 8.217 8.217
Tied Grant Ongoing Scheme
2 122 147 78 Construction of Govt. Girls Middle High School, Shahra-e-Aiwan-e-Tijarat, Lahore
Approved 62.002 3.000 65.002 10.900 0.000 10.900 5.909 0.000 5.909 0.000 3.000 3.000
Missing Facilities in Colleges(Amount Rs. 187.350 M Scheme
Provision of Missing Facilities in the Colleges Govt. college Ravi Road Lahore (21.500 M) Govt. Shalimar College Lahore (18.500) Govt. Degree College Women, Kot Khawaja Saeed, Lahore (45.400 M) Govt. Islamia College Commerce, Lahore (14.50 M) Govt. Model Degree College for Women Model Town, Lahore (33.000 M)
Approved 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
3 120 139 Provision of Missing Facilities at Govt. College Ravi Road, Lahore.
Approved 21.500 0.000 21.500 21.500 0.000 21.500 0.000 0.000 0.000 21.500 0.000 21.500
145 Provision of Missing Facilities at Govt. Shalimar college, Lahore
Approved 18.500 0.000 18.500 18.500 0.000 18.500 0.000 0.000 0.000 18.500 0.000 18.500
123 143 22 Provision of Missing Facilities at govt. Degree College for Women, kot khawaja Saeed, Lahore. Amended
Approved 45.576 1.653 47.229 45.576 1.653 47.229 0.000 0.000 0.000 45.576 1.653 47.229
CDG Lahore - Consolidated ADP 2012-13
32
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
126 151 108 Provision of Missing Facilities, at Govt. Islamia College of Commerce, Lahore
Approved 14.500 0.000 14.500 14.500 0.000 14.500 0.000 0.000 0.000 14.500 0.000 14.500
126 152 127 Construction of Academic Block &Admin. Block at Govt. College (W), Model Town, Lahore.
Approved 33.000 0.000 33.000 33.000 0.000 33.000 0.000 0.000 0.000 33.000 0.000 33.000
122 148 107 Construction of Additional Class Rooms Block at Govt. college for Women Wahdat Colony, Lahore.
Approved 10.884 0.000 10.884 10.884 0.000 10.884 0.000 0.000 0.000 10.884 0.000 10.884
119 143 23 Construction of Multipurpose Hall in Govt. College for Women Shad Bagh, Lahore
Approved 12.000 0.000 12.000 12.000 0.000 12.000 0.000 0.000 0.000 12.000 0.000 12.000
126 151 107 Construction of Post Graduate Block at Govt. Science College Wahdat Road, Lahore
Approved 6.350 0.000 6.350 6.350 0.000 6.350 0.000 0.000 0.000 6.350 0.000 6.350
Missing Facilities in School Scheme 2007-08
4 119 142 73 Reconstruction of school building at CDG Boys H/S Gawalmandi, Lahore
Approved 13.603 0.000 13.603 0.250 0.000 0.250 0.250 0.000 0.250 1.750 1.750
5 121 149 92 Construction of 2nd floor of new constructed building. Demolishing of old block, Construction of Admin block, provision of furniture/sc: Equipment’s and Up-gradation of Govt. Islamia H/S Multan Road Lahore to higher secondary level
Approved 30.766 1.000 31.766 4.000 0.000 4.000 4.000 0.000 4.000 12.210 12.210
6 121 149 92 Demolishing of Fatima Block and Reconstruction of 20- Class Rooms (Double story) with Toilet Block on each story-2-sciennce Labs -and 1- Laboratory, Raising of Boundary Wall, Tuff tiles
Approved 23.653 1.000 24.653 5.000 0.000 5.000 5.000 0.000 5.000 2.500 2.500
CDG Lahore - Consolidated ADP 2012-13
33
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
on ground, provision of water Coolers and furniture at Government, Islamia Mukarram Girls High School, Sodiwal Quarters, Multan Road, Lahore.
7 126 151 110 Construction of Building (Multistory) with toilet blocks on each story, for Govt. Girls H/S Kharak, Lahore at K-Block, Sabza Zar, and Lahore.
Approved 36.533 1.000 37.533 23.133 0.000 23.133 19.740 0.000 19.740 2.850 2.850
8 127 154 132 Construction of building (Multistory) with toilet blocks on each story at Govt. practicing Girls H/S town ship Lahore.
Approved 37.023 0.800 37.823 6.000 0.000 6.000 6.000 0.000 6.000 6.333 6.333
Missing Facilities in School Scheme 2009-10
9 118 137 7 Provision of missing Facilities at CDG GHS, Factory Area, Shahdara, Lahore (Amended)
Approved 19.628 0.000 19.628 19.347 0.000 19.347 11.719 0.000 11.719 7.628 7.628
10 118 138 8 Provision of Missing Facilities at Government Islamia P/S, Jia Musa, Lahore. (Amended)
Approved 7.756 0.000 7.756 7.675 0.000 7.675 6.918 0.000 6.918 0.757 0.757
11 118 137 1 Provision of Missing Facilities at Govt. Girls Elementary School, Nain Sukh, Shahdara, Lahore (NA-118) Up-Graded as Secondary Level (Revised)
Approved 5.580 0.000 5.580 5.580 0.000 5.580 4.000 0.000 4.000 1.580 1.580
12 123 143 22 Provision of Missing Facilities at CDG Girls H/S, Kot Khawaja Saeed, Lahore.
Approved 7.919 0.000 7.919 5.425 0.000 5.425 4.507 0.000 4.507 0.918 0.918
Ring Road Affected School
13 130 155 60 Construction of Govt. Boys High School, in Taj Pura UC-60 (Bowli Camp) at Herbanspura, Lahore.
Approved 13.000 2.000 15.000 39.422 2.000 41.422 0.000 0.000 0.000 13.000 2.000 15.000
CDG Lahore - Consolidated ADP 2012-13
34
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
14 130 155 60 Construction of Govt. Girls Middle School, in Taj Pura UC-60 (Bowli Camp) at Herbans Pura, Lahore
Approved 11.151 1.563 12.714 23.450 2.000 25.450 0.000 0.000 0.000 11.151 1.563 12.710
15 130 155 60 Construction of Govt. Boys high School Chachowali, Ismail Pura Bedian Road, Lahore.
Approved 41.653 2.000 43.553 35.484 2.000 37.484 33.816 0.000 33.816 3.208 2.000 5.208
16 130 155 60 Construction of Govt. Boys Middle School Chachowali, at Bedian Road, Lahore.
Approved 25.043 2.000 27.043 8.756 2.000 10.756 9.417 0.000 9.417 0.699 2.000 2.699
Special Dev. Package PP-141 Colleges
17 119 141 Construction of additional Class Rooms’ at Govt. Girls College Shad Bagh Lahore.
Approved 10.000 0.000 10.000 9.856 0.000 9.856 8.756 0.000 8.756 1.100 1.100
18 119 141 Construction of Class Rooms Stadium Steps Boundary Wall and Jangla Govt. Girls College Kot Khawaja Saeed. Lahore.
Approved 10.000 0.000 10.000 9.836 0.000 9.836 7.436 0.000 7.436 2.400 2.400
ADP Scheme
19 118 138 7 Construction of Additional Class Rooms’, Sc, Lab, Office stairs, Toilet Block, Renovation of existing building, Earth filling & reconstruction of B/wall at CDG high School, Islam Nagar Aziz Colony, Shahdara, Lahore.
Approved 19.469 1.000 20.469 4.166 0.000 4.166 4.166 0.000 4.166 4.385 4.385
Non ADP New (Rs. 17.500 M received from FD, Rs. 5.020 M add to ADP Scheme of Malikpur)
20 Construction of Building of Govt. Primary School, Toor.
Approved 10.265 1.000 11.265 0.000 0.000 0.000 3.818 0.000 3.818 6.447 1.000 7.447
Missing Facilities in School Schemes 2010-11 (DFID)
21 Const. of Govt. Model Girls High School, Canal View, Lahore City. (Revised)
Approved 13.188 0.000 13.188 0.000 0.000 0.000 5.737 0.000 5.737 7.451 7.451
22 Construction of 05 Classrooms With Verandah with strip Foundation for
Approved 6.486 0.000 6.486 0.000 0.000 0.000 2.309 0.000 2.309 4.177 4.177
CDG Lahore - Consolidated ADP 2012-13
35
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Triple story Building, Stair Case Drinking Water Facilities at Govt. Boys Elementary School Charrar Aziz Bhatti Town, Lahore Cantt. (Revised)
23 Provision of Missing Facilities in Govt. Islamia High School, Misri Shah, Lahore. (Revised)
Approved 4.967 0.000 4.967 0.000 0.000 0.000 3.800 0.000 3.800 1.167 1.167
24 Construction, Of 6 Addition Classrooms, Toilet Block, Drinking Water at Girls Primary School, Aziz Colony, Shahdara, Lahore,
Approved 2.577 0.000 2.577 0.000 0.000 0.000 2.466 0.000 2.466 0.104 0.104
25 Construction, of CDG Girls High School Jia Musa Shahdara, Lahore City.
Approved 5.091 0.000 5.091 0.000 0.000 0.000 4.000 0.000 4.000 1.091 1.091
3 SECTOR MNA / MPA PACKAGE 2010-11
MNA's Schemes.
26 118 Construction of additional Classrooms, Examination hall and Provision of fare face gutka at Govt. MPE High School, Shahdara, and Lahore.
Approved 10.000 0.000 10.000 0.000 0.000 0.000 9.941 0.000 9.941 0.059 0.059
27 118 Construction of three Classrooms (ground floor & first floor) with Veranda at Govt. Girls Middle School Dheer, Shahdara, Lahore.
Approved 4.000 0.000 4.000 0.000 0.000 0.000 3.600 0.000 3.600 0.400 0.400
28 119 Construction of additional Classrooms and provision of drinking Water facilities at Govt. Madrat-tul-Binat H/S Misri Shah, Lahore.
Approved 12.142 0.000 12.142 0.000 0.000 0.000 10.360 0.000 10.360 1.442 1.442
29 120 Construction of additional classrooms ground floor & first floor and mumty at Govt. Girls Middle School
Approved 5.023 0.000 5.023 0.000 0.000 0.000 1.457 0.000 1.457 1.960 1.960
CDG Lahore - Consolidated ADP 2012-13
36
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Gaoshala Band Road, Lahore, (Revised)
30 120 Construction of four additional class rooms double story extra for deep foundation at CDG Girls Middle School Ibrahim Road, Lahore.
Approved 4.265 0.000 4.265 0.000 0.000 0.000 3.643 0.000 3.643 0.281 0.281
31 123 Construction of five class rooms at CDG H/S, Baghbanpura, Lahore.
Approved 3.250 0.000 3.250 0.000 0.000 0.000 2.334 0.000 2.334 0.916 0.916
32 124 Construction of two additional class rooms with varanda and stair mumty third floor rising of boundary wall at CDG Boys H/S Bilal Colony UC-42 Shalimar Town, Lahore.
Approved 2.000 0.000 2.000 0.000 0.000 0.000 1.621 0.000 1.621 0.353 0.353
33 125 Provision of missing Facilities at Govt., Islamia High School, Lahore Cantt.
Approved 18.000 0.000 18.000 0.000 0.000 0.000 6.310 0.000 6.310 0.885 0.885
34 128 Provision of missing Facilities Govt., MS Khizra Abad Lahore.
Approved 3.705 0.000 3.705 0.000 0.000 0.000 1.572 0.000 1.572 2.133 2.133
MPA's Schemes.
35 139 Construction of Hall at CDG Boys High School, IslamPura Karishan Nagar, Lahore City.
Approved 9.150 0.000 9.150 0.000 0.000 0.000 0.000 0.000 0.000 9.150 9.150
36 140 Provision of Missing Facilities at Govt. H/S Mazang, Lahore.
Approved 5.970 0.000 5.970 0.000 0.000 0.000 4.539 0.000 4.539 1.387 1.387
37 140 Provision of Missing Facilities CDG Girls H/S Mazang Adda, Lahore.
Approved 2.666 0.000 2.666 0.000 0.000 0.000 1.812 0.000 1.812 0.222 0.222
38 141 Construction of Additional Class Rooms at Govt., Madrasa-ul-Banat High School, Misri Shah, Lahore (phase-II)
Approved 8.932 0.000 8.932 0.000 0.000 0.000 6.821 0.000 6.821 1.832 1.832
39 142 Up-gradation / Construction of 4-class
Approved 3.323 0.500 3.823 0.000 0.000 0.000 3.027 0.000 3.027 0.296 0.296
CDG Lahore - Consolidated ADP 2012-13
37
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
rooms with three story foundation of City District Govt. Junior Model School Masti Gate (Middle to High level)
40 148 Construction of two new Class rooms, eight toilet block and mumty and provision of missing facilities atCDG Boys High School Rehman Pura, Lahore.
Approved 5.292 0.000 5.292 0.000 0.000 0.000 4.376 0.000 4.376 0.767 0.767
41 149 Construction of Building Portion Items & Missing Facilities at Govt., H/S, 531-A, Gulshan-e-Ravi, Lahore.
Approved 6.578 0.000 6.578 0.000 0.000 0.000 5.832 0.000 5.832 0.131 0.131
42 151 Re-Construction of 4-Class rooms & toilet block at CDG Junior Model School, Huma Block (Flats) Allama Iqbal town, Lahore.
Approved 6.459 0.000 6.459 0.000 0.000 0.000 4.736 0.000 4.736 0.673 0.673
43 152 Construction of stair case, boundary wall, tuff paver, toilet block, drinking water facilities and provision of ceiling fans at Govt., Model H/S, Model Town, Lahore.
Approved 5.640 0.000 5.640 0.000 0.000 0.000 2.153 0.000 2.153 3.354 3.354
44 154 Construction of Hall at Govt., practicing Girls High School, Township, Lahore.
Approved 3.200 0.000 3.200 0.000 0.000 0.000 2.276 0.000 2.276 0.724 0.724
DEVELOPMENT PACKAGE FOR MNA / MPA 2011-12 MNA’s Missing Facilities Schemes.
45 118 Re-Construction of 4-Class rooms, Earth Filling at Govt., Elementary School, Mughaliapark, Shahdara, Lahore.
Approved 6.639 0.000 6.639 0.000 0.000 0.000 5.750 0.000 5.750 0.889 0.889
46 118 Construction of 4-additional class rooms, toilet block, drinking water facilities at Govt. Primary
Approved 3.570 0.000 3.570 0.000 0.000 0.000 3.000 0.000 3.000 0.500 0.500
CDG Lahore - Consolidated ADP 2012-13
38
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
School. Jadah, Shahdara, Lahore.
47 121 Construction of verandah on Ground Floor, and construction of 5-class rooms with verandah on first floor, Toilet Block and Boundary wall at Govt., Girls Middle School, Nonarian, and Lahore.
Approved 6.526 0.000 6.526 0.000 0.000 0.000 6.136 0.000 6.136 0.390 0.390
48 125 Construction of 05-class rooms with verandah, stairs, Mumty and Hall at Govt. Middle School. Muft Pura, Lahore.
Approved 4.354 0.000 4.354 0.000 0.000 0.000 3.808 0.000 3.808 0.546 0.546
49 125 Construction of 03 class rooms, stairs and mumty at Govt. Middle School, Korey Walton Road, Lahore NA-125
Approved 3.593 0.000 3.593 0.000 0.000 0.000 0.925 0.000 0.925 2.668 2.668
50 127 Construction of 5-additional class rooms with verandah, toilet block and provision of drinking water facilities at Govt. Girls Middle Dhalla, kot Lakhpat, Lahore.
Approved 4.500 0.000 4.500 0.000 0.000 0.000 3.900 0.000 3.900 0.600 0.600
51 127 Construction of 3-additional class rooms, and provision of drinking water facilities at CDG Girls Primary School, sector 5-B-1, Township, Lahore.
Approved 3.255 0.000 3.255 0.000 0.000 0.000 2.703 0.000 2.703 0.497 0.497
52 127 Construction of 4 Additional class Rooms, Toilet Block in Govt. Girls Middle School Sector A-II, Township. (NA-127)
Approved 3.745 0.000 3.745 0.000 0.000 0.000 1.300 0.000 1.300 2.445 2.445
53 128 Construction of 4-Additional Class Rooms stairs & Mumty Toilet
Approved 7.387 0.000 7.387 0.000 0.000 0.000 2.928 0.000 2.928 4.459 4.459
CDG Lahore - Consolidated ADP 2012-13
39
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
block and provision of Drinking Water facilities at Govt. Girls Middle school Satto Katla Lahore.
MNA's Model School Schemes.
54 118 Construction of 6-Class rooms with verandah at Govt. Girls Higher Secondary School, Shahdara Town, Lahore (Revised).
Approved 5.095 2.385 7.480 0.000 0.000 3.240 2.232 5.472 1.750 0.153 1.903
55 119 Construction of additional class rooms at G.F & F.F at govt. High School, Chamra Mandi. Lahore.
Approved 3.500 0.000 3.500 0.000 0.000 1.556 0.000 1.556 1.994 1.994
56 119 Construction of Multipurpose Hall in Govt., Islamia High School, Misri Shah, Lahore. (Revised)
Approved 4.000 0.000 4.000 0.000 0.000 1.237 0.000 1.237 2.763 2.763
57 121 Construction of 4-Class rooms, Science Lab, Toilet Block, and Boundary wall at CDG High School, Sanda Kalan, Lahore.
Approved 3.790 0.000 3.790 0.000 0.000 0.000 2.201 0.000 2.201 1.589 1.589
58 123 Construction of Govt., Girls Higher Secondary School, Singa Pur, Lahore.
Approved 4.102 0.000 4.102 0.000 0.000 0.000 0.000 0.000 0.000 4.102 4.102
59 125 Construction of 6149 sfrt Building at 1st floor Govt., Islamia High School, Lahore Cantt.
Approved 7.460 0.000 7.460 0.000 0.000 0.000 7.237 0.000 7.237 0.223 0.223
MPA's Missing Facilities Scheme.
60 137 Construction of 8-additional Class rooms and Construction of Boundarywall at Govt. Primary School, Bullo Colony, Shahdara, Lahore.
Approved 7.321 0.000 7.321 0.000 0.000 5.800 0.000 5.800 1.500 1.500
61 138 Construction of 2-Additional Class rooms & renovation of existing building of Govt., Girls
Approved 3.208 0.000 3.208 0.000 0.000 1.486 0.000 1.486 1.722 1.722
CDG Lahore - Consolidated ADP 2012-13
40
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Primary School, Jadah, Shahdara, Lahore.
62 139 Renovation of Existing Building, Toilet Block, provision of Tuff pavers Courtyard at CDG Junior Model School, chohan Road, Lahore.
Approved 1.263 0.000 1.263 0.000 0.000 0.000 0.911 0.000 0.911 0.352 0.352
63 139 Construction of 2-class rooms with verandah (Double story), Toilet block and provision of drinking water facilities at Govt., Jinah Islamia Girls Middle School, Mohani Road, Lahore.
Approved 2.204 0.000 2.204 0.000 0.000 0.000 2.098 0.000 2.098 0.106 0.106
64 139 Construction of (3+3), class rooms Ground & first floor with stair, Verandah& Mumty at (primary portion) CDG. Boys High School, Shish Mahal, Bilal Gunj, Lahore City.
Approved 5.500 0.000 5.500 0.000 0.000 0.000 3.942 0.000 3.942 1.558 1.558
65 141 Construction of additional class rooms on 1st floor at CDG Girls primary School, Iqbal Park, and Lahore.
Approved 3.194 0.000 3.194 0.000 0.000 2.670 0.000 2.670 0.524 0.524
66 141 Reconstruction of class rooms at Ground & 1st Floor, Mumty, Boundary wall at CDG Junior Model School, Chah Miran, Sultan pura, Lahore.
Approved 4.262 0.000 4.262 0.000 0.000 1.700 0.000 1.700 2.562 2.562
67 143 Construction of 3-Additional class rooms with verandahBoundary Wall with Gate & Gate Pillars Toilet Block Earth Filling and Provision of Drinking water Facilities at Govt. Primary School Yasrab Colony, Lahore.
Approved 5.642 0.000 5.642 0.000 0.000 3.800 0.000 3.800 1.842 1.842
CDG Lahore - Consolidated ADP 2012-13
41
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
68 143 Construction of additional Class Rooms, Toilet Block and provision of Drinking Water at Govt., Taleem-e-tarbiat M/S Bagat Pura, Lahore.
Approved 5.841 0.000 5.841 0.000 0.000 4.700 0.000 4.700 1.141 1.141
69 146 Reconstruction of 2-additional Class Rooms and Drinking Water Facilities at Govt. Dar Ul Aloom, Primary School, Larek Colony, Ghaziabad, Mughalpura, Lahore.
Approved 2.000 0.000 2.000 0.000 0.000 1.750 0.000 1.750 0.250 0.250
70 147 Construction of 2-class rooms with Verandah at 1st and 2nd floor, Toilet block, and provision of Drinking water Facilities at CDG Middle School, New Garhi Shahu, Lahore.
Approved 4.070 0.000 4.070 0.000 0.000 0.000 3.793 0.000 3.793 0.277 0.277
71 148 Construction of Toilet Block provision of water facilities Renovation of Boundary wall provision of Gate and Pillars and renovation of existing Building at CDG, Girls Middle School, Ghazli Road, Samanabad, Lahore (pp-248)
Approved 3.790 0.000 3.790 0.000 0.000 0.000 2.344 0.000 2.344 1.446 1.446
72 149 Renovation of existing building block external Development at CDG Junior Model School Multan Road Lahore (primary portion)
Approved 7.462 0.000 7.462 0.000 0.000 0.000 6.824 0.000 6.824 0.638 0.638
73 149 Construction of 5-Class rooms at Govt., Girls High School, Sodiwal Colony, Lahore.
Approved 4.038 0.000 4.038 0.000 0.000 0.000 2.657 0.000 2.657 1.381 1.381
74 152 Construction of 4-Class rooms with verandah at
Approved 3.815 0.000 3.815 0.000 0.000 0.000 2.442 0.000 2.442 1.373 1.373
CDG Lahore - Consolidated ADP 2012-13
42
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
1st floor, stair case at G.floor, Mumty at 2nd floor, Toilet Block Gate and Gate pillar & provision of Drinking Water facilities at Govt. APWA Girls Middle School, Model Town, Lahore.
75 152 Construction of 3-Class rooms with Verandahs, stair at Ground floor, stair Mumty at first floor, Toilet Block, provision of drinking Water Facilities at Govt. Boys primary School, Grumangat, A-01 Block 462-A Gulberg iii, Lahore (pp-152).
Approved 3.540 0.000 3.540 0.000 0.000 0.000 0.025 0.000 0.025 3.515 3.515
76 153 Construction of Ground & 1st Floor at CDG Girls High School, Sitara Colony, Chungi Amer Sadhu, Lahore.
Approved 11.500 0.000 11.500 0.000 0.000 6.986 0.000 6.986 4.514 4.514
77 156 Construction of Building at 2nd Floor in Govt. Elementary School, Custom Colony Lahore.
Approved 6.896 0.000 6.896 0.000 0.000 0.000 0.100 0.000 0.100 6.796 6.796
MPA; s Model School Schemes
78 137 Construction of B-Class rooms with Verandah, toilet block, septic tank, provision of drinking water facilities at CDGHigh School, Factory Area, Shahdara, Lahore (Revised)
Approved 6.290 1.200 7.490 0.000 0.000 4.200 1.100 5.300 2.090 0.100 2.190
79 138 Re-Construction of 8-Class rooms with Verandah at CDG Girls High School, Qila Lachman singh, Ravi Road, Lahore (Revised)
Approved 6.050 1.450 7.500 0.000 0.000 6.000 1.398 7.398 0.052 0.052
80 139 Construction of 2- Approved 6.547 0.758 7.305 0.000 0.000 0.000 6.447 0.423 6.870 0.100 0.335 0.435
CDG Lahore - Consolidated ADP 2012-13
43
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Additional Class rooms with Verandah, 2-Labs, Mumty and provision of Drinking water Facilities at CDG Girls School, Islampura, Krishan Nagar, and Lahore. (Revised)
81 140 Construction of 2-Class Rooms with Verandah, 2-Labs rooms, Ground & First Floor at Govt. Islamia High School, Dev Samraj Road, Sanat Nagar, Lahore City for Model School. (Revised)
Approved 6.736 0.764 7.500 0.000 0.000 0.000 6.736 0.585 7.321 0.000 0.179 0.179
82 141 Demolishing of existing building and Construction of double story building for primary section at Govt. Girls High School, Dodi Peer, and Lahore.
Approved 7.500 0.000 7.500 0.000 0.000 6.300 0.000 6.300 1.200 1.200
83 142 Construction of 3 Class rooms Double story Mumty, provision of Phase special Brick Gutka at Govt. Girls High School, Lohari Gate, and Lahore. (Revised).
Approved 7.441 0.000 7.441 0.000 0.000 0.000 7.198 0.000 7.198 0.243 0.243
84 143 Improvement / Renovation of school Building at Govt. Comprehensive Higher Secondary School, Ghorey Shah, Lahore.
Approved 7.500 0.000 7.500 0.000 0.000 5.900 0.000 5.900 1.600 1.600
85 145 Construction of 3 Class Rooms with Verandah and 2 Labs at 2nd Floor at CDG High School, Salamatpura. (Revised)
Approved 4.000 0.000 4.000 0.000 0.000 0.000 0.731 0.000 0.731 3.269 3.269
86 146 Construction of Additional Classrooms at Govt. Boys High School, Tajpura
Approved 6.450 0.050 6.500 0.000 0.000 2.600 0.000 2.600 3.850 0.050 3.900
CDG Lahore - Consolidated ADP 2012-13
44
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Scheme, Lahore.
87 147 Construction of 2-Labs with Lab Tables Ground Floor Hall at First floor and stair and Mumty and Drinking water facilities at CDG Girls High School Munawar Sultan Road Lahore. (Revised)
Approved 6.846 0.654 7.500 0.000 0.000 0.000 4.124 0.654 4.778 2.722 0.000 2.722
88 148 Construction of five additional class rooms 8 No. Toilet at Govt. Girls High School, Sultan Ahmed Road, Ichhara, Lahore.
Approved 4.770 0.000 4.770 0.000 0.000 0.000 2.231 0.000 2.231 2.539 2.539
89 150 Construction of 2nd & 3rd floor, Boundary wall with Gate & Gate Pillars Govt. Mussarat Girls High School, Band Road, Lahore. (Revised)
Approved 5.858 1.367 7.225 0.000 0.000 0.000 5.422 1.092 6.514 0.436 0.275 0.711
90 151 Construction of 3 additional class rooms, with Veranda at ground floor, mumty on second floor and toilet block at CDG Girls High School, Wahdat Colony, Lahore. (Revised)
Approved 3.925 0.309 4.234 0.000 0.000 0.000 3.825 0.000 3.825 0.000 0.309 0.309
91 151 Reconstruction of complete building of CDG Girls High School, Sitara Colony, Lahore (Phase-ii)
Approved 7.500 0.000 7.600 0.000 0.000 6.141 0.000 6.141 0.859 0.000 0.863
92 154 Construction of 5-additional class rooms and toilet block at Govt. High School, Town ship, Main Market, Lahore. (Revised)
Approved 5.304 2.196 7.500 0.000 0.000 3.500 2.196 5.696 1.750 0.000 1.750
93 160 Construction of Hall and Provision of Drinking Water Facilities at Govt. High School, Niaz Baig. Lahore.
Approved 7.500 0.000 7.500 0.000 0.000 0.000 6.739 0.000 6.739 0.761 0.761
CDG Lahore - Consolidated ADP 2012-13
45
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
94 161 Construction of 4-additional class rooms with Veranda, toilet block, Water facilities at Govt. Girls High School, Arriyan, Lahore ( Revised)
Approved 5.550 1.950 7.500 0.000 0.000 3.787 1.650 5.437 1.750 0.300 2.050
Up- Gradation of Schools 2011-12
95 128 Up-Gradation (additional class rooms) of Govt. Middle School, Village Shadewal Majha to High School, Lahore (NA-128)
Approved 4.170 0.000 4.170 0.000 0.000 0.000 1.985 0.000 1.985 2.185 2.185
96 157 Up-gradation (additional class rooms) of Govt. Girls Primary School, Nathoki Lahore Cantt to Middle Level (pp-157).
Approved 4.170 0.000 4.170 0.000 0.000 0.000 0.000 0.000 0.000 4.170 4.170
97 160 Up-gradation (additional class rooms) of Govt. Girls Middle School, Bhogan Nishter Town, Lahore (pp-160)
Approved 4.170 0.000 4.170 0.000 0.000 1.300 0.000 1.300 2.870 2.870
98 161 Up-gradation (additional class rooms) of Govt. Girls Primary School, Manak, Lahore (pp-161).
Approved 4.170 0.000 4.170 0.000 0.000 1.200 0.000 1.200 2.970 2.970
Missing Facilities in Schools 2011-12
99 161 Raising Boundary Wall & Renovation of Existing Building in Govt. Elementry School Pajian Lahore (pp-161).
Approved 2.992 0.000 2.992 0.000 0.000 2.500 0.000 2.500 0.492 0.492
100 161 Construction of Toilet Block Drinking water facility in Govt. Girls High School Arrian Lahore. (pp-161)
Approved 1.004 0.000 1.004 0.000 0.000 0.000 0.000 1.004 1.004
101 161 Construction of Toilet Block in Govt. Girls Primary school Bhalli Gill, Lahore. (pp-161)
Approved 0.504 0.000 0.504 0.000 0.000 0.085 0.000 0.085 0.419 0.419
Total Education 399.558
CDG Lahore - Consolidated ADP 2012-13
46
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
ROAD & STREETS
ADP Scheme
102 121 150 114 Construction of Main Road from Sheikh General store to Sabzazar Main Road C-Block
Approved 4.662 4.662 3.128 0.000 3.128 0.000 0.000 0.000 3.128 3.128
103 122 147 95,96
Rehabilitation of Jail Road, Lahore
Approved 23.770 23.770 16.886 0.000 16.886 0.000 0.000 0.000 16.886 16.886
104 118 138 9 Improvement of Ravi Road from Badami Bagh over Head Brodge to Fruit Market, Lahore & Improvement / Reconstruction of Road inside Fruit Mandi, Foot Path & Green Belt
Approved 15.401 15.401 0.700 0.000 0.700 10.716 0.000 10.716 1.308 1.308
105 129 159 146 Improvement Rehebilitation of Road from Khana Nau Chedu Kang Shrif Jia Baggaj kot Arian, Length k.m 4+00 to to 15.8 km=11.8 km
Approved 71.550 71.550 19.033 0.000 19.033 6.900 0.000 6.900 11.211 11.211
106 126 152 129 Construction of Tuff Tiles Amir Market Katchi Abadi Market & Jatti Market. Atta Turk Block, Noshahi Market, Aurangzaib Block, Garden Town, Lahore.
Approved 1.460 1.460 0.390 0.000 0.390 0.000 0.000 0.000 0.390 0.390
107 126 152 116 Rehabilitation of Road from Jinnah Hospital to Round About Fasil Town, Lahore.
Approved 21.551 21.551 0.050 0.000 0.050 0.000 0.000 0.000 0.050 0.050
108 Construction of Road Divider in front of CCPO Office, Lahore.
Approved 3.445 3.445 3.445 0.000 3.445 0.000 0.000 0.000 3.445 3.445
(Adda Plot to Mull Adda)
109 128 161 124 Widening / Improvement of Road from Adda Plot to Mall Adda Length = 9.22 km (Group-1) (Land Acquisition)
Approved 77.230 0.000 77.230 2.000 0.000 2.000 0.000 0.000 0.000 2.000 0.000 2.000
110 128 161 124 Widening / Improvement Approved 74.768 0.000 74.768 2.000 0.000 2.000 0.000 0.000 0.000 2.000 0.000 2.000
CDG Lahore - Consolidated ADP 2012-13
47
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
of Road from Adda Plot to Mall Adda Length = 9.22 km (Group-ii) (Land Acquisition)
111 128 161 124 Widening / Improvement of Road from Adda Plot to Mall Adda (km 0.00 to km4.75 (Group-1). (km 4.75 to 9.22 (Group-II), (km 0.00 to 9.22 (Group-III)
Approved 359.835 0.000 359.835 196.523 0.000 196.523 83.438 0.000 83.438 89.868 0.000 89.868
114 124 Widening / Improvement of Entrance Road Forensic Laboratory Near Thokar Multan Roads, Lahore (Length = 1573 Rft),
Approved 20.995 0.000 20.995 0.000 0.000 0.000 15.210 0.000 15.210 5.755 5.755
115 Rehabilitation of Davis Road, Lahore. (Revised)
Approved 45.914 0.000 45.914 0.000 0.000 0.000 21.664 0.000 21.664 24.250 24.250
116 Rehabilitation of Davis Road, Lahore.
Approved 48.788 0.000 48.788 0.000 0.000 0.000 28.419 0.000 28.419 20.369 20.369
117 Construction of Metaled Road from Ferozpur Road to Masjid-E-Ibrahim and Link PCC street Masjid-E-Ibrahim to Makhan Shah Darbar Asif town, 21-km Ferozpur road, Lahore.
Approved 4.994 0.000 4.994 0.000 0.000 0.000 2.000 0.000 2.000 2.994 0.000 2.994
118 Improvement and Widening of Sultan Ahmed Road, from Naqsha stop to Malik Chowk.
Approved 37.800 0.000 37.800 0.000 0.000 0.000 10.682 0.000 10.682 27.118 27.118
119 Construction of PCC Imam Bargah Khadooja Tul Kubra wali Gali Multani Colony, UC-35, Lahore.
Approved 3.393 0.000 3.393 0.000 0.000 0.000 1.000 0.000 1.000 2.393 2.393
120 Improvement of New Garcy Brier Sher Pao Bridge, Lahore. (Revised)
Approved 19.136 0.000 19.136 0.000 0.000 0.000 12.143 0.000 12.143 7.746 7.746
121 Rehabilitation of Road from Branderth Road Shah Alam Market, Lahore. (Revised)
Approved 20.370 0.000 20.370 0.000 0.000 0.000 9.364 0.000 9.364 11.006 11.006
CDG Lahore - Consolidated ADP 2012-13
48
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
122 Rehabilitation of Road from Branderth Chowk to Eik Moria Pull, Lahore.
Approved 9.998 0.000 9.998 0.000 0.000 0.000 0.000 0.000 0.000 9.998 9.998
123 Construction of Road start from Julkey stops to Budokay village, pp- 159, NA-129, Lahore.
Approved 2.814 0.000 2.814 0.000 0.000 0.000 0.000 0.000 0.000 2.814 2.814
124 Rehabilitation of Race Course Road, Lahore.
Approved 66.281 0.000 66.281 0.000 0.000 0.000 66.148 0.000 66.148 0.133 0.133
City Package Schemes
125 120 140 79 Carpeting of Rashid Street Saadi Park, Chiragh Din Road (Portion) from Kala Pehalwan to Temple Road and St # 5 Muslim Colony UC-79
Approved 2.500 0.000 2.500 1.271 0.000 1.271 0.987 0.000 0.987 0.284 0.000 0.284
126 120 140 80 PCC and Sewerage St # 26 Lower Mall Road and Liaqatabad Links UC-80
Approved 1.500 0.000 1.500 0.548 0.000 0.548 0.350 0.000 0.350 0.198 0.000 0.198
127 120 139 80 Construction St no 1 Ilyas park with Links out Fall Road
Approved 3.500 0.000 3.500 0.766 0.000 0.766 0.732 0.000 0.732 0.034 0.000 0.034
128 120 140 80 Carpeting & Sewerage Firdous Park, Jhori Park Ganga st Sanat Nagar UC-80
Approved 2.000 0.000 2.000 0.717 0.000 0.717 0.280 0.000 0.280 0.437 0.000 0.437
129 120 139 80 Carpeting of Road Mula Bukhsh Chowk / PCC of Shah Jahan Road and Drainage Jhogian Baway Opposite Lady Waling Hospital Ravi Road, Lahore.
Approved 2.500 0.000 2.500 0.595 0.000 0.595 0.385 0.000 0.385 0.210 0.000 0.210
130 120 140 81 PCC St No 4,5,6 Prem Nagar UC-81
Approved 1.800 0.000 1.800 0.176 0.000 0.176 0.000 0.000 0.000 0.176 0.000 0.176
131 120 140 81 Tuff Tiles Prem Nagar Ground Block No 10 UC-81
Approved 0.700 0.000 0.700 0.070 0.000 0.070 0.000 0.000 0.000 0.070 0.000 0.070
132 120 140 81 PCC Khaleeq Butt Wali Gali with link Muslim Colonhy UC-81
Approved 1.500 0.000 1.500 0.113 0.000 0.113 0.000 0.000 0.000 0.113 0.000 0.113
133 120 140 82 Improvement / Carpeting Approved 5.000 0.000 5.000 0.625 0.000 0.625 0.152 0.000 0.152 0.473 0.000 0.473
CDG Lahore - Consolidated ADP 2012-13
49
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
of Alam Gir Road from Noori Building to Akhari Bus stop Islam pura UC-82
134 120 139 83 Carpeting of Islam Street Shrif Park Link Rasheed Street Qureshi Building Farooq-E-Azam park UC-83
Approved 2.000 0.000 2.000 0.671 0.000 0.671 0.461 0.000 0.461 0.210 0.000 0.210
135 120 139 83 PCC Bilal Street Ahmad Street Durani Road Chohan Park UC-83
Approved 1.600 0.000 1.600 0.154 0.000 0.154 0.000 0.000 0.000 0.154 0.000 0.154
136 120 139 83 Tuff Tiles Jannat Street Nawaz Street Rafique Street Links Chohan Park UC-83
Approved 1.500 0.000 1.500 0.184 0.000 0.184 0.116 0.000 0.116 0.068 0.000 0.068
137 120 139 85 PCC Sardar Street with Links Shafi Park Sanda near Takia Raijian Wala and Shah Jahan street Sanda UC-85
Approved 2.000 0.000 2.000 0.540 0.000 0.540 0.456 0.000 0.456 0.084 0.000 0.084
LRRP (Phase-II) Badami Bagh Package Schemes
138 118 138 FWO Links Street Main Bazar Data Nagar, L=2050 Rft (2nd Revised)
Approved 16.810 0.000 16.810 4.760 0.000 4.760 4.761 0.000 4.761 0.789 0.789
139 118 138 FWO Links Street Chowk Data Nagar to Railway Crossing L-1125 Rft (3rd Revised)
Approved 13.041 0.000 13.041 0.152 0.000 0.152 0.000 0.000 0.000 0.152 0.152
140 118 138 FWO Links Street Mehmood Ghaznavi Street Banghali Bagh, L=5230 Rft
Approved 12.217 0.000 12.217 1.681 0.000 1.681 0.000 0.000 0.000 1.681 1.681
141 118 138 FWO Construction of Rigid Pavement Elahi Buksh Road, L=1000 Rft (1st Revised)
Approved 14.795 0.000 14.795 2.549 0.000 2.549 0.000 0.000 0.000 2.549 2.549
142 118 138 FWO Construction of Road from Pedo Factory Railway Godwns, L=1000 Rft
Approved 5.466 0.000 5.466 0.058 0.000 0.058 0.000 0.000 0.000 0.058 0.058
143 118 138 FWO Construction of Rigid Pavement Aslam Road, Data Nagar, L=5500 Rft (4 Revised)
Approved 51.162 0.000 51.162 20.000 0.000 20.000 9.866 0.000 9.866 1.924 1.924
LRRP (Phase-II) Shahdara Package Schemes
CDG Lahore - Consolidated ADP 2012-13
50
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
144 118 138 7 Rehabilitation of Main Bazar Road Shahdara, Lahore. (1st Revised)
Approved 37.595 0.000 37.595 5.000 0.000 5.000 0.000 0.000 0.000 14.003 14.003
145 118 138 7 Construction of road from Chowk Siraj Park to Chowk Jhalaran, Jhalaran Colony to Paracha Colony Graveyard and main Paracha Colony, Shahdara (2nd Revised)
Approved 8.710 0.000 8.710 2.488 0.000 2.488 0.000 0.000 0.000 2.488 2.488
146 118 138 7 Construction of Old Narowala Road Shahdara, Lahore. (4th Revised)
Approved 25.133 0.000 25.133 5.000 0.000 5.000 0.000 0.000 0.000 15.893 15.893
147 118 138 7 Construction of Road Muhammad Din Fan Chowk to Farooq-e-Azam Chowk Shahdara, Lahore. (1st Revised)
Approved 3.866 0.000 3.866 1.479 0.000 1.479 0.000 0.000 0.000 1.479 1.479
148 118 138 7 Rehabilitation of road from Shahdara Mor to Old Ravi Bridge to Jahangir Tomb Lahore. (1st Revised)
Approved 43.955 0.000 43.955 5.000 0.000 5.000 0.000 0.000 0.000 18.679 18.679
149 118 138 7 Construction of Lajpat Road with Concrete Paver Shahdara, Lahore, (3rd Revised)
Approved 30.155 0.000 30.155 10.000 0.000 10.000 0.000 0.000 0.000 18.447 18.447
150 118 138 7 Carpeting from Railway Crossing Clifton Colony to Shahdara Hospital (1st Revised)
Approved 3.975 0.000 3.975 2.692 0.000 2.692 0.000 0.000 0.000 2.685 2.685
151 118 138 7 Construction of Road from Begum Bagh to Miraj Park, Lahore, (Revised)
Approved 5.964 0.000 5.964 3.020 0.000 3.020 0.000 0.000 0.000 3.020 3.020
152 118 138 7 Construction of Street / Sewerage in kot Muhammad Hussain Shahdara, Lahore. (1st Revised)
Approved 1.394 0.000 1.394 0.491 0.000 0.491 0.000 0.000 0.000 0.491 0.491
153 118 138 7 Construction of Mehmood Road with concrete paver Shahdara, Lahore. (1st
Approved 7.430 0.000 7.430 3.506 0.000 3.506 0.000 0.000 0.000 3.506 3.506
CDG Lahore - Consolidated ADP 2012-13
51
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Revised)
154 118 138 7 Construction of Street / Sewerage Jhangir park Shahdara, Lahore. (4th Revised)
Approved 18.572 0.000 18.572 5.000 0.000 5.000 0.000 0.000 0.000 11.129 11.129
155 118 138 8 Construction of Jia Mousa Bazar Shahdara, Lahore. (1st Revised)
Approved 10.468 0.000 10.468 6.137 0.000 6.137 0.000 0.000 0.000 6.137 6.137
156 118 138 8 Construction of Road Makki Masjid road Boora Park, Lahore. (1st Revised)
Approved 6.892 0.000 6.892 2.547 0.000 2.547 0.000 0.000 0.000 2.547 2.547
157 118 138 7 Construction of Approach Road Railway Station Larex Colony, Shahdara, Lahore. (1st Revised)
Approved 6.579 0.000 6.579 1.484 0.000 1.484 0.000 0.000 0.000 1.484 1.484
158 118 138 7 Construction of Road from Toll Plaza to Old Ravi Bridge Shahdara, Lahore. (1st Revised)
Approved 2.582 0.000 2.582 1.120 0.000 1.120 0.000 0.000 0.000 1.120 1.120
159 118 138 7 Construction of Road with Concrete paver Sui Gas Road Shahdara, Lahore. (1st Revised)
Approved 10.511 0.000 10.511 4.007 0.000 4.007 0.000 0.000 0.000 4.007 4.007
160 118 138 5 Construction of Main Dhair Road Bandook Sian Road and Majeed park to Qaiser Town, Shahdara, Lahore, (3rd Revised)
Approved 46.191 0.000 46.191 8.000 0.000 8.000 0.000 0.000 0.000 18.367 18.367
161 118 138 7 Construction of Road from Jhalanran chowk to Gorey Shah to Ladhey Shahd Road Shahdara, Lahore. (1st Revised)
Approved 10.005 0.000 10.005 2.474 0.000 2.474 0.000 0.000 0.000 2.474 2.474
162 118 137 2 Construction of Road with Concrete Paver Main Baazar Yousuf park (3rd Revised)
Approved 11.916 0.000 11.916 7.148 0.000 7.148 0.000 0.000 0.000 7.148 7.148
163 118 138 4 Construction of Road / Drain Haji Kot Kala Kathi road, Lahore, (1st Revised)
Approved 6.150 0.000 6.150 6.150 0.000 6.150 0.000 0.000 0.000 6.150 6.150
164 118 138 4 Rehabilitation of Main Road Nain Sukh (3rd
Approved 9.383 0.000 9.383 4.230 0.000 4.230 0.000 0.000 0.000 4.230 4.230
CDG Lahore - Consolidated ADP 2012-13
52
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Revised)
LRRP (PHASE-II) NA_119 (PP-141 & 142) Schemes
165 119 142 SAP Improvement of Road from Madina Chowk to Bund Road (Shahbaz Road) L=4500 W=17-1/2. (1st Revised)
Approved 21.807 0.000 21.807 9.000 0.000 9.000 0.000 0.000 0.000 9.000 9.000
Big City Package Schemes
166 118 137 8 Construction of Malik Sharif Road, Begum Kot Near Baradari Road, Lahore.
Approved 46.256 0.000 46.256 36.293 0.000 36.293 0.000 0.000 0.000 36.293 36.293
PP-160 MPA Package Govt. of Punjab Funding Schemes
167 128 160 119 Construction of Metaled Road, Remaining part of Bypass Halloki Road PP-160 (L=1400 Rft).
Approved 2.253 0.000 2.253 2.070 0.000 2.070 0.000 0.000 0.000 2.070 2.070
168 128 160 144 Rehabilitation of Road from Defense Road to Tibba Village along Rahi Nallah PP-160 (L=1.68 km)
Approved 6.517 0.000 6.517 4.828 0.000 4.828 4.400 0.000 4.400 0.428 0.428
169 128 160 117 Rehabilitation of Road from Jamia Masjid to 246 Shahbaz block and Street in Azam Garden PP-160 (L=1600 Rft)
Approved 1.645 0.000 1.645 0.995 0.000 0.995 0.000 0.000 0.000 0.605 0.605
TIED GRANT GENERAL
(Rs. 6.857 M Transfer to PHA from Rs. 124.700 M)
170 141 Construction of Link Road from Charrar Drain (Combined Factor) to Ayshiana Housing Project, Lahore, (Revised)
Approved 124.700 0.000 124.700 49.754 0.000 49.754 40.176 0.000 40.176 84.524 84.524
Raiwind Schemes
171 Rehabilitation of Lahore Road Tablighi Moot No-4 (Inside Raiwind City) Parallel Railway Line Length=6600 Rft
Approved 27.538 0.000 27.538 14.070 0.000 14.070 0.088 0.000 0.088 13.992 13.992
172 Rehabilitation of Raiwind Manga Road KM No. 1 & 2
Approved 17.983 0.000 17.983 4.961 0.000 4.961 0.049 0.000 0.049 4.912 4.912
CDG Lahore - Consolidated ADP 2012-13
53
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
(Inside Raiwind City) Length = 4800 Rft
173 Rehabilitation of Raiwind Sundor Road KM No. 15 (Inside Raiwind City) Length = 3600 Rft
Approved 16.576 0.000 16.576 4.099 0.000 4.099 0.000 0.000 0.000 4.099 4.099
174 Reconstruction of Road from Main Raiwind Road to Khayaban-e-Jinnah Road via Govt. School Ali Raza Abad NA-128 Length= 2.10 KM
Approved 18.092 0.000 18.092 17.660 0.000 17.660 11.449 0.000 11.449 6.211 6.211
Special Dev. Package PP-141 Roads
175 119 141 Expand of Main Swami Nager Road, Lahore. (PP-141) (2nd Revised)
Approved 15.958 0.000 15.958 15.396 0.000 15.396 13.588 0.000 13.588 1.943 1.943
176 119 141 Construction of Metal Road Chah Meeran Road to Nelam Cinema. Lahore. (PP-141) Length= 2200 FT (Revised)
Approved 9.613 0.000 9.613 9.427 0.000 9.427 8.009 0.000 8.009 0.908 0.908
177 119 141 Construction of PCC Road Chamra Mandi Godam Road. Lahore. (PP-141) Length = 1000 FT (2nd Revised)
Approved 10.378 0.000 10.378 5.103 0.000 5.103 10.102 0.000 10.102 0.276 0.276
178 119 141 Construction of RCC Main Shadbagh Road. 3-Roads, Lahore. (PP-141) Length= 1000FT (Revised)
Approved 12.788 0.000 12.788 3.898 0.000 3.898 3.667 0.000 3.667 0.231 0.231
179 119 141 Improvement of Road from Chowk Neelam Cinema to Kachu Pura, Lahore. (Revised)
Approved 8.605 0.000 8.605 9.545 0.000 9.545 6.042 0.000 6.042 2.563 2.563
180 119 141 Construction of Main Road Kachi Abadi slab of Drain and PCC of Link to Badami Bagh, Railway Station, Lahore,
Approved 6.465 0.000 6.465 2.432 0.000 2.432 2.104 0.000 2.104 0.328 0.328
181 119 141 Carpeting of Road from Fiaz Bagh to Railway Quarters, Lahore.
Approved 4.593 0.000 4.593 1.110 0.000 1.110 0.431 0.000 0.431 0.679 0.679
CDG Lahore - Consolidated ADP 2012-13
54
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Special Dev. Package PP-143 Roads
182 123 143 Construction of PCC Molvi Azam Wali Gali UC-16, Taj Ghazi Park in UC-14 & Aurangzaib wali Gali in UC-14, Construction of Nala PP-143, Lahore. Length = 2350 FT
Approved 3.000 0.000 3.000 2.594 0.000 2.594 1.921 0.000 1.921 0.866 0.866
Special Dev. Package PP-144 Roads
183 123 144 Improvement of Street, Road Behind Police station ESA Abad in UC-32, Lahore, (PP-144) Length= 2900 FT
Approved 2.873 0.000 2.873 1.531 0.000 1.531 1.503 0.000 1.503 0.028 0.000 0.028
184 123 144 Improvement of National Road in UC-37, Lahore, (PP-144) Length= 2000 FT
Approved 5.362 0.000 5.362 4.811 0.000 4.811 4.650 0.000 4.650 0.161 0.161
185 123 144 Construction of Girls College Road in UC-38, Lahore: (PP-144) Length = 1400FT
Approved 3.571 0.000 3.571 3.547 0.000 3.547 3.503 0.000 3.503 0.044 0.044
186 123 144 Construction of Main Street ,Link Street Malik Pur UC-37, Lahore. (Revised)
Approved 4.514 0.000 4.514 2.344 0.000 2.344 2.341 0.000 2.341 0.077 0.077
187 123 144 Construction of Ibrahim Colony Road and Links in UC-35, Lahore. (PP-144) Length= 2980 FT
Approved 4.881 0.000 4.881 4.881 0.000 4.881 4.839 0.000 4.839 0.042 0.042
188 123 144 Construction of Madhu Purani Lal Hussain Road and links UC-34, Lahore, (PP-144) Length= 4950 FT
Approved 9.243 0.000 9.243 3.659 0.000 3.659 3.642 0.000 3.642 0.017 0.017
189 123 144 Construction of Atta Road Purani Eid Gah Near Shalimar Garden in UC-36, Lahore
Approved 5.163 0.000 5.163 5.363 0.000 5.363 5.053 0.000 5.053 0.110 0.110
190 123 144 Construction of RCC Sultan Mehmood Road, Lahore, (PP-144) Length= 1500 FT
Approved 6.910 0.000 6.910 1.351 0.000 1.351 1.016 0.000 1.016 0.335 0.335
Special Dev. Package NA-128 Roads
CDG Lahore - Consolidated ADP 2012-13
55
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
191 128 Rehabilitation / Construction of PCC Road and Drain from Hajveri Chowk to Punj Grian Chung NA-128, Length= 1200 FT L(Drain)= 1200Rft (Revised)
Approved 7.998 0.000 7.998 7.998 0.000 7.998 7.647 0.000 7.647 0.351 0.351
Dev. Schemes PP-142 Package 2010-11
192 119 142 27 Carpeting of whole Main Road inside Akbari Mandi Lahore UC-27
Approved 5.401 0.000 5.401 5.401 0.000 5.401 5.282 0.000 5.282 0.119 0.119
193 119 142 27 Construction /PPC of Main Road Sheranwala Gate UC-27
Approved 1.648 0.000 1.648 1.648 0.000 1.648 0.975 0.000 0.975 0.673 0.673
194 119 142 28 Construction of Road Lohari Gate Adjacent office UC_28
Approved 2.451 0.000 2.451 2.451 0.000 2.451 1.930 0.000 1.930 0.521 0.521
195 119 142 29 Recondition / Carpeting of Road from Noor Mahallah Samian UC-29
Approved 2.676 0.000 2.676 2.676 0.000 2.676 2.505 0.000 2.505 0.171 0.171
196 119 142 30 PCC Main Kahmiri Gate UC-30
Approved 1.473 0.000 1.473 1.473 0.000 1.473 0.000 0.000 0.000 1.473 1.473
197 119 142 27 Carpeting Sadda Karan Androon Mochi Gate Lahore UC-27
Approved 3.768 0.000 3.768 3.768 0.000 3.768 3.540 0.000 3.540 0.228 0.228
198 119 142 Rehabilitation and Repair of Hospital Rood (Opposite to Akbar Market)
Approved 7.496 0.000 7.496 1.744 0.000 1.744 1.648 0.000 1.648 0.096 0.096
199 119 142 74 Rehabilitation of Road Shah Abdul Muali to Lahore Hotel UC-74
Approved 1.462 0.000 1.462 1.462 0.000 1.462 1.388 0.000 1.388 0.074 0.074
200 119 142 74 PCC Flooring Main Road Pathi Ground UC-74
Approved 1.963 0.000 1.963 0.676 0.000 0.676 0.364 0.000 0.364 0.312 0.312
201 119 142 74 PCC Flooring behind Ghala Mandi Land Bazar Near Office UC-74 Opposite Do Moria Pull
Approved 5.244 0.000 5.244 4.636 0.000 4.636 2.035 0.000 2.035 2.601 2.601
202 119 142 77 Rehabilitation of Road Dalgran Chowk to Dil Muhammad Road UC-77
Approved 1.418 0.000 1.418 0.292 0.000 0.292 0.270 0.000 0.270 0.022 0.022
203 119 142 77 Rehabilitation of Abdul Approved 3.954 0.000 3.954 2.901 0.000 2.901 2.827 0.000 2.827 0.074 0.074
CDG Lahore - Consolidated ADP 2012-13
56
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Karim road Qila Gujar Singh UC-77
204 119 142 77 Rehabilitation Usmania Colony Through Radio Station UC-77
Approved 1.036 0.000 1.036 0.161 0.000 0.161 0.000 0.000 0.000 0.161 0.161
205 119 142 Rehabilitation of Main Bazar Qila Gujar Singh Up to Police Line
Approved 2.445 0.000 2.445 0.908 0.000 0.908 0.744 0.000 0.740 0.164 0.164
206 119 142 Rehabilitation of Montgomery park Road UC-37
Approved 1.695 0.000 1.695 0.068 0.000 0.068 0.000 0.000 0.000 0.068 0.068
GENERAL SCHEMES
207 Acqusation of Land / Assessment of structure for Construction of Dual Carriageway Approach Road from Bakri Road to Ashiyana Housing Scheme No, II, Lahore
Approved 284.106 0.000 284.106 0.000 0.000 0.000 44.396 0.000 44.396 239.310 239.710
208 Construction & Widening of Road from Ferozpur to Dfense Road along Hadyara Drain Kacha Lahore.
Approved 279.419 0.000 279.419 0.000 0.000 0.000 93.429 0.000 93.429 185.990 0.000 185.990
209 Construction of Open Drain (size 3' X 4' at Joggian UC-14. Lahore. (Remaining Portion)
Approved 3.891 0.000 3.891 0.000 0.000 0.000 1.000 0.000 1.000 2.891 2.891
210 Rehabilitation of Allama Iqbal Road , Lahore (Rs< 50 M to WSA)
Approved 593.259 0.000 593.259 0.000 0.000 0.000 293.571 0.000 293.571
115.867 115.867
Large City Package Rs. 500 million Schemes
211 141 Construction of PCC road in Main Bazar Soofia Abad from Ferozpur Road to Jamia Mosque Rubbani Length = 1.3 km, UC-141
Approved 13.436 0.000 13.436 0.000 0.000 13.118 0.000 13.118 0.318 0.318
212 141 Construction of PCC and Roads start from Hakim Chowk up to Combined Fabric Factory Attari Saraba Ferozpur Road,
Approved 18.049 0.000 18.049 0.000 0.000 12.941 0.000 12.941 5.100 5.100
CDG Lahore - Consolidated ADP 2012-13
57
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Lahore. UC-141
213 Rehabilitation of Queens Road (Fatima Jinnah), Lahore (Amended).
Approved 70.850 0.000 70.850 0.000 0.000 64.596 0.000 64.596 6.254 6.254
214 Rehabilitation of Shalimar link Road
Approved 51.800 0.000 51.800 0.000 0.000 43.911 0.000 43.911 7.889 7.889
215 Rehabilitation of Road from Begum Kot Chowk to Near Ravi Bridge via Farrukha Abad Baradari Road, Shahdara, Lahore, (Rs, 14.996 M to PHA)
Approved 75.000 0.000 75.000 0.000 0.000 54.829 0.000 54.829 5.175 5.175
216 Rehabilitation of Road Link Jahangir Tomb Shahdra, Lahore.
Approved 50.000 0.000 50.000 0.000 0.000 15.188 0.000 15.188 34.812 34.812
217 Rehabilitation / Improvement of Road from Bath Billage to Nanoo Dogar Village
Approved 10.950 0.000 10.950 0.000 0.000 8.366 0.000 8.366 2.584 2.584
218 Rehabilitation of Lytton Road , Lahore.
Approved 30.000 0.000 30.000 0.000 0.000 25.441 0.000 25.441 4.559 4.559
219 Rehabilitation of Road from Naulakha Police Station to Eik Moria Pull.
Approved 38.207 0.000 38.207 0.000 0.000 38.091 0.000 38.091 0.116 0.116
220 Rehabilitation / Improvement of Road from Eik Moria Pull to Darbar Haider Sian (Circular Road), Lahore.
Approved 95.496 0.000 95.496 0.000 0.000 75.944 0.000 75.944 19.556 19.556
221 Widening / Improvement of Road from Rohi Nallah Road to Basic Health Unit Bullar Village, PP-159, Lahore,
Approved 9.955 0.000 9.955 0.000 0.000 9.275 0.000 9.275 0.680 0.680
222 Rehabilitation of Road from Bedian Road to Bhutta Chowk and Foju Akrm To Gohawa Village, Lahore.
Approved 7.500 0.000 7.500 0.000 0.000 5.392 0.000 5.392 2.108 2.108
223 Rehabilitation of Durand Road Lahore, (Amended)
Approved 21.500 0.000 21.500 0.000 0.000 21.489 0.000 21.489 0.011 0.011
CDG Lahore - Consolidated ADP 2012-13
58
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
224 Rehabilitation of Empress Road Lahore, (L=1.38 km w=35') 2nd Amended
Approved 24.000 0.000 24.000 0.000 0.000 21.707 0.000 21.707 3.773 3.773
225 Construction of Road from Ghousia Chowk, College Road to Hakim Chowk Johar Town, Lahore (L=1.08 km w=20')
Approved 13.830 0.000 13.830 0.000 0.000 2.571 0.000 2.571 11.259 11.259
226 Widening / Improvement Construction of Road from Adda plot to Mall Adda right side of distributor (L=5.17 km w=20')
Approved 17.130 0.000 17.130 0.000 0.000 5.022 0.000 5.022 12.108 12.108
227 Rehabilitation of Zarar Shaheed Road Lahore, (L=1.10 km w=24') Amended
Approved 38.000 0.000 38.000 0.000 0.000 37.827 0.000 37.827 0.173 0.173
228 Rehabilitation Widening and Improvement of Jallo Park Link Road up to Railway Phatic Lahore.
Approved 24.898 0.000 24.898 0.000 0.000 24.794 0.000 24.794 0.104 0.104
229 Rehabilitation of Road at Fasil Park UC_04
Approved 6.233 0.000 6.233 0.000 0.000 3.131 0.000 3.131 3.099 3.099
230 Construction of Road Main Road along Rohi Nallah via Dera Mian Siraj PP-160 (Revised)
Approved 21.895 0.000 21.895 0.000 0.000 9.275 0.000 9.275 12.620 12.620
Rs. 230.000 MILLION PACKAGES
Rs. 40.000 M Divert to Scheme "Darbar Haider Sian" in Rs. 500.000 M PACKAGE
Road Schemes
231 118 PCC street Main Janua st Muslim park Rehan Street Arfat Park Jia Mousa Shahdara Lahore.
Approved 2.107 0.000 2.107 0.000 0.000 1.846 0.000 1.846 0.261 0.261
232 118 PCC Street Nursery Chowk to Tufail Butt Chowk k Jia Mousa Shahdara Lahore.
Approved 1.445 0.000 1.445 0.000 0.000 1.288 0.000 1.288 0.157 0.157
233 118 PCC of St No 8/A+B Link Lajpat Road Shahdara Lahore
Approved 1.164 0.000 1.164 0.000 0.000 0.000 0.000 1.164 1.164
234 118 PCC Street Fazal Abass Approved 2.657 0.000 2.657 0.000 0.000 1.924 0.000 1.924 0.733 0.733
CDG Lahore - Consolidated ADP 2012-13
59
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Gujar Fasil Park Shahdara Lahore
235 118 PCC of Main street Mosque Saddique Ali park Abass Insari etc Haji Kot Shahdara Road Shahdara Lahore
Approved 2.876 0.000 2.876 0.000 0.000 2.072 0.000 2.072 0.804 0.804
236 118 PCC of jinnah Road Masjid Ibrahim to Masjid Khajoor Wala Chowk Shahdara
Approved 2.311 0.000 2.311 0.000 0.000 0.000 0.000 2.311 2.311
237 118 PCC Street of Tiba Dandy Wada Awais Qarni park and Mian Liaqat Street Kot llam Din Shahdara
Approved 1.067 0.000 1.067 0.000 0.000 0.622 0.000 0.622 0.445 0.445
238 118 PCC Street Sardar Khan, Factory Phulian Wali Latif Park and street shukar sui Gas Hassan Colony Shahdara Lahore
Approved 1.197 0.000 1.197 0.000 0.000 0.000 0.000 1.197 1.197
239 118 PCC street Shah Colony Bazzar St No 14 and Masjid Ahal-E-Hadees Ashfaq Paracha Colony Shahdara
Approved 1.751 0.000 1.751 0.000 0.000 1.041 0.000 1.041 0.710 0.710
240 118 PCC Latif Sohil Road Shahdara
Approved 1.154 0.000 1.154 0.000 0.000 0.447 0.000 0.447 0.707 0.707
241 118 PCC of Master Muneer St Muhallah Bandook Shahdara Town Lahore
Approved 1.226 0.000 1.226 0.000 0.000 0.811 0.000 0.811 0.415 0.415
242 118 PCC Street Masjid Wali and Doctor Javid Wali New Ravi Kalifton Shahdara Lahore
Approved 1.382 0.000 1.382 0.000 0.000 1.315 0.000 1.315 0.067 0.067
243 118 Providing and Tuff Tiles in Darbar Ahmed Shah Wali Takia Khusrian Shahdara
Approved 1.874 0.000 1.874 0.000 0.000 0.000 0.000 1.874 1.874
244 118 Construction &Boundary Wall and Jungla Cricket Foot Ball Ground and Walkin Track Bound Road
Approved 4.875 0.000 4.875 0.000 0.000 0.000 0.000 4.875 4.875
245 118 PCC Street Molvi Liaqat and Botta Driver Madrassa Darulaum and street Labay
Approved 1.531 0.000 1.531 0.000 0.000 0.334 0.000 0.334 1.197 1.197
CDG Lahore - Consolidated ADP 2012-13
60
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
wali Begum Punch Shahdara
246 118 PCC of Malik Rafi Ran wala Kot Shahab Din Road Shahdara Lahore
Approved 1.103 0.000 1.103 0.000 0.000 0.000 0.000 1.103 1.103
247 118 Construction of PCC street Rehman street No 1 & Links Rehman street NO, 9, Links street No, 13. Mubarak street Electric Market and Link UC-74, Lahore
Approved 3.150 0.000 3.150 0.000 0.000 3.109 0.000 3.109 0.041 0.041
248 118 Construction of PCC Street Rehman Street no 5, Rehman Street No, 7, Link Street D Type Quarter Street No, 16, Shujah Butt UC-74, Lahore
Approved 2.950 0.000 2.950 0.000 0.000 2.723 0.000 2.723 0.227 0.227
249 118 Construction of PCC street & Drams Malki Street No, 182 PCC streets Sohani Street NO. 24 & Links street No, 23, Lahore
Approved 2.390 0.000 2.390 0.000 0.000 1.163 0.000 1.163 1.127 1.127
250 118 Construction of Carpeting Gordwara street Qila Gujar Sing & street No, 43, Mala Ram Park Qila Gujar Sing & Street Nom 43 Mala Ram Park Qila Gujar Sing UC-77, Lahore
Approved 2.330 0.000 2.330 0.000 0.000 2.256 0.000 2.256 0.074 0.074
251 142 74 Construction of PCC Street Gas Quarter Railway Road & Street Mai Bakhtawer UC-74, Lahore
Approved 1.400 0.000 1.400 0.000 0.000 1.291 0.000 1.291 0.109 0.109
252 159 Construction of Road from Lahore Badian Road Km NO. 28 up to Boucher Khana Distributer along its left Bank towards Ferozpur Road, Lahore. (Revised)
Approved 17.982 0.000 17.982 0.000 0.000 15.683 0.000 15.683 2.299 2.299
253 12 PCC Main Street Hussain Park UC-12
Approved 2.025 0.000 2.025 0.000 0.000 1.993 0.000 1.993 0.032 0.032
CDG Lahore - Consolidated ADP 2012-13
61
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
254 12 PCC Street Baba Shadi Hall and Streets Data Nagar UC-12.
Approved 2.043 0.000 2.043 0.000 0.000 0.825 0.000 0.825 1.218 1.218
255 12 PCC Street Imam Bargah Allah Hoo wali Nabi Pura Naveed Park UC-12
Approved 1.524 0.000 1.524 0.000 0.000 1.479 0.000 1.479 0.045 0.045
256 12 PCC Street B-19 Qaddafi Park Badami Bagh Lahore,UC-12
Approved 1.832 0.000 1.832 0.000 0.000 1.790 0.000 1.790 0.042 0.042
Rs. 100.000 MILLION PP-149 PACKAGE
Road Schemes
257 149 84 Construction of PCC Anwar Khan Goli Street Abu Bakar Colony Bund Road Lahore, UC-84
Approved 2.340 0.000 2.340 0.000 0.000 2.317 0.000 2.317 0.023 0.023
258 149 84 Construction of Main Bazzar Ghousia Colony, UC-84, Lahore
Approved 5.652 0.000 5.652 0.000 0.000 3.100 0.000 3.100 2.552 2.552
Rs. 60.000 M FOR MPA/MNA
NA-123 (Allocation of 20.000 million)
259 123 Construction of Chaan Peer Wali Gali Mehar Bashir Colony, Lahore
Approved 2.566 0.000 2.566 0.000 0.000 0.000 0.000 2.566 2.566
260 123 Construction of PCC & Sewer street No. 17.A Chand Park, Street No. 06, Atif park, Iqbal Begum st.. Tawar Wali Goli near Noori Masjid Gulbahar Colony & street No. 2, Rana Clinic Wali Sheller Chowk in UC-35 Lahore,
Approved 2.562 0.000 2.562 0.000 0.000 0.623 0.000 0.623 1.939 1.939
261 123 Construction of PCC Ahmad Wali Gali & link Haji park in UC-15, Lahore.
Approved 0.747 0.000 0.747 0.000 0.000 0.696 0.000 0.696 0.051 0.051
262 123 Construction of PCC Main Chan Miran Road Tangy Wali Adda in Uc-20, Lahore
Approved 2.172 0.000 2.172 0.000 0.000 2.129 0.000 2.129 0.043 0.043
263 123 Construction of PCC street No. 1, 2, Block-A Farooq
Approved 2.590 0.000 2.590 0.000 0.000 2.512 0.000 2.512 0.078 0.078
CDG Lahore - Consolidated ADP 2012-13
62
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Park & Haji Saeed Wali Gali Atif Park in UC-35, Lahore.
264 123 Construction of PCC Street No, 151, Pathanan Wali Shah Abdul Ghani, Street No, 145 Rehman street, Madho Lal Hussain, Yakian Wali Gali Chowk Nagina in UC-34, Lahore.
Approved 1.849 0.000 1.849 0.000 0.000 1.811 0.000 1.811 0.038 0.038
265 123 Construction of PCC Street Hajveri park in UC-35, Lahore
Approved 2.002 0.000 2.002 0.000 0.000 0.000 0.000 2.002 2.002
266 123 Construction of PCC street Muslim park in UC-34, Lahore.
Approved 1.322 0.000 1.322 0.000 0.000 0.000 0.000 1.322 1.322
267 123 Construction of PCC Street No.171 Khursheed Street Madina Colony Street Haji Aray Wali Basharat Road in UC-36, Lahore
Approved 2.440 0.000 2.440 0.000 0.000 0.000 0.000 2.440 2.440
268 123 Construction of PCC Street No-2, link Street Nabipura Arian in UC-33, Lahore
Approved 1.750 0.000 1.750 0.000 0.000 0.000 0.000 1.750 1.750
PP-148 (20.000 M & Rs. 7.200 M to WASA)
269 148 Rehabilitation of Samanabad Girls College Road Hassan Market Road Usman Ghani Road Sardar Street Abdullah Street UC-106. PP. 148.
Approved 4.924 0.000 4.924 0.000 0.000 0.000 0.048 0.000 0.048 4.876 4.876
270 148 Rehabilitation of Bank Colony Sheikh Ghulam Mohi-UD-Din Street Khawajagan Street, Friend Colony Assghar Hameed Bhutta Street, Anwar park UC-105, Lahore.
Approved 2.548 0.000 2.548 0.000 0.000 0.000 0.270 0.000 0.270 2.278 2.278
271 148 Rehabilitation of Karmabad Road Akab School Wali Road Link
Approved 5.328 0.000 5.328 0.000 0.000 0.000 0.513 0.000 0.513 4.815 4.815
CDG Lahore - Consolidated ADP 2012-13
63
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Khalid Street, Khalid Raza Street, Malik Afzal Din Road UC-107, PP-148, Lahore.
PP-149 (Allocation of 20.000 million)
272 149 Construction of PCC Al-Aziz Street Abu Bakar Bazar Street No-51 Tanveer Park Anwar street NO-18 UC-84 & 85, Lahore,
Approved 7.450 0.000 7.450 0.000 0.000 0.000 0.000 0.000 0.000 7.450 7.450
273 149 Construction of PCC Abu Bakar Street Malik park Carpeting of P&D Colony Multan Road Lahore
Approved 4.518 0.000 4.518 0.000 0.000 0.000 0.370 0.000 0.370 4.148 4.148
274 149 Construction of Joy Shah Road, Lahore
Approved 5.000 0.000 5.000 0.000 0.000 0.000 0.351 0.000 0.351 4.649 4.649
275 149 Construction of Carpet New Shalimar Road along with Nallah Gulshan-e-Ravi, Lahore
Approved 3.000 0.000 3.000 0.000 0.000 0.000 0.000 0.000 0.000 3.000 3.000
Rs. 30.000 M Package (PP-161 Rs, 20.000 M + RS. 10.000 M)
276 161 Construction of Road from Melad Chowk to old Markaz Road in Raiwaind City PP-161, Lahore,
Approved 10.269 0.000 10.269 0.000 0.000 0.000 0.439 0.000 0.439 9.830 9.830
277 161 Construction of Road from Multan Road to Jhuggian Shariat Ullah Via Dera Mian Ashraf, PP-161. Lahore
Approved 9.934 0.000 9.934 0.000 0.000 0.000 0.613 0.000 0.613 9.321 9.321
278 161 Construction of Covered Drain Size (2'*2.50') from Govt., Girls Middle School, Maraka Quarters to Rohi Nallah Mohlanwal Multan Road PP- 161, Lahore, (Right Side)
Approved 7.421 0.000 7.421 0.000 0.000 0.000 1.061 0.000 1.061 6.360 6.360
279 161 Construction of PCC and Drain in Pijian Village, PP-161, Lahore,
Approved 2.376 0.000 2.376 0.000 0.000 0.060 0.000 0.060 2.316 2.316
RS. 10.000 MILLION PACKAGE OF HAMZA SHAHBAZ SHARIF OUT OF CDGL OWN FUNDING
CDG Lahore - Consolidated ADP 2012-13
64
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Road schemes
280 Construction of tile Flooring sald Mitha Bazar and Links, Koocha Daroogha Nazool Koocha Saithan, Koocha Mohamdia, Mohalla City Muslim League, Dhian Singh Links Street Gujjar Gali, Kali Mata, Mama Bhanja and links, etc. UC. 30
Approved 1.852 0.000 1.852 0.000 0.000 0.000 0.000 1.852 1.852
281 Construction of tile Flooring Taxali Gate and Links, Juj Latif, Gadi Mohalla Sheikhpurian, Chetram Ali park and Links Street. Etc. UC # 30
Approved 1.899 0.000 1.899 0.000 0.000 0.000 0.000 1.899 1.899
282 Construction of tile Flooring Rim Market, Masjid Begum Shahi, Barood Khana My Da Mandar Pani Wala Talab, Masti Gate, Kashmiri Gate, Kabil mal sooha Bazar, Choona Mandi and Links, etc. UC# 30
Approved 1.916 0.000 1.916 0.000 0.000 0.000 0.000 1.916 1.916
283 Construction of tiles Flooring Sabz pir and Links, Tehsil Bazar and Links, Amna school and Links, Mandar Wali Gali, Havely Dhian Singh, Chowk Tranum Cinema and Links, UC# 30
Approved 1.809 0.000 1.809 0.000 0.000 0.000 0.000 1.809 1.809
284 Construction of tile Flooring Koocha Rehmat Raj, Mohalla Sathan, Khoohi vera, Wadda vera koocha Naqarshianm Mohala Jalootian and Links Street, etc, UC#29
Approved 1.808 0.000 1.808 0.000 0.000 0.000 0.000 1.808 1.808
CDG Lahore - Consolidated ADP 2012-13
65
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
285 Construction of tile Flooring Madan Bhayan Chowk Jhanda, mohalla Goji Tarkhan, Links Street Bismillah, Koocha Phula Nanak, Mohalla jalotian, Links street Ghati Sheesh Mahal, Manja Vera Koocha Sardaran and Links street, etc. UC# 29
Approved 1.818 0.000 1.818 0.000 0.000 0.000 0.000 1.818 1.818
286 Construction of tile Flooring mohalla Samian, Bazar Jaj Latif, Jogi Mohalla, Koocha Pehwana Koocha Faqir khana, Gali Tofail wali, Tabala sheikhan, Street My Gulabo and Links streets etc. UC# 29
Approved 1.896 0.000 1.896 0.000 0.000 0.000 0.000 1.896 1.896
287 Construction of tile Flooring Shah Alam Market and Links Havely Pathran wali, pari Mahal Links street Bazar Sada Karan and Links, etc. UC # 28
Approved 1.887 0.000 1.887 0.000 0.000 0.000 0.000 1.887 1.887
288 Construction of tile Flooring Shah Alam market and Links Havely Pathran wali, Pari mahal links street Bazar sada karan and links. Etc UC# 28
Approved 1.895 0.000 1.895 0.000 0.000 0.000 0.000 1.895 1.895
289 Construction of tile Flooring Koocha Pir sherazi koocha pir Bholla, Chowk Matti, Koocha Ghousia Koocha Elahi Baksh Links Street Mari Gate chowk Jhanda Links chowk Bakhari , etc UC# 28
Approved 1.892 0.000 1.892 0.000 0.000 0.000 0.000 1.892 1.892
290 Construction of tile Flooring Links street
Approved 1.884 0.000 1.884 0.000 0.000 0.000 0.000 1.884 1.884
CDG Lahore - Consolidated ADP 2012-13
66
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Khawaja Saad Rafique, sootar Mandi Links Sheesha Moti joray Mori, Bazar wochu wali Bhadur kali katali kapuran soha Bazar Awami Links, etc, UC# 28
291 Construction of tile Flooring Koocha Mashkian and Links street Gujar Gali, Mohalla sheian, kashmirion Tabla Nawabsahab, Mohallah pir Gili Mian Koocha Jahan Khan Havely Mian Khan Kasara Bazar Links Khoocha Chabak swaran, etc, UC# 28
Approved 1.909 0.000 1.909 0.000 0.000 0.000 0.000 1.909 1.909
292 Construction of tile Flooring Main Bazar and Links Chota Mohalla Kakkyzian, Links Gali street koocha, Jahan khan, Pir Gilania, Karadi Mohalla, etc UC# 27
Approved 1.892 0.000 1.892 0.000 0.000 0.000 0.000 1.892 1.892
293 Construction of tile Flooring Androon yakki Gate, Koocha Mali Tali, Main Bazar Alfashian Katri Raja Anand Links, etc, UC# 27
Approved 1.827 0.000 1.827 0.000 0.000 0.000 0.000 1.827 1.827
294 Construction of tile Flooring Mochi Gate link sada karan, Koocha Qazi Khana, Mughal Havely Mohalla Sheian, Kashmirian links Gujar Gali Hatam Hussania Hall Gali Hamam Wali Akbari Mandi and links, etc UC# 27
Approved 1.916 0.000 1.916 0.000 0.000 0.000 0.000 1.916 1.916
295 Construction of tile Flooring Androon Sheiran
Approved 1.900 0.000 1.900 0.000 0.000 0.000 0.000 1.900 1.900
CDG Lahore - Consolidated ADP 2012-13
67
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
wala links Neogaranm Catra Bawa Das Links, Kashhmiri Ghatti, Bangla Ayub Shah, and Androon Kashmiri Rara Talian, etc. UC# 27
DEVELOPMENT PACKAGE FOR MNA / MPA 2011-12
MNA's / MPA's Farm to Market Roads (FMR)
296 128 160 Rehabilitation of Road from Marghzar colony to Niaz Baig Lahore
Approved 10.150 0.000 10.150 0.000 0.000 9.019 0.000 9.019 1.131 1.131
297 128 160 Construction of Road from Multan Road (BATA Factory) to Ali Hussain Abad, Lahore
Approved 5.000 0.000 5.000 0.000 0.000 4.806 0.000 4.806 0.194 0.194
298 128 160 Rehablitation / Imp. Of Multan Road to kot Hayat via Dera kali Khokar, Lahore
Approved 5.182 0.000 5.182 0.000 0.000 4.843 0.000 4.843 0.339 0.339
299 128 160 Rehab. / Imp. Of Road from Canal Bridge Azmir town to Multan Road via Chung village, Lahore
Approved 13.300 0.000 13.300 0.000 0.000 8.083 0.000 8.083 5.217 5.217
300 128 161 Rehabilitation of Road Milad Chowk to Qila samika via Qila sher Shah Singh Manga Mandi Lahore
Approved 7.498 0.000 7.498 0.000 0.000 5.650 0.000 5.650 1.848 1.848
301 128 161 Re.Cont. of Road from Multan Road to jia ka Tibba via Chah Tambooli. Lahore
Approved 12.500 0.000 12.500 0.000 0.000 11.836 0.000 11.836 0.664 0.664
302 128 161 Const. of Road Multan Board to Canal (Hanjerwali) NA-128
Approved 7.568 0.000 7.568 0.000 0.000 6.358 0.000 6.358 1.210 1.210
303 128 160 Const. of Road from Main Road shahpur Kanjran along Shahpur Kanjran Roi Nalla, PP-160, NA-128.
Approved 11.235 0.000 11.235 0.000 0.000 8.097 0.000 8.097 3.138 3.138
304 128 160 Const. of Road from Khanke juggian to Nano Dogar Village. NA-128.
Approved 7.500 0.000 7.500 0.000 0.000 5.190 0.000 5.190 2.310 2.310
CDG Lahore - Consolidated ADP 2012-13
68
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
305 129 160 Rehab. / Imp. Of Road start from Ferozpur Road to Havelian Gajumatta via Qabristan Gajumatta, Lahore
Approved 3.401 0.000 3.401 0.000 0.000 3.287 0.000 3.287 0.114 0.114
306 128 161 Rehab. Of Road from Sui Asal Road to Jado Dheer Village PP-161, NA-128.
Approved 3.500 0.000 3.500 0.000 0.000 3.206 0.000 3.206 0.294 0.294
307 129 160 Rehab. / Imp. Of Road jia Bagga to Chedu village (Remaining Portion)
Approved 14.003 0.000 14.003 0.000 0.000 13.386 0.000 13.386 0.617 0.617
308 129 159 Rehab. Of Road start from Hadayara Drain toward Aashiyana Housing Scheme along Charrar Drain. Lahore
Approved 20.156 0.000 20.156 0.000 0.000 19.110 0.000 19.110 1.046 1.046
309 129 159 Rehab. / Imp. Of Road from Hadyara Drain to Qureshi Wala village, Lahore
Approved 6.895 0.000 6.895 0.000 0.000 6.674 0.000 6.674 0.221 0.221
310 129 159 Rehab. / Imp. Of Road from Old Kahna Main Ferozpur Road up to Gurdwara (Length = 1.2 km) Lahore, NA-129
Approved 7.030 0.000 7.030 0.000 0.000 6.854 0.000 6.854 0.176 0.176
311 129 159 Rehab. / Imp. Of Road to Kartbath, Gaga up to Noorpur village, Lahore (Length = 8.7 km) Lahore NA-129
Approved 25.015 0.000 25.015 0.000 0.000 24.204 0.000 24.204 0.811 0.811
312 130 157 Rehab. / Imp. Of Road Barki to Koiran . (Revised)
Approved 10.310 0.000 10.310 0.000 0.000 9.881 0.000 9.881 0.429 0.429
313 130 157 Rehab. / Imp. Of Road from Ring Road to Karal Pind. (Revised)
Approved 36.512 0.000 36.512 0.000 0.000 33.900 0.000 33.900 2.612 2.612
314 130 157 Carpeting of Main Laka Dair Road
Approved 7.974 0.000 7.974 0.000 0.000 0.189 0.000 0.189 7.785 7.785
315 145 Construction & Rehabilitation of Road from More Chowk to Ring Road UC-39. Lahore, (L = 4100 Rft, w= 20 Ft).
Approved 19.928 0.000 19.928 0.000 0.000 9.883 0.000 9.883 10.045 10.045
CDG Lahore - Consolidated ADP 2012-13
69
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
(Revised)
Total Road & Streets 1421.898
HEALTH
Tied Grant Schemes
296 Construction of Dispensary at Kot Asad Ullah khan Manga Mandi, Lahore.
Approved 2.091 2.062 4.153 0.000 0.000 0.000 1.900 0.000 1.900 0.000 2.062 2.062
297 Up-Gradation ofOutdoor Facilities and better Equipment for Sodiwal Dispensary, Lahore
Approved 14.200 0.800 15.000 0.000 0.000 0.000 14.200 0.000 14.200 0.000 0.800 0.800
298 Provision of Missing Facilities i.e. One Ambulance, One UPS 1000 Watt and one Electric water Cooler for Rural Health Centre Raiwind District, Lahore.
Approved 0.000 4.057 4.057 0.000 0.000 0.000 0.000 0.000 0.000 4.057 4.057
299 Construction of 25 BeddedHospital at Lalquarters, Samandabad, Lahore.
Approved 149.910 26.555 176.165 0.000 0.000 0.000 8.256 0.000 8.256 5.944 0.800 6.744
300 Provision of Fund of salaries of 05 District Program Coordinators, 75 CDC supervisor, 01 Computer Operator, 66 Data entry Operator, 875 Sanatory Patrols and 250 LHW's under Scheme titled "prevention and control Program of Epidemic in Punjab.
Approved 0.000 24.059 24.059 0.000 0.000 0.000 0.000 16.300 16.300 7.759 7.759
301 Renovation of Public Health Nursin School, 5-Montgomery Road, Lahore.
Approved 4.594 0.000 4.594 0.000 0.000 0.000 0.000 0.000 0.000 4.594 4.594
302 Renovation / Civil work in Labor Room at Mian Munshi DHQ Hospital- 1. Lahore.
Approved 1.200 0.000 1.200 0.000 0.000 0.000 0.000 0.000 0.000 1.200 1.200
CDG Lahore - Consolidated ADP 2012-13
70
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
RS. 10.000 MILLION PACKAGE PP-149
303 Up-Gradation of Sodiwal Dispensary in to 20 Bedded Hospital, Lahore (Out Door Facilities, and Better Eiqupment) (Phase II)
Approved 36.163 13.693 49.856 0.000 0.000 0.000 0.000 0.000 0.000 36.163 36.163
Total Health 63.379
AGRICULTURE
Tied Grant Schemes
304 Renovation / Additional Alteration of Veterinary Hospital, at Ali Raza Abad, Lahore. (Amended)
Approved 0.200 0.000 0.200 0.000 0.000 0.000 0.120 0.000 0.120 0.080 0.080
305 Renovation / Additional Alteration of Veterinary Hospital, at Chung, Lahore. (Amended)
Approved 2.075 0.000 2.075 0.000 0.000 0.000 0.500 0.000 0.500 1.575 1.575
306 Renovation / Additional Alteration of Veterinary Hospital, & A.1. Centre Khana, Lahore. (Amended)
Approved 4.612 0.000 4.612 0.000 0.000 0.000 0.900 0.000 0.900 3.712 3.712
307 Promotion of Drip & Sprinkler Irrigration System in the Punjab.
Approved 0.000 16.463 16.463 0.000 0.000 0.000 0.000 15.769 15.769 0.694 0.694
Total Agriculture 6.061
LITERACY
Tied Grant
308 130, 121, 128, 129
158, 149, 150, 160, 161, 159,
65, 84, 114, 119, 121, 123, 124, 125, 146, 149
stablishment of District Literacy Management Information system (LiTMIS), Establishment of Audit Literacy Centers, (3-Cycles)-(250) in Districts, Establishments of Non-Formal Basic Education Schools (100 NFBE in District)
Approved 0.000 36.694 36.694 0.000 2.681 2.681 11.303 0.000 11.303 2.318 2.318
309 118, 123,
137, 138,
4, 11,
Establishments of 70 NFBE School & 40 ACL's CDGL.
Approved 0.000 18.093 18.093 0.000 0.000 0.000 0.000 2.998 2.998 0.993 0.993
CDG Lahore - Consolidated ADP 2012-13
71
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
129, 128, 127,
144, 157, 162, 161, 153, 159,
36, 64, 120, 122, 131, 145
Total Literacy 3.311
GENERAL BUILDING
ADP Schemes
310 120 140 80 Addition / Alteration Jinnal Hall First Floor for Office of Project Management Unit (PMU) for PPP Intergrated Solid Waste Management in Lahore.
Approved 6.900 0.000 6.900 0.400 0.000 0.400 0.000 0.000 0.000 0.400 0.400
311 128 161 125 Constructin of 2 No, Patwar Khana Manga / Maraka (Revised)
Approved 34.104 34.104 4.000 0.000 4.000 0.000 0.000 0.000 11.952 11.952
312 Shifting of Badami Bagh Bus Terminal at Thokar Niaz Baig, Lahore, (Phase-II) Revised
Approved 85.346 0.000 85.346 0.000 0.000 0.000 46.650 7.108 53.758 31.588 31.588
313 Repair of Residence P-155 (indoor) at Gulberg, Lahore.
Approved 0.420 0.000 0.420 0.000 0.000 0.000 0.000 0.000 0.000 0.420 0.420
Tied Grant
314 Construction of Basket Ball Court & Hockey Ground at Ashiyana Housing Scheme, Lahore.
Approved 84.025 0.000 84.025 10.000 0.000 10.000 46.650 7.108 53.758 30.267 30.267
315 Shifting of Badami Bagh Bus Terminal at Thokar Niaz Baig, Lahore,
Approved 191.371 0.000 191.371 0.000 0.000 0.000 128.295 3.614 131.909
59.462 59.462
Total General Building 134.089
SPECIAL EDUCATION
(TIED GRANT ONGOING SCHEMES)
Package I Rs. 18.960 M + Package II Rs. 97.359 M package III RS. 92.00 M= Rs. 208.319 M Received From (GOP)
316 Establishments of Institutions for slow
Approved 0.000 3.046 3.046 0.000 0.066 0.066 0.000 0.000 0.000 0.000 1.147 1.147
CDG Lahore - Consolidated ADP 2012-13
72
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Learner at District Level
317 Punjab Devolped Social Services Programme (PDSSP) (Rs. 18.960 M)
Approved 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
i Provision of staff on Hiring Basic to newely Established special Education Centres in District, Lahore.
0.000 7.560 7.560 0.000 7.560 7.560 0.000 0.000 0.000 0.000 7.560 7.560
ii Provision of Hearing Aids to 300 Hearing Impaired Students,
0.000 2.100 2.100 0.000 2.100 2.100 0.000 0.000 0.000 0.000 2.100 2.100
318 126 152 99 Construction of Building of Govt, Special Education Centre Nishtar Town, Lahore (2nd Amended)
Approved 45.473 0.800 46.273 35.592 0.000 35.592 28.092 0.800 28.892 6.700 0.000 6.700
319 123 143 16 Construction of Building of Govt, Special Education Centre Shalimar Town, Lahore (2nd Amended)
Approved 45.384 0.800 46.184 44.184 0.000 44.184 11.350 0.800 12.150 32.034 0.000 32.034
320 122 148 93 Up-gradation of Govt. Middle School for Physically Disable Children Lahore from Middle to Secondary Level,
Approved 0.000 0.000 1.245 1.245 0.000 0.000 0.000 0.000 1.245 1.245
321 126 151 104 Up-gradation of Govt. Instituate for the Blind Girls, Allama Iqbal Town, Lahore from Middle to Secondery Level
Approved 0.000 0.000 2.045 2.045 0.000 0.000 0.000 0.000 2.045 2.045
322 120 139 68 Re Construction / Renovation of Building and Boundry Wall of Govt. Sunrise Institute for the Blind Ravi Road, Lahore, (Amended)
Approved 40.364 0.050 40.414 40.414 0.000 40.414 0.200 0.000 0.200 40.164 0.050 40.214
(Tied Grant Ongoing Schemes)
Package I Rs. 18.960 M + Package II Rs. 97.359 M package III RS. 92.00 M= Rs. 208.319 M Received From (GOP)
Tied Grant (PDSSP) Schemes
323 Govt. Central High School for Deaf, Gulberg ii, Lahore.
Approved 0.000 0.170 0.170 0.000 0.170 0.170 0.000 0.000 0.000 0.170 0.170
324 Govt. Instituye for Blind, Sheranwala Gate, Lahore. (
Approved 40.000 0.000 40.000 39.630 0.000 39.630 0.200 0.000 0.200 39.800 39.800
CDG Lahore - Consolidated ADP 2012-13
73
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Amended)
325 Govt. Deaf and Defective Hearing High School for Girls, Lahore, (Amended)
Approved 2.000 0.280 2.280 1.964 0.000 1.964 1.600 0.000 1.600 0.400 0.280 0.680
326 Govt. Shadab Training Institute of Special Education (M.R), Lahore
Approved 0.000 0.130 0.130 0.000 0.130 0.130 0.000 0.000 0.000 0.000 0.076 0.076
327 Govt. Degree College of special Education, Gulberg-ii, Lahore. (Amended)
Approved 1.645 0.150 1.795 1.645 0.000 1.645 1.400 0.000 1.400 0.245 0.150 0.395
328 Govt. Special Education Centre. Ravi Town, Lahore, (Amended)
Approved 12.000 0.000 12.000 12.000 0.000 12.000 1.900 0.000 1.900 10.100 10.100
Total Special Education 144.266
ELECTRICAL & MECHANICAL
329 Rehabilitation of street lights at Canal bank road from Mughal Pura to BRB Canal
Approved 49.752 0.000 49.752 0.000 0.000 0.000 0.000 0.000 0.000 7.277 7.277
Total Electrical & Mechanical 7.277
TRANSFER PAYMENT
Rs. 100 M Package PP-149 WASA Schemes
WASA Schemes
330 149 Providing and Fixing Water Filtration Plants with Arsenic Removal Unit at UC- NO-87, PP-149, Lahore
Approved 1.560 0.000 1.560 0.000 0.000 0.000 0.000 0.000 0.000 1.560 1.560 19-05-2012
331 149 Providing and Fixing Water Filtration Plants with Arsenic Removal Unit at UC- No. 88, PP-149. Lahore
Approved 1.560 0.000 1.560 0.000 0.000 0.000 0.000 0.000 0.000 1.560 1.560 19-05-2012
332 149 Providing and Fixing Water Filtration Plants with Arsenic Removal Unit at UC- NO- 92, PP-149, Lahore
Approved 1.360 0.000 1.360 0.000 0.000 0.000 0.000 0.000 0.000 1.360 1.360 19-05-2012
Construction of Links Road from Charrar Drain (Combined Factor) to Ayshiana Housing Project, Lahore (PHA)
333 Providing and Fixing Water Filtration Plants with
Approved 6.857 0.000 6.857 0.000 0.000 0.000 0.000 0.000 0.000 6.857 6.857 19-05-2012
CDG Lahore - Consolidated ADP 2012-13
74
Gs# NA# PP# UC# Name of scheme Approval status
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-
revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-
12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Date of approval of the scheme
Arsenic Removal Unit at UC- NO- 92, PP-149, Lahore
Total Transfer Payment 11.337
CDG Lahore - Consolidated ADP 2012-13
75
Annual Development Programme (2012-13) Ongoing Account-IV.
(Rs. In Million)
S.# Sector Head of account
No Of Scheme
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Education
1 Ongoing ADP Acc-iv 1 36.260 1.500 37.760 30.000 0.000 30.000 21.883 0.000 21.883 8.217 0.000 8.217
Tied Grant Scheme
General Scheme Acc-iv 1 62.002 3.000 65.002 10.900 0.000 10.900 5.909 0.000 5.909 0.000 3.000 3.000
Missing Facilities Colleges 2009-10 Acc-iv 1 162.310 1.653 163.963 162.310 1.653 163.963 0.000 0.000 0.000 162.310 1.653 163.963
Missing Facilities Colleges 2007-08 (PESRP)
Acc-iv 5 141.578 3.800 145.378 38.383 0.000 38.383 34.990 0.000 34.990 25.643 0.000 25.643
Missing Facilities Colleges 2009-10 (PESRP)
Acc-iv 4 40.883 0.000 40.883 38.027 0.000 38.027 27.144 0.000 27.144 10.883 0.000 10.883
Ring Road Affected School Acc-iv 4 90.847 7.563 98.410 107.112 8.000 115.112 43.233 0.000 43.233 28.058 7.563 35.621
Special Develipment Package Acc-iv 2 20.000 0.000 20.000 19.692 0.000 19.692 16.192 0.000 16.192 3.500 0.000 3.500
ADP Scheme Acc-iv 1 19.469 1.000 20.469 4.166 0.000 4.166 4.166 0.000 4.166 4.385 0.000 4.385
(Rs 17.500 M Scheme (Revised from Fd) Acc-iv 1 10.265 1.000 11.265 0.000 0.000 0.000 3.818 0.000 3.818 6.447 1.000 7.447
Total Education 262.659
Road & Streets
Ongoing ADP Acc-iv 23 867.844 0.000 867.844 244.155 0.000 244.155 201.536 0.000 201.536 244.729 0.000 244.729
Tied Grant Scheme
City Package 200-10 Acc-iv 13 28.100 0.000 28.100 6.430 0.000 6.430 3.919 0.000 3.919 2.511 0.000 2.511
LRRP Acc-iv 28 442.724 0.000 442.724 125.173 0.000 125.173 14.627 0.000 14.627 161.637 0.000 161.637
CM's big city package 2009-10 Acc-iv 1 46.256 0.000 46.256 36.293 0.000 36.293 0.000 0.000 0.000 36.293 0.000 36.293
PP-160 MPA package Govt of Punjab Funding Scheme
Acc-iv 3 10.415 0.000 10.415 7.893 0.000 7.893 4.400 0.000 4.400 3.103 0.000 3.103
General Scheme Acc-iv 1 124.700 0.000 124.700 49.754 0.000 49.754 40.176 0.000 40.176 84.524 0.000 84.524
Raiwind Scheme Acc-iv 4 80.189 0.000 80.189 40.790 0.000 40.790 11.586 0.000 11.586 29.214 0.000 29.214
Special Dev. Package 2010-11 PP-141 Acc-iv 7 68.400 0.000 68.400 46.911 0.000 46.911 43.943 0.000 43.943 6.928 0.000 6.928
Special Dev. Package 2010-11 PP-143 Acc-iv 1 3.000 0.000 3.000 2.594 0.000 2.594 1.921 0.000 1.921 0.866 0.000 0.866
Special Dev. Package 2010-11 PP-144 Acc-iv 8 42.517 0.000 42.517 27.487 0.000 27.487 26.547 0.000 26.547 0.814 0.000 0.814
2 Special Dev. Package 2010-11 NA-128 Acc-iv 1 7.998 0.000 7.998 7.998 0.000 7.998 7.647 0.000 7.647 0.351 0.000 0.351
Dev. Schemes PP-142 Package 2010-11 Acc-iv 15 44.130 0.000 44.130 30.265 0.000 30.265 23.508 0.000 23.508 6.757 0.000 6.757
General Scheme Acc-iv 3 567.416 0.000 567.416 0.000 0.000 0.000 138.825 0.000 138.825 428.591 0.000 428.591
Allama Iqbal Road Acc-iv 1 593.259 0.000 593.259 0.000 0.000 0.000 293.571 0.000 293.571 115.867 0.000 115.867
Large city package (Rs. 500 M & Rs. 200 M)
Acc-iv 20 638.729 0.000 638.729 0.000 0.000 0.000 492.908 0.000 492.908 132.298 0.000 132.298
Rs. 230 M Develipment package Acc-iv 26 67.346 0.000 67.346 0.000 0.000 0.000 44.012 0.000 44.012 23.334 0.000 23.334
Rs. 1000 M PP_149 Package Acc-iv 2 7.992 0.000 7.992 0.000 0.000 0.000 5.417 0.000 5.417 2.575 0.000 2.575
Rs. 60.000 M package for MPA / MNA NA-123, PP-148 & PP-149 (Rs. 20,000 Million)
Acc-iv 17 52.768 0.000 52.768 0.000 0.000 0.000 9.323 0.000 9.323 43.445 0.000 43.445
CDG Lahore - Consolidated ADP 2012-13
76
S.# Sector Head of account
No Of Scheme
Approved cost-
capital
Approved cost-
revenue
Approved cost-total
BE 2011-12-capital
BE 2011-12-revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Rs. 30.000 M Package (PP-161 Rs. 20,000 M / Rs, 10.000 M )
Acc-iv 4 30.000 0.000 30.000 0.000 0.000 0.000 2.173 0.000 2.173 27.827 0.000 27.827
Rs. 10000 Million package of Hamza Shehbaz Sharif
Acc-iv 16 30.000 0.000 30.000 0.000 0.000 0.000 0.000 0.000 0.000 30.000 0.000 30.000
Total Road & Streets 1381.664
Health
3 Tied Grant Scheme Acc-iv 8 208.158 71.226 279.384 0.000 0.000 0.000 0.000 24.356 16.300 55.660 7.719 63.379
Total Health 63.379
Agriculture
4 Tied Grant Suplimentry New Scheme 2010-11
Acc-iv 4 6.887 16.463 23.350 0.000 0.000 0.000 1.520 15.769 17.289 5.367 0.694 6.061
Total Agriculture 6.061
Literacy
5 Tied Grant Acc-iv 2 0.000 54.787 54.787 0.000 2.681 2.681 11.303 2.998 14.301 2.318 0.993 3.311
Total Literacy 3.311
General Building
ADP New 2011-12 Acc-iv 4 126.770 0.000 126.770 4.400 0.000 4.400 46.650 7.108 53.758 44.360 0.000 44.360
6 Tied Grant New 2011-12 Acc-iv 2 275.396 0.000 275.396 10.000 0.000 10.000 174.945 10.722 185.667 89.729 0.000 89.729
Total General Building 134.089
Special Education
7 Tied Grant ADP Acc-iv 7 131.221 14.356 145.577 120.190 13.016 133.206 39.642 1.600 41.242 78.898 14.147 93.045
Tied Grant (PDSSP) Acc-iv 6 55.645 0.730 56.375 55.239 0.300 55.539 5.100 0.000 5.100 50.545 0.676 51.221
Total special Education 144.266
Electrical & Mechanical
8 ADP Schemes Acc-iv 1 49.752 0.000 49.752 0.000 0.000 0.000 0.000 0.000 0.000 7.277 0.000 7.277
Total Electrical & Mechanical 7.277
Transfer Payment
9 Tied Grant Schemes Acc-iv 4 11.337 0.000 11.337 0.000 0.000 0.000 0.000 0.000 0.000 11.337 0.000 11.337
Total Transfer Payment 11.337
10 CCB Schemes Acc-iv 113 0.000 0.000 0.000 104.658 0.000 104.658 0.000 0.000 0.000 98.947 0.000 98.947
11 CCB Block Allocation Acc-iv 0 0.000 0.000 0.000 1061.072 0.000 1061.072 0.000 0.000 0.000 1061.072 0.000 1061.072
CDG Lahore - Consolidated ADP 2012-13
77
ANNUAL DEVELOPMENT PROGRAMME (2012-13) ONGOING SDA
Rs. in Million)
S.# Sector Head of account
No Of Scheme
Approved cost-
capital
Approved cost-
revenue
Approved Cost Total
BE 2011-12-capital
BE 2011-12-revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Education
1 Missing Facilities Schools 2010-11 (DFID) SDA 5 32.309 0.000 32.309 0.000 0.000 0.000 18.312 0 18.312 13.99 0 13.990
3 Sector MNA / MPA Package 210-11 MNA's Schemes.
SDA 9 62.385 0.000 62.385 0.000 0.000 0.000 40.838 0 40.838 8.429 0 8.429
3 Sector MNA / MPA Package 210-11 MPA's Schemes.
SDA 10 57.210 0.500 57.710 0.000 0.000 0.000 35.572 0 35.572 18.536 0 18.536
Development Package for MNA / MPA 2010-11 SDA 50 262.829 13.083 275.912 0.000 0.000 0.000 181.830 11.33 193.16 80.081 1.753 81.834
Up-Gradation of Schools 2011-12 SDA 4 16.680 0.000 16.680 0.000 0.000 0.000 4.485 0 4.485 12.195 0 12.195
Missing Facilities Schools 2010-11 SDA 3 4.500 0.000 4.500 0.000 0.000 0.000 2.585 0 2.585 1.915 0 1.915
Total Education 136.899
Road & Streets
2 Development Package for MNA / MPA 2010-11 FMR Schemes
SDA 20 234.657 0.000 234.657 0.000 0.000 0.000 194.456 0 194.456 40.201 0 40.201
PP-160 MPA Package Govt. of Punjab Funding Schemes
Acct-Iv 3 10.415 0.000 10.415 7.893 0.000 7.893 4.400 0 4.4 3.103 0 3.103
General Schemes Acct-Iv 1 124.700 0.000 124.700 49.754 0.000 49.754 40.176 0 40.176 84.524 0 84.524
Raiwind Schemes Acct-Iv 4 80.189 0.000 80.189 40.790 0.000 40.790 11.586 0 11.586 29.214 0 29.214
Special Dev. Package 2010-11 PP-141 Acct-Iv 7 68.400 0.000 68.400 46.911 0.000 46.911 43.943 0 43.943 6.928 0 6.928
Special Dev. Package 2010-11 PP-143 Acct-Iv 1 3.000 0.000 3.000 2.594 0.000 2.594 1.921 0 1.921 0.866 0 0.866
Special Dev. Package 2010-11 PP-144 Acct-Iv 8 42.517 0.000 42.517 27.487 0.000 27.487 26.547 0 26.547 0.814 0 0.814
Special Dev. Package 2010-11 NA-128 Acct-Iv 1 7.998 0.000 7.998 7.998 0.000 7.998 7.647 0 7.647 0.351 0 0.351
Dev. Schemes PP-142 Package 2010-11 Acct-Iv 15 44.130 0.000 44.130 30.265 0.000 30.265 23.508 0.000 23.508 6.757 0.000 6.757
General Schemes Acct-Iv 3 567.416 0.000 567.416 0.000 0.000 0.000 138.825 0.000 138.825 428.591 0.000 428.591
Allama Iqbal Road Acct-Iv 1 593.259 0.000 593.259 0.000 0.000 0.000 293.571 0.000 293.571 115.867 0.000 115.867
Large City package (Rs. 500 M & Rs. 200 M) Acct-Iv 20 638.729 0.000 638.729 0.000 0.000 0.000 492.908 0.000 492.908 132.298 0.000 132.298
Ra. 230 M Development Package Acct-Iv 26 67.346 0.000 67.346 0.000 0.000 0.000 44.012 0.000 44.012 23.334 0.000 23.334
Rs. 100.000 M pp_149 package Acct-Iv 2 7.992 0.000 7.992 0.000 0.000 0.000 5.417 0.000 5.417 2.575 0.000 2.575
Rs. 60.000 M package for MPA/MNA NA-123, PP-148 & PP-149 (Rs. 20.000 Million)
Acct-Iv 17 52.768 0.000 52.768 0.000 0.000 0.000 9.323 0.000 9.323 43.445 0.000 43.445
RS. 30.000 M package (PP-161 Rs. 20.000 M + Rs. 10.000M)
Acct-Iv 4 30.000 0.000 30.000 0.000 0.000 0.000 2.173 0.000 2.173 27.827 0.000 27.827
Rs. 10.000 Million package of Hamza Shahbaz Sharif
Acct-Iv 16 30.000 0.000 30.000 0.000 0.000 0.000 0.000 0.000 0.000 30.000 0.000 30.000
Development of package for MNA / MPA 2011-12 FMR Schemes
SDA 20 234.657 0.000 234.657 0.000 0.000 0.000 194.456 0.000 194.456 40.201 0.000 40.201
Total Road & Streets 1016.896
Health
3 Tied Grant Schemes Acct-Iv 8 208.158 71.226 279.384 0.000 0.000 0.000 0.000 24.356 16.300 55.660 7.719 63.379
CDG Lahore - Consolidated ADP 2012-13
78
S.# Sector Head of account
No Of Scheme
Approved cost-
capital
Approved cost-
revenue
Approved Cost Total
BE 2011-12-capital
BE 2011-12-revenue
BE 2011-12-total
RE 2011-12-capital
RE 2011-
12-revenue
RE 2011-12-total
BE 2012-13-capital
BE 2012-
13-revenue
BE 2012-13-total
Total Health 63.379
Agriculture
4 Tied Grant Supplementary new Schemes 2011-12
Acct-Iv 4 6.887 16.463 23.350 0.000 0.000 0.000 1.520 15.769 17.289 5.367 0.694 6.061
Total Agriculture 6.061
Literacy
5 Tied Grant Acct-Iv 2 0.000 54.787 54.787 0.000 2.681 2.681 11.303 2.998 14.301 2.318 0.993 3.311
Total Literacy 3.311
General Building
6 ADP New 2011-12 Acct-Iv 4 126.770 0.000 126.770 4.400 0.000 4.400 46.650 7.108 53.758 44.360 0.000 44.360
Tied Grant new 2011-12 2 275.396 0.000 275.396 10.000 0.000 10.000 174.945 10.722 185.667 89.729 0.000 89.729
Total General Building 134.089
Special Education
7 Tied Grant (ADP) Acct-Iv 7 131.221 14.356 145.577 120.190 13.016 133.206 39.642 1.600 41.242 78.898 14.147 93.045
Tied Grant (PDSSP) Acct-Iv 6 55.645 0.730 56.375 55.239 0.300 55.539 5.100 0.000 5.100 50.545 0.676 51.221
Total special Education 144.266
Electrical & Mechanical
8 ADP Schemes Acct-Iv 1 49.752 0.000 49.752 0.000 0.000 0.000 0.000 0.000 0.000 7.277 0.000 7.277
Total Electrical & Mechanical 7.277
Transfer Payment
9 Tied Grant Schemes Acct-Iv 3 11.337 0.000 11.337 0.000 0.000 0.000 0.000 0.000 0.000 11.337 0.000 11.337
Total Transfer Payment 11.337
10 CCB Schemes Acct-Iv 113 0.000 0.000 0.000 104.658 0.000 104.658 0.000 0.000 0.000 98.947 0.000 98.947
11 CCB Block Allocation Acct-Iv 0 0.000 0.000 0.000 1061.072 0.000 1061.072 0.000 0.000 0.000 1061.072 0.000 1061.072
CDG Lahore - Consolidated ADP 2012-13
81
Water & Sanitation Agency
Summary of Annual Development Programme 2012-13
Programme
No. of Schemes
Budget Estimate 2012-13
(Rs. in million)
%
Ongoing Scheme 7 313.365 45%
New Scheme 7 383.000 55%
Total 14 696.365 100%
WASA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
83
Water & Sanitation Agency Annual Development Programme 2012-13 - by Category
Category
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Replacement 3 155.95 41% 3 155 50% 6 311 45%
Refurbishment 3 178 46% 3 152 49% 6 330 47%
Up-gradation 0 - 0% - - 0% 0 0 0%
Other 1 50.00 13% 1 5 2% 2 55 8%
Total 7 384 100% 7 312 100% 14 696 100%
50% 55% 50% 45% 100% 100%
Share of Schemes by Category in WASA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
85
Water & Sanitation Agency
Annual Development Programme 2012-13 - by Sector
Sector
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Sewerage 1 75 20% 4 178 57% 5 253 36%
Water Supply 3 150 39% 1 30 10% 4 180 26%
Drainage 1 53 14% 1 100 32% 2 153 22%
Others * 2 105 27% 1 5 2% 3 110 16%
Total 7 384 100% 7 312 100% 14 696 100%
50% 55% 50% 45% 100% 100%
* Includes budget estimates for Block Allocation, Feasibility Studies, etc.
Share by Sector in WASA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
87
Water & Sanitation Agency
Annual Development Program 2012-13 - by Scheme Sr. No.
ADP No.
Name of Scheme
Approval
Status
Approved Cost
T.S Cost Total Exp. Up to
June 12
Provision for 2012-13 Revised allocation for 2012-13
Funds released till 31.01.13 Funds Utilized
Till 31.01.13
%age Utilization on
releases (17/14x
100)
Total accumulative expenditure
till the current
month (7+17)
Financial Progress till the current month (%)
Physical Progress till the current month
Throw Forward
Col 5-7-11
Total Capital
Revenue Total Ca p i t a l
Revenue
Total Cap i t a l
Revenue
ADP Ongoing Schemes
1 1499 Laying of sewer Lines, construction of drain and Disposal Station for Niaz Drainage System UC-118, WASA, LDA, District, Lahore
Approved
75.950 75.950 14.482 25.950 0 25.950 25.950 0 25.950 25.950 0 25.950 12.259 47% 26.741 35% 72% 35.518
2 1500 Miscellaneous Sewerage and Drainage requirements of different Towns of Lahore.
Approved
1,068.000 1,068.000
673.422 100.000 0 100.000 100.000 0 100.000 50.000 0 50.000 48.000 96% 721.422 68% 85% 294.578
3 1501 Trunk Sewer Shadi Pura to Salamat Pura
Approved
751.014 751.014
751.014 30.000 0 30.000 0.000 0 30.000 15.000 0 15.000 0.600 4% 751.614 100% 100% 0.000
4 1502 Retrieval of Sewerage & Drainage for Lahore City. (Phase-II)
Approved
930.410 - 309.410 22.000 0 22.000 22.000 0 22.000 8.600 0 8.600 0.000 0% 309.410 33% 100% 599.000
5 1503 Appointment of Consultant for Feasibility Studies, Planning & Design of Waste Water Treatment
Approved
37.489 37.489 20.325 5.000 0 5.000 5.000 0 5.000 5.000 0 5.000 0.000 0% 20.325 54% 60% 12.164
CDG Lahore - Consolidated ADP 2012-13
88
Sr. No.
ADP No.
Name of Scheme
Approval
Status
Approved Cost
T.S Cost Total Exp. Up to
June 12
Provision for 2012-13 Revised allocation for 2012-13
Funds released till 31.01.13 Funds Utilized
Till 31.01.13
%age Utilization on
releases (17/14x
100)
Total accumulative expenditure
till the current
month (7+17)
Financial Progress till the current month (%)
Physical Progress till the current month
Throw Forward
Col 5-7-11
Total Capital
Revenue Total Ca p i t a l
Revenue
Total Cap i t a l
Revenue
Plant Lahore.
6 1504 Replacement of existing outlived 20 tube wells (2/4 cusec) in different areas of Lahore.
Approved
169.130 169.130
126.147 30.415 0 30.415 30.415 0 30.415 30.415 0 30.415 30.415 100% 156.562 100% 100% 12.568
7 1505 Restoration of Original Cross Section (40 feet) of Sattu Katla Drain from Ferozepur Road to Peco Road, Lahore.
Approved
326.000 326.000
76.491 100.000 0 100.000 100.000 0 100.000 50.000 0 50.000 30.000 60% 106.491 33% 55% 149.509
Total of ADP Ongoing Schemes:
3,357.993 2,427.583
1,971.291 313.365 0 313.365 283.365 0 313.365 184.965 0 184.965 121.274 66% 2,092.565 1,103.337
New ADP Schemes
1 1531 Coverage of Cantt. Drain Passing through Territory of Punjab Institute of Cardiology, Lahore.
Approved
53.000 - 0.850 53.000 0 53.000 53.000 0 53.000 23.000 0 23.000 0.000 0.850 2% - -0.850
2 1532 Punjab Water & Sanitation Academy, Lahore (JICA Assisted)
Approved
411.082 - 0.000 55.000 0 55.000 55.000 0 55.000 31.600 0 31.600 0.000 0% 0.000 0% 1% 356.082
3 1533 Lahore Water Supply Sewerage & Drainage Improvement Project (Japanese
Un- Approved
42,249.000 0.000 0.000 75.000 0 75.000 75.000 0 75.000 0.000 0 0.000 0.000 0% 0.000 0% - 42174.000
CDG Lahore - Consolidated ADP 2012-13
89
Sr. No.
ADP No.
Name of Scheme
Approval
Status
Approved Cost
T.S Cost Total Exp. Up to
June 12
Provision for 2012-13 Revised allocation for 2012-13
Funds released till 31.01.13 Funds Utilized
Till 31.01.13
%age Utilization on
releases (17/14x
100)
Total accumulative expenditure
till the current
month (7+17)
Financial Progress till the current month (%)
Physical Progress till the current month
Throw Forward
Col 5-7-11
Total Capital
Revenue Total Ca p i t a l
Revenue
Total Cap i t a l
Revenue
Assisted)
4 1534 Preparation of Master Plan for Water Supply, Sewerage & Drainage System for Lahore - PC-II
Approved
85.000 0.000 0.000 50.000 0 50.000 50.000 0 50.000 20.000 0 20.000 0.000 0% 0.000 0% - 35.000
5 1535 Provision of Water Supply, Sewerage & Drainage system for UC: 117, 118, 119 & 120, Lahore.
Un- Approved
3,168.000 0.000 0.000 50.000 0 50.000 50.000 0 50.000 0.000 0 0.000 0.000 0% 0.000 0% - 3118.000
6 1536 Replacement of outlived, deeper and inadequate water supply lines with HDPE Pipes (Gastro Phase-II)
Un- Approved
300.000 300.000
0.000 50.000 0 50.000 50.000 0 50.000 0.000 0 0.000 0.000 0% 0.000 0% 100% 250.000
7 1537 Block Allocation for initiation of Waste Water Treatment Plant Project in Lahore.
Un- Approved
100.000 100.000
0.000 50.000 0 50.000 50.000 0 50.000 0.000 0 0.000 0.000 0% 0.000 0% 100% 50.000
Total of New Schemes 46,366.082 400.000
0.850 383.000 0 383.000 383.000 0 383.000 74.600 0 74.600 0.000 0.850 45,982.232
ADP Ongoing & New Schemes: 49,724.075 2,827.583
1,972.141 696.365 0 696.365 666.365 0 696.365 259.565 0 259.565 121.274 47% 2,093.415 47,085.569
CDG Lahore - Consolidated ADP 2012-13
93
LDA (TEPA & UD Wing)
Summary of Annual Development Programme 2012-13
S. No.
Programme
No. of
Schemes
Budget Estimate 2012-13
(Rs. in million)
%
A. TEPA LDA 55 21,617.156 71%
Annual Development Programme 45 21,377.272 99%
Deposit work Expenditure 9 126.269 1%
Refund of Securities 1 113.615 1%
B UD Wing LDA 125 8903.640 29%
Development Expenditure (LDA Own Sources) 117 8,382.696 94%
Other ADP 8 520.944 6%
Total 180 30,521 100%
LDA (TEPA & UD Wing) ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
95
Traffic Engineering & Transport Planning Agency Summary of Annual Development Programme 2012-13.
S. No.
Programme
No. of
Schemes
Budget Estimate 2012-13
(Rs. in million)
%
A. Annual Development Programme 45 21,377 98%
Ongoing Schemes 41 21,229.27
New schemes 4 148.000
B. Deposit work Expenditure 9 126.269 1%
C. Refund of Securities 1 113.615 1%
Total 55 21,617 100%
TEPA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
97
Traffic Engineering & Transport Planning Agency Annual Development Programme 2012-13 - by Category
Category
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Replacement 2 90.00 61% 35 20723 97% 37 20813 96%
Refurbishment 2 58.00 39% 14 575 3% 16 633 3%
Up-gradation 0 - 0% 1 57 0% 1 57 0%
Other - - - 1 114 1% 1 114 1%
Total 4 148 100% 51 21,469 100% 55 21,617 100%
7% 1% 93% 99% 100% 100%
Share of Schemes by Category in TEPA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
99
Traffic Engineering & Transport Planning Agency Annual Development Programme 2012-13 - by Sector
Sector
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Roads 2 36 24% 33 20987.532 98% 35 21,023.532 97%
Transport Planning 1 52 35% 5 178.918 1% 6 230.918 1%
Sports 0 - 0% 1 36.000 0% 1 36.000 0%
Others * 1 60 41% 12 266.679 1% 13 326.679 2%
Total 4 148 100% 51 21,469 100% 55 21,617 100%
7% 1% 93% 99% 100% 100%
* Includes Deposit work, Refund of security, Feasibility Study
Share by Sector in TEPA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
101
Traffic Engineering & Transport Planning Agency Annual Development Programme 2012-13 - by Scheme
(Rs.in Million)
Sr. No
Name of Schemes 2011-2012 2013
Budget Estimates
Revised Estimates
Budget Estimates
A Ongoing Schemes
1 Construction of Shalimar interchange 0 34.437 276.471
2 Road marking and installation of traffic signals at Shahra e Quaid e Azam , jail road, lower mall , railway station road network and main boulevard Gulberg
57 0 57
3 Improvement /repair of canal bank road from university campus underpass to canal view bridges near thokar flyover
114.551 0 0
4 Remodeling of canal bank road from dharam pura underpass to thokar niaz baig Lahore 147.203 47.3 89.903
5 Widening &rehabilitation of MM Alam road from hussain chowk to main boulevard gulberg 142.079 0 132.079
6 Construction of alternate route to Raiwind road from khyaban e jinnah crossing to defence road along butcher kahna distributary , Lahore
2000 951.364 48.636
7 Construction of PCC sewerage at peer colony , qadir colony, iqbal park koray pinds 0 6.98 3.02
8 Construction of PCC sewerage at al-noor town , model colony no 1 & 2 farooq colony 0 8.468 1.532
9 Construction of PCC sewerage at Firdouse park javed colony millat park 0 4.761 0.239
10 Construction of PCC sewerage at Muhammad Pura , mehboob colony gulistan colony 0 4.685 0.315
11 Construction of PCC sewerage at Keer Khurd cantt, view manawala 0 9.148 0.852
12 Construction of PCC sewerage at Bao wala sahjpal pind derh pindi 0 4.467 0.533
13 Construction of PCC Sewerage at gohava , haji park, chachuwali , kalar colony and bhatta kahar 0 8.962 1.038
14 construction of PCC sewerage at amarsidhu gulshtan colony , shahid town , munawar abad, mayo muhalla (PP-155), Lahore
0 4.332 0.668
15 Construction of PCC sewerage at Sadar bazar ghousia colony jhallaran lal kurti 0 5.742 1.758
16 Construction of PCC sewerage at mian meer 0 3.715 0.258
17 Construction of PCC sewerage at Main cantt, hussain abad, qasim pura and khan colony 0 2.485 1.515
18 Construction of PCC Sewerage at Nadir abad , arif abad and gulshan ali colony 0 3.666 3.334
19 Construction of PCC sewerage at Islam nagar shama colony , gulbahar colony and sheraz villaz 0 2.683 2.317
20 Construction of PCC sewerage at Madina colony, shaheen colony and akram abad 0 3.212 1.788
21 Construction of PCC sewerage at LDA quarters peeter colony and gulshan colony 0 6.461 1.039
CDG Lahore - Consolidated ADP 2012-13
102
Sr. No
Name of Schemes 2011-2012 2013
Budget Estimates
Revised Estimates
Budget Estimates
22 Construction of PCC sewerage at Nishat colony and maryam colony 0 2.944 2.056
23 Construction of PCCseweraege at R A Bazar 40 quarters 0 1.807 0.693
24 Construction of PCC sewerage at Railways officers katchi abadi ghousia colony 0 1.985 0.515
25 Bus rapid transit system for Lahore 0 4602.134 19865.007
26 Consultancy service to purpose solutions for improvement traffic flow at canal bank road junction along with realignment of underpass at jail road Lahore
0 0 4.5
27 Improvement of junctions and remodeling bottleneck at canal road 0 46.859 77.774
28 Laying of synthetic hockey stadium field light, ideal park hockey ground , township Lahore 0 0 36
29 Construction of main johar town road from shoukat khanum hospital to raiwind road (2nd carriageway) 1.815 1.815 0
30 Construction of Southern bypass road from UBD canal to college road (2nd carriageway) 15.831 15.831 0
31 Remodeling of road between block B2, A2 and B3 from hussain chowk to gurumangat road (workshop chowk ) gulberg III Lahore
0.971 0.971 0
32 Improvement of Moulana Shoukat ali road from canal to feroz pur road via PECO Road (7km) 177.268 102.228 75.039
33 Road remodeling&traffic circulation olan of Govt complex area close to jain mander 55.908 2.885 53.023
34 Construction of underpass at canal crossing ferozpur road Lahore 6.8 0 6.8
35 Feasibility studies & designs for grade separation facilities at mughal pura canal /railway crossing near dryport Lahore, railway line to connect khurshid alam road with hussain chowk gulberg III Lahore, Railways crossing for southern bypass sec. from college road to ferozpur road Lahore , canal bank crossing for connecting moulana shaukat ali road with wahdat road / multan road at karim block Lahore
25 0 25
36 Construction of structure road from khyaban e jinnah to Valencia town Lahore (phase I) 188.019 109.515 68.773
37 Rehabilitation of Maulana shabor usmani road from "Y" junction new garden town to maulana shoukat ali road
11.969 0 11.969
38 Integrated traffic management system , ferozpur road Lahore (pilot Project) 30.871 0 30.871
39 Development of public facility for the model area Lahore 0 0 1.795
40 P/F Road signage road marking at six major road 0 0 4.44
41 Installation of new traffic signals at various location in Lahore 0 0 47.982
42 Trafic management plan for Lahore city through Rd making signals &road safety devices 0 0 38.565
43 Rehabilitation of shami road from khalid butt chowk to hamdani chowk Lahore 0 0 2.131
44 Improvement & rehabilitation of Khurshid alam road to RA Bazar , Lahore 0 0 2.921
45 Construction of underpass at railway level at MS Ali road , Lahore 0 0 249.096
CDG Lahore - Consolidated ADP 2012-13
103
Sr. No
Name of Schemes 2011-2012 2013
Budget Estimates
Revised Estimates
Budget Estimates
New Schemes
1 Construction of missing link by extension of maulana shaukat ali road to wahdat road at karim block , allama iqbal town , Lahore
10 0 30
2 Feasibility study of RBT corridor for Lahore (PC II) 0 0 60
3 Improvement of civil geometry of molecular laboratory on Canal Bank Road near Doctor's Hospital 0 0 6
4 Extension of TEPA office building 0 0 52
Total 2985.285 6001.842 21377.245
B DEPOSIT WORK EXPENDITURE
1 Maintenance / Repair/Rehabilitation / Installation &Up-gradation of traffic signals in Lahore city 56.7 23.29 56.7
2 Remodeling EME and Mohanwala junction Scheme at Central bank road Lahore 29.643 0 29.643
3 Construction of Sports club at Ravi road Lahore 0 40 18
4 Remodeling of thokar Niaz Baig intersection Lahore (C&W Department) 0 13.372 2.328
5 Installation of Trafic Signals at Kalma Chowk Lahore (C&W Dept) 0 6.186 1.556
6 Construction of Flyover along Ferozpur Road Canal Bank Road / Wahdat Road Junction C&W Dept 0 0 10.602
7 Restoration of road cut made by WASA at Moulana shoukat ali road from Gasoline CNG to PECO Road Lahore 0 3.751 0.044
8 Improvement of Parking &Up-gradation of connecting roads network to Liberty Market Lahore 2.356 2.122 0
9 Installation of Traffic Signals at Thokar niaz baig (flyover intersection) (C&W Dept) 6.553 2.085 4.468
10 Refurbishment and traffic management at basement of LDA plaza Lahore 2.928 0 2.928
Total 98.18 90.806 126.269
Refund of Securities 11.064 9.584 113.615
CDG Lahore - Consolidated ADP 2012-13
104
Urban Development Wing
Summary of Annual Development Programme 2012-13
S. No.
Programme
No. of
Schemes
Budget Estimate 2012-13
(Rs. In million)
%
A. Annual Development Expenditure (LDA Own Sources)
117 8,382 94%
B. Other than ADP 8 520 6%
Total 125 8,903 100%
UD Wing ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
106
Urban Development Wing
Annual Development Programme 2012-13 - by Category
Category New
% Ongoing
% Total
% No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
Replacement 15 2,446.43 65% 20 2958 57% 35 5405 61%
Refurbishment 46 1,297.47 35% 40 1545 30% 86 2843 32%
Up-gradation 0 - 0% 0 0 0% 0 0 0%
Other - - - 4 656 13% 4 656 7%
Total 61 3,744 100% 64 5,160 100% 125 8,904 100%
49% 42% 51% 58% 100% 100%
Share of Schemes by Category in UD Wing ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
108
Urban Development Wing
Annual Development Programme 2012-13 - by Sector
Sector New
% Ongoing
% Total
% No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
No. of Schemes
Rs.in Million
Housing Schemes 9 2,060 0.55 9 81 2% 18 2142 24%
Flat and Building 7 387 10% 10 597 12% 17 984 11%
Roads 45 1,296 35% 21 1210 23% 66 2506 28%
Parking Palaza - - - 1 501 10% 1 501 6% Others * - - - 23 2771 54% 23 2771 31%
Total 61 3,744 100% 64 5,160 100% 125 8,904 100%
49% 42% 51% 58% 100% 100%
* Includes budget estimates for Block Allocation, Deposit Work, ADP Loans, Refund of security
Share by Sector in UD Wing ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
110
Urban Development Wing Annual Development Programme2012-13 - by Components
S.No.
Programme
No. of
Schemes
Budget Estimate 2012-13
(Rs. in million)
%
A. Development Expenditure (LDA Own Sources) 117 8,383 94%
Housing Schemes 18 2,141.675 26%
Block Allocation (Housing Schemes) 1 15.000 0.18%
Flat and building expenditures 17 984.045 12%
Other Development Schemes 12 1,955.008 23%
Lahore Rehabilitation Program 66 2,506.343 30%
Government ADP Schemes Financed from LDA Resources
2 280.000 3%
Parking Plazas 1 500.625 6%
B. ADP Deposit Works 8 521 6%
ADP Loans /Government Grants 2 53.000 10%
Deposit Work Expenditure 6 387.944 74%
Refund of Security Deposit of Contractors 80.000 15%
Share by Components in UD Wing ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
112
Urban Development Wing
Annual Development Programme - 2012-13- by Scheme Status Classification Budget
Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
1 2 3
Schemes Financed form LDA sources (Figures in Million)
I) Housing Schemes (Exp)
a) New Schemes
1. Approved LDA Avenues
For Government Servants
a)Roads 100 33.659 500
b) Sewerage/water supply/drainage 140 59.605 592
c) Electricity 340 0 340
d) Sui gas 20 7.152 20
e) Horticulture 41.2 18.839 23
f) Building 5 8.85 5
g) Boundary wall & main gates 30 0 20
Total 676.2 128.105 1500
2. Approved Finance and trade Centre Area Johar Town
a. Construction of Road Network 500 33.101 550.425
TOTAL 500 33.101 550.425
3. Un- Approved
New development Housing schemes
a. Lump sum Provision for New Housing Schemes 200 1.761 10
TOTAL 200 1.761 10
SUB TOTAL (a) NEW SHEMES(1-3) 1376.2 162.967 2060.425
b) ONGOING SCHEMES (Exp)
1. Approved Jubilee Town Schemes
a. Arboriculture 30 0 19.75
b. Electricity 13 7.475 5
TOTAL 43 7.475 24.75
2. Approved Johar town Schemes Ph. II
Electricity 30 1.173 25
TOTAL 30 1.173 25
3. Approved Johar town Schemes Ph. I
Electricity 1.5 0 1
TOTAL 1.5 0 1
4. Approved Sabzazar Scheme Ph. II
Electricity 2 0 2
TOTAL 2 0 2
5. Approved Sabzazar Scheme Ph. I
a. Roads 5 4.635 0
b. Electricity 12 0 12
TOTAL 17 4.635 12
6. Approved
Mohlawanla Housing Scheme
Electricity 14 2.738 10
TOTAL 14 2.738 10
7. Approved
Mustafa Town Scheme
a. Electricity 2.5 0 3
CDG Lahore - Consolidated ADP 2012-13
113
Status Classification Budget Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
b. Water Supply 3.5 0 3.5
TOTAL 6 0 6.5
SUB TOTAL (b) ONGOING SCHEMES(1-7) 113.5 16.021 81.25
c)
Un-Approved COMPLETED SCHEMES
Block allocation for missing links/ removal of encroachments, roads, sewerage, electricity and water supply in completed schemes
15 3.936 15
Sub Total © Completed schemes 15 3.936 15
GRAND TOTAL (I) HOUSING SCHEMES (a+b+c) 1504.7 182.924 2156.675
II) Flat and building expenditures
a) NEW SCHEMES
1. Un-Approved Constructions of parking plazas adjacent to LDA office Johar Town
0 0 100
2. Un-Approved Construction of Houses of LDA offices/officials at jubilee town
25 0 65
3. Un-Approved Generators for LDA buildings and schools 16 0 25
4. Un- Approved
Construction of laboratory for directorate of quality control at Johar Town
2 0 3
Total Un-Approved Schemes 43 0 193
5. Approved Construction of community center Garden Town 0 0 183
6. Approved Construction of Commercial plaza at 4-A Gulberg-V 10 0 10
7. Approved Repair and renovation of LDA building and one window cell Johar Town
0 0 1.045
Total Approved Schemes 10 0 194.045
SUB TOTAL (a) NEW SCHEMES (1-7) 53 0 387.045
b) ONGOING SCHEMES
1. Approved Construction of LDA offices at Jauhar Town (4Lifts) 160 125.761 160
2. Approved Construction of Sports Complex block D-II Johar Town 0 0.482 170
3. Approved Construction of hockey stadium at Johar Town 0 43.109 95
4. Approved Construction of Parks and Ride plaza in front of Salt n Paper Liberty Market Gulberg
100 92.046 60
5. Approved Construction of Cricket Pavilions at various sites in Lahore
100 52.915 47
6. Approved Add/Alteration & Renovation of LDA buildings 30 12.584 25
7. Approved Vertical extension of existing OWO building at Johar Town
15 0 20
8. Approved Fire alarm and security system (CCTV) for LDA buildings 12 0.621 15
9. Approved Construction of Mian Nawazsharif Sports complex at Gujjarpura
15 6.929 4
10. Approved Construction of Cricket stadium at Sabzazar Scheme 50 74.13 1
11. Approved Construction of LDA schools at Sabzazar Scheme 12 1.811 0
12. Approved Construction of LDA schools PH II,III at MA Johar Town 2 0 0
13. Approved Construction of community center in Muslim Town 16 6.825 0
14. Approved Construction of Office Building at Quaid e Azam Town 1 0 0
15. Approved Supply installation of 2 passenger Lifts in LDA Complex 0 0.62 0
SUB TOTAL (b) ONGOING SCHEMES (1-15) 513 417.833 597
TOTAL (II) FLATS AND BUILDINGS (a+b) 566 417.833 984.045
OTHER DEVELOPMENT SCHEMES
1. Un-Approved Priority Works 500 330.322 350
2. Un-Approved Purchase of Vehicles 10 3.751 10
3. Un-Approved Block Allocation of Re development Schemes
CDG Lahore - Consolidated ADP 2012-13
114
Status Classification Budget Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
Gulberg Schemes 0 0 200
Johar Town Schemes 0 0 100
TOTAL UN APPROVED SCHEMES 510 334.073 660
4. Approved Shifting of Fruits and Vegetable market Kot Lakhpat 1169 197.352 971.648
5. Approved Construction of Pedestrian Bridges in Model Bazar Gujjar purra
164 125.362 39.256
6. Approved Development of Venus Housing Schemes 90 89.145 15
7. Approved Fabrication/Fixing of Fiber Glass sun Shade over Pedestrian Bridge near shalimar Flyover Lalpul Lahore
0 0 3.849
8. Approved Pending liabilities of Priority Works 271.885 210.49 258.632
9. Approved Improvement / Ant termite around LDA Model High Schools Johar Town
0 0 1.623
10. Approved Compensation due to court decree/ settlement of Land Dispute
2.5 0.717 2.5
11. Approved Preparation of Land classification Plans etc 5 0 2.5
12. Approved Development of Graveyard in block F/I Jauhar Town 5 1.207 0
Total Approved Schemes 1707.385 624.273 1295.008
TOTAL (III) OTHER DEVELOPMENT SCHEMES 2217.358 958.346 1955.008
(IV) LAHORE REHABILITATION PROGRAMME
a) NEW SCHEMES
1. Un-Approved Construction of Road from E block to Doctor Hospital under High Tension Line Johar Town
0 0 250
2. Un-Approved Construction of Road along Khamba Distributary from Nursery Chowk to Southern Bypass Johar Town
0 0 150
3. Un-Approved Improvement carpeting of Road from Liaqat Chowk to Kharak drain Sabzazar Scheme
0 0 35
4. Un-Approved Improvement of Road from Moulana Shaukat Ali Road to Chandni Chowk along both side Sattokatla Drain QAT
0 0 25
5. Un- Approved
Construction of Bridge at Chandni Chowk Quaid e Azam Town
0 0 25
6. Un-Approved Widening improvement of Road along Cantt Drain from F block Gulshan e Ravi to Bund Road
0 0 24.5
7. Un-Approved Improvement of Road from Sher Shah road to Chota Ravi Drain Gujjarpura Scheme
0 0 18
8. Un-Approved Improvement of Road from Sher pao bridge to Gurumangat Gulberg
0 0 15
9. Un-Approved Improvement of Road from Pizza hut to Ghalib market dual carriageway gulberg
0 0 9
10. Un-Approved
Construction of monument at Istanbul Chowk & Qadir TOPBAS I intersection
0 0 6.5
11. Un-Approved
Improvement of Road from MM Alam Road towards CNG Pump Liberty to B Block Gulberg
0 0 6
12. Un-Approved
Improvement of Road from KFC MM Alam Road to Ghalib market near CNG Pump Gulberg
0 0 6
13. Un-Approved
Imp &Carpeting of Road from Khamba distributary to F Block main boulevard MA Johar Town
15 0 20
14.Un-Approved
Imp &carpeting of service road from Southern bypass to Shadiwall M A Johar Town
6 0 7
15.Un-Approved
Carpeting of Road from B Block to AI Nabi Pura Gulberg 0 0 6
16.Un-Approved
W/Imp. &Carpeting of Road from Grid Station to Cantt Drain Bridge Sabzazar Ph. II
20 0 20
CDG Lahore - Consolidated ADP 2012-13
115
Status Classification Budget Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
17.Un-Approved
Remodeling of adda plot junction Riawind Road 0 0 70
18Un- Approved
Raising of Bridges / culverts at various drains obstructing the water flow
150 0 65
19.Un- Approved
Remodeling of Race Course park junction Jail Road 15 0 15
20 Un- Approved
Construction of Ayub Road Near PECO Road Kot Lakhpat
6 0 8
21.Un- Approved
W/I of Al-Madina Road from Moulana Shaukat Ali Road to Barkat Chowk , sector B/I, Quaid e Azam Town Lahore
0 0 192.862
Total Un-Approved Schemes 212 0 973.862
22. Approved W/I &Carpeting of Road from Neelam block Awain chowk to Multan Road along g Kharak Drain (R/S) A.I.Town
0 0 142.33
23. Approved Construction of approached road to Tajpura Scheme from Ghaziabad to Amna Masjid
25 0 25
24. Approved Imp&Carpeting of 20 m wide Road along Trade Centre Johar Town
15 0 20
25. Approved Imp/carpet of road in Fateh Ghar / Gulshan Park 0 0 14.053
26. Approved Construction of the road from Gulshan e Iqbal (old well) to 38 College Block Allama Iqbal Town
0 0 16.237
27. Approved Imp/Carpeting of Road in Block K Part II Johar Town 0 0 10.31
28. Approved Construction of the Parking and tracks from Community Centre LDA Ave -I
0 0 10.652
29. Approved Construction of Service Road Taj bhag Phatak to Lalpul with Link PP 153
0 0 11.384
30. Approved W/I of Road Along Drain from Jurre Pull to Karim Block Market Bridge AIT
0 0 9.072
31. Approved Imp/Carpet. Of the Road in /Kamran Nishter & Mehran Block Allama Iqbal Town
0 0 9.067
32. Approved Imp. Of Service Road Ashfaq Chowk Johar Town 0 0 4.399
33. Approved Imp/Carpeting of the Road Plt # 240 to 268 & 280 to 100 Block G/I (Saigal state) Johar Town
0 0 3.432
34. Approved Imp/Carpet. Of the Road from Lahore Grammar Senior School 364 E/I, Johar Town
0 0 4.75
35. Approved Electrification of Block B/I Gujjarpura Scheme 0 0 5.264
36. Approved Imp/Carpet. Of the Road for Lahore Grammar Girls Campus 534-G/I , Johar Town
0 0 2.29
37. Approved Construction of missing Road Links Block M Johar Town 0 0 2.514
38. Approved Construction of road to Fateh Garh & Repair of service road
0 0 7.441
39. Approved Construction of Missing Road Links in Block F/I Johar Town-I
0 0 3.141
40. Approved Imp/Carpet. Of Road in Block E , J & N sabzazar Scheme 0 0 4.973
41. Approved P/F Tuff Tiles & Kerb stone on Main Boulevard Gulberg 0 0 1.476
42. Approved Imp/Carpet of Road in Block J/II (part -II) Johar Town 0 0 4.768
43. Approved Imp/Carpet. Of Jand Muhammad from Kachi Kothi Raiwind road to Nayab Street
0 0 4.86
43. Approved Imp/carpet. Of Khairay Shah Road behind chiled protection bureau Mughalpura
0 0 4.4
45. Approved P/L of Tuff Pavers Jamia Masjid Allah Wali Kareem Block 0 0 0.745
CDG Lahore - Consolidated ADP 2012-13
116
Status Classification Budget Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
Allama Iqbal Town
Total Approved Schemes 40 0 322.558
SUB TOTAL NEW SCHEMES (1-45) 252 0 1296.42
LAHORE REHABILITATION PROGRAMME ONGOING SCHEMES
1. Approved Constructionof 40 m Wide Road from PIA chowk to southern bypass
0 45.5 191
2. Approved Improvement of Khyban e Firdousi Johar Town 0 0 230
3. Approved Rehab/ Imp . Peco Road from Peco roundabout to Lahore bridge Ferozpur Road
0 82.593 95
4. Approved Construction of Service Road along Khybaan e Jinnah from Shaukat Khanum Hospital Junction to riawind Road
200 87.974 141
5. Approved Improvement of shabir Usmani Road from Y junction to Faisal town Roundabout
0 0 166.603
6. Approved Replacement of 2Nos Outlived Force main from LMP block Johar Town to Sattukatla Drain
0 0 69.815
7. Approved Widening and Improvement of Model Town Link Road 113 114.017 53.717
8. Approved Construction of Madr e Millat Road Quaid e Azam Town 150 21.801 60
9. Approved W/Imp . Road along High Tension Wire from Bogiwal Road to China Chowk Gujjarpura
0 0 60
10. Approved Impr/Rehabilitation of Ferozpur Road From Kartaba Chwk to Khaira distributary Chungi Amer Sidhu Lahore
156 68.239 15
11. Approved Traffic Circulation Plan at Lalpul , w/I Canal Bank Road 0 0 54.165
12. Approved W/Imp of Road from Doctors Hospital to Tikka Chowk M.A Jauhar Town
28 21.922 20
13. Approved Improvement of Abu al Hasan Asfahani Road Faisal Town Lahore
110 114.114 10
14. Approved Improvement of 45 m Wide main road from Southern Bypass to Shadiwall M.A Jauhar Town
15 4.744 10
15. Approved Construction of Bridge at Butt Chowk , College Road Township
5 1.519 5
16. Approved Improvement &Carpeting of Main Boulevard Gulshan e Ravi from Multan Road to Band Road
15 7.252 9.5
17. Approved Improvement Carpeting of Internal Roads in Blocks P, R & M M. A Jauhar Town
11 0 11
18. Approved Improvement of Road from P Block Junction to Grid Station Sabzazar Scheme Ph. II
20 14.609 3
19. Approved Imp/Carpeting of Service Road Opposite Jinnah Hospital Faisal Town
0 0 3.8
20. Approved Imp of Rad approaching to House # 568, Block F-II M.A Johar Town Ph. II Lahore
0 0 1.023
21. Approved Construction of Bridge at Cantt Drain Gulshan e Ravi 35 22.787 0.3
22. Approved Construction of Road from Butt Chowk College Road to WASA Tanki no 4 Quaid e Azam Town
0.7 0 0
23. Approved Improvement &Carpeting of 20 M Wide Road from main boulevard Sabzazar to Bund Road
1 0 0
24. Approved Improvement and Carpeting of Road from F-II Park Link Doctors Hospital Road Block G Johar Town
4 0 0
25. Approved Construction of Boundary wall around Jinnah Park F-II & D-II Parks, Johar town
5 13.551 0
26. Approved Imp/Carpet of Captain Naseem Shaheed Road A.I.Town 4.5 4.167 0
27. Approved Imp/Carpet of Road From Bismillah Chowk to Multan 5 4.7 0
CDG Lahore - Consolidated ADP 2012-13
117
Status Classification Budget Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
Road
28. Approved P/L Tuff Paver in front of Minhaj ul Hussain Masjid Block H-III Johar Town Ph. II Lahore
0 1.887 0
29. Approved Construction of Alternate Route to Raiwind Road from Khyaban e Jinnah crossing to Defence Road Along Butcher Kahna distributary Lahore
0 130.549 0
Total Approved Schemes 878.2 761.925 1209.923
30. Un- Approved
45 m Wide Road leading to Trade Centre 1-17 Q & 9-M wide Roads (Part II) in Johar Town Scheme
35 0 0
31. Un-Approved
Widening and Improvement of Allahoo Chowk Roundabout M A Jauhar town
25 0 0
32. Un-Approved
Imp/Carpet of Hakim Chowk Johar Town 20 0 0
Total Un-Approved Schemes 80 0 0
SUB TOTAL (b) ONGOING SCHEMES (1-32) 958.2 761.925 1209.923
TOTAL (IV) LAHORE REHABILITATION PROGRAMME 1210.2 761.925 2506.343
(V) GOVT.ADP SCHEMES FINANCED FROM LDA RESOURCES
1. Approved Road from Babu Sabu to Multan Road Via Sabzazar Scheme
169 97.402 152
2. Approved Widening and Improvement of Bogiwal Road from G.T Road to Bund Road
194 135.294 128
3. Approved Widening and Improvement of Main Boulevard New Garden Town from Kalma Chowk to Canal Bridge through Y junction
174 198.654 0
4. Approved Construction of Structure Road from Khyban e Jinnah to Valencia town
112.862 102.719 0
5. Approved Providing and Installation of Gantry Sings at Underpasses Canal Bank Road
1.846 0.988 0
TOTAL (V) GOVT.ADP SCHEMES FINANCED FROM LDA RESOURCES 651.708 535.057 280
(VI) PARKING PALAZA
1. Un-Approved Motorcycle Plaza Yaseen Street Hall Road 39.602 0 0
2. Un-Approved Car Parking Plaza Neela Gunbad 389.7 0.827 0
3. Approved Car Parking and Commercial Plaza Moon Market AIT 590.627 132.485 500.625
TOTAL (VI) PARKING PALAZA 1019.929 133.312 500.625
(VII) MEGA PROJET GOVERNMENT OF THE PUNJAB
1. Un-Approved Underpass at Kalma Chowk garden Town 0 0 0
2. Approved Overhead Bridge at Canal Ferozpur Road 2000 1000 0
TOTAL (VII) MEGA PROJET GOVERNMENT OF THE PUNJAB 2000 1000 0
TOTAL (I-VII) SCHEMES FINANCED FROM LDA SOURCES 9169.922 3989.397 8382.696
1 Imp/Carpeting of 45m Wide road from U.B.D canal to shadiwal chowk in johar town
28 0.514 28
2 Widening improvement and carpeting of road along satokatla drain from ferozpur road to moulana shoukat ali road
25 0 25
TOATL 1. ADP LOANS/GOVERNMENT GRANTS 53 0.514 53
II. DEPOSIT WORK EXPENDITURES
1 Lahore press club housing schemes 50 2.885 50
2 Katchi Abadies 2.5 0 100
3 Construction of hospital at sbazazar scheme 0 0 230
4 Construction of bridge at cantt drain in samnabad between poonch road and fatehsher road
16.68 16.832 0
5 New work at fatimah jinnah college for women 5 29.07 0
CDG Lahore - Consolidated ADP 2012-13
118
Status Classification Budget Estimate 2011-12
Revised Estimate 2011-12
Budget Estimate 2012-13
6 Repair and maintenance of service hospital 1 0 0
7 nawab town housing scheme 5 3.129 0.314
8 restoration of road cut made in various schemes/sites 1 24.335 2.13
9 Development of various parks PHA 0 61.365 5.5
TOTAL II. DEPOSIT WORK EXPENDITURES 81.18 137.616 387.944
III.REFUND OF DEPOSIT EXPENDITURE
1 Refund of Security Deposit of Contractors 80 59.605 80
TOTAL III.REFUND OF DEPOSIT EXPENDITURE 80 59.605 80
TOTAL ADP DEPOSIT WORKS(I-III) 214.18 197.735 520.944
CDG Lahore - Consolidated ADP 2012-13
120
Parks &Horticulture Authority
Summary of Annual Development Programme 2012-13
S. No.
Programme
No. of
Schemes
Budget Estimate 2012-13
Rs. In million
%
A. Development Schemes 8 381.000 96%
New Schemes 8 381.000
B. Other Schemes 4 17.000 4%
Total 12 398.000
PHA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
122
Parks &Horticulture Authority Annual Development Programme 2012-13 - by Category
Category
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Replacement - - - 4 241 63% 4 241 61%
Refurbishment 4 17 100% 3 40 10% 7 57 14%
Up-gradation - - 0 0 0% 0 0 0%
Other 1 100 26% 1 100 25%
Total 4 17 100% 8 381 100% 12 398 100%
33% 4% 67% 96% 100% 100%
Shaer of Schemes by Category in PHA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
124
Parks &Horticulture Authority Annual Development Programme 2012-13 - by Sector
Sector
New %
Ongoing %
Total % No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million No. of
Schemes Rs.in
Million
Beautification of roads
0 - 0% 2 135 35% 2 135 34%
Beautification of Parks
4 17 100% 3 120 31% 7 137 34%
Establishment of new parks
0 - 0% 1 20 5% 1 20 5%
Others * 0 - 0% 2 106 28% 2 106 27%
Total 4 17 100% 8 381 100% 12 398 100%
33% 4% 67% 96% 100% 100%
Share by Sector in PHA ADP 2012-13
CDG Lahore - Consolidated ADP 2012-13
126
Parks &Horticulture Authority
Annual DevelopmentProgramme 2012-13 - by Scheme No. Programme Budget Estimate 2012-13
A) New Development Schemes:-
1 Development schemes (Government Grants) Old PC-I Schemes 0
2 Development schemes (Government Grants) New PC-I Schemes 0
3 Deposit works 100.000
4 Jashan-e-Baharan projects 0
5 Construction / Repair of Civil Works 15.000
6 Construction / Repair work of fountains & Parks (EME & W/S) 15.000
7 Establishment/development/extension of nurseries 20.000
8 Improvement of arboretum and allied facilities at Jallo 5.000
9 Development / improvement of existing schemes /
Parks & Gardens including LBC Green strips & Green belts 100.000
10 Development / improvement of high landscape
routes, chowks, roundabouts and triangles 120.000
12 Purchase of durable goods, machinery, vehicles
and equipment’s 6.000
13 Funds required to disburse liabilities arising from Dev. works 0
Total New Development Schemes 381.000
B) Specified Projects:-
1 Upkeep of "Minar-e-Pakistan park." 4.000
2 Upkeep of "Gulshan-e-lqbal Park" 3.000
3 Upkeep of "Jillani Park (Former Race Course Park)" 8.000
4 Upkeep of "Saint Marry Park" 2.000
Total Specified Projects 17.000
Total: 398.000
CDG Lahore - Consolidated ADP 2012-13
127
Glossary of Terms Budget- A budget is government’s annual financial plan describing the proposed expenditure
and the means of financing them.
Budget Estimate - It means, in relation to expenditure, the expenditure proposed for the
financial year, and, in relation to receipts, the receipts expected to be realized during that
financial year.
Budget Year or Financial Year- Budget year means the year commencing on the 1st July of
a calendar year, and ending on the 30th June of the following calendar year for which the
budget documents are prepared.
Capital Account is the account of expenditure incurred with the object either of
increasing concrete assets of a material and permanent character, or of reducing recurring
liabilities, and of the receipts of capital nature intended to be applied as set-off to capital
expenditure.
Capital Receipt refers to a receipt obtained from sources of finance other than Revenue.
Examples include loans, advances, grants, etc.
Development Scheme- Refers to an activity undertaken to acquire, build or improve physical
assets or develop human resources and is provided within the development expenditure grant.
Development scheme usually has a finite life and a specific source of funding.
Expenditure- This includes current and development expenditure on revenue account and
current and development expenditure on capital account. The term ‘expenditure’ as used in
budget documents usually covers budget estimates, revised estimates and actual expenditure.
Fiscal Transfer- Fiscal Transfers means the share of local governments with the Provincial
Consolidated Fund worked out as Allocable Amount, in accordance with the Award of the
Provincial Finance Commission and transferred to the Districts on a monthly basis.
Grant- Grant means the amount granted, or deemed to have been granted, by the competent
authority in respect of a demand for grant.
Revised Estimate- Is an estimate of the probable receipts or expenditure, for a financial year,
framed in the course of that year, with reference to the transactions already recorded.
Savings and Surrenders- Amount un-utilized out of budget allocation is called ‘Saving’.
Relinquishment of allocated funds by a spending department is called ‘Surrender’. This
generally happens when the allocated funds are not likely to be spent by that spending
department in a fiscal year.
Source- Source denotes the source of funds: capital or Revenue. Revenue means all receipts
raised by the government through levies, taxes etc. All other receipts (i.e. through loans, debt,
sale of assets etc.) are Capital Receipts.