conceptual plan - welcome to environmentenvironmentclearance.nic.in/writereaddata/online/risk... ·...
TRANSCRIPT
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 77
CONCEPTUAL PLAN
INTRODUCTION
M/s Lancet Infocom Pvt. Ltd. has announced the launch of new IT/ ITES project, which is
located at Plot No.1, Sector -140 Noida (U.P). The project will be built on a plot area measuring
20,000 sq mt. (or 4.94 Acres). The IT project would have space for IT/ITES, Commercial, etc.
The entire project has been planned in such a manner that all the modern lifestyle requirements
are perfectly fulfilled. The main purpose and benefit of the project are as under:
To enhance the surrounding with greenery, landscaping and recommended aesthetics.
To provide the world class infrastructure and amenities.
The salient features of the project include:
Fire Fighting system as per NBC
Earthquake Resistant structure considering the seismicity of the area
Integrated Security System
Wastewater Management
Power Backup
Sufficient green area
SITE LOCATION AND SURROUNDINGS
The IT/ ITES project is located at Plot No.1, Sector -140 Noida (U.P). The Co-ordinates of the
project site are 28°30'51"N &, 77°25'8"E. Google earth image & Toposheet showing project site
& surroundings are enclosed as Annexure I & II respectively.
CONNECTIVITY
The project site is in close proximity to the Noida Greater Noida Express way road. The site lies
in the National Capital Region (NCR) and is well connected to Delhi, Gurgaon and Ghaziabad
by a network of wide roads and expressway.
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 78
Table 1: Connectivity
AREA STATEMENT
The total area of site is estimated 20,000 m2
(or 4.94 acres). The detailed Area Statement is
provided below in Table 2. Possession letter is attached as Annexure III.
Table 2: Area Statement
S.No Particulars Area
(in m2)
Percentage
(%)
1. Plot Area 20,000
2. Permissible Ground Coverage @ 30% 6000 30
3. Achieved Ground Coverage (@ 29.99%) 5999.998 29.99
4. Total Permissible FAR (@ 2.00)
Permissible FAR for Buildings (@ 2.00)
Permissible Services FAR (@15% of 2.00 FAR)
46,000
40,000
6000
5. Achieved FAR for buildings 39999.173
6. Achieved institutional services FAR (Incl. in Achieved
FAR)
3738.09
7. Achieved additional FAR for services 3943.376
8. Total Achieved FAR 43,942.549
9. Non FAR area (excluding Basement) 15,027.466
10. Non-FAR Basement Area 33088
11. Total Non-FAR 48,115.466
12. Total Built up Area (8+11) 92,058.015
S.No. Connectivity Name of the facility Distance and Direction from the
project site
1. Nearest Highway Noida Greater Noida
Expressway Road
NH-2 (Mathura Road)
Dadri main road
1.77 km, SSW
11.57 Km, W
2.21 Km, NNE
2. Nearest Railway
Station Ghaziabad Railway station
Badarpur Metro Subway
Tughlakabad railway
station
15.24 km, N from the project site.
11.54 Km, WSW
11.84 Km, W
3. Nearest Airport Indira Gandhi
International Airport
30.34 Km, WNW
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 79
13. Open Area 14,000.002 70
14. Landscape Area (50 % of Open Area) 7,192.12 36
15. Refuge Area (Terrace Area) 250
Population
The population of the IT/ITES project is estimated to be 7946 including staff and Visitor.
Population Breakup is given below in table 3 as:
Table 3: Population Break up
S.No Unit Type FAR PPU/
Persons
Total
Population
1. Institutional
Shops 3738.09 1 person/3 Sqm 1246
Staff @ 5% of total shop population 62
Visitor @95 % of total shop population 1184
Office 40204.459 1 person/6 Sqm 6700
Staff 6030
Visitor 670
Grand Total 7946
WATER REQUIREMENT
During construction phase water will be supplied by private water tankers, whereas during
operation phase water supply will be provided through the Municipal water supply. Total water
requirement will be approx. 434 KLD, out of which domestic water requirement will be 302
KLD. Fresh water requirement will be 211 KLD which is 70% of the domestic water demand.
One-time fresh water requirement will be 434 KLD. Daily water requirement calculation is
given below in Table 4:
Table 4: Calculations for Daily Water Demand
S.No Unit Type Area (in
m2)/
DU’s
Total
Population
Rate of
water
demand
(lpcd)
Total water
Requirement (KLD)
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 80
1. Institutional
Shops 3,738.09
Staff 62 45 2.8
Visitor 1184 15 17.76
Office 40,204.459
Staff 6030 45 271.35
Visitor 670 15 10.05
TOTAL 301.96 say 302 KLD
3. Horticulture and
Landscape development
7,192.12 1 Lt./m2 7
4. HVAC (25000 Tones) 125 KLD
Total (1+2+3+4) 434 KLD
Table 5: Total Wastewater Calculations
The water balance diagrams during dry & rainy season are shown below in Figure 1 & 2:
Domestic Water Requirement 302 KLD
Fresh(70% of domestic Water
Demand) 211 KLD
Flushing (30 % of domestic
Water Demand) 91 KLD
Wastewater Generated
(80% fresh + 100% flushing) 260 KLD
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 81
*One time fresh water requirement will be 434 KLD
Figure 1: Water Balance Diagram for non rainy season
Recycled Water
FRESH
WATER*
(211 KLD)
WASTEWATER
GENERATED
(260KLD)
STP CAPACITY KLD
(290 KLD)
@ 80%
@90 %
234 KLD
FLUSHING
(91 KLD)
@ 100%
Wastewater
HORTICULTURE
(7 KLD)
7 KLD
91 KLD
HVAC
(125 KLD)
125 KLD
Discharge to CSTP
(11 KLD)
11 KLD
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 82
*One time fresh water requirement will be 434 KLD
Figure 2: Water Balance Diagram for rainy season
Wastewater Generation & Treatment
It is expected that 260 KLD of wastewater shall be generated from project site during operation
phase. Wastewater will be treated in the STP provided within the complex generating
recoverable water from STP which will be recycled within the project site. Out of 234 KLD of
treated wastewater 91 KLD will be utilized in flushing, 7 KLD for horticulture and 125 KLD in
HVAC during non rainy season and rest 11 KLD will be discharge in CSTP. During rainy
season 91 KLD for flushing and 125 KLD in HVAC, rest 18 KLD will be discharge in CSTP.
Recycled Water
FRESH WATER*
(211 KLD)
WASTEWATER
GENERATED
(260 KLD)
STP CAPACITY (290
KLD)
FLUSHING
(91 KLD)
@ 80%
@ 100%
Waste water
91 KLD
125KLD
HVAC
(125 KLD)
18 KLD Discharge to CSTP
(18 KLD)
@90 %
234 KLD
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 83
SEWAGE TREATMENT TECHNOLOGY
MBBR Technology
Sewerage System
An external sewage network shall collect the sewage from all units, and flow by gravity to the
proposed sewage treatment plant.
Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
Reduced net daily water requirements, source for Horticultural purposes by utilization of the
treated wastewater.
Reduced dependence on the public utilities for water supply and sewerage systems.
Sludge generated from the Sewage Treatment Plant shall be rich in organic content and an
excellent fertilizer for horticultural purposes.
a. Wastewater Details
a) Daily load : 260 KLD
b) Duration of flow to STP : 24 hours
c) Temperature : Maximum 32oC
d) pH : 7 to 9.5
e) Color : Mild
f) T.S.S. (mg/l) : 100-400 mg/l
g) BOD (mg/l) : 200-300 mg/l
h) COD (mg/l) : 500-700 mg/l
b. Final discharge characteristics
a) pH :
6.5 to 7.5
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 84
b) Oil & Grease : <10 mg/l
c) B.O.D. : <10 mg/l
d) C.O.D. : <100 mg/l
e) Total Suspended Solids : <10 mg/l
c. Treatment Technology
MBBR TECHNOLOGY
Moving bed bio-film reactor technology is based on the principle of attached growth process.
Raw sewage will be collected under gravity into the equalization tank after allowing to pass
through the bar screen. Screens will be provided in screen chambers and it will be manually
cleaned by going down to a platform. The bar screen, by removing coarse solids from the
sewage help in protecting the raw sewage pump.
Fully submersible centrifugal non-clog sewage handling pump will be provided in the
collection cum equalization tank to pump the collected waste water to the next MBBR tanks.
Automatic level controller will be provided in the tank to turn the pump off at the low water
level in the tank and to start the pump when water level is high automatically. Air will be
introduced in this tank to prevent any potential foul smell problem & to provide the mixing of
wastewater to avoid the sedimentation of solids in this tank. Air Grid used for aeration
purpose shall be non-clog.
The sewage collected in equalization tank is pumped the moving bed bioreactor. There shall
be two nos. of bioreactors in series for the efficient working and removal of BODs for the
required retention time. The process inside the moving bed bioreactors consists of adding
small cylindrical-shaped polyethylene/polypropylene carrier elements in aerated basins to
support biofilm growth. The small cylinders are provided with a cross inside the cylinder and
longitudinal fins on the outside. The biofilm carriers
are maintained in the reactor by the use of a
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 85
perforated plate with appropriate slot at the tank outlet. Air agitation or mixers are applied in
a manner to continuously circulate the packing. The packing may fill 25 to 50 percent of the
tank volume. Specific surface area of the packing is about 450-500m2/m
3 of bulk packing
volume. The waste water from first bioreactor flows by gravity through the perforated
plate/mesh to the next bioreactor kept in series. Inside the bioreactors, aerobic bacteria grow
in an attached growth from around the moving plastic media inside the reactors. The bacteria
have to reduce BOD & COD of waste water in the presence of oxygen provided through the
air grids located at the bottom of the reactors. The Process does not require any return
activated sludge flow or backwashing.
From the bio-reactors, the effluent passes by gravity into the clarifier (Tube Settling Tank).
Clarifier will be a hopper bottom sedimentation tank provided with appropriate size PVC
tube deck media. The suspended solids will settle at the bottom of the tank & clear
supernatant will overflow to filter feed tank through outlet launder. The collected sludge at
bottom shall be transferred through pumps to sludge holding tank.
The clear supernatant after clarifier will be collected in to filter feed tank. This tank will act
as housing tank for filter feed pumps. The clarified & dis-infected water will be then fed to
filtration unit.
Filtration unit consisting of Dual Media sand filter, activated carbon filter and ultra filtration
system (optional) will remove the residual impurities such as odor/color, suspended solids,
BOD/COD. The treated water after the filtration unit will be collected in Irrigation cum
Flushing water storage tank from where it is transferred to flushing water tank at terrace &
Irrigation System.
Excess sludge from the bottom of the settling tank will be removed and transferred to sludge
holding tank. Air grid shall be provided in this tank to avoid conversion into anaerobic
conditions, thickening of sludge and keep sludge in homogenous condition. The digested &
thickened sludge shall be further thickened through Sludge Dewatering System (Filter press
with screw pump) and disposed off periodically through closed tanker or can be reused as
manure.
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 86
Figure: 2 Schematic Diagrams for STP Based on MBBR Technology
Sewer System
The alignment and slope of the sewer line will follow the road network, drains or natural ground
surface and will be connected to the trunk sewers. The discharge point will be a treatment plant,
a pumping station, a water course or an intercepting sewer. Pumping stations would be provided
at places where the natural slope of the terrain is insufficient to permit gravity flow or the cost
of excavation is uneconomical to do the same.
RAIN WATER HARVESTING
The storm water collection system for the premises shall be self-sufficient to avoid any
collection/stagnation and flooding of water. The amount of storm water run-off depends upon
many factors such as intensity and duration of precipitation, characteristics of the tributary area
and the time required for such flow to reach the drains. The drains shall be located near the
carriage way along either side of the roads. Taking the advantage of road camber, the rainfall
run off from roads shall flow towards the drains. Storm water from various areas shall be
connected to adjacent drain by a pipe through catch basins.
1) Since the existing topography is congenial to surface disposal, a network of storm water
pipe drains is planned adjacent to roads. All building roof water will be brought down
through rain water pipes.
2) Proposed storm water system consists of pipe
drain, catch basins and seepage pits at regular
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 87
intervals for rain water harvesting and ground water recharging.
3) For basement parking, the rainwater from ramps will be collected in the basement storm
water storage tank. This water will be pumped out to the nearest external storm water drain.
4) The peak hourly rainfall of 50 mm/hr shall be considered for designing the storm water
drainage system
Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak
hourly rainfall has been considered as 50 mm/hr. Length, width and depth of a Recharge pit is
4m, 2m and 3.5 m respectively and constructed for recharging the water. The bottom of the
recharge structure will be kept 5 m above this level. At the bottom of the recharge pit, a filter
media is provided to avoid choking of the recharge bore. Design specifications of the rain water
harvesting plan are as follows:
Catchments/roofs would be accessible for regular cleaning.
The roof will have smooth, hard and dense surface which is less likely to be damaged
allowing release of material into the water. Roof painting has been avoided since most
paints contain toxic substances and may peel off.
All gutter ends will be fitted with a wire mesh screen and a first flush device would be
installed. Most of the debris carried by the water from the rooftop like leaves, plastic bags
and paper pieces will get arrested by the mesh at the terrace outlet and to prevent
contamination by ensuring that the runoff from the first 10-20 minutes of rainfall is flushed
off.
No sewage or wastewater would be admitted into the system.
No wastewater from areas likely to have oil, grease, or other pollutants has been connected
to the system.
Calculations for storm water load
Roof-top area = Ground Coverage = 5999.998 m2
Green Area (softscape green area) = 3000 m2
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 88
Paved Area = Total Plot Area – (Roof-top Area + Green Area)
= 20000– (5999.998 + 3000)
= 11,000.002 m2
Runoff load to be utilized for artificial ground water recharge:
Runoff from Roof-top Area = 5999.999 × 0.05 × 0.8
= 239.99 m3/hr
Taking 15 minutes of retention time, total storm water load = 239.99/4 =59.99 m3/hr
Taking the effective length, breadth & depth of a Recharge pit 4 m, 2 m & 3.5 m respectively,
Volume of a single Recharge pit = l×b×h = (4 × 2 × 3.5)
= 28 m3
Hence no. of pits required approx. = 59.99/28 = 2 Pits
Runoff load to be stored in tanks:
Runoff from Green Area = 3000× 0.05 × 0.1
= 15 m3/hr
Runoff from Paved Area = 11,000.002 × 0.05 × 0.75
= 412.50 m3/hr
Total Runoff Load = 427.50 m3/hr
Taking 15 minutes Retention Time, Total volume of storm water = 277.35/4
= 106.88 m3
Volume of a tank = 48 m3
Hence No. of tanks required = 2 tanks
Total of 2 rainwater harvesting pits & 2 rainwater harvesting tanks are proposed.
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 89
Figure 4: Typical Rain Water Harvesting Pit Design
VEHICLE PARKING FACILITIES
Adequate provision will be made for car/vehicle parking at the project site. There shall also be
adequate parking provisions for visitors so as not to disturb the traffic and allow smooth
movement at the site.
Parking Required:
As per MoEF norms:
For IT/ITES = 1 ECS/50 m2 FAR area
= 41991.552 /50= 840 ECS
For Restaurants and Canteen (Food Courts) = 1 ECS/20 seats =4.7 ECS or 5 ECS
Total parking required = 845ECS
As per Noida bye-laws:
For IT/ ITES = 1 ECS /50 m2 FAR area
= 41991.552 /50= 840 ECS
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 90
For Food Court = 1ECS/30 m2 FAR area
= 783.908/30 =26.130 m2 = 26 ECS
Total Parking required= 870 ECS
Table 6: Parking Proposed
S. No. Particular Parking Proposed
(in ECS)
1. Basement-1st 534
2. Basement 2nd
534
3. Podium Parking (1st level ) 123
4. Podium Parking (2nd
level) 111
Total parking proposed = 1302 ECS
POWER REQUIREMENT
The power supply shall be supplied by Noida Power Corporation Limited (NPCL). The
maximum load for the Centrade park project will be approx. 3945 kW and will be supplied by 2
no’s of transformers of capacity 2000kVA each.
Details of D.G Sets
There is provision of 2 no. of DG sets of total 1500 kVA capacity for power back up in the IT
park project. The DG sets will be equipped with acoustic enclosure to minimize noise
generation and adequate stack height for proper dispersion.
SOLID WASTE GENERATION
Solid waste would be generated both during the construction as well as during the operation
phase. The solid waste expected to be generated during the construction phase will comprise of
excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following steps
are proposed to be followed for the management of solid waste:
Construction yards are proposed for storage of construction materials.
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 91
Solid Waste
Construction
Waste
Construction waste,
Broken Bricks,
Waste Plaster
Empty Cement
Bags
Used in re-filling, raising
site level
Reused for road
making
Excavated Soil
Top soil conserved for landscaping,
balance used in re-
filling
The excavated material such as topsoil and stones will be stacked for reuse during later
stages of construction.
Excavated top soil will be stored in temporary constructed soil bank and will be reused for
landscaping of the IT/ITES project.
Remaining soil shall be utilized for refilling / road work / rising of site level at locations/
selling to outside agency for construction of roads etc.
Figure 5: Solid Waste Management Scheme
(Construction Phase)
During the operation phase, waste will comprise domestic waste and estimated quantity of the
waste shall be approx. 1828 Kg/ per day (including STP sludge) (@ 0.15 kg per capita per day
for the floating population, 0.25 kg per capita per day for the staff members and landscape
wastes @ 0.2 kg/acre/day). Following arrangements will be made at the site in accordance to
Municipal Solid Wastes (Management and Handling) Rules, 2000.
Table 7: Calculation of Solid Waste Generation
S.No. Category Waste generated Waste generated
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 92
(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, Central Public Health & Environment Engineering Organization,
Ministry of Urban Development, (Government of India, May 2000))
Collection and Segregation of waste
1) A door to door collection system will be provided for collection of waste in colored bins.
2) The local vendors will be hired to provide separate colored bins for dry recyclables and
Bio-Degradable waste.
3) Litter bin will also be provided in open areas etc.
Treatment of waste
Bio-Degradable wastes
1) Bio-degradable waste will be subjected to organic waste convertor and the compost will
be used as manure.
2) STP sludge is proposed to be used for horticultural purposes as manure.
3) Horticultural Waste is proposed to be composted and will be used for gardening
purposes.
Recyclable wastes
i. Grass Recycling – The cropped grass will be spread on the green area. It will act as
manure after decomposition.
ii. Recyclable wastes like paper, plastic,
metals etc. will be sold off to recyclables.
(kg per capita per day) (kg/day)
A. Staff 6092 @ 0.25 kg/day 1523
B. Visitors 1854 @ 0.15 kg/day 278
C. Landscape waste (or
1.73 acres)
@ 0.2 kg/acre/day 0.346
D. STP sludge [( Initial BOD - Final BOD) x 0.35 x
water load]/1000
26.39
TOTAL SOLID WASTE GENERATED 1828 kg/day
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 93
E- Waste will be managed by as per the norms E-Waste (Management & Handling)
Rules, 2011.
Disposal
Recyclable and non-recyclable wastes will be disposed through Govt. approved agency. Hence,
the Municipal Solid Waste Management will be conducted as per the guidelines of Municipal
Solid Wastes (Management and Handling) Rules, 2000. A Solid waste management Scheme is
depicted in the following figure for the IT/ITES project.
Figure 6: Solid Waste Management Scheme (Operation Phase)
"E-waste" is a popular, informal name for electronic products nearing the end of their "useful
life.”E-wastes are considered dangerous, as certain components of some electronic products
contain materials that are hazardous, depending on their condition and density.
The hazardous content of these materials pose a threat to human health and environment.
Discarded computers, televisions, VCRs, stereos, copiers, fax machines, electric lamps, cell
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 94
phones, audio equipment and batteries if improperly disposed can leach lead and other
substances into soil and groundwater.
Many of these products can be reused, refurbished, or recycled in an environmentally sound
manner so that they are less harmful to the ecosystem. Reducing e-waste requires that we
reduce, reuse, recycle and recover. The goal is nothing less than zero land fill. Network of
scrap dealers will be encouraged to procure from door to door for the smaller quantities.
E-Waste will be managed as per the E-waste (Management and Handling Rules)’2011.
UPPCB/CPCB approved E-Waste dealers will be motivated to procure from Secondary
collection point in the project site.
GREEN AREA
Total green area measures 7192.12 m2
i.e. which is 50% of open area which will be area under
tree plantation within the project and along the roads. One tree per 80 sq. mt. of plot area out of
which minimum 50 % to be in the category of evergreen trees.
Table 8: Green Belt Development
S. No. Evergreen Trees
1. Azadirachta indica
2. Alstonia scholaris
3. Millingtonia hortensis
4. Gravellia robusta
5. Anthocephalus Chinensis
6. Delonix regia
7. Ricinus communis
8. Salix caprea
9. Prosopis stephaniana
10. Citrus limon
11. Bauhinia acuminata
12. Clerodendron innerme
Ornamental Trees
1. Areca palm
2. Bougainvillea
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 95
3. Cleredendron innerme
4. Cycas circinalis
5. Euphorbia carcasana
6. Elaeocarpus ganitrus (Rudraksh) 7. Nyctanthes arbor-tristis(Parijat)
Table 9: No. of Trees to be planted
1. As per Noida Bye Laws 1 tree/100 sq.m. of open space
Open area 14,000.002 m
2
Trees required 14000.002/100 = 140 Trees
2. As per MoEF norms 1 tree/ 80- sq.m. of plot area
Plot area 20,000 m
2
Trees required 20,000/80 = 250 Trees
3. Number of Trees proposed to be planted 250 Trees
DETAILS OF CONSTRUCTION MATERIALS
List of building materials being used at site:
1. Coarse sand
2. Fine sand
3. Stone aggregate
4. Stone for masonry work
5. Cement
6. Reinforcement steel
7. Pipe scaffolding (cup lock system)
8. Bricks
9. CLC fly ash blocks
10. P.V.C. conduit
11. MDS, MCBs
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 96
12. PVC overhead water tanks
13. 2 1/2'’ thick red colour paver tiles
14. PPR (ISI marked)
15. PVC wastewater lines
16. S.W. sewer line up to main sewer
17. PVC rain water down take
18. Stainless steel sink in kitchen
19. Joinery hardware- ISI marked
MATERIALS USED FOR CONSTRUCTION & THEIR U-VALUES
Type of Construction U values (in W/m2deg C)
Walls:
Brick:
Plastered both sides 3.24
Solid Unclastered 2.67
Plastered both sides 2.24
Concrete, Ordinary, Dense:
-152mm 3.58
-203mm 3.18
Concrete block:
CLC Fly ash block 1.19
Hollow Concrete block, 220mm, single skin, outside rendered, inside plastered:
CLC Fly ash block 1.70
Roofs Flat
Reinforced concrete slab, 100mm, scarred 63-
12 mm, 3 layers bituminous felt
3.35
Floors:
Concrete on ground or hardcore fill 1.13
+ Grano, Terrazzo or tile finish 1.13
+ Wood block finish 0.85
Exposure South Sheltered:
Single glazing 3.97
Double glazing 6 mm space 2.67
IT/ITES project
“Centrade”
At Plot No. 1, Sector 140, NOIDA CONCEPTUAL PLAN
Noida, U.P
M/s Lancet Infocom Pvt. Ltd. 97
LIST OF MACHINERY USED DURING CONSTRUCTION
(i) Dumper
(ii) Concrete mixer with hopper
(iii) Excavator
(iv) Concrete Batching Plant
(v) Cranes
(vi) Road roller
(vii) Bulldozer
(viii) RMC Plant
(ix) Tower Cranes
(x) Hoist
(xi) Labor Lifts
(xii) Pile Boring Machines
(xiii) Concrete pressure pumps
(xiv) Mobile transit mixer