PURPOSE: Per Revised Code of Washington (RCW) 53.20.010 the purpose of this comprehensive scheme is to outline the long range plans for the Port of Brownsville. This includes capital improvement projects and maintenance projects that will further enhance the facilities and use of the Port of Brownsville by the port district community. MISSION STATEMENT: Providing public access for safe and responsible use of marine resources. INFORMATION: This document provides information in sections to allow the reader quick access to areas of interest. The sections are as follow: Section 1: Goals and Objectives …………………… Page 3 Section 2: Capital Improvement Plan …………………… Page 7 Section 3: Inventory ………………………………….. Page 12 Section 4: Port Evaluation ……………………………. Page 16 Section 5: Demand and Need Analysis ……………… Page 19 Section 6: Public Involvement Process ……………… Page 20 Section 7: Port Of Brownsville General Information … Page 22 Section 8: Frequently Asked Questions ……………… Page 25 Section 9: Brownsville Area History ………………… Page 27 Section 10: Port of Brownsville History ……………… Page 30 Section 11: Citizen Elected Commissioners …………. Page 33
3
GoalsandObjectives The goals and objectives listed below are the goals and objectives suggested during the Committee’s sessions. It is the intent of the Port and the Committee to update the Comprehensive Scheme at least biannually so that it is a working, dynamic document. The Committee fully expects that the Port’s goals and objectives will change every few years as the top priorities are met and new projects / priorities are established. The following is a list of projects/objectives within each goal in order of precedence assigned by the Committee. This list makes no distinction between capital projects or non capital projects.
Goal To provide a comprehensive framework for future decision making throughout the Port organization
Objective Develop and implement a comprehensive scheme that best matches
the use of the property in order to enhance the public’s access and enjoyment of the water while being environmentally conscientious.
Goal To enhance and expand public saltwater access and facilities
NOTE Where necessary, accomplish architectural and engineering design
studies on the below objectives, and coordinate with Federal, State and Local agencies to ensure compliance with applicable requirements.
Objective Repair boat launch (2)
◊ Extend boat launch for maximum utilization at lower tides ◊ Level cement sections and repair cracks ◊ Repair Kayak & Pedestrian Ramp ◊ Repair / replace as necessary
Objective Remodel / Expand / Repair; Port Office, Rental house, Deli, Yacht Club, Auxiliary Offices and Storage as well as any and all Ancillary support buildings.
◊ Ventilation ◊ Additional office space ◊ New Deck ◊ Windows ◊ Floor leveling ◊ New Doors ◊ Roof Repair / Replacement
Objective Encourage community involvement and special events ◊ Wooden boat show / Automobile (Hot Rod) club /
Sponsored events (Brownsville Appreciation Day) / Sailing & Kayak Events (Water Trails Festival Keys to Keyport) / Suquamish (Native American) gatherings, Pier Peer, Haunted Harbor.
4
Objective Redesign and expand parking facilities to accommodate larger vehicles and trailers. Storm water improvement
◊ Widen vehicle and trailer entrance on east side of Ogle road ◊ Add additional parking at north end of existing parking lot
◊ Restripe parking lot to accommodate larger vehicles and trailers ◊ Resurface as necessary ◊ Storm water improvement Objective Monitor Existing Rock Bulkhead ◊ Engineering study to determine structural integrity and safety ◊ Repair when and where necessary Objective Develop walking trail / Beautification of natural resources ◊ Pond, stream & gully areas. ◊ PAR Exercise course ◊ Trail Enhancements (picnic sites / fences / interpretive signage) Objective Marketing / Advertisement Objective Encourage economic development within the Port district. Objective Expand existing camera security system Objective Develop open storage facility ◊ Trailerable boats ◊ RV’s Objective Develop / Add playground equipment Objective Acquire property that supports the mission statement as it becomes
available ◊ Contiguous property lines or immediate use should not be a
requirement of purchase ◊ Facilitate obtaining donated property Objective Ogle Road Improvement Safety / Pedestrian Safety / Fish Passage ◊ Modify Ogle Rd Curve ◊ Install sidewalks as needed ◊ Crosswalk from parking lot to marina ◊ Add rumble strips as needed ◊ Remove culvert and put in fish friendly passage Objective Change look of Marina Entrance ◊ Change location of existing mailboxes ◊ Add landscaping feature
5
Goal To maintain and enhance existing boating, moorage, and support facilities including support for our local Native American Tribe.
NOTE Where necessary, accomplish architectural and engineering design
studies on the below objectives, and coordinate with Federal, State and Local agencies to ensure compliance with applicable requirements.
Objective Clean, inspect & repair as necessary East, North and South
Breakwaters Objective Modify, relocate, expand North Breakwater / Improve wave
attenuation on North side of Marina, Secure with piling
Objective Remodel, Replacement, Rebuild and / or upgrade Marina to include ◊ Remodel, Replace, Rebuild Main Marina Pier ◊ Remove and replace creosote piling ◊ Remove concrete walkway slabs. New design to be determined ◊ Rewiring the marina and ancillary electrical equipment ◊ Upgrading lighting ◊ New water lines ◊ New fire main ◊ In dock sewer system ◊ Remove and replace creosote pilings ◊ Dredge marina Objective Develop additional moorage Objective Develop Marina Tenant Storage Facility
Objective Install trailer / boat wash down system Objective Dinghy / kayak storage for tenants and guests Objective Develop Dry Storage
Objective Develop / Install Operational Wi-Fi Objective Install public address system throughout the facility Objective Provide Backup emergency generator
6
Priority Project / Objective
1 REMODEL, REPLACE, REBUILD MARINA 2 REPAIR BOAT LAUNCH AND KAYAK RAMP 3 DEVELOP WALKING TRAIL W/ENHANCEMENTS AND PAR EXERCISE
COURSE 4 REDESIGN AND EXPAND PARKING FACILITIES TO ACCOMMODATE
LARGER VEHICLES 5 EXPAND EXISTING CAMERA SECURITY SYSTEM 6 DEVELOP / INSTALL OPERATIONAL WI-FI 7 DEVELOP PLAYGROUND AREA 8 CHANGE LOOK OF MARINA ENTRANCE 9 CLEAN INSPECT REPAIR AS NECESSARY NORTH, EAST AND SOUTH
BREAKWATERS 10 OGLE ROAD SAFETY IMPROVEMENT / PEDESTRIAN SAFETY / PORT
PARKING 11 PUBLIC ADDRESS SYSTEM ON DOCK FOR EMERGENCY EVENTS 12 DEVELOP ADDITIONAL MOORAGE 13 DEVELOP TENANT STORAGE 14 REMODEL PORT BUILDING & ANCILLARY SUPPORT BUILDINGS 15 MONITOR/ REPAIR AS NECESSARY ROCK BULKHEADS 16 DEVELOP OPEN STORAGE AREA 17 INSTALL TRAILER / BOAT WASH DOWN SYSTEM 18 MODIFY, RELOCATE, EXPAND NORTH BREAKWATER / WAVE
ATTENUATION 19 ENCOURAGE COMMUNITY INVOLVEMENTS AND SPECIAL EVENTS 20 DINGHY / KAYAK STORAGE FOR TENANTS AND GUESTS 21 ENCOURAGE ECONOMIC DEVELOPMENT 22 ACQUIRE PROPERTY 23 MARKETING / ADVERTISEMENT 24 BACKUP EMERGENCY GENERATOR
7
Capital Improvement Program (revised for 2018 and beyond) This document is the embarkation point for our planned biennial updating of the Comprehensive Scheme thus making it a living and useful planning document for all facets of Port management. The previous Capital Improvement Program sections from prior Comprehensive Schemes are available in previous documents.
Priority Year Objective Project Description Estimated
Cost
Potential Funding Sources
1 2018 &
beyond
Expansion, replacement, rebuild marina
Continue rebuild of marina including Main pier.
$1,600,000 to
$2,000,000
In House, Bonds, Local Option Capital Asset Lending (LOCAL) Grants
2 2018 Rebuild/ Repair boat launch cement slabs including kayak ramp
Extend ramp, level. Cement rocks in place.
$950,000 RCO and In House
3 2019 2020
Develop Walking Trail
Develop PAR course and walking trail
$250,000 In House and grants
4 2022 Redesign & expand parking facilities to accommodate larger vehicles
Expand and re-stripe parking lot to accommodate larger vehicles and trailers
$100,000 In House and Grants
5 2019 Expand existing camera security system
Add camera to parking lot, fire station, and docks
$40,000 In house and grants
6 TBD Develop / Install Operational Wi-Fi
Install antenna's and ancillary equipment to provide Wi-Fi to the entire marina
$10,000 In House
7 2019 Playground Equipment
Insurance approved equipment only.
$6,000 $10,000
In House and grants
8 TBD Change look of marina entrance
Move mailboxes add landscaping
$4,500 In House
9 Ongoing Clean inspect repair as necessary N, E & S Breakwaters
Repair bull rail and whalers. Add piling and pile hoops, seal cracks.
As Necessary
to accomplish
In House & grants
8
10 2025 Ogle Rd. Safety Improvement / Pedestrian Safety / Port Parking / storm water
Increase curve radius install pedestrian crossing add boat launch staging lane. Restripe/ add parking
$400,000
Kitsap County Roads, In House
11 TBD Public Address System
Install public address system on docks for emergency announcements
TBD In house Grants
12 2022 And
Beyond
Develop Additional Moorage
Investigate various areas for possible development of additional moorage
TBD In House
13 Open Develop tenant storage
Design and then build Marina tenant Storage on existing port property
TBD In House
14 2030 Remodel / expand Port Office and ancillary buildings
Add additional space. Upgrade utilities as necessary. Install ventilation.
TBD In House
15 Ongoing Monitor / Repair rock bulkhead
When necessary obtain inspection from trusted engineering firm to determine next course of action with rock wall and then follow through on recommended course of action.
TBD In House
16 Open Develop open storage facility
This area will be used to store boat trailers, RV's or similar type items.
TBD In House
9
17 Open Install trailer/boat wash down system
Establish suitable area on existing port property to install trailer/boat wash down system. This may become a state mandated project at some time in the future.
Millions Possible State Parks Grant and In House
18 Open Modify, relocate, expand north breakwater & wave attenuation on north side of marina
Possible plans are to move north breakwater approximately 190 feet to the north then adding wave attenuation to West end toward shore or build new breakwater to meet needs. Add docks and finger piers to increase moorage.
$2.5 to $4 million
In House, Bonds, Local Option Capital Asset Lending (LOCAL) Grants
19 Ongoing Encourage Special Events
Wooden Boat Show, Automobile (hot rod) club Sponsored events Brownsville Appreciation Day, San Juan 21 and/or Cal 20 sailing events, Water Trails Festival Keys to Keyport, Suquamish (Native American) gathering, Haunted Harbor
$1,000 Annually
$12,000
BAD $1,000 WWT
Annually
$1,000 Annually
In House
20 2018 Dinghy / Kayak Storage for Tenants and guests
Investigate suitable site and feasibility of building.
$6,000.00 In House
21 Ongoing Encourage Commercial Facilities
There is no specific project planned at this time. This will be a project of opportunity as they develop.
TBD In House
10
22 Ongoing Acquire property There is no specific acquisition planned at this time. This will be a project of opportunity as they develop. Contiguous property lines or immediate use should not be a requirement of purchase. Facilitate obtaining donated property
TBD In House, Grants, Partnering with other entities
23 Ongoing Marketing and Advertisement
There is no specific marketing stratagem for the Port.
$5,000.00 Annually
In House
24 Open Obtain and install backup generator in case of loss of power for extended period.
$100,000 In House