CONCRETE REPAIR
PROCEDURE & MEASURE
8/30/2015 1
APRIL 25, 2015
SAUDI DIYAR CONSULTANTS ARCHITECTS & ENGINEERS 24 North Jeddah building A & B Prince Sultan Street, Al-Nadha District Kingdom of Saudi Arabia Tel: +966 2 699 9888. Fax: +966 2 699 9777, E-mail: [email protected]; web: www.diyar.com
Classification of Repair Minor Concrete Repair Deep Concrete Repair
Honey combed voids
Tie Rod holes
Minor voids
Cavities in concrete
Mass concrete in loose profile
8/30/2015 2
Range of Void
05 mm to 25mm (Approx)
Range of Void
30 mm to 125mm (Approx)
Execution Sequence Minor Concrete Repair Deep Concrete Repair
• Surface preparation 1. Hammer, chisel, jack hammer
2. Cleaning with air blower/compressed air
• Application of bonding agent on substrata (old concrete)
• Application of Repairing material
• Curing
• Surface preparation 1. Chipping/scabbling of concrete by jack
hammer 2. Remove loose concrete, cleaning with air
blower or brush
• Expose the reinforcement of structural element
• Application of protection coat on the steel surface (against corrosion)
• Application of bonding agent on substrate surface(old concrete)
• Installation of rigid, water tight formwork
• Application of Repairing material
• Curing
8/30/2015 3
8/30/2015 4
Diagnosis & Treatment (D&T)
Concrete repair, execution sequence
Engr: Adil Rehman
Engr: Emad Hamdy
Area Responsible:
8/30/2015 5
MINOR CONCRETE REPAIR
TUNNEL WALLS/ COLUMNS:
Fair faced surface/ small voids repair
MATERIAL:
Nitobond AR Renderoc-FC Renderoc-HF
8/30/2015 6
WORK SEQUENCE:
• Safe Access
• Mark repair area
• Surface cleaning ( Remove dirt, oil, other contaminants)
• Chipping/ scabbling by Hammer & chisel, jack hammer
• Cleaning of surface with air blower & brush.
• Apply Nitobond A.R on substrata surface (old concrete)
• Apply Renderoc-FC by hand tools (Trowels, scrapers)
• Apply Renderoc-HF by hand tools (Trowels, scrapers)
• Curing, Renderoc-FC ( may not be required or cured with A.R)
• Curing, Renderoc-HF ( curing compound)(Concure /A.R
or Traditional way, wet hessian, water etc)
• Review technical data sheets for particular material
8/30/2015 7
Mixing:
Renderoc-FC: 4 Litres fresh water, 1.2 Litre (20-Kg bag) Nitobond A.R, 4 litre Renderoc-H.F: 3 Litres fresh water (25-Kg bag) Review data sheets particularly each material
8/30/2015 8
Review the Illustrations
9
Comments:
Location:
Honey combed in wall,
Minor voids
Retaining R.C Wall
in tunnel
Honeycombs in
8/30/2015 10
Honeycombs in
8/30/2015 11
Unrepaired area
Surface repair area
8/30/2015 12
Surface repaired area
Unrepaired area
8/30/2015 13
DEEP CONCRETE REPAIR
COLUMNS:
Deep voids repair
MATERIAL:
Nitoprime Zincrich (for steel protection) Nitobond EP (for concrete bonding agent) Renderoc HF (for repair material) Curing compound (Concure or traditional method)
8/30/2015 14
WORK SEQUENCE:
Safe Access
Mark repair area
Surface cleaning ( Remove dirt, oil, other contaminants)
Concrete chipping by jack hammer, remove loose concrete, expose steel if necessary.
Cleaning of rebars by steel wire brush, sand blasting if necessary.
Apply Nitoprime Zincrich on clean rebars (two coats)
Apply Nitobond EP on clean substrata (old concrete), two coats
Install formwork (rigid and tight)
Apply silicone to seal the formwork (water tight)
Apply Renderoc-HF
Curing, (use curing compound )(concure/A.R or traditional way, wet hessian, water)
Review technical data sheets & method statement entire material.
8/30/2015 15
Mixing:
• Renderoc-H.F: 4.3 to 4.5 Litres fresh water, 25-Kg bag • Nitobond EP (slow set base, slow set hardner) • Nitoprime Zincrich (2.5 Litre, ready to apply) • Review data sheets particularly each material
8/30/2015 16
Review the Illustrations
Requires deep Repair
8/30/2015 17
Surface preparation
8/30/2015 18
Breaking by Jack hammer , Debris of concrete
8/30/2015 19
Application of Nitoprime Zincrich
8/30/2015 20
Application of Nitobond EP
Install Formwork
8/30/2015 21
Application of silicone
8/30/2015 22
Mixing of Renderoc-HF
Measurement of water
8/30/2015 23
Application of Renderoc-HF
8/30/2015 24
After remove formwork
Close up
8/30/2015 25
Cure, Wet Hessain (water)
8/30/2015 26
NON REPAIRABLE
WORK SEQUENCE:
• Fact and finding
• Cavities probing
• Prepare initial illustrations report
• Get Engr, David & Rehan expert opinion in this regard
• Demolish the structural element by jack hammer or stitch coring etc.
Marked location plan V.B= Very bad columns Colored columns= Need repair
8/30/2015 27
Column to be
demolished
8/30/2015 28
8/30/2015 29
Column to be
demolished
8/30/2015 30
Column to be
demolished
8/30/2015 31
SPECIAL THANKS;