Regional Connector Transit Project Community Leadership Council
2nd Hope Station & Flower St Committees January 17, 2017
1
EAT SHOP PLAY LOCAL
2
Eat Shop Play Local
> Free Metro marketing campaign
> Make it easier for the public to
• Eat at local restaurants
• Shop at local stores
• Play at local destinations
during and after construction of the Regional Connector Transit Project
3
Eat Shop Play Local
> Social Media Promotion
> Monthly Newsletter
> Eat Shop Play Meet-Ups
> Business Spotlights
> Vendor Table Opportunities at
Metro Headquarters
> Business Profiles on Metro.net
> Community Partners
4
Eat Shop Play Fortune Fridays
> Weekly Social Media Contest
> Show Metro how you #EatShopPlay in #DTLA!
> Win a limited edition 7-day Metro TAP card
> Winners announced on every Friday
> First winner: January 27th
> Visit metro.net/riding/eatshopplay
5
CONSTRUCTION UPDATE
2nd/Hope Station
6
2nd/Hope Area Schedule
JAN FEB MAR APR MAY JUN
Support of excavation (SOE)
Excavation
Tieback and bracing installation
Haul out material
Invert (station floor) construction
Forming, placement of rebar
Concrete pour (mud slab, followed by invert)
7
Ongoing Activities & Current Work Hours > Excavation, support of
excavation (SOE), bracing and hauling
> Approximately 15–20 feet remaining
> Work hours:
– Monday–Friday: 7 am–3:30 pm; 3:30 pm–2:00 am
– Saturday–Sunday: 8 am–8 pm
8
PEDESTRIAN BRIDGE DESIGN
2nd/Hope Station
9
Station Configuration
10
Elevation View
11
Design Revised in Response to Community Feedback
12
> Design changes include:
– Removed benches
– Removed tiered-planters
– Relocated planters to allow for a more direct pedestrian pathway
– Reconfigured pathway allows 3 & 2 people on each side of planters
– Added security gate
– Added ADA tactile path
Initial Design (2016)
13
Updated Design – Benches Removed & Planters Relocated
14
Initial Design (2016)
15
Revised Design – Benches Removed & Planters Relocated
16
17
Plan View with Path of Travel
2nd/Hope Pedestrian Bridge
> Security
– A uniformed officer at station
– CCTV cameras
– Security gate on east end of bridge
> Maintenance
– Metro’s custodial services (trash collection, maintenance of rails, floors & glass)
– Segmented glass panels
– Trees will be maintained by The Broad through an agreement with Metro
18
Implementation Schedule
19
Design Release
January 2017
Design
2017 Construction
2019
CONSTRUCTION UPDATE
Flower St/Financial District
20
Flower St/Financial District Ongoing/Look Ahead Schedule
Activity JAN FEB MAR APR MAY JUN
24” waterline relocation south of 6th St. (nights)
Deck installation 4th–5th St. and 5th St. intersection (weekends only)
Pre-trenching (weekdays) and piling 5th–6th St (east side)
Tieback removal at 3rd St.
6th/Flower - Power relocation (utility investigation south of 5th St)
21
Deck Installation Modified Closure Details
> Open: Flower St (3rd to 5th St) and 4th St (Figueroa to Flower St) traffic lane reductions through January 20, 2017 only
> Starting at 7 pm, Friday through 5 a.m., Monday
> Activities include:
– Roadway removal
– Excavation
– Hanging of utilities
– Cap beam installation
22
− Deck beam installation − Deck panel installation − Grade deck transition
Deck Installation Closure Dates
Modified weekend closure dates with one through lane open at Flower St:
> 7 pm on January 20 – 5 am on January 23
Full closure of Flower St resumes and continues every weekend through March:
> 7 pm on January 27 – 5 am on January 30
23
Decking on Flower St, 4th to 5th St
> Mitigations – Open one Flower St lane (3rd to 5th St); 4th St
(Figueroa to Flower St) until January 20, 2017
– Activities such as saw cutting, grinding and roadway removal will be performed before 9 pm
– Sound barriers will be in place
– Lights will be directed toward the work zone
– Use of back-up alarms will be minimized
– Flaggers will assist motorists
– In-language 24/7 hour hotline—213.922.7277
24
Ongoing Activities
> Tieback removal at 3rd Street, excavation completed (on photo)
> Back fill operation ongoing through first week of February
25
Ongoing Activities
> 24” water line relocation on Flower St, south of 5th and 6th St intersection
> Utility investigation south of 5th St in preparation for power relocation
> Pile installation at 5th St/Flower intersection
26
Pile Installation East Side Flower St, 5th to 6th St
> Utility investigation
– Monday–Friday, 9 am–3:30 pm
– Saturday, 8 am–6 pm
> Pile Installation
– From 5th St/Flower intersection to south of 6th St
27
Pile Installation East Side Flower St, 5th to 6th St – March 2017
> Three south bound lanes
> One left turn lane
28
STATION NAMING UPDATE
29
Station Naming Update
30
Timeline • September through December 2016
• Stakeholder outreach/input
• November through December 2016 • Online survey conducted • Over 1100 responses received
• January 2017 • Board report pending
• February 23, 2017
• Anticipated Metro Board hearing
Contact Us