CONFIGURATION MANAGEMENT
ECS Release 6A Training
CONFIGURATION MANAGEMENT
ECS Release 6A Training1
625-CD-612-001
Overview of Lesson
• Introduction • Configuration Management Topics
– M&O role in CM activities – Configuration Control Boards (CCBs) – Configuration Change Request (CCR) Process – Software Change Process – Hardware Change Process – Baseline Change Process
• Practical Exercise
2 625-CD-612-001
Objectives
• Overall: Proficiency in ECS Configuration Management
– Describe M&O role in CM activities – List Configuration Control Boards (CCBs), roles, and
responsibilities – Process a Configuration Change Request (CCR) – Prepare a request for impact analysis – Process a software change – Review Configuration Parameters in Configuration
Registry – Process a hardware change – Process a baseline change Not currently fully supported
3 625-CD-612-001
Importance
Lesson provides preparation for several roles to ensure effective CM for implementation of system changes
• CM Administrators • System Engineers, System Test Engineers,
Maintenance Engineers
4 625-CD-612-001
M&O Role and CM Activities
• Maintenance and Operations CM activities – After acceptance of ECS – Administrative and technical support of change control – Documentation and coordination of changes to site
hardware, software, and procedures – Configuration identification
– Maintenance and control of technical documentation
– Configuration status accounting – Recording and reporting information about the configuration
status of ECS documentation, hardware, and software – XRP-II
– Configuration audits – M&O supports internal and ESDIS assessments of project
compliance with relevant CM plans 5
625-CD-612-001
Problem Management Change Adjudication Development, Deployment and Installation
M&O Role: Change Management
TT DB 2
Pr
NCR DB 5
CCR DB 14
p
DAAC Top 20
Patch CCR/ECO/DCN
Class I CCRs
Future Release CCRs
DM/CM Document Master DB
17
A
Approved Status
ECS Configuration Baseline DB
19
Content/Cost/Schedule Coordination
g
Trouble Ticket (TT) Submitters �� DAACs �� Help Desk
1
Submit TT DB 2
Status
TT Investigators
Assign 3
Status
Status Report
TT Tele-conference
�� TT Management - Assess Impact - Prioritize - Assign - Status/Report - Close
�� DAAC Top 20 - Request Updates - Status
4
Priority Assign Close
NCR DB 5
Initial Priority Forward
Submit
Status NCR Assignee
Sustaining Engineering
7
Assign6
DAAC Top 20 Status
NCR Prioritization Team
- Impact and program priority
8
DAAC Top 20
M&O CCB/IPT Chair 15
Priority Status
Sustaining Engineering20
Patch CCR/ECO/DCN
Sustaining Engineering Deployment IPT
�� Patch Content �� Cost/Schedule Estimates �� Track NCR Work-off and
Testing �� Patch Release CCR/ECO/
DCN �� Conducts PSRs
9 10
Priority
NCR Board Recommends
Closure
11
Verified NCRs
CCR DB 14
CCR Closure
Progress Reports
M&O CCB
�� Attends PSR �� Approves CCR/ECO/DCN �� Approves NCR Closing �� Monitors/Supports
Changes
13
Verified NCRs
CCR Submitters �� DAACs �� Sustaining Engineering
Requests for Perfective
Change CCRs
12
Data Management
Drawing ECOs/DCNs
16
DM/CM Document Master DB
17
Document/Drawing Masters
Changes Installed
(ECO Closed) Status
SMC/DAACs
18CCR Approval & Schedule
Approved Status
ECS Configuration Baseline DB
19
Changes Shipped
(Released) Status
Perfective Change Request
Perfective Change
Coordination
ESDIS CCB (SS PCMB)
21
Class I CCRs 22
Future Release CCRs
ECS Development Facility (EDF)/
Science Development (SCDV) CCB
Sustaining Engineering
- Create Changes/ Procure - Test Changes
23
CCR/ECO/DCN: - Patches - Install Instructions - Requirement/Design
Documents - Configuration Baseline
Changes - OPS Procedures
Test Plans and Procedures Test Report
Content/Cost/Schedule Coordination
6 625-CD-612-001
M&O Role: Science Software CM
• Science Software CM – developed at Science Computing Facilities – upon delivery to DAAC, enters custody
of DAAC CMO – SSI & T: DAAC management and I &T team – M&O role
• support during I & T • support DAAC Manager after acceptance • if Science Software has inter-DAAC dependencies, support
coordination with affected DAACs • ensure any necessary coordination with ESDIS prior to
moving Science Software into production operations
7 625-CD-612-001
System Operations Support
• SOS -- System Operations Support
– liaison between sites and ESDIS CCB – liaison between operations and the Sustaining
Engineering Organization (SEO) – coordination of CM functions – maintenance of Change Request Manager (DDTS) – oversight for dissemination of controlled items to sites – monitoring of installed configurations of hardware and
software for conformance to approved baselines – M&O ensures coordination and availability of needed
data for change management
8 625-CD-612-001
M&O Role: Maintenance of the M&O Libraries
• Maintenance of M&O Documentation and Software Library – both common and site-specific software – site personnel responsible for CM associated with
library
9 625-CD-612-001
M&O Role: Library Administration
• Soft or hard copy maintained in library • Document support directories
– CUSTOM/docs: file descriptive materials
– CUSTOM/docserver: document repository
• Microsoft Access database for library holdings and index
• Baseline Manager tool for documents that are under baseline CM control
10 625-CD-612-001
Baseline Control
• Baseline control milestones during maintenance and operations – Installation Plan (IP): COTS hardware configuration – Consent to Ship Review (CSR): hardware and software
configuration and plans for host sites – Release Readiness Review (RRR): documents state of
configuration items at each host site – Operational Readiness Review (ORR): documents flight
certified, ESDIS-approved, fully integrated EGS
• Site authority – ESDIS - authority over changes to common software – site CCB - authority over site-specific Class II changes – site-specific parameters for COTS software – specific configuration of tools and utilities, as delegated
by ESDIS 11 625-CD-612-001
Configuration Identification
• Establishes unique identifiers for ECS control items: Hardware, Software, Databases, Documentation
• ECS System Baseline Specification identifies Configuration Items (CIs) – Defines configuration baseline data structure and data
schema – Delineates how items will be named, described,
versioned, and controlled – Defines the item’s associated engineering specifications
and location of the actual controlled baseline data (including the ECS Configuration Baseline database)
• Configuration Baseline may change with a new System Release or with a patch
12 625-CD-612-001
Configuration Status Accounting
• Reports, metrics, records to support configuration management with status tracking information – identification and resolution of configuration problems
(e.g., Trouble Ticket, NCR listings, progress reports) – M&O CCB review/approval of baseline changes (e.g.,
CCR listings,progress reports, CCB agendas, minutes) – monitoring progress for change implementation (e.g.,
ECO/DCN status reports, IPT Drop Matrix listings) – maintenance of ECS Configuration Baseline status (e.g.
Approved/Shipped Changes, Installed Changes) – Verification and auditing of baselines (e.g. discrepancy
metrics/reports reflecting differences between the approved and installed baselines in both the testing environment in the Verification and Acceptance Test Center [VATC] or Performance Verification Center [PVC] and at the DAACs) 13
625-CD-612-001
Configuration Audits
• Conducted by ECS CMO, supported by site CM • Functional Configuration Audit (FCA) and
Physical Configuration Audit (PCA) validate that: – as built configuration compares with the approved
baseline – test results verify that each ECS product meets its
specified performance requirements to the extent determinable by testing
– the as-built configuration being shipped compares with the final configuration tested in the VATC
• Differences between the audited configuration and the final tested configuration are documented
• Automated scripts compare DAAC configurations to baseline documentation
14 625-CD-612-001
CCB Hierarchy
NASA Headquarters Earth Science Enterprise
Configuration Control Board (CCB)Mission Planning, CCRs, ECPs, and
Management of ECS Operations
ESDIS CCB
Science Systems Project Configuration Management Board
(PCMB)
Mission Systems Project Configuration Management Board
(PCMB)
CCRs, Impacts, DirectivesControl of ECS
Product Baseline
ECS CCB
M&O CCB, Release CCBs, FOS Segment CCB, and
EDF CCB
Site-Level CCBs Control Operational Baseline
DAAC CCB at each site
M&O provides services; ATO integrates and tests next release
until RRR acceptance
Controls Operational Baseline
SCF CCB Controls Science SW Baseline
Algorithm Development, Integration, and Test;
Scientific Investigations
EOC CCB Controls Operational Baseline
M&O provides services; ATO integrates and tests next release
until RRR acceptance
SMC CCB Controls Operational Baseline
M&O provides services; ATO integrates and tests next release
until RRR acceptance
Network/Scheduling/Services
ECPs, DRs, and Technical Direction
Feedback of all System Changes,
TTs, CCRs
Sustaining Engineering Changes to Common Baseline
System Acceptance
(RRR)
Technical Direction
EMOS Only
(CSR/RRR/ORR/ Approved Upgrades)
Science Only
System Enhancements
Level 1
Level 2
Level 3
Level 4
15 625-CD-612-001
CM Responsibilities
• ESDIS Management – establishes ECS CM policies
• CCBs – classify, prioritize, evaluate, recommend, and approve
(within their authority) changes to baselines
• CM Administrators (at SMC, EOC, DAACs, SCFs) – establish and maintain CM records – facilitate the configuration change request (CCR)
process – monitor and report status of proposed and approved
CM actions – support their respective CCB (as required)
16 625-CD-612-001
CM Responsibilities (continued)
• Sustaining Engineering Organization (SEO) -– assesses feasibility and cost, schedule and
performance impacts of proposed system-wide changes – implements such changes when directed by ESDIS
• DAAC Sustaining Engineers -– assess DAAC impacts of system-wide proposed
changes – develop and maintain ESDIS-approved DAAC-specific
modifications to ECS products
• Maintenance Engineers -– maintain ECS HW and report configuration changes
resulting from maintenance actions
17 625-CD-612-001
18
ECS CCB
ECS Development
CCBs
Potential changes, Change authorization
Impact assessments, Incorporation schedules, ORR baseline, Release baseline
ESDIS CCB
Mission Systems PCMB
Science Systems PCMB
ESDIS Project Office ECS System Items
Sc only
EMOS only
Potential changes, Change authorization, M&O baseline updates, Incorporation schedules
Impact assessments, Incorporation schedules, ORR Baseline Release baseline
DAAC CCB at each site
“CM” at
each SCF
SMC CCB
EOC CCB
Host Site CCBs
Deliver Science Algorithms
Operational CCB Relationships
Potential changes, Incorporation changes, M&O baseline update, Site extensions, Impact assessments
ORR baselines, EP baselines M&O baseline updates, Operational documentation, Potential changes, Technical direction, Science algorithms, SCF services
Coordination of system-level SW distribution and inventory; problem reporting, network management, and baseline management
Mission Operations configuration control of ECS FOS and external interfaces to EDOS, NISN, and ETS
FOS Segment
CCB
Release CCBs
M&O CCB
ECS Enhancement CCRs
Site Tailored Items
Coordination of science algorithms, SCF services, data production, archive, and distribution services as allowed by policy
625-CD-612-001
Science Software and Change Control
• Science Computing Facility (SCF) performs configuration control – Software and Databases to be executed at another site – SCF resources that are made available to EOSDIS
community • ECS M&O function directed by DAAC CCB
– Accepts science software and data from the SCF – Provides services to support EOC control of the EOC
operational baseline • Central coordination by Project Control Manage
ment Board – ECS integrity and quality of service – Coordination with internal and external networks,
systems, facilities – ESDIS CCB visibility into ECS operations – Convenient user administrative services 19
625-CD-612-001
Configuration Change Requests (CCRs)
• No undocumented changes – all requests for change documented using CCR form – CCR generated against the baseline affected by the
proposed change – Form can be completed electronically
• Word processing form • Change Request Manager tool (CM Administrator)
• CCB review – CCR submitted to appropriate CCB – CCR form may also be a cover sheet for a request to
CCB for a deviation or waiver from baseline
20 625-CD-612-001
ECS CCR Form
Earth Observing System Data and Information System (EOSDIS) Core System (ECS)
Configuration Change Request (CCR)
1. Configuration Change Board (CCB) ESDIS:___ CS:___ SMC:___ DAAC: GSFC___, LaRC ___, ASF___, EDC___, JPL___, NSIDC___, ORNL___ EOC:___
2. CCR No.
3. Submitted Date: 4. Revision 5. Priority Emergency Urgent Routine
6. Change Class 7. Status
8. CCR Title:
9. Originator: Org: e-mail: phone: 10. Approval:__________________________ _______________
signature date
11. Reason for Change
12. Description of Change
13. Impact Analysis: Cost: None Small Medium Large
Evaluation Engineer: Org: e-mail: phone: Impact Evaluators: ESDIS___; ECS Dev___; SEO___; SMC___; DAACs: GSFC___,
LaRC ___, ASF___, EDC___, JPL___, NSIDC___, ORNL___; EOC___; Others_______________________________________________
(indicate attachment ___)
(indicate attachment ___)
(indicate attachment ___)
(indicate attachment ___)
(Not exceeding $100,000) ($100,000 to $500,000) (Over $500,000)
14. Comments: (Indicate Sites/ Organizations Affected)
15. Board Action: Approved Withdrawn Disapproved Deferred Until_____ date
Further Action Required: ECP Waiver Deviation Tech Direction Contract Mod. DCN Other:_______________________________________________
16. CCB Approval Chair:_______________ ________
signature date
17. CCR Implemented CM Admin. signature:_________ date:____
E
21 625-CD-612-001
Request for Impact Analysis
• Support of ESDIS CCB may require assessment of the impact of a proposed CCR on local or system maintenance and operations
• Assessing the impact of CCRs with significant system implications and/or potential system-wide application may require the assistance of the ECS development organization
• Formal request for impact assessment according to Mission Operation Procedures for the ECS Project (611-CD-510-001)
• Impact assessments consolidated into a CCR Impact Summary
23 625-CD-612-001
CCR Impact Analysis Form
CCR Impact Analysis
Responder Request Number: ____ Responder:______________________ Responder Point of Contract:
address:____________________ ___________________________ phone:______________________ e-mail:______________________
CCB Schedule Date:_____________ CCR Number:___________________ CCR Log Date:___________________ CCR Originator:__________________ CCR Originator Point of Contract:
address:____________________ ___________________________ phone:______________________ e-mail:______________________
Evaluation Engineer: ______________ Evaluation Engineer Point of Contact:
address:___________________ __________________________ phone:_____________________ e-mail:_____________________
Requested Return Date:____________
Rough Order of Magnitude (ROM) Impact Analysis
Basis of Estimate:
Technical Assumptions and Comments:
Cost Impact: None [ ] Small [ ] < $100,000 Medium [ ] $100,000 < x < $500,000 Large [ ] > $500,000
Schedule Impact:
Technical Assessment: ( Your impact analysis should consider the implementation approach; interfaces affected; HW or SW changes required; documentation changes required -- change from/to pages; suggested alternatives, if any; and impact to security features. If your system is not impacted, please provide that information to the CM Administrator. )
Comments: Signed:__________________________
(Responder) Date:________________
24 625-CD-612-001
CCR Impact Summary
CCR Impact Summary
Evaluation Engineer: ______________ Evaluation Engineer Point of Contact:
address:____________________ ___________________________ phone:_____________________ e-mail:_____________________
CCR Board Date:_____________
Resources Summarized:
Technical Summary:
ROM Summary (BOE, Cost, and Schedule):
Recommendation:
Signed:__________________________ (Evaluator)
Date:________________ 25 625-CD-612-001
Software Baselines and Changes
• Software release is through ESDIS SMC or, with ESDIS permission, directly to the sites – Version Description Document (VDD) provides summary
documentation package – ECS Project CMO assembles and packages the delivery
• Change Scenarios – COTS software problem – custom software problem – science software upgrade – COTS software upgrade – system enhancement
26 625-CD-612-001
Transfer Functional Flow
ESDIS CCB
SEO CM Administrator
directs transfer of
SW Maintenance Change
Notify DAAC
MSS (SMC)
Invoke Baseline Manager
MSS (SMC)
Invoke Software
Distribution Manager
(SDM)
MSS (SMC)
Copies, transfers S/W from Library to
SDM
MSS (SMC)
Provides DAAC
Receiving Address
MSS (SMC)
Sends S/W Package to DAAC
MSS (DAAC)
Sends S/W Package to DAAC
Check Pkg MSS (DAAC)
Plan Installation
of Maintenance Change S/W
Software Transfer & Installation:
27625-CD-612-001
28
Installation Functional Flow
Sustaining Engineering--
S/W Maintainer
DAAC CCB
DAAC CM Administrator
directs installation of
SW Maintenance Change
Execute
MSS
Install with ECS
Assistant
Initiate
MSS
Makes/ Builds
S/W
Execute
MSS
Distributes
Perform
MSS
Tests
[failure]
Trouble Ticket Review Board
(TTRB)
Refer for problem resolution Resolution
Execute
MSS
Runs in operational
environment
Perform
MSS
Notifies TTRB of Results
Notify
DAAC CCB
DAAC CM Administrator updates the
Baseline Record and Inventory
Software Transfer & Installation:
625-CD-612-001
Software Transfer
• When software maintenance change package is ready and approved by ESDIS CCB, SEO CM Administrator requests SMC to distribute
• SMC CM Administrator promotes the change to the Operational Baseline and updates the Baseline Record and Inventory Record
29 625-CD-612-001
Software Change Installation
• Review/approval by ESDIS precedes systematic installation – VDD final updates for system and center-specific
material; final VDD is published – Installation of the build and operational and user
documentation IAW installation schedule • ECS Assistant for installation • Scripts for System Administrator to do installation
– Controlled document updates provided to SEO Document Maintenance and entered into CM
– CM system updated to reflect M&O and center-specific baselines
30 625-CD-612-001
Software Change Installation (Cont.)
• Implementation and test of software by DAAC Software Maintenance Engineer – Tests individual packages (unit, subsystem, system) – Runs full final software in operational environment – Notifies SMC of results
• DAAC CM Administrator updates site baseline record using Baseline Manager (BLM) tool – DAAC CCR Number – Software package identification – Package name – Software upgrade name – Version – File structure – Type – Installation date 31
625-CD-612-001
Configuration Parameters
• Default settings may or may not be optimal for local operations
• Changing parameter settings – May require coordination among Configuration
Management Administrator, Database Administrator, and Operations personnel
– Some parameters accessible on GUIs – Some parameters changed by editing configuration files – Some parameters stored in databases
• Configuration Registry (Release 5B, 2nd delivery) – Script loads values from configuration files – GUI for display and modification of parameters – Move (re-name) configuration files so ECS servers
obtain needed parameters from Registry Server when 32starting
625-CD-612-001
Hardware Baselines and Changes
• Hardware baseline established at Release Readiness Review (RRR) following formal Physical Configuration Audit (PCA) and Functional Configuration Audit (FCA) – ESDIS approves establishment of operations baseline – Configuration baseline recorded in Engineering Release
Record – M&O conducts testing of builds to ensure proper
implementation of CCRs with no defects introduced
• Change Scenarios – COTS hardware problem repair that requires a CCR – System enhancement
35 625-CD-612-001
Hardware Change Installation
• Repair with part of same make, model, version does not require CCR
• Change in make, model, version of a part to be used for repair, e.g., in an emergency, necessitates CCR to document the change – Review/approval by site CCB – Review by SEO/ESDIS for impacts/applicability to other
sites – Provision of controlled document updates to SEO
Document Maintenance and entry into CM – CM system updates to reflect change – Audits (FCA/PCA)
36 625-CD-612-001
Changes to the Baseline
• CM Tools for baseline changes – Change Request Manager: DDTS – Baseline Manager: XRP-II – Inventory/Logistical Manager: XRP-II
Incomplete: ine Database may not be deployed; Inventory Database for information only
Basel
• Related tools – From Management Subfunction software
• Trouble Ticket System (TTS) • Problem reporting and tracking • Used by users, operators, system administrators
37 625-CD-612-001
CCR Approval Flow
ECS CCB and Other CCBs
ESDIS CCB (PCMB)
Site CCB Site
Engineering Site
Operations
TT Telecon
Approved TT
1
Escalate TT?
2
CCR Proposed
3
CCR Telecon
4
Rew
ork
Status = PENDING
5Status =
PENDING
6Impact Assess
ment
7
8 Status = APPROVE
Status = APPROVE
Status = APPROVE
10
9 CCR Telecon
11
Schedule Implement
ation
12
TT Telecon
13 CCR
Implemented
14
M&O CCB
TT Telecon
Resolve TT/NCR
No
Yes
38 625-CD-612-001
Baseline Terms and Concepts
• Baseline Management is to identify and control baselined versions of hardware and software, and maintain a complete history of baseline changes
• Control Item is any ECS item under version control by CM
• Configuration Item (CI) is an aggregation of hardware, firmware, software, or any discrete component or portion, which satisfies an end user function and is designated for configuration control
• Baseline is a configuration identification document or set of such documents formally designated by the Government at a specific time in the life cycle of a CI
• Configured Article is a control item reportable as part of the Configured Articles List (CAL)
39 625-CD-612-001
Baseline Terms and Concepts (Cont.)
• ECS Structure and Baseline Terms – Assembly: an item made up of other items
• Parent: a higher-level item (e.g., an assembly) • Child: an item that is a component of a higher-level item
– Bill of Material: list of items that comprise an assembly – Product Structure: the parent-child pairings that define
the bill of material for an assembly; each product structure record specifies the effective dates and quantities for a single component of a parent for each engineering change
– Active Date: the date a component becomes effective in an assembly’s bill of material
– Inactive Date: the date a component is no longer effective in an assembly’s bill of material
40 625-CD-612-001
Baseline Terms and Concepts (Cont.)
• ECS Structure and Baseline Terms (Cont.) – Engineering Change: a mechanism for grouping,
reporting, and controlling product changes collectively – Revision: sequence number of a product structure
change to an assembly; signifies a change to the configuration of an assembly that does not alter its form, fit, or function
– Implementation Status: a record describing the deployment of a control item to a site and the current state and associated date of its implementation; each control item has one record for each site to which it is deployed
– Exporting Data: creating a formatted file or records extracted from the BLM database; control item engineering change, product structure, and interdependency records may be extracted and sent to another BLM site via ftp
– Importing Data: loading BLM data from a formatted file 41
625-CD-612-001
Product Structure - Design View
S ub system -1 ver: 2.0
C om p o nent - 1 ver: 2.0
C o m p o nent - n ver: 2.0
HW CI - 1 ver: 2.0
HW C I n ver: 2.0
SW C I 1 ver: 2.0
CS C 1 ver: 2.0
CS C - n ver: 2.0
SW C I - n ver: 2.0
Sub system 2 ver: 2.0
S ub system - 3 ver: 2.0
S ub system -4 ver: 2.0
EC S Pro d uct B a seline ver: 2.0
Configured Articles
42 625-CD-612-001
Product Structure - Operational (Network) View
S i te 1 O p e ra ti o n a l N e t w o r k B a s e l in e ve r : 2 . 0
S ite n F D D I N e t w o r k - 1 ve r: 2 .0
S it e n F D D I R in g 1 v e r : 2 . 0
H u b m o d e l: x x
F D D I C o n c e n t r a t o r m o d e l : x x
P r in te r m o d e l: x x
P l a tfo r m /P ro c e s s o r m o d e l : x x
R A I D m o d e l : x x
D is k D riv e - 1 m o d e l : x x
D is k D riv e - n m o d e l : x x
M o n i t o r m o d e l : x x
M e m C a rd m o d e l : x x
H a rd w a re B u n d le v e r : 2 . 0
P r o g ra m n ve r: 2 .0
D a t a b a s e n ve r: 2 .0
D a ta n ve r: 2 .0
C o n fig P a r a m s n ve r: 2 .0
I n s t a l la b le U n it 1 v e r: 2 . 0
P r o g r a m n v e r : 2 . 0
D a ta b a s e n v e r : 2 . 0
D a ta n v e r : 2 . 0
C o n fig P a ra m s n v e r : 2 . 0
In s ta ll a b le U n it n ve r : 2 . 0
P a c k a g e 1 (c u s t o m ) v e r : 2 . 0
P ro d u c t 1 ve r : n n
P ro d u c t n ve r : n n
P a c k a g e n (C O T S ) v e r :2 . 0
O S ve r : n n
O S P a tc h 1 ve r : n n
O S P a tc h n ve r : n n
O S P a tc h e s v e r: 2 .0
P ro g r a m P a tc h - 1
P ro g r a m P a tc h - n
P r o g ra m P a t c h e s v e r : 2 . 0
S o ft w a r e B u n d l e ve r: 2 .0
D is k P a rt itio n 1 v e r : 2 . 0
D is k P a r t it io n 2 ve r: 2 .0
F o rm - 1 ve r: 2 .0
F o rm - 2 ve r: 2 .0
C o n fi g u r a t io n D a ta ve r : 2 . 0
H o s t 1 v e r : 2 . 0
H o s t n ve r : 2 . 0
C o n fi g u r a t i o n D a t a ve r: 2 .0
S it e n F D D I R in g - n v e r : 2 . 0
F D D I S w it c h / R o u te r m o d e l : x x
C o n fi g u r a t i o n D a t a ve r: 2 .0
S it e - n F D D I N e t w o r k n ve r: 2 .0
S i te n H IP P I N e tw o r k v e r: 2 . 0
C o n fig u ra ti o n D a t a v e r : 2 . 0
S ite n N e tw o r k ve r : 2 . 0
S ite - n D o c u m e n t s ve r : 2 . 0
S i te n O p e ra t i o n a l N e t w o r k B a s e l in e ve r : 2 . 0
E C S O p e r a t i o n a l N e t w o r k B a s e li n e ve r: 2 .0
Configured Articles
43 625-CD-612-001
(Subsystem) View
S ite 1 O p e ra tio n a l S u b sys t e m B a s e lin e ve r: 2 . 0
S ite n S u b s y s te m 1 ve r: 2 . 0
H o s t 1 ve r: 2 .0
P la t fo rm / P ro c e s s o r m o d e l: xx
R A I D m o d e l: xx
D is k D riv e 1 m o d e l: xx
D is k D riv e n m o d e l: xx
M o n it o r m o d e l: xx
M e m C a rd m o d e l: xx
H a rd w a re B u n d le ve r: 2 . 0
P ro g ra m n ve r: 2 . 0
D a t a b a s e n ve r: 2 . 0
D a ta n ve r: 2 . 0
C o n fig P a ra m s - n ve r: 2 . 0
I n s ta lla b le U n it - 1 ve r: 2 . 0
P ro g ra m n ve r: 2 .0
D a t a b a s e n ve r: 2 .0
D a t a n ve r: 2 .0
C o n fig P a ra m s - n ve r: 2 .0
In s t a lla b le U n it - n ve r: 2 . 0
P a c k a g e - 1 (c u s t o m ) ve r: 2 . 0
P ro d u c t 1 ve r: n n
P ro d u c t n ve r: n n
P a c k a g e - n (C O T S ) ve r: 2 . 0
O S ve r: n n
O S P a tc h 1 ve r: n n
O S P a tc h n ve r: n n
O S P a tc h e s ve r: 2 . 0
P ro g ra m P a t c h - 1
P ro g ra m P a t c h - n
P ro g ra m P a tc h e s ve r: 2 . 0
S o ft w a re B u n d le ve r: 2 .0
D is k P a rt it io n - 1 ve r: 2 . 0
D is k P a rtit io n - 2 ve r: 2 . 0
Fo r m 1 ve r: 2 . 0
Fo r m 2 ve r: 2 . 0
C o n fig u ra t io n D a t a ve r: 2 . 0
H o s t n ve r: 2 . 0
P rin t e r m o d e l: xx
F D D I S w itc h / R o u te r m o d e l: x x
H u b m o d e l: xx
F D D I C o n c en t ra t or m o d e l: xx
S ite n S u b s y s te m n ve r: 2 . 0
S it e n D o c u m e n ts ve r: 2 . 0
S it e - n O p e ra t io n a l S u b s ys te m B a s e lin e ve r: 2 .0
E C S O p e ra t io n a l S yb s ys t e m B a s e lin e ve r: 2 . 0
Configured Articles
Product Structure - Operational
44625-CD-612-001
XRP-II Hierarchical Menu Structure
Baseline Management System Tools
Main
ILM Main Menu System Utilities MenuBaseline Management
Disk Partition Items Only
All Control Items Hardware Items OnlySoftware Items OnlyHost Items Only Document Items Only
Control Item Master
Engineering Change Entry Engineering Change Items Page
Engineering Change Approval Engineering Change Items Page
Bill of Material
Product Structure Manager Replace Component in Selected Bills
All Control Items QueryHardware Items QuerySoftware Items QueryHost Items QueryDocument Items QueryDisk Partition Items QueryProduct Structure QueryEngineering Change Query
Query Menu
Implementation Status Query
Unit of Measure Manager Unit of Measure Conversion Vendor Master Manager Control Item Interdependency Mgr
Vendor Address Maintenance Implementation Status Control Item Date Manager Low Level Code Manager
Utilities Menu
Responsible Organization Maintenance Item Class Manager Function Manager Clone Manager
MultiLevel Bill Reports Summarized Bill Reports MultiLevel Where Used Reports Configuration Item List - One Configuration Item List - Two Configured Articles Reports Version Description Reports Site Baseline Report Change History
Reports Menu
BOM Comparison Reports Hardware/Software/Patch Map Reports Software Baseline Reports Site - Host MapBaselined Documents Reports 46
625-CD-612-001
(Cont.)
Baseline Management System Tools
Main
ILM Main Menu System Utilities MenuILM Main Menu
EIN Entry EIN Manager EIN Structure Manager EIN Inventory Query
EIN Menu
EIN Installation EIN Shipment EIN Transfer EIN Archive EIN Relocation Inventory Transaction Query
EIN Transactions
Order Point Parameters Manager Generate Order Point Recommendations Recommended Orders Manager Transfer Order Point Orders Consumable Inventory QuerySpares Inventory QueryTransfer Consumable & Spare Mat’l
Inventory Ordering Menu
Material Requisition Manager Material Requisition Master Purchase Order Entry Purchase Order Modification Purchase Order Print Purchase Order Status Receipt Confirmation Print Receipt Reports Purchase Order Processing Vendor Master Manager
PO/Receiving Menu
Work Order EntryWork Order Modification Preventative Maintenance Items Generate PM Orders Work Order Parts Replacement HistoryMaintenance Work Order Reports
Maintenance Codes Maintenance Contracts Authorized Employees
Maintenance Menu
Work Order Status Reports
ILM Inventory Reports EIN Structure Reports Install/Receipt Report EIN Shipment Reports
ILM Report Menu
Transaction History Reports PO Receipt Reports Open Purchase Order Reports Installation Summary Reports
Employee Manager Assembly Manager System Parameters Manager Inventory Location Manager Buyer Manager Hardware/Software Codes Status Code Manager Report Number Export Inventory Data
ILM Master Menu
DAAC Export Inventory Data OEM Part Numbers Shipment Number Manager Carriers ILM Import Records Sales/Purchase Terms Maintenance Reason Code Maintenance Site Codes for Scanned Data Scanned Data Process Scanned Data
License Entitlement Manager License Manager License Allocation Manager Maintenance Contracts Adjust License Quantities
License Menu
XRP-II Hierarchical Menu Structure
47625-CD-612-001
(Cont.)
Baseline Management System Tools
Main
ILM Main Menu System Utilities MenuSystem Utilities Menu System Tools System Parameters Manager System Defaults Manager Note Code Maintenance Data Delete Utility Calendar Utility Calendar Report Transaction Log Transaction Archive Site Master Manager Machine Network Maintenance Commodity Code Maintenance Import BLM Records Export Release Records Export Site-Unique Change Records Export SMC Change Records
Screen Manager User Manager Groups Manager Screen Permission Control Menu Manager Printer Manager Data Dump Utility Data Load Utility Call Accell System
XRP-II Hierarchical Menu Structure
48625-CD-612-001