concrete 2014a-lecture7
TRANSCRIPT
Lecture 7 - Concrete
Objectives:-
1.To learn the units of measurement of concrete.2.To relate the measurement as per clauses in SMM23.To determine the classification of sizes for slabs.
Outcomes:-1.Able to differentiate the different clauses used for the measurement of concrete2.Able to write down the dimensions based on the drawings.
Unit of measurement
• Measurement to be in m3 or volume for all structural members.
Clause F3.3 Isolated foundation base
• 1. To identify the footing.
• 2. To include the number.
Foundation - Footing
Clause F3.4 - Casings
• 1. Concrete support to hand railing.
• 2. Measurement to include the number of support.
Steel railing
Concrete support
Clause F3.5 ground beams
• Concrete for ground beams must not be group with other members like stump and footings.
Ground beams
Stump
Footing
Clause F.3.6 Casing to steel ground beam
• Concrete casing is needed to provide protection to the steel beam.
Concrete casing
Steel beam
Clause F2,F3. 8 & 9 Beds and suspended slabs
• Measurement of slab shall be under the following categories:-
• A. Not exceeding 100mm.• B. 100mm to 150mm• C. 150mm to 300mm.• D. Exceeding 300mmGround floor slab
1st. Floor slab
Clause F.3.10 Troughed slab
• Slab of this shape must be separated and named as troughed slab.
• To state overall thickness.
A (overall thickness)
b
Coffered / troughed slab
Clause F.3.11 Upstand, kerbs
• These are smaller structures whereby the construction would be slower and more laborious.
Upstand
Kerb
Coping
Low wall
Clause F.3.12 Walls
• Reinforced concrete wall is a structure to prevent landslide or movement of earth to a lower level.
Retaining wall
Kicker
Hill
Clause F.3.12 Fascia and fins.
• These are beams are very thin in thickness and mainly served as decorative surface and sun shading.
• The construction of these beams is very difficult due to the thinness.
Fascia beam
Fins
Clause F.3.16 steps and staircases
• These structure is very difficult to construct due to the different sizes and drops.
Staircase
Steps
Clause F.3.17 Tops and cheeks of dormers
• As the construction of the small structure is in a very high level and involved very delicate job the cost could be high.
Dormers
Clause F.3.19 Machine bases
• The construction of plinth shall mean the support of a machine like a water pump or the water tank support.
Water tank
Concrete plinth
Concrete slab
Clause F.3.20 Filling to pockets.
• 1. Volume of void exceeding 0.10m3 to be measured in m3 and to state how many number.
• 2. Volume less than 0.10m3 to be enumerated irrespective of sizes.
R.C. slab with pockets of voids to be filled.
Clause F.4.2 Joints.
• Casting of large panel slabs shall be in panels and the joints could include waterstop, expansion or compression joints and be measured in meters.
R.C .slab cast in panels
A B
C D
Airport runway
• Construction of runway for planes must be strong and durable.
The concrete slab must be flexible to withstand the contraction and expansion.
Expansion joints
Clause F.7.3 Guniting
• It is a slope improvement system to prevent the slope from failing.
• The concrete is splayed to the surface of the slope and the measurement is in m2 stating the thickness.