Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation European Stakeholder Committee 14 March 2017

Upload: others

Post on 19-Apr-2020

12 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

Common Grid Model and Operational Planning Data environment (OPDE)

concepts and development

Jean-Philippe Paul

System Operation European Stakeholder Committee14 March 2017

Page 2: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

From SOGL/CACM requirements to implementation by all TSOs and RSCs

Page 2

SOGL (/CACM)

Operational planning activities to

be coordinated

RSCs to provide 5 services based

on CGM

All data shared in a common OP

Data Environment (OPDE)

Common format definition

CGM

Methodology

Data quality controls

CGMA (Alignment of Net

Positions) service

Applications

& general

services Merging

function

CGMES 2.4

Reliable &

secure network

Page 3: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

Data Exchange & Services Conceptual Picture

Page 3

OPDEstorage: OPDM

Protocols: ECP/EDX

Data Publishing

Data Subscription

TSO

Data Publishing Data Subscription

Data Publishing

Data Subscription

RSC

Individual Grid Model

IGM

1.Subscription to all IGMs

2.Merging process

3. Publishing of CGMATOM

CGMA – QAS

PEVF - Boundary

common

applications

common midware

services

Page 4: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

OPDE and ATOM Service Providers

Page 4

ATOM

BACKBONENODE

ATOM BACKBONE

NODE

TSO

TSO

TSO

RSC

ATOM BACKBONE

NODE

ATOM BACKBONE

NODE

NETWORK

APPLI-

CATION

(OPDE)

Shared component

hosting and operation

Shared component

hosting and operation

ECP DirectoryEDX

Catalogue

OPDM Service Provider

CGMA Boundary

ManagementQA

Portal

OPDM Service Provider

RSCRSC

Network operation center

Network security center

Page 4

Page 5: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

SUPPLIER Agreements

• Operating OPDE

• Hosting of OPDE shared components

• IT operation of OPDE shared components

• OPDE ASC (Application Network Centre)

• OPDE Service desk

• Operating ATOM

• ATOM NOC (Network Operation Centre)

• ATOM NSC (Network Security Centre)

Contract framework :ENTSO-E – Legal Party in the middle

Users:

TSOs

RSCs

Suppliers:

RSCs

TSOs

IT providers

ENTSO-ECorporate

Entity

USER Agreements

• Access to OPDE

• Access to ATOM

Page 5

Page 6: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

CGM-OPDE Program Phases: current planned milestones

Page 6

11 December 201713 January 2017 11 June 2018

Development

Phase

Develop software,

Services and

the ATOM network

All TSO’s/RSC’s

Implement

CGMES

Set up of the

ATOM/OPDE

design and

contract

Transition

Phase

TSO’s/RSC’s

connect to OPDE/

ATOM

Test processes,

optimize

(individual)

connections/

process

Hybrid merging

(RG CE only)

Stability

Phase

Parallel run of

UCTE + CGMES of

6 months (RGCE only)

CGMES provided for

operational purposes,

fallback to UCTE

format possible

Users of CGMES data

get used to new data

format in operational

processes

Operational

Phase

CGMES used for

pan-European

operational

services

Page 7: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

THANK YOU FOR YOUR ATTENTION

Jean-Philippe PaulPG Coordinated Security Analysis Convenor

RTE

Page 8: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

System Operation Framework*Implementation Activities

Tahir Kapetanovic

System Operation European Stakeholder Committee14 March 2017

* System Operation Guideline and Network Code Emergency & Restoration

Page 9: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

KEY IMPLEMENTATION ACTIVTIES

Page 9

IMPLEMENTATION** SO Guideline only, because ER is Network

Code hence no „implementation“ after its

entering into force

Data exchange, § 40(6)

Y-1 outage planning scenarios, § 65

Operational security analysis method., § 75

Synchronous area agreements, § 118

Min. FCR activation in CE & Nordic, § 156(10-11)

Min. inertia study per SA, § 39(3)(a)

Outage coordination methodology, § 84

Short/medium term adequacy, § 81

Determination of LFC blocks, § 141(2)

YA/DA/ID CGM from IGM, §§ 67(1), 70(1) * A large part of SO GL

implementation –

subject to NRAs

approval – is prepared

through rollout of 5

standard services by

the Regional Security

Coordinators

RSCs*

… RSCs

REPORTING

ICS Report, § 15SO GL NC ER

RSC Report § 17

LFC Report § 16

RSC on TSOs defence & restoration plans, § 6(3)

ENTSO-E on market suspension consistency, § 36

& REPORTING

Page 10: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

RSC „WHATABOUTS“

Page 10

#1: „trigger“ in the past

* „Options for the future of power systems regional coordination“, FTI-CR Study, www.entsoe.eu

All TSOs‘

MLA

12/2015

#2: contract

#5: Possible future enhancements of:

operational planning, balancing,

long-term adequacy, network

planning*

CACM SO GL & NC ER

#3: legal framework

#4: five stand. services by RSCs

CORESOTSC

NORDIC RSC

BALTIC RSC

SCC

SEE-T RSC

Page 11: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

PRELIMINARY TIMELINE

Page 11

1

20182 3 6 74 5 8 9 10 11 12 1

20192 3 6 74 5 8 9 10 11 12

1st published, for 2019

1st

rp

td

ue ICS Report, § 15SO GL NC ER

RSC Report § 17

LFC Report § 16

RSC on TSOs defence & restoration plans, § 6(3)

ENTSO-E on market suspension consistency, § 3609/2019

09/2019

09/2020

201710 11 128 96 7

LEGEND

SO GL EIF

Public consultation / WS

Stakeholder workshop

Delivery by TSOs/ENTSO-E

Approval by NRAs

no methodology approval, but rollout as 1 of 5 RSC

services

5

Data exchange, § 40(6)

Min. FCR activation in

CE & Nordic, §156(10-11)

Tim

elin

e in

clu

din

g N

RA

ap

pro

va

l

Determ. of LFC blocks, §141(2)

Oper. security analysis method., § 75

Synchronous area agreements, § 118

Min. inertia study per SA, § 39(3)(a)

Outage coordination methodology, § 84

Short/medium term adequacy, § 81

YA/DA/ID CGM, §§ 67(1),70(1)

Y-1 outage planning scenarios, § 65

CBA methodology

Proposal of min. activation period

Page 12: Common Grid Model and Operational Planning Data ......Common Grid Model and Operational Planning Data environment (OPDE) concepts and development Jean-Philippe Paul System Operation

THANK YOU FOR YOUR ATTENTION

Tahir KapetanovicSO Framework Convenor

ENTSO-E RSC Project Manager

Austrian Power Grid AG