commissioning plan step 2 - reva

Upload: almaporyak

Post on 03-Jun-2018

233 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    1/64

    PRINCE MOHAMMAD BIN ABDULAZIZ INTERNATIONAL AIRPORT IN MEDINA (SAUDI ARABIA)

    CONSULTANCY SERVICES FOR

    TEST &COMMISSIONING PLAN

    STEP 2:DRAFT COMMISSIONING PLAN

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    2/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    3/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    1 FOREWORD1. Reference is made to the Services Agreement for Consultancy Services for Test and

    Commissioning Plan and to its Attachment 1.

    2. As per Attachment 1 chapters 4.3 & 5, the Step 2 (Draft Commissioning Plan) is defined as:A draft version of the Test & Commissioning Plan, that will be further amended after writing of the

    Specifications per System and to take into account comments from the Subcontractors.

    The Test & Commissioning Plan will:

    a. Advise about the organization of the Test & Commissioning team at the EPC level;

    b. Identify the exhaustive list of subsystems and systems to be tested and commissioned, with the

    Subcontractors that will provide them;

    c. Define the successive and progressive Test & Commissioning steps (as addressed in paragraph 4.1),

    from Factory Acceptance Test and Test Lab test till final integration, including O&M documentation;

    d. Provide Guidelines for the writing of the Commissioning Specification per System;

    e Provide Guidelines for the test principles (full testing random method average )

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    4/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    2 COMMISSIONING ORGANIZATION2.1 COMMISSIONING SCOPE

    Commissioning is a systematic process of ensuring that all building systems perform

    interactively according to the design intent and the owners operational needs.

    The Commissioning process is intended to achieve the following specific objectives:

    Ensure that applicable equipment and systems are installed according to themanufacturers recommendation and to the industry acceptable standards and that they

    receive adequate operational check-out by the installing contractors.

    Verify and document proper performance of equipment and systems and the inter-relationship between systems.

    Ensure readiness and integration of all systems allowing starting ORAT phase

    2.2 COMMISSIONING PROCESS2.2.1 PHASES

    In order to cope with the above scope, a commissioning process in 5 phases will be followed.

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    5/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    Phase 3:

    This phase is covering all tests from phase 2 to phase 4 which means communication tests,remote functional tests, performance tests and interface tests (phase 3.11). Interface tests

    are numbered 3.11 but all interfaces must be tested as soon as possible through mock ups or

    site platforms in order to validate at the soonest the proper implementation on site (risk is

    lower if the interface has already been tested in phase 0)

    This phase requires Network

    Phase 4:

    This phase is covering the integrated tests and is based on a couple of scenario in order to

    ensure the full integration of all systems before starting the Operational Trials (ORAT).

    This phase requires all systems to be commissioned up to phase 3

    All the above phases and related reports will be a prerequisite with the As built drawings, the

    O&M manuals and the Training for the handover of the project and the start of the defect

    liability period.

    2.2.2 COLOR CODINGR f i t b l hi h i th h litti d t ll th t fl h t

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    6/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    30th

    May 2013Revision A Page 6 of 13

    Package

    Mechanical

    Package

    Electrical/ULV

    Package

    IT

    Package

    Conveying

    Package

    Screening

    Package AGL

    Phase 1Mechanical installation

    Phase 1Electrical installation

    Phase 1IT installation

    Phase 2Power up/Setting up

    Phase 2Deployment/Local functional tests

    Phase 3Remote functional tests/Performance tests

    Phase 3.11Interface tests

    Phase 4Integrated tests

    Handover to ORAT

    Phase 0FAT/Platform tests

    Building areas handed over

    Power available

    LAN operational

    All systems commissioned in stand alone mode

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    7/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    30th

    May 2013Revision A Page 7 of 13

    2.3 COMMISSIONING TEAM

    Below is described a possible organization for the commissioning team. The number of Commissioning Package manager can be reduced pending on

    the manager skills (for example, the Commissioning Conveying manager could also manage the Screening commissioning package).

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    8/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    a. Commissioning ManagerManaging the overall commissioning of the project

    Interfacing with all package managers and the design department

    Reporting to the Project Manager

    b. Commissioning Team ManagerManaging all package commissioning manager

    Organizing all phase 3.11 interface test (in coordination with the Integration manager)

    Reporting to the Commissioning Manager

    c.

    Integration ManagerWriting the Integrated test procedures used during phase 0.1 and phase 4

    Organizing all the phase 0.1 and phase 4 tests

    Reporting to the Commissioning Manager

    d. LEED CxSupervising the Electrical/Mechanical subcontractor in all aspects related to LEED

    Witnessing tests related to the LEED certification

    Producing the Summary Commissioning Report as per LEED requirements.

    Reporting to the Commissioning Manager

    e. Package Commissioning ManagerManaging the sub contractor in all aspects related to commissioning

    Reviewing all test procedures/sheets provided by the subcontractor

    Witnessing all functional tests

    R i h C i i i

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    9/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    3 COMMISSIONING PLAN FOR ALL SYSTEMSFor all following systems, two documents have been developed:

    - One flow chart showing graphically the sequence of the commissioning phases and thelinks with internal and external tasks.

    - One Excel sheet detailing each commissioning phase in term of content, pre-requisites,attendees,

    List of the systems in line with Step 1 analysis:

    - Package Electricalo VDGS/GOSo FASo PASo SMISo SACS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    10/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    11/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    30th

    May 2013Revision A Page 11 of 13

    System name

    External

    prerequisite

    External

    interface

    Commissioning

    phase where

    subcontractor

    is alone

    Commissioning

    phase where

    several

    subcontractors

    are required

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    12/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    30th

    May 2013Revision A Page 12 of 13

    Package Phase Descript io n Cont ent Spli t t ing Procedure At t end ees Prerequisit es Remarks

    PBB Phase 1.1 PBB

    Mechanical

    Installation o f all PBB mechanical

    items

    - qualit y check

    - l evel/alignment

    - torque

    per st and by T hys sen - Thyssen

    - M AJV Package

    team

    -stand area handed over by Building

    - anchor bol ts installed (contro lled by Thyssen)

    - all drawings/documents approved

    - material available

    Fixed link bridge to b e ready to finalize

    connection with PBB

    Phase 1.2 PBB

    Electrical

    Installation of all PBB electrical

    components (panels, trunking,

    cables, senso rs )

    - qualit y check

    - termination

    - labelling

    per st and by T hys sen - Thyssen

    - M AJV Package

    team

    - Phase 1.1PBB Mechanical done

    - all drawings/documents approved

    - material available

    Phase 2.1PBB Power up for all PBB electrical

    cabinets

    - continuity/insulation test

    - power up

    - phase rotation

    per st and by T hys sen - Thyssen

    - M AJV Package

    team

    - Phase 1.2 PBB Electrical do ne

    - power available fro m Building (including feeding

    cables)- no major M echanical/Electrical snags

    - all drawings/documents approved

    Possible to start with g enerator power

    To install VDGS operator panel during

    this p hase.

    Phase 2.2 PBB Commiss ioning of the PBB - funct ional tes ts

    - safety tests

    - anticollision tests

    per st and by T hys sen - Thyssen

    - MA JV Package team

    - M A JV

    Commissioning

    - Phase 2.1PBB done

    - all drawings/documents approved

    Phase 1.1GPU

    Mechanical

    Installation o f all GPU mechanical

    items

    - qualit y check

    - l evel/alignment

    - torque

    per s tand by Thyssen - Thyssen/AXA

    - M AJV Package

    team

    - Phase 1.1PBB Mechanical done (including f ixing f rames)

    - all drawings/documents approved

    - material available

    To do one asap and to perform the

    rest all to gether when all PBB' s are

    ready.

    GPU includes PBB connected units and

    standalone units.

    Phase 1.2 GPU

    Electrical

    Installation of all GPU electrical

    components

    - qualit y check

    - termination

    - labelling

    per s tand by Thyssen - Thyssen/AXA

    - M AJV Package

    team

    - Phase 1.1GPU M echanical done

    - all drawings/documents approved

    - material available

    Phase 2 GPU Commissioning of the GPU - continuity/insulation test

    - power up

    - phase rotation

    - configuration

    - f unctional tests

    per s tand by Thyssen - Thyssen/AXA

    - MA JV Package team

    - M A JV

    Commissioning

    team

    - Phase 1.2 GPU Electrical done

    - power available fro m Building (including feeding

    cables)

    - no major M echanical/Electrical snags

    - all drawings/documents approved

    Phase 1.1

    PCA/Hose

    Mechanical

    Installation of all PCA/Hose

    mechanical items

    - qualit y check

    - l evel/alignment

    - torque

    per s tand by Thyssen - Thyssen/AXA

    - M AJV Package

    team

    - Phase 1.1PBB Mechanical done (including f ixing f rames)

    - all drawings/documents approved

    - material available

    To do one asap and to perform the

    rest all to gether when all PBB' s are

    ready

    Phase 1.2

    PCA/Hose

    Electrical

    Installation of all PCA/Hose

    electrical components

    - qualit y check

    - termination

    - labelling

    per s tand by Thyssen - Thyssen/AXA

    - M AJV Package

    team

    - Phase 1.1PCA/ Hose Mechanical done

    - all drawings/documents approved

    - material available

    Phase 2

    PCA/Hose

    Commissioning of the PCA/Hose - continuity/insulation test

    - power up

    - phase rotation

    - configuration

    - f unctional tests

    per s tand by Thyssen - Thyssen/AXA

    - MA JV Package team

    - M A JV

    Commissioning

    team

    - Phase 1.2 PCA/ Hose Electrical do ne

    - power available fro m Building (including feeding

    cables)

    - no major M echanical/Electrical snags

    - all drawings/documents approved

    Phase 3 .11 PB B Int erf aces t est s - int erlo ck t est s wi th

    PCA/GPU/VDGS

    - interface tests with

    MCS/SCADA/TOIP/FAS

    per s tand by Thyssen - Thyssen/AXA

    - Safegate

    - MA JV Package team

    - M A JV

    Commissioning

    team

    - Phase 2.2 PBB and Phase 2 GPU/PCA/Hose done

    - network connection available

    - VDGS/M CS/SCADA/T OIP/FAS avai lable

    - no major Phase 2 snags

    - all drawings/documents approved

    FAS interface is just a signal (dry

    contact)

    GPU/PCA interface with PBB with dry

    contacts then PBB to SCADA by

    software.

    Phase 3.12 PBB Performance test and degraded

    mode

    - power b reak down t ests

    (UPS/Batt ery, Generator ,

    Tow bar)

    - water test

    per s tand by Thyssen - Thyssen/AXA

    - MA JV Package team

    - M A JV

    Commissioning

    team

    - Phase 2.2 PBB done

    - all drawings/documents approved

    Phase 4.01 Integrated test Aircraft Arrival and

    Departure scenario

    one s tand by M A JV - A ll i nvo lved sub

    contractors

    - MA JV Package team

    - M A JV

    Commissioning

    team

    - Investor and Investor IE

    - Phase 3.11and 3.12 PBB d one

    -GOS/RM S/Bi l l ing avai lable

    - availability of an aircraft

    - all drawings/documents approved

    If aircraft with engines ON, possible to

    validate the complete process

    including RMS/GOS/VDGS/Billing

    with flight schedule and block

    ON/OFF.

    If aircraft with engines OFF, to

    concentrate on PBB/GPU/PCA.

    System name

    List of all

    phases. One box

    = one Excel line

    Detail the

    content of

    each phase

    Indicate the way the phase will be split

    from a functional/geographical point of

    view. This is the basis of the step 3.

    Who is supposed to

    write the test

    procedures/sheetsWho is supposed to

    attend the tests

    List of external and

    internal prerequisites

    Remarks / Comments /

    Reminders / Experiences

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    13/64

    MAJV

    Consultancy Services for Test & Commissioning Plan

    4 ANNEX 1

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    14/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    15/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    16/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    17/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    ORGANISATION

    Electrical PAS Phase 0.0 PAS Study - Schematic Diagram

    - SAT Document

    by BNJV - BNJV

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    - SAT Document

    Electrical PAS Phase 0.2 PAS Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - BNJV

    - MAJV Package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    - Splitting Strategy Test

    - Definition of PAS Commisioning Team (Main

    Commisionning, Contractor and Sub Contractor

    Representative)

    DEPLOYMENTS

    Electrical PAS Phase 2.00 PAS Installation of all IT hardware and network Report To IT's Table Complete by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    Electrical PAS Phase 2.11 PAS Power Up - Electrical realisation Complete by BNJV - BNJV

    - MAJV Package team

    Accessibility of area - Control Center

    Electrical PAS Phase 2.12 PAS Deployment of PAS - Loudspeaker

    - Amplifier

    - Micro

    - etc...

    Complete by BNJV - BNJV

    - MAJV Package team

    Accessibilit y of area - Conformed at Split ting St rategy Test

    - Following by Test Schedule Document

    GLOBAL TEST

    Electrical PAS Phase 3.10 PAS Communication Test - power up

    - IT hardware configuration

    by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    -Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - Network available for the line array

    - all drawings/documents approved

    - material available

    - Communication Validated

    E lec tri ca l PAS Ph as e 3. 11 PAS PAS In terfa ces Refer to Diagram by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done - Automatic Action

    - response to alarm

    - loss of communication

    - Exchange Table

    - Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    Electrical PAS Phase 3.12 PAS PAS Functionnalities - Redundancies

    - Automatic Annoucement

    - Emergency\Priority

    - Backup

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done - Monitoring

    - Degraded Mode Philosophy

    - etc..

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 40% Others

    _Increased % if Crashed Test

    Electrical PAS Phase 3.13 PAS PAS Zoning Test - Emergency Announced

    - Operationnal Announced

    per PAS Zone by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    Phase 3.10 Done -STI Measurement

    - Confomity of End Device

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    OPERATIONNAL TESTAll Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

    All Phase 4.02 Safety Integrated Test - Safety processus Verification per FAS Zone by MAJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Safety Scenarios

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    18/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0

    CommissioningDocument

    BuildingMEP

    Phase 2.11Electrical Deployment

    Phase 2.00

    IT LAN Deployment

    Phase 3.10

    CommunicationTest SMIS

    Package Electrical

    SMIS

    SMIS FAT could be the same than both FATCCTV, SACS.

    Global

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Integrated Commissioning Step

    Link with a Mirror Step ofAnother Package

    Phase 3.11SACS Interface

    Phase 3.11CCTV Interface

    Phase 3.11SMIS

    Interfaces

    Phase 3.11SCADA Interface

    Phase 3.12SMIS

    Functionalities

    Phase 4.01

    INTEGRATED TEST

    Operational AirportCommissioning under Scenario

    Phase 0.1Test PlatformSMIS FAT

    HMI

    Functionnalities

    .

    SMIS depends of SACS and CCTV realization

    Phase 0.1

    SACS FAT

    Phase 01

    CCTV FAT

    Commissioning Step (Stand Alone)

    Phase 2.12SMIS Deployment

    Phase 0.2

    Site Organization

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    19/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    ORGANISATION

    Electrical SMIS Phase 0.0 SMIS Study - Schedule of SMISs

    - FAT and SAT Document

    by BNJV - BNJV

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    Electrical SMIS Phase 0.1 SMIS Test Platform - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    - Redundancy

    - SMIS Management

    by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - FAT Document Validated This FAT could be use to be CCTV and SACS one also.

    Electrical SMIS Phase 0.2 SMIS Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - BNJV

    - MAJV Package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    DEPLOYMENTS

    Electrical SMIS Phase 2.00 SMIS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    Electrical SMIS Phase 2.11 SMIS Power Up - Electrical realisation per Area n by BNJV - BNJV

    - MAJV Package team

    - handover of the area by Building and MEP

    - power available

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    Electrical SMIS Phase 2.12 SMIS Deployment of SMIS device - Connection

    - labelling

    - Servers and Workstation

    per Area n by BNJV - BNJV

    - MAJV Package team

    - material available

    - all drawings/documents approved

    GLOBAL TEST

    Electrical SMIS Phase 3.10 SMIS Communication Test - power up

    - IT hardware configuration

    per Area by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Phase 3.10

    - all drawings/documents approved

    - Communication Validated between SMIS equipment

    and between interfaced VLAN (CCTV, SACS)

    E le ct ri ca l S MI S P hase 3. 11 SM IS S MI S I nt er face s Refer to Diagram per Type by BNJV - BNJV- MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.11 Done- all interfaced systems available

    - Automatic and Manual Action- Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    Electrical SMIS Phase 3.12 SMIS SMIS Functionnalities - Validation In-Site of FAT

    - Backup

    - Redundancy

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.11 Done - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 30% Others

    _Increased % if Crashed Test

    OPERATIONNAL TEST

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    20/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    21/64

    Package Electrical

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    22/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0Commissioning

    Document

    Phase 0.1Test Platform

    SMIS FAT

    BuildingMEP

    Phase 2.11

    Electrical Deployment

    Phase 2.13Camera Deployment

    Phase 2.20Unit TestCamera

    Phase 2.00IT LAN Deployment

    Phase 3.10Communication

    Test

    Per area

    Per area

    Phase 3.13Global Camera Test

    Phase 3.11CCTV

    Interfaces

    Phase 3.12CCTV

    Functionalities

    Network

    Elec

    ManagementSystem

    IT + ELEC

    cam

    TEST CAMERA PHASE 3.13

    SCS

    Package Electrical

    CCTV

    Stand Alone Test Equipment

    FAT Validation

    Per area

    Global

    Camera Management

    HMIFunctionnalities

    .

    TEST CAMERA PHASE

    2.20

    Stand

    AloneMoving Unit

    Test

    ELEC For

    Mobile Camera

    Phase 2.12

    SCS Deployment Per area

    Commissioning Step

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Integrated Commissioning Step

    Phase 4.01

    INTEGRATED TESTOperational AirportCommissioning under Scenario

    MCS

    Phase 3.11SMIS

    Interface CCTV

    Link with a Mirror Step of

    Another Package

    Phase 0.2Site Organization

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    23/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    ORGANISATION

    Electrical CCTV Phase 0.0 CCTV Study - Schedule of CCTVs

    - Definition of CCTVs Type

    - FAT and SAT Document

    by BNJV - BNJV

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    FAT report/Material submital available to prove that

    all the devices tests as described in specification have

    been performed in factory

    Electrical CCTV Phase 0.1 SMIS Test Platform - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    - Redundancy

    - Recording Philosophy

    - CCTV Management

    by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - FA T Document Val idat ed Funct ionnal Design is fina li zed wit h a ccepta nce of FAT

    realization

    - Defined Clearly VMS Interfaces between Hardware

    and Software

    Electrical CCTV Phase 0.2 CCTV Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - BNJV

    - MAJV Package team- MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    DEPLOYMENTS

    Electrical C CTV Phas e 2.00 CCTV Installatio n o f all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/ TAV-IT

    - MAJV Package team

    Electrical CCTV Phase 2.11 CCTV Power Up - Electrical realisation per Area n by BNJV - BNJV

    - MAJV Package team

    - handover of the area by Building and MEP

    - power available

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    Electrical CCTV P hase 2.12 CCTV Deployment of SCS - Outlet Validation per Area n by BNJV - BNJV

    - MAJV Package team

    - handover of the area by Building and MEP

    - floor IDF with switches available

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    Electrical CCTV Phase 2.13 CCTV Deployment of CCTV device - quality check

    - level/alignment

    - Connection

    - labelling

    per Area n by BNJV - BNJV

    - MAJV Package team

    - handover of the area by Building and MEP

    - to follow the progress of phases 2.11 and

    2.12

    - material available

    - all drawings/documents approved

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    - Installation with In-site Parameters indeed

    UNIT TEST

    Electrical CCTV Phase 2.20 CCTV Deployment of Unit Test CCTV - Unit Physical Test

    - Utilization of a End Device Test

    Tools.

    per Area n-1 by BNJV - BNJV

    - MAJV Package team

    - MAJV Commissioning team

    - Phase 2.xx Done

    - all drawings/documents approved

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    6 The tool can record a picture of onsite camera and

    prepared a final document report par area to validate

    Quality and point of view.

    GLOBAL TEST

    Electrical CCTV Phase 3.10 CCTV Communication Test - power up

    - IT hardware configuration

    per Area by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Phase 3.10

    - all drawings/documents approved

    - Communication Validated

    E lect rica l CCTV P ha se 3 .1 1 CCTV CCTV I nt erfa ces Refer to Diagram per Type by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.10 Done

    - all interfaced systems available

    - Automatic and Manual Action

    - Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    Electrical CCTV Phase 3.12 CCTV CCTV Functionnalities - Validation In-Site of FAT

    - Recording

    - Backup

    - Redundancy

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.10 Done - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    - WallScreen behaviour, User Management

    - Recording

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 20% Others

    _Increased % if Crashed Test

    Electrical CCTV P hase 3.13 CCTV Global Camera Test - Validation Camera on VMS(Archiver, Viewer, Intrusion

    detection, etc..)

    per Area by BNJV - BNJV- MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Ph as e 3 .1 0 a nd 2. 20 Do ne - Be ha vi ou r o f e ac h C am er a o n V MS So ft wa re- Name, Correct View, Function, Default

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 20%

    _Increased % if Crashed Test

    OPERATIONNAL TEST

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    24/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    25/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    ORGANISATION

    Electrical

    SCADA

    Phase 0.0 SCADA Study - Schedule of SCADAs

    - FAT and SAT Document

    by BNJV - BNJV

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    Electrical

    SCADA

    Phase 0.1 SCADA Test Platform - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    - Redundancy

    - SCADA Management

    by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - FAT Document Validated Like all HMI's, a FAT is recommended to ensure

    consistency between End-User needs and the tools.

    Electrical

    SCADA

    Phase 0.2 SCADA Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - BNJV

    - MAJV Package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    DEPLOYMENTS

    Electrical

    SCADA

    Phase 2.00 SCADA Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    Electrical

    SCADA

    Phase 2.11 SCADA Power Up - Electrical realisation per Area n by BNJV - BNJV

    - MAJV Package team

    - handover of the area by Building and MEP

    - power available

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    Electrical

    SCADA

    Phase 2.12 SCADA Deployment of SCADA device - Connection

    - labelling

    per Area n by BNJV - BNJV

    - MAJV Package team

    - material available

    - all drawings/documents approved

    Servers and Workstations

    GLOBAL TEST

    Electrical

    SCADA

    Phase 3.10 SCADA Communication Test - power up

    - IT hardware configuration

    per Area by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Phase 2.xx

    - all drawings/documents approved

    - Communication Validated between SCADA

    equipment and between interfaced VLAN (CCTV,

    SACS)

    Electrical

    SCADA

    P hase 3. 11 SC AD A S CA DA I nt er face s Refer to Diagram per Type by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.10 Done

    - all interfaced systems available

    - Automatic and Manual Action

    - Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    Electrical

    SCADA

    Phase 3.12 SCADA SCADA Functionnalities - Validation In-Site of FAT

    - Backup

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.11 Done - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 30% Others

    _Increased % if Crashed Test

    OPERATIONNAL TEST

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

    Package Electrical

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    26/64

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0Commissioning

    Document

    Building

    MEP

    Phase 2.11Electrical Deployment

    Phase 2.12

    IPTV Deployment

    Phase 2.00IT LAN Deployment

    Phase 3.10Communication

    Test IPTV

    Package Electrical

    IPTV

    Global

    Global

    Commisionning Step

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Key Elements

    End Device Out of Scope

    Integrated Commisionning Step

    Link with a Mirror Step ofAnother Package

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    27/64

    Package Electrical

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    28/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0Commissioning

    Document

    BuildingMEP

    Phase 2.11

    Electrical Deployment

    Phase 2.12MCS Deployment

    Phase 2.00IT LAN Deployment

    Phase 3.10Communication

    Test MCS

    Phase 3.11Interface Test

    g

    MCS

    Loadcharge

    Wide System Interfaced

    Global

    Global

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Integrated Commisionning StepCommisionning Step (Stand Alone)

    Link with a Mirror Step ofAnother Package

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    29/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    ORGANISATION

    Electrical

    MCS

    Phase 0.0 MCS Study - Schedule of Clock

    - Definition of Clock Type

    - ICD global described each

    Interface

    - FAT and SAT Document

    by BNJV - BNJV

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    FAT report/Material submital available to prove that

    all the devices tests as described in specification have

    been performed in factory

    DEPLOYMENTS

    Electrical

    MCS

    Phase 2.00 MCS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    Electrical

    MCS

    Phase 2.11 MCS Power Up - Electrical realisation per Area n by BNJV - BNJV

    - MAJV Package team

    Accessibility of area - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    Electrical

    MCS

    Phase 2.12 MCS Deployment of MCS device - quality check

    - level/alignment

    - termination

    - labelling

    Global by BNJV - BNJV

    - MAJV Package team

    Accessibility of area - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    - Installation of CLOCK with In-site Parameters indeed

    GLOBAL TEST

    Electrical

    MCS

    Phase 3. 10 MC S Communica tion Test - power up

    - IT hardware configuration

    Global by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    -Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    - Communication Validated

    Electrical

    MCS

    Phase 3.11 MCS Interface Test - Verify Reception by at least one

    other vlan that NTP signal is

    received

    Global by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    Phase 3.10 Done MCS Final Validation

    Package Electrical

    VDGS/GOS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    30/64

    Phase 1

    VDGS

    Phase 2

    VDGS

    Supports(post,

    gantry)

    AODB/FIDS

    SCADA

    MCS (NTS)

    VDGS/GOS

    Consultancy Services for Test & Commissioning Plan

    Phase 4.01Phase 1

    GOSPhase 2

    GOS

    Phase 3.11

    GOS

    Apronpainting

    Phase 1.2PBB

    Electrical

    Power LAN

    Data center/Control Room

    PBB

    Phase 3.11

    VDGS

    EMS/SCADA?

    Phase 3.12GOS

    Phase 3.10GOS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    31/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Electrical

    VDGS/GOS

    Phase 1 VDGS Installation of all mechanical/electrical items - quality check

    - level/alignment

    - termination

    - labelling

    pe r s tand b y S afe gate - Saf egat e

    - MAJV Package team

    - stand area handed over by Building with proper

    supports

    - Phase 1.2 PBB Electrical done (to fix the

    operator panel in PBB cabin)

    - all drawings/documents approved

    - material available

    Phase 2 VDGS Power up and commissioning - continuity/insulation test

    - power up

    - setting up

    - functional test

    pe r s tand b y S afe gate - Saf egat e

    - MAJV Package team

    - MAJV Commissioning team

    - Phase 1 VDGS done

    - apron painting done

    - building power available

    - all drawings/documents approved

    Possible to perform this phase with temporary apron

    marking and temporary power.

    Phase 3.11 VDGS Interface test of the system - interlock test with PBB

    - interface test with EMS/SCADA

    pe r s tand b y S afe gate - Saf egat e

    - MAJV Package team- MAJV Commissioning team

    - Phase 2 VDGS done

    - PBB/EMS/SCADA available- all drawings/documents approved

    Interface with EMS/SCADA to be clarified by MAJV

    Phase 1 GOS Installation of all IT hardware and network - quality check

    - cable test

    - termination

    - labelling

    c om pl ete b y S afe gate - Saf egat e

    - MAJV Package team

    - data centers/control room (power socket, data

    sockets, light, A/C) handed over

    - all drawings/documents approved

    - material available

    Phase 2 GOS Power up and commissioning - power up

    - IT hardware configuration

    - functional test

    c om pl ete b y S afe gate - Saf egat e

    - MAJV Package team

    - MAJV Commissioning team

    - Phase 1 GOS done

    -power available

    - all drawings/documents approved

    Possible to start with temporary power

    Phase 3.10 GOS Communication tests - communication tests

    - fleet mix configuration

    c om pl ete b y S afe gate - Saf egat e

    - MAJV Package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 2 VDGS and GOS done

    - LAN available

    - all drawings/documents approved

    To ensure the proper/definitive fleet mix is used (fleet mix

    must be consistent between VDGS, GOS, RMS and Apron

    marking)

    Phase 3.11 GOS Interface test of the system - interface test with MCS

    - interface test with SCADA

    - interface test with AODB/FIDS

    c om pl ete b y S afe gate - Saf egat e

    - MAJV Package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.10 GOS done

    - LAN available

    - all interfaced systems available

    - all drawings/documents approved

    Phase 3.12 GOS Remote functional tests and degraded modes - remote functional test (operational

    scenario)

    - degraded modes

    c om pl ete b y S afe gate - Saf egat e

    - MAJV Package team

    - MAJV Commissioning team- Investor and Investor IE

    - Phase 2 VDGS and Phase 3.10 GOS done

    - LAN available

    - all drawings/documents approved

    Phase 4.01 Integrated test Aircraft Arrival and Departure scenario one stand by MAJV - All involved sub contractors

    - MAJV Package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.11 and 3.12 PBB done

    - PBB/RMS/Billing available

    - availability of an aircraft

    - all drawings/documents approved

    If aircraft with engines ON, possible to validate the

    complete process including RMS/GOS/VDGS/Billing with

    flight schedule and block ON/OFF.

    If aircraft with engines OFF, to concentrate on

    PBB/GPU/PCA.

    Package Electrical

    EMS/LCS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    32/64

    Phase 1

    Mechanical

    Phase 1

    Electrical

    Phase 2.1

    Power up

    Phase 2.2

    Static tests

    BuildingElectrical

    rooms

    Phase 1EMS

    Phase 3.10

    EMS/LCS

    IT rooms

    IB

    SCADA

    Phase 2EMS

    MCS (NTS)

    VDGS?

    EMS/LCS

    Consultancy Services for Test & Commissioning Plan

    Phase 3.12

    EMS/LCS

    Phase 3.13

    EMS/LCS

    Phase 3.11

    EMS/LCS

    LANPower Phase 4.01

    Phase 1LCS

    IT roomsPhase 2

    LCS

    AODB?

    Power

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    33/64

    Package P hase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Electrical

    EMS/LCS

    Phase 1Mechanical Mechanical installation

    - generator,

    - UPS,

    - Transformer

    - central battery system

    - all cabinets

    - quality check

    - fixing

    - level/alignment

    per major equipment by BNJV - BNJV

    - MAJV package team

    - all drawings/documents approved

    - material available

    FAT report/Material submital are mandatory to

    ensure consistency with design.

    Phase 1E lec tr ic al E lectrical in s tal lat io n

    - trunking

    - cables

    - quality check

    - cable fixing

    - termination

    - cold test/insulation test

    per major equipment by BNJV - BNJV

    - MAJV package team

    # NO M? T he t ar ge t i s t o b e s af e t o e ne rg iz e ( im po rt an t s te p t o

    be documented)

    Phase 2.1Power up Power up for all equipment - power up

    - voltage check

    - phase rotation

    - lamps

    per major equipment by BNJV - BNJV

    - MAJV package team

    - LEED Cx

    - phase 1 electrical done

    - power available

    - all drawings/documents approved

    FAT report/Material submital are mandatory to

    ensure consistency with design and to avoid

    repeating all "internal" tests already performed in

    factory.

    Phase 2.2Static tests Static test - Live tests

    - Earth resistance

    per major equipment by BNJV - BNJV

    - MAJV package team

    - LEED Cx

    p ha se 2. 1 po we r u p d on e A t a ll s ta ge s, LE ED Cx to ch ec k c om pl ia nc e w it h LE ED

    requirements

    Phase 1EMS Installation of all IT hardware - quality check

    - termination

    - labelling

    per EMS controller by BNJV - BNJV

    - MAJV package team

    - IT rooms (finishes, A/C, light, desk)

    available

    - all drawings/documents approved

    - material available

    Phase 1LCS Installation of all IT hardware - quality check

    - termination

    - labelling

    Complete by BNJV - BNJV

    - MAJV package team

    - IT rooms (finishes, A/C, light, desk)

    available

    - all drawings/documents approved

    - material available

    Phase 2EMS Power up - power up

    - GUI check

    - functional test

    per EMS controller by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - LEED Cx

    - phase 1 EMS done

    - power available

    Phase 2LCS Power up - power up

    - GUI check

    - functional test

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - LEED Cx

    - phase 1 LCS done

    - power available

    Phase 3.10EMS/LCS Communication test - network address check

    - exchange table check

    - labelling and address control

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - LEED Cx

    - phases 2.x done

    - network available

    Phase 3.11EMS/LCS Interface tests - interface tests with all impacted systems Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - LEED Cx

    - phase 3.10 done

    - all interfaced systems available

    - ICD's approved

    P ha se 3 .1 2E MS /L CS O per at ing t es t - R emo te c ont ro l - F au lt /st at us /me ter ing ch ec k

    - control command test

    - operational tests (Manual and Auto (time or

    photocell))

    - control and measuring of energy consumption

    Complete by BNJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - LEED Cx

    - phase 3.10 done

    Phase 3.13EMS/LCS Performance test - availability tests- endurance tests

    - redundancy and backup power systems check,

    - illumination check

    Complete by BNJV - BNJV- MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - LEED Cx

    - phase 3.12 done

    Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - BNJV

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - LEED Cx

    Phase 3 Done - Different Operationnal Scenarios

    Main Prerequisites Synthesis

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    34/64

    BuildingMEP

    SCS

    IT LAN

    ELEC

    EndDevice

    ControlDevice

    EndDevice

    ControlDevice

    EndDevice

    Communication between

    End and Control Device

    HardwareSoftware

    Rack EquipmentFiber Wiring

    Power

    Cable Power

    Power Providing IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTVPAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODBBRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    IT

    AODB

    BRS

    CPS

    CUXX

    FIDS

    RMS

    TOIP

    WIFI

    ULV

    SCADA

    IPTV

    PAS

    MCS

    SMIS

    SACS

    CCTV

    FAS

    Prerequisites are necessary

    Prerequisites must be countourned byusing adapted tools and methods

    Package IT

    LANS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    35/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0

    CommissioningDocument

    Phase 0.2Site Organization

    Phase 3.10

    LANsCommunication

    Test

    LAN S

    Integrated Commisionning Step

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Commisionning Step (Stand Alone)

    Building

    MEP

    Phase 2.11

    Electrical Deployment

    LANs Communication commissioning

    Major Step

    Phase 2.12

    SCS Deployment

    Per area

    Phase 2.13

    LANs Deployment

    Phase 2.14LANs Configuration

    Phase 4.01

    INTEGRATED TESTOperational Beahvior

    Commissioning under Scenario

    Phase 3.12

    LANsFunctionalities

    Site Optimisation depends ofCompleteness Study

    Phas e 2.00IT LAN DEPLOYMENT

    Per area

    Per area

    Per area

    Per area

    Link with a Mirror Step of

    Another Package

    All Systems

    A method should be edited to define how

    lan's up of depending

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    36/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Phase 0.00 ORGANISATION

    IT LAN Phase 0.0 LAN Study - Schedule of LANs

    - FAT and SAT Document

    - IP Address List (ULV, IT, etc..)

    and port configuration

    by TAV-IT - TAV-IT

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    - Final SD for each IT and ULV System

    IP Address List is a Main Document.

    It could improve considerably time on-site for :

    _ Manage Interfaces

    _ Reduce Time of Step Commisionning

    IT LAN Phase 0.2 LAN Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - TAV-IT

    - MAJV Package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    P ha se 2 . 00 D EP LO YM EN TS

    IT LAN Phase 2.11 LAN Electrical Deployment - Electrical realisation per Area n by BNJV - BNJV- MAJV Package team

    Accessibi lity of area - Conformed at Splitting Strategy Test- Following by Test Schedule Document

    IT LAN Phase 2.12 LAN SCS Deployment - Outlet Validation per Area n by BNJV - BNJV

    - MAJV Package team

    Accessibil ity of area - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    IT LAN Phase 2.13 LAN Deployment of LAN device - Room quality check

    - level/alignment

    - Cable structure Acceptance

    - labelling

    per Area n-1 by TAV-IT - TAV-IT

    - MAJV Package team

    - power available

    - all drawings/documents approved

    - Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    IT LAN Phase 2.14 LAN LAN Configuration - power up

    - IT hardware configuration

    - IT Link validation

    per Area n-1 by TAV-IT - TAV-IT

    - MAJV Package team

    -Phase 2.13 Done Integration of each VLAN

    Integration of IP Management Requirement

    Link\Trunk Configuration

    ICT LAN

    NIC

    SGS, SA, etc

    P ha se 3. 00 GLO BAL T ES T

    IT LAN Phase 3.10 LAN Communication Test - Validation for each "User" of

    Lan's that communication is

    available

    - Validation of Necessary

    Gateways for "users" (MCS, etc)

    per Area by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 2.14 Done If IP Adress List and port configuration had been

    transmitted in Phase 2.14; this step could be a stand-

    alone step realized by each Interfaced Users'.

    Otherwise it could be i ntegrated test and time

    consuming taskfor each representant.

    IT LAN Phase 3.12 LAN LAN Functionnalities - Degraded Mode Philosophy

    - Redundancy

    - LAN Management

    - Load Bandwitchvalidation

    - Performance, QoS, etc

    Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done Validation of SAT

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 40% Others

    _Increased % if Crashed Test

    Phase 4.00 OPERATIONNAL TEST

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 .12 Done - Different Operationnal Scenarios

    Package IT

    AODB/RMS/IBSCADA EMS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    37/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0Commissioning

    Document

    Phase 0.1Test Platform

    FAT

    Phase 0.2

    Site Organization

    Phase 2.00

    IT LAN Deployment

    Phase 3.10

    AODBCommunication

    Test

    Phase 3.12AODB

    Funtionnalities

    AODB/RMS/IB

    FAT Validation

    Global

    ICDFunctionnalities

    .

    Phase 3.11AODB Interfaces

    Integrated Commisionning Step

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Phase 3.13ITS Functionalities

    3.13.a RMS

    A lot of InterfacesDetailed Analysys in Phase 0.0 needed

    Phase 4.01

    INTEGRATED TESTOperational Behavior

    Commissioning under Scenario

    Commisionning Step (Stand Alone)

    Phase 3.11

    CUPPS Interface

    Phase 3.11

    FIDS Interface

    GOSIT MANAGEMENT

    MCS

    BRS

    BHS

    Link with a Mirror Step of

    Another Package

    Phase 2.10AODB Servers

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    38/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Phase 0.00 ORGANISATION

    IT AODB\IB\RMS Phase 0.0 AODB Study - Schedule of AODBs

    - FAT and SAT Document

    by TAV-IT - TAV-IT

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    FAT report/Material submital available to prove that

    all the devices tests as described in specification have

    been performed in factory\Laboratory

    Provide All necessary ICD Documents

    IT AODB\IB\RMS Phase 0.1 AODB Test Platform - Degraded Mode Philosophy

    - Redundancy

    - AODB Management

    - HMI Functionalities (RMS)

    by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - F AT D oc um en t Va li da te d F un ct io nn al D es ig n is f in al iz ed w it h ac ce pt an ce o f FA T

    realization

    RMS Functionnalities

    IT AODB\IB\RMS Phase 0.2 AODB Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 0.0 Done Definition of Test and Method

    Phase 2.00 DEPLOYMENTS

    IT AODB\IB\RMS Phase 2.00 AODB LAN deployment Report To IT's Table per area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    IT AO DB\IB\RMS Phas e 2.10 AODB Dep lo yment o f AODB S ervers - Ins ta lla tion and Con figuratio n of AO DB

    Servers

    per room by TAV-IT - TAV-IT

    - MAJV Package team

    - power available

    - all drawings/documents approved

    - Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    Installation of AODB Server

    Phase 3.00 GLOBAL TEST

    IT AODB\IB\RMS Phase 3.10 AODB Communication Test - power up AODB Equipment Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Phase 2.10 Done

    - AODB Network Configuration Done

    Communication Validated

    I T A OD B\ IB\ RMS P ha se 3 .1 1 A OD B A OD B I nte rf ac es Refer to Diagram per Type by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done Validation of all ICD

    Validation of Exchange table

    Validation of Request

    Recommendations :

    _ 100% Done by Contractor_ Commissioner : 100%

    If available, to perform through RMS GUI's

    IT AODB\IB\RMS Phase 3.12 AODB AODB Functionnalities - Degraded Mode Philosophy

    - Redundancy

    - AODB Management

    Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 3.10 Done Validation of SAT

    Validation of Number of Workstationinstalled

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 40% Others

    _Increased % if Crashed Test

    IT AODB\IB\RMS Phase 3.13x IT Functionnalities Interfaces - HMI Functionnalities

    - Redundance

    - Degraded Mode philosophy

    - Backup

    Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.11 Done

    Phase 3.12 Done

    Validation of RMS

    Validation of Number of Workstation installed

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 20%

    _Increased % if Crashed Test

    Phase 4.00 OPERATIONNAL TEST

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT

    - MAJV package team- MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done Different Operationnal Scenarios

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    39/64

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    40/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Phase 0.00 ORGANISATION

    IT BRS Phase 0.0 BRS Study - Schedule of BRSs

    - FAT and SAT Document

    by TAV-IT - TAV-IT

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    FAT report/Material submital available to prove that

    all the devices tests as described in specification have

    been performed in factory\Laboratory

    - Provide All necessary ICD Documents

    IT BRS Phase 0.1 BRS Test Platform - Degraded Mode Philosophy

    - Redundancy

    - HMI Functionalities

    by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - F AT D oc um en t Va li da te d F un ct io nn al D es ig n is f in al iz ed w it h ac ce pt an ce o f FA T

    realization

    BRS Functionnalities

    IT BRS Phase 0.2 BRS Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    Phase 2.00 DEPLOYMENTS

    IT BRS Phase 2.00 BRS Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    IT BRS Phase 2.10 BRS Deployment of BRS Servers - Installation and Configuration of BRS

    Servers

    by TAV-IT - TAV-IT

    - MAJV Package team

    - power available

    - all drawings/documents approved

    - Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    Installation of BRS Server

    Phase 3.00 GLOBAL TEST

    IT BRS Phase 3.10 BRS Communication Test - power up BRS Equipment Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Phase 2.10 Done

    - BRS Network Configuration Done

    - Communication Validated

    IT BRS Phase 3.11 BRS BRS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done - Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    IT BRS Phase 3.12 BRS BRS Functionnalities - Degraded Mode Philosophy

    - Redundancy

    Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 3.10 Done - Validation of SAT

    - Validation of Number of Workstationinstalled

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100% Of Critical \ 40% Others

    _Increased % if Crashed Test

    IT BRS Phase 3.13 IT Functionnalities Interfaces - HMI Functionnalities

    - Redundance

    - Degraded Mode philosophy

    - Backup

    - Handset deployment

    Global by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.11 Done

    Phase 3.12 Done

    - Validation of Number of Workstation installed

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 20%

    _Increased % if Crashed Test

    Phase 4.00 OPERATIONNAL TEST

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

    Package IT

    CUPPS / CUSS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    41/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0

    CommissioningDocument

    Phase 0.1

    Test PlatformFAT

    Phase 0.2

    Site Organization

    Building

    MEP

    Phase 2.11

    Electrical Deployment

    Phase 2.14CUPPS\CUSS Deployment

    Phase 2.20

    Unit TestCUPPS

    Phase 2.00

    IT LAN Deployment

    Phase 3.10

    CUPPSCommunicationTest

    Per area

    Per

    StrategicZone

    Phase 3.12

    CUPPSFuntionnalities

    MCS

    FAT Validation

    Per area

    Global

    HMIFunctionnalities

    .

    Phase 3.11

    CUPPSInterfaces

    Desk Interfaces

    Phase 2.12

    Desk Deployment Per area

    Phase 2.13

    SCS Deployment Per area

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Phase 3.11AODB

    Phase 4.01

    INTEGRATED TESTOperational Behavior

    Commissioning under Scenario

    Integrated Commisionning StepCommisionning Step (Stand Alone)

    Link with a Mirror Step of

    Another Package

    DCSInterface

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    42/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    P ha se 0 .0 0 O RG AN ISA TI ON

    IT CUPPS Phase 0.0 CUPPS Study - Schedule of CUPPSs

    - Definition of CUPPSs Type

    - FAT and SAT Document

    by TAV-IT - TAV-IT

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    FAT report/Material submital available to prove that

    all the devices tests as described in specification have

    been performed in factory

    IT CUPPS Phase 0.1 CUPPS Test Platform - HMI Presentation

    - CUTE\CUSS\CUPPS

    - CUPPS Management

    by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - FA T Do cu me nt Va li da te d F un ct io nn al D es ig n is f in al iz ed w it h ac ce pt an ce of F AT

    realization

    IT CUPPS Phase 0.2 CUPPS Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    P ha se 2 .0 0 D EP LOY MEN TS

    IT CUPPS Phase 2.00 IT LAN Installation of all IT hardware and network Report To IT's Table per Area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    IT CUPPS Phase 2.11 CUPPS Power Up - Electrical realisation per Area n by BNJV - BNJV

    - MAJV Package team

    Accessibil ity of area - Con formed at Sp litting St rat egy Test

    - Following by Test Schedule Document

    IT CUPPS Phase 2.12 CUPPS Desk Deployment per Area n by MAJV - MAJV Accessibility of area - Conformed at Splitting Strategy Test

    - Following by Test Schedule Document

    IT CUPPS Phase 2.13 CUPPS SCS Deployment - Outlet Validation per Area n by BNJV - BNJV

    - MAJV Package team

    Accessibil ity of area - Con formed at Sp litting St rat egy Test

    - Following by Test Schedule Document

    IT CUPPS Phase 2.14 CUPPS Deployment of CUPPS device - quality check

    - level/alignment

    - termination

    - labelling

    per Area n by TAV-IT - TAV-IT

    - MAJV Package team

    Accessibil ity of area - Con formed at Sp litting St rat egy Test

    - Following by Test Schedule Document

    - Installation with In-site Parameters indeed

    UNIT TEST

    IT CUPPS Phase 2.20 CUPPS Deployment of Test CUPPS Phase 1 - Unit Physical Test per Area n-1 by TAV-IT - TAV-IT- MAJV package team

    - MAJV Commissioning team

    Phases 2.1x Done - Conformed at Splitting Strategy Test- Following by Test Schedule Document

    P ha se 3.00 GLOBAL TEST

    IT CUPPS Phase 3.10 CUPPS Communication Test - power up

    - IT hardware configuration

    per Area by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    -Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    - Communication Validated

    IT CUPPS Phase 3.11 CUPPS CUPPS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done - Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    - Configuration with all required DCS

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    IT CUPPS Phase 3.12 CUPPS CUPPS Functionnalities - Validation In-Site of FAT Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team- Investor and Investor IE

    Phase 3.10 Done - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy- Validation Number of CUTE\CUSS\CUPPS

    P ha se 4 .0 0 O PE RA TI ON NA L T ES T

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

    Phase 2.00

    Package Electrical & IT

    FIDS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    43/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0

    CommissioningDocument

    Phase 0.1

    Test PlatformFAT

    Phase 0.2Site Organization

    BuildingMEP

    Phase 2.11Electrical Deployment

    Phase 2.13FIDS Deployment

    Phase 2.20

    Unit Test FIDS

    Phase 2.00

    IT LAN Deployment

    Phase 3.10

    CommunicationTest FIDS

    Per area

    Per area Phase 3.12FIDS

    Funtionnalities

    Link BNJV/IT

    FAT Validation

    Per area

    Global

    HMI

    Functionnalities

    .

    Phase 3.11FIDS

    Interfaces

    Deployment or Study Step

    Step depending of another SubPackage orPackage

    Phase 2.12

    SCS Deployment Per area

    Integrated Commisionning StepCommisionning Step (Stand Alone)

    ULV

    Phase 4.01

    INTEGRATED TEST

    Operational BehaviorCommissioning under Scenario

    Link with a Mirror Step ofAnother Package

    Phase 2.14FIDS Servers

    Phase 3.11PASMCS

    Phase 3.11TOIP

    Phase 3.11

    AODB

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    44/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    P ha se 0 .0 0 O RG AN IS AT IO N

    IT FIDS Phase 0.0 FIDS Study - Schedule of FIDSs

    - Definition of FIDSs Type

    - FAT and SAT Document

    by TAV-IT - TAV-IT

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    FAT report/Material submital available to prove that

    all the devices tests as described in specification have

    been performed in factory\Laboratory

    IT FIDS Phase 0.1 FIDS Test Platform - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    - Redundancy

    - FIDS Management

    by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - FA T Document Val idat ed Funct ionnal Design is fina li zed wit h a ccepta nce of FAT

    realization

    IT FIDS Phase 0.2 FIDS Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    P ha se 2. 00 D EP LO YM EN TS

    IT FI DS P ha se 2. 00 IT LA N F ID S I ns ta ll at io n o f al l IT ha rd wa re a nd ne tw or k

    FIDS Server

    Report To IT's Table per Area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    IT FIDS Phase 2.11 FIDS Power Up - Electrical realisation per Area n by BNJV - BNJV

    - MAJV Package team

    A ccessibility of area - Conf ormed at Splitting Strategy Test

    - Following by Test Schedule Document

    IT FIDS Phase 2.12 FIDS SCS Deployment - Outlet Validation per Area n by BNJV - BNJV

    - MAJV Package team

    A cces sibility of area - Conf ormed at Splitting Strategy Test

    - Following by Test Schedule Document

    IT FIDS Phase 2.13 FIDS Deployment of FIDS device - quality check

    - level/alignment

    - termination

    - labelling

    per Area n by TAV-IT - BNJV

    - MAJV Package team

    A cces sibility of area - Conf ormed at Splitting Strategy Test

    - Following by Test Schedule Document

    - Installation of FIDS with In-site Parameters indeed is

    recommended

    IT FIDS Phase 2.14 FIDS Deployment of FIDS Servers - Installation and Configuration of

    FIDS Servers

    by TAV-IT - TAV-IT

    - MAJV Package team

    - power available

    - all drawings/documents approved

    - Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    UNIT TEST

    IT FIDS Phase 2.20 FIDS Deployment of Test FIDS Phase 1 - Unit Physical Test per Area n-1 by TAV-IT - TAV-IT- MAJV package team

    - MAJV Commissioning team

    Phases 2.1x Done - Conformed at Splitting Strategy Test- Following by Test Schedule Document

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 10%

    _Increased % if Crashed Test

    P ha se 3. 00 G LO BA L T ES T

    IT FIDS Phase 3.10 FIDS Communication Test - power up

    - IT hardware configuration

    - interface test with LAN ICT

    per Area by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    -Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    - Communication Validated

    IT FIDS Phase 3.11 FIDS FIDS Interfaces Refer to Diagram per Type by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done - Validation of all ICD

    - Validation of Exchange table

    - Validation of Request

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 100%

    If available, prefer to perform test with BHS\GOS

    IT FIDS Phase 3.12 FIDS FIDS Functionnalities - Validation In-Site of FAT

    - Backup

    Complete by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3.10 Done - HMI Presentation

    - Alarms Simulation

    - Degraded Mode Philosophy

    MID\WID\RID\SID etc.

    - Validation of Number ofWorkstation installedRecommendations :

    _ 100% Done by Contractor

    _ Commissioner : 20%

    _Increased % if Crashed Test

    P ha se 4 .0 0 O PE RA TI ON NA L T ES T

    All Phase 4.01 Integrated Test - Full Operationnal Scenario Complete by MAJV - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    Phase 3 Done - Different Operationnal Scenarios

    Package IT

    TOIP

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    45/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0Commissioning

    Document

    Phase 0.2Site Organization

    Phase 2.00

    Deployment of IT LAN

    Phase 3.10

    TOIPCommunication

    Test

    Phase 3.12TOIP Funtionnalities

    End device Deployment need Servers

    Configuration

    Recommend to configure end-device in controlroom to ensure behaviour before connect and

    do Unit Test

    Phase 3.11

    TOIP Interfaces

    Integrated Commisionning Step

    Deployment or Study Step

    Step depending of another SubPackage or

    Package

    Phase 4.01

    INTEGRATED TESTOperational Behavior

    Commissioning under Scenario

    Commisionning Step (Stand Alone)

    Phase 3.11FIDS Interface

    MCS

    Link with a Mirror Step of

    Another Package

    Phase 2.10TOIP Servers

    Phase 2.20

    TOIPUnit Test

    Phase 2.11TOIP

    Deployment

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    46/64

    Package IT

    WIFI

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    47/64

    Key Elements

    Consultancy Services for Test & Commissioning Plan

    Phase 0.0Commissioning

    Document

    Phase 0.2Site Organization

    Phase 2.00 WIFI

    Deployment of IT LAN

    Phase 3.10

    WIFICommunication

    Test

    Commissioning Signal Quality per Zone

    Global

    Integrated Commisionning Step

    Deployment or Study Step

    Step depending of another SubPackage or

    Package

    Commisionning Step (Stand Alone)

    Link with a Mirror Step of

    Another Package

    Phase 2.10WIFI

    Controllers

    Phase 3.11

    WIFIZone Test

    Phase 2.11Deployment Of Wifi Device Global

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    48/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Ph as e 0 .0 0 O RGA NIS ATI ON

    IT WIFI Phase 0.0 WIFI Study - Schedule of WIFIs

    - SAT Document

    - Phone List and Number

    by TAV-IT - TAV-IT

    - MAJV Package team

    - Contractors and Sub-Contractors

    Designation

    IT WIFI Phase 0.2 WIFI Organization - Planning of Deployement

    - Validation of SAT Schedule

    by MAJV - TAV-IT

    - MAJV Package team

    - MAJV Commissioning team

    Phase 0.0 Done - Definition of Test and Method

    Ph as e 2 .0 0 D EPL OYM ENT S

    IT WIFI Phase 2.00 WIFI Installation of all IT hardware and network Report To IT's Table per area by TAV-IT - BNJV/TAV-IT

    - MAJV Package team

    IT WIFI Phase 2.10 WIFI Deployment of WIFI Contr ollers* - Installation and Configur ation of WIFI

    Servers

    by TAV-IT - TAV-IT

    - MAJV Package team

    - power available

    - all drawings/documents approved

    - Data centers/Control rooms handed over

    (finishes, A/C, furnished, light)

    - all drawings/documents approved

    - material available

    Installation of WIFI Server

    IT WIFI Phase 2.11 WIFI Deployment of WIFI device - quality check

    - Configuration

    - labelling

    per area by TAV-IT - TAV-IT

    - MAJV Package team

    Accessibility of area - Need Server to be configured

    - Could be parameter in a "Control Room" to be sure

    that End-device is on and optimize time deployment

    and test

    Ph as e 3 .0 0 G LO BA L T ES T

    IT WIFI Phase 3.10 WIFI Communication Test - power up WIFI Equipment

    - interface test with LAN ICT

    Global by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Phase 2.10 Done

    - WIFI Network Configuration Done

    - Communication Validated

    IT WIFI Phase 3.11 WIFI WIFI Zone Test - Qulaity of Signal deployed in the zone

    - Bandwith with a lot of connected user

    simultanously

    - Check Acces Right Users

    per area by TAV-IT - TAV-IT

    - MAJV package team

    - MAJV Commissioning team

    - Investor and Investor IE

    P ha se s 3 .1 0 a nd 2. 11 Do ne - Co nf or me d a t S pl it ti ng St ra te gy Te st

    - Following by Test Schedule Document

    Recommendations :

    _ 100% Done by Contractor

    _ Commissioner : 15%

    _Increased % if Crashed Test

    Package Conveying

    PBB

    GOS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    49/64

    Phase 1.1PBB

    Mechanical

    Phase 1.2PBB

    Electrical

    Apron/

    Anchor bolts

    Power

    TOIP

    SCADA

    Phase 2.1

    PBB

    MCS (NTS)

    FAS

    Consultancy Services for Test & Commissioning Plan

    Phase 1.1GPU

    Mechanical

    Phase 1.2GPU

    Electrical

    Phase 1.1PCA/HoseMechanical

    Phase 1.2PCAHoseElectrical

    VDGS

    Phase 2.2

    PBB

    Phase 3.12

    PBB

    Phase 2

    GPU

    Phase 2

    PCA/Hose

    LAN

    Phase 4.01

    GOS

    Phase 3.11PBB

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    50/64

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    PBB Phase 1.1 PBB Mechanical Installation of all PBB mechanical items - quality check

    - level/alignment

    - torque

    per stand by Thyssen - Thyssen

    - MAJV Package team

    -stand area handed over by Building

    - anchor bolts installed (controlled by Thyssen)

    - all drawings/documents approved

    - material available

    Fixed link bridge to be ready to finalize connection with PBB

    P ha se 1 .2 P BB E lect rica l I nsta llat ion of a ll P BB e lect rica l components (pa nels , trunking , ca bles, sensors ) - qua li ty check

    - termination

    - labelling

    per stand by Thyssen - Thyssen

    - MAJV Package team

    - Phase 1.1 PBB Mechanical done

    - all drawings/documents approved

    - material available

    Phase 2.1 PBB Power up for all PBB electrical cabinets - continuity/insulation test

    - power up

    - phase rotation

    per stand by Thyssen - Thyssen

    - MAJV Package team

    - Phase 1.2 PBB Electrical done

    - power available from Building (including

    feeding cables)

    - no major Mechanical/Electrical snags

    - all drawings/documents approved

    Possible to start with generator power

    To install VDGS operator panel during this phase.

    Phase 2.2 PBB Commissioning of the PBB - functional tests- safety tests

    - anticollision tests

    per stand by Thyssen - Thyssen- MAJV Package team

    - MAJV Commissioning team

    - Phase 2.1 PBB done- all drawings/documents approved

    Phase 1.1 GPU Mechanical Installation of all GPU mechanical items - quality check

    - level/alignment

    - torque

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - MAJV Package team

    - Phase 1.1 PBB Mechanical done (including fixing

    frames)

    - all drawings/documents approved

    - material available

    To do one asap and to perform the rest all together when

    all PBB's are ready.

    GPU includes PBB connected units and standalone units.

    Phase 1.2 GPU Electrical Installation of all GPU electrical components - quality check

    - termination

    - labelling

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - MAJV Package team

    - Phase 1.1 GPU Mechanical done

    - all drawings/documents approved

    - material available

    Phase 2 GPU Commissioning of the GPU - continuity/insulation test

    - power up

    - phase rotation

    - configuration

    - functional tests

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - MAJV Package team

    - MAJV Commissioning team

    - Phase 1.2 GPU Electrical done

    - power available from Building (including

    feeding cables)

    - no major Mechanical/Electrical snags

    - all drawings/documents approved

    Phase 1.1 PCA/Hose

    Mechanical

    Installation of all PCA/Hose mechanical items - quality check

    - level/alignment

    - torque

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - MAJV Package team

    - Phase 1.1 PBB Mechanical done (including fixing

    frames)

    - all drawings/documents approved

    - material available

    To do one asap and to perform the rest all together when

    all PBB's are ready

    Phase 1.2 PCA/Hose

    Electrical

    Installation of all PCA/Hose electrical components - quality check

    - termination

    - labelling

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - MAJV Package team

    - Phase 1.1 PCA/Hose Mechanical done

    - all drawings/documents approved

    - material available

    Phase 2 PCA/Hose Commissioning of the PCA/Hose - continuity/insulation test- power up

    - phase rotation

    - configuration

    - functional tests

    pe r s tand b y T hy ss en - Th ys se n/ AXA- MAJV Package team

    - MAJV Commissioning team

    - Phase 1.2 PCA/Hose Electrical done- power available from Building (including

    feeding cables)

    - no major Mechanical/Electrical snags

    - all drawings/documents approved

    Phase 3.11 PBB Interfaces tests - interlock tests with PCA/GPU/VDGS

    - interface tests with MCS/SCADA/TOIP/FAS

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - Safegate

    - MAJV Package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 2.2 PBB and Phase 2 GPU/PCA/Hose done

    - network connection available

    - VDGS/MCS/SCADA/TOIP/FAS available

    - no major Phase 2 snags

    - all drawings/documents approved

    FAS interface is just a signal (dry contact)

    GPU/PCA interface with PBB with dry contacts then PBB to

    SCADA by software.

    Phase 3.12 PBB Performance test and degraded mode - power break down tests (UPS/Battery,

    Generator, Tow bar)

    - water test

    pe r s tand b y T hy ss en - Th ys se n/ AXA

    - MAJV Package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 2.2 PBB done

    - all drawings/documents approved

    Phase 4.01 Integrated test Aircraft Arrival and Departure scenario one stand by MAJV - All involved sub contractors

    - MAJV Package team

    - MAJV Commissioning team

    - Investor and Investor IE

    - Phase 3.11 and 3.12 PBB done

    - GOS/RMS/Billing available

    - availability of an aircraft

    - all drawings/documents approved

    If aircraft with engines ON, possible to validate the

    complete process including RMS/GOS/VDGS/Billing with

    flight schedule and block ON/OFF.

    If aircraft with engines OFF, to concentrate on

    PBB/GPU/PCA.

    Phase 2.2HBS CT

    Package Conveying

    BHS Phase 2.2OOG inline

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    51/64

    Phase 1BHS SW &

    Grating

    Phase 1BHS

    Mechanical

    Phase 1.1BHS

    Electrical

    Phase 2.1

    BHS PLC

    Phase 2.2

    BHS PLC

    Phase 2.3

    BHS PLC

    Phase 3.11BHS

    Interfaces

    Phase 4.01Building

    MEP

    Normal &UPS power

    Phase 1.1BHS IT

    Phase 2.1BHS IT (Scada)

    Phase 3.10BHS IT (SAC)

    BHScontrol

    room

    Phase 1

    BHS CCTV

    Phase 2.1

    BHS CCTV

    AODB (FIDS)

    DCS (BSM/BPM)

    SCADA BIDS

    Phase 1.2BHS

    Electrical

    Phase 1.2BHS IT

    MCS (NTS)

    FAS

    Consultancy Services for Test & Commissioning Plan

    Phase 3.12

    BHS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    52/64

    FAS

    Access Control

    Package Conveying

    LET

    - Speaker

    - Card readerPAS

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    53/64

    Phase 1.1

    LiftMechanical

    Phase 1.2Lift Electrical

    Phase 2.1Lift

    Phase 2.2Lift

    Phase 3.11

    Lift

    3rd partycertification

    BuildingShaft/Pit

    Phase 1

    Lift intercom

    Phase 2

    Lift intercom

    Consultancy Services for Test & Commissioning Plan

    Phase 1LET Monitoring

    Phase 3.10LET Monitoring

    Phase 1.1Escalator

    Mechanical

    Phase 1.2Escalator

    Electrical

    Phase 2.1Escalator

    Phase 2.2Escalator

    Phase 3.11Escalator

    BuildingShaft

    Phase 1.1Travelator

    Mechanical

    Phase 1.2Travelator

    Electrical

    Phase 2.1Travelator

    Phase 2.2Travelator

    Phase 3.11

    Travelator

    BuildingShaft

    FASPower

    Power

    LAN

    - Car floor

    SCADA

    MCS

    Landings(floor/wall)

    Phase 3.12Travelator

    Phase 3.12

    Escalator

    Phase 3.11LET Monitoring

    Phase 3.12Lift

    ITRoom

    Package Phase Description Content Splitting Procedure Attendees Prerequisites Remarks

    Conveying Phase 1.1Lift I ns ta ll at io n of a ll m ec ha ni ca l it em s - q ua li ty c he ck

    /

    p er li ft b y T hy ss en - Th ys se n -area handedover byBuilding(shaft/pit)

    /

    Temporary lightingrequired

  • 8/12/2019 Commissioning Plan Step 2 - RevA

    54/64

    LET Mechanical - level/alignment

    - torque

    - MAJV Package team - all drawings/documents approved

    - materialavailable

    P hase 1 .2 L if tElectr ica l I nstal lation of a l lelectr ica l items - quality check

    - termination

    - labelling

    p er li ft b y T hy ss en - Th ys se n

    - MAJV Package team

    -landings(floor/wall) handedover toinstall

    landingindicator andpushbuttons

    - Phase 1.1LiftMechanicaldone

    - all drawings/documents approved

    - materialavailable

    Notto installlanding indicators/pushbuttons if walls

    are notfinished

    Phase 2.1 Lift Power up - continuity/insulation test

    - power up

    - phase rotation

    p er li ft b y T hy ss en - Th ys se n

    - MAJV Package team

    - normal power availablefrom Building

    - Phase 1.2LiftElectrical done

    - all drawings/documents approved

    To startwith temporary power if necessary

    Phase 2.2 Lift Commissioning - configuration

    - settingup

    - functionaltest

    p er li ft b y T hy ss en - Th ys se n

    - MAJV Package team

    - MAJV Commissioningteam

    - Phase 2.1done

    -all devicesout of LET scopetobe installed

    (nomoreinstallationrequired)

    - all drawings/documents approved

    To include tests for grouped lifts when necessary

    Phase 3.11 Lift Interfaces tests - interface