New York State Energy Research and Development Authority Commercial Industrial Stakeholder Meeting 10/26/2015 October 26, 2015

Upload: others

Post on 14-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

New York State Energy Research and Development Authority

Commercial Industrial

Stakeholder Meeting10/26/2015

October 26, 2015

Page 2: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

2

New York State Energy Research and Development Authority

Agenda• Introduction

• Competitive Bid Program Update

• Commercial / Industrial MW Block Update

• Soft Cost Reduction Strategies

• Programmatic Discussion

Page 3: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

3

New York State Energy Research and Development Authority

Summary of

Competitive Bid

Program

Page 4: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

4

New York State Energy Research and Development Authority

0

20000

40000

60000

80000

100000

120000

140000

160000

Central Hudson Gasand Electric

Consolidated Edison National Grid NYS Electric and Gas Orange and RocklandUtilities

Rochester Gas andElectric

[kW

]Competitive Actual/Expected Installed Capacity*

2012 2013 2014 2015 2016

*: Actual installed capacity as of 10/20/2015; Total installed capacity for 2015 and 2016 are estimated.

Page 5: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

5

New York State Energy Research and Development Authority

PON 2956 Update

ConEdison Rest of State

Number of Projects 33 77

Total Capacity [MW] 10 158

Average Incentive [$/W-dc] 0.53 0.42

Average Installed Cost [$] 3.25 2.06

2956 Contracts as of 10/26/2015

*Strategic incentive not included

Page 6: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

6

New York State Energy Research and Development Authority

PON 2484

PON 2589-1

PON 2589-2

PON 2589-3

PON 2956

PON 2860

*Strategic incentive not included

$0.41/W-dc ROS

$0.53/W-dc ConEd

Page 7: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

7

New York State Energy Research and Development Authority

Commercial / Industrial

MW Block Activity To

Date

Page 8: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

8

New York State Energy Research and Development Authority

ROS Total capacity [MW]

38

Number of Projects 29

MonetaryVolumetric

1910

ConEdisonTotal capacity [MW]

1.8

Number of Projects 2

Page 9: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

9

New York State Energy Research and Development Authority

Current Interconnection Pipeline

0

100

200

300

400

500

600

700

Consolidated Edison Central Hudson Gas& Electric

National Grid New York StateElectric and Gas

Orange & RocklandUtilities

Rochester Gas &Electric

[MW

]Interconnection Pipeline

(As of 09/30/2015)

Connected Proposed

Page 10: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

10

New York State Energy Research and Development Authority

Integration Barrier to REV• Conducted a gap analysis to determine each utility’s current interconnection

application practices and processes

• Develop a holistic approach to address grid-integration issues as a necessary prerequisite for the long-term viability of REV

• Goal: Simplify, expedite and streamline the interconnection processes

Page 11: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

11

New York State Energy Research and Development Authority

Shared Solar• CDG season is open today!• New Remote Net Metering/Community Net Metering tariffs in effect• Utility Operating Procedures to be released on Nov. 9 • Phase I: Now-April 30

• Opportunity Zones and projects with >20% low income customers• Phase II: May 1

Page 12: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

12

New York State Energy Research and Development Authority

ROS Megawatt Block Incentive Structure

BLOCKPBI ($/W)

MONETARY CREDITING

PBI ($/W) VOLUMETRIC

CREDITING

BLOCK VOLUME (MW-DC)

1 $0.34 $0.40 120

2 $0.28 $0.40 120

3 $0.21 $0.39 130

4 $0.15 $0.39 130

5 $0.11 $0.37 140

6 $0.06 $0.35 140

7 $0.05 $0.33 150

8 $0.04 $0.28 150

9 $0.02 $0.22 160

10 $0.01 $0.16 170

11 $0.01 $0.09 180

$0.00$0.02$0.04$0.06$0.08$0.10$0.12$0.14$0.16$0.18$0.20$0.22$0.24$0.26$0.28$0.30$0.32$0.34$0.36$0.38$0.40

1 2 3 4 5 6 7 8 9 10 11

PBI ($/W) MONETARY CREDITING PBI ($/W) VOLUMETRIC CREDITING

Page 13: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

13

New York State Energy Research and Development Authority

Con Ed Megawatt Block Incentive Structure

BLOCKPBI

($/W)

BLOCK VOLUME (MW-DC)

1 $0.63 15

2 $0.61 20

3 $0.59 20

4 $0.57 25

5 $0.55 25

6 $0.51 30

7 $0.46 30

8 $0.39 35

9 $0.33 35

10 $0.26 40

11 $0.20 45

12 $0.13 50

13 $0.07 55

$0.00

$0.10

$0.20

$0.30

$0.40

$0.50

$0.60

$0.70

1 2 3 4 5 6 7 8 9 10 11 12 13

Page 14: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

14

New York State Energy Research and Development Authority

Discussion Points• Contractor experience requirements – any issues?• Assignments• Payments structure? (3 years of performance, 4 payments of 25%)• Applications for CDG projects• Your thoughts

Page 15: Commercial Industrial Stakeholder Meeting · 2015-10-26 · Stakeholder Meeting 10/26/2015 October 26, 2015. 2 New York State Energy Research and Development Authority Agenda •

15

New York State Energy Research and Development Authority

Thank you for your participation!

Suggested Agenda Items for our next Meeting?

Stakeholder docs & info:

• http://ny-sun.ny.gov/About/Stakeholder-Meetings.aspx

Input welcome: