COMMERCIAL BUILDING DESIGN FOR COVID-19 & BEYOND June 18 th , 2020 Luke Leung, PE, P ENG, LEED Fellow 1

Upload: others

Post on 19-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

FY2018 BUSINESS PLAN 01

COMMERCIAL BUILDING DESIGN FOR COVID-19 & BEYONDJune 18th, 2020

Luke Leung, PE, P ENG, LEED Fellow

1

Page 2: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

SPACES

SYSTEMS

Page 3: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

SPACES

SYSTEMS

Page 4: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ACCELERATORS TO OCCUPANCY

SKIDMORE, OWINGS & MERRILL LLP

OUTDOOR VS. INDOOR

Indoor transmission of SARS-CoV-2 Hua QIAN, Te MIAO2, Li LIU , Xiaohong ZHENG , Danting LUO , and Yuguo Li,

2 7322

Page 5: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

5

SOLAR IMPACTSARS-COV2 :

TOP: AIR90% reduction from 200 minutes to 4.5 minutes

BOTTOM: STAINLESS STEEL90% reduction in 7 minutes

Page 6: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

6https://projects.iq.harvard.edu/files/covid-pm/files/pm_and_covid_mortality.pdf

AIR QUALITY

“…increase of only 1 g/m3 in PM2.5 is associated with a 15% increase in the COVID-19 death rate..”

Harvard T.H. Chan School of Public Heath

Page 7: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

Indirect Health Effects of Relative Humidity Indoor EnvironmentArundel AV, Sterling EM et al.

Relative Humidity:• 40-60%

Page 8: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

Indirect Health Effects of Relative Humidity Indoor EnvironmentArundel AV, Sterling EM et al.

Relative Humidity:• 40-60%

viruses

Viruses

Page 9: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

Page 10: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

RESUSPEND - FLOOR

Detection of air and surface contamination by SARS-CoV-2 in hospital rooms of infected patientsPo Ying Chia, Kristen Kelli Coleman, for the Singapore 2019 Novel Coronavirus Outbreak Research Team

Page 11: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

https://www.pinterest.com/pin/368732288234236219/

CARPET VS. HARD FLOOR

Almost 20 Times More Material

Page 12: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

SPACES

SYSTEMS

Page 13: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

#

Epidemic plan from base building

BASE BUILDING CONSIDERATIONS

“Employees should wear a cloth face covering to cover their nose and mouth in all areas of the business.”COVID-19 Employer Information for Office Buildings

Presenter
Presentation Notes
Add Base Building Slide vs. Lobby Slide: Graphic Clarity; Hierarchy
Page 14: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

LOBBY

1. Pressurized2. Sanitized3. Time - touchless

Page 15: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,
Page 16: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

RESUSPEND - TOILET

Detection of air and surface contamination by SARS-CoV-2 in hospital rooms of infected patientsPo Ying Chia, Kristen Kelli Coleman, for the Singapore 2019 Novel Coronavirus Outbreak Research Team

Page 17: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

Occupancy Indicator

Occupancy Indicator

TOILET

1. Continuous exhaust2. Door hold open3. Consider occupants indicator

Presenter
Presentation Notes
Olin
Page 18: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

18

WILL OUTBREAKS IMPACTOTHER FLOORS?

• Korean Call Center:o 97 of the 811 employees tested positiveo 94 sat on the same floor

https://wwwnc.cdc.gov/eid/article/26/8/20-1274_article

Page 19: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ATRIUM

Presenter
Presentation Notes
Interior atriums facilitate passive ventilation when warm air rises and exhausts at the top of the atriums, pulling in cooler air at the lower atrium levels.
Page 20: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

ENVIRONMENT

SPACES

SYSTEMS

Page 21: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,
Page 22: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,
Page 23: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

DOAS – RADIANT

Page 24: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

DOAS – CHILLED BEAM

Page 25: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

25

DOAS - NIST

https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/

Integrated Exposure: 1.5E4 (#s/M3)

Exposure Concentration: 2.3E0 (#s/M3)

Page 26: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

DOAS – FAN COIL OR VRF

Page 27: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,
Page 28: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

VAV

Page 29: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

2980

%

Fan

Fan

20%

20%

VAV SYSTEMMINIMUM OUTSIDE AIR

Time

VirusCount

Enhanced Filter

Page 30: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

MERV 8

MERV 13

BETTER FILTERMERV 8 - MERV 13

Page 31: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

MERV 8

MERV 13

BETTER FILTERMERV 8 - MERV 13

Page 32: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

32

MERV 8 VS MERV 13

https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/

Integrated Exposure: 8.0E3 (#s/M3)

Exposure Concentration: 1.6E0 (#s/M3)

Integrated Exposure: 4.8E3 (#s/M3)

Exposure Concentration: 1.1E0 (#s/M3)VAV with MERV 13

(Minimum OA)

VAV with MERV 8(Minimum OA)

Page 33: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

33

VAV SYSTEM100% OUTSIDE AIR

Fan

Fan

Filter and Coil

Shutoff Return

100%

100%

Page 34: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

34

MERV 8 VS 100% OUTSIDE AIR

https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/

Integrated Exposure: 8.0E3 (#s/M3)

Exposure Concentration: 1.6E0 (#s/M3)

Integrated Exposure: 4.5E3 (#s/M3)

Exposure Concentration: 1.0E0 (#s/M3)VAV with

100% Outside Air

VAV with MERV 8Minimum OA

Page 35: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

35https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/

Integrated Exposure: 8.0E3 (#s/M3)

Exposure Concentration: 1.6E0 (#s/M3)

Integrated Exposure: 4.5E3 (#s/M3)

Exposure Concentration: 1.0E0 (#s/M3)VAV with

100% Outside Air

VAV with MERV 8(Minimum OA)

Integrated Exposure: 4.8E3 (#s/M3)

Exposure Concentration: 1.1E0 (#s/M3)VAV with MERV 13

(Minimum OA)

VAV MINI VS 100% OA

Page 36: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

36

DOAS VS VAV

https://pages.nist.gov/CONTAM-apps/webapps/FaTIMA/

Integrated Exposure: 1.0E4 (#s/M3)

Exposure Concentration: 2.3E0 (#s/M3)

Integrated Exposure: 8.0E3 (#s/M3)

Exposure Concentration: 1.6E0 (#s/M3)

Integrated Exposure: 4.8E3 (#s/M3)

Exposure Concentration: 1.1E0 (#s/M3)

DOAS

VAV with MERV 13(Same OA as DOAS)

VAV with MERV 8(Same OA as DOAS)

Page 37: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

#

UVC LIGHTS

Page 38: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

EMERGING TECHNOLOGIES

• Emerging light spectrum technologies:o 315-400 nm UVa fixtureso 220 nm Far UVc lampso 405 nm visible spectrum lamps

• Pulsed Xenon (Pulsed UV)

• Bipolar Ionization/Corona Discharge

• Photocatalytic Oxidation (PCO)

http://2bize.com/uv%20spectrum.html

Page 39: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

HEALTH THREATS (UN WHO)3. Pandemic

Page 40: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

HEALTH THREATS (UN WHO)2. Chronic Diseases

Page 41: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

HEALTH THREATS (UN WHO)1. Climate Change

Page 42: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

FY2018 BUSINESS PLAN 01

COMMERCIAL BUILDING DESIGN FOR COVID-19 & BEYONDJune 18th, 2020

Luke Leung, PE, P ENG, LEED Fellow

42

Page 43: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

#

ELEVATORS

1. Prolong exposure – 15 minutes

http://www.elitecabs.com/index.php/cab-designs/elite-cab-design1205/freight-and-s?fID=65

Presenter
Presentation Notes
Luke
Page 44: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

#

ELEVATORS

1. Prolong exposure – 15 minutes

2. Turn on elevator lift ventilation fan- 6’x6’x8’- 95% Elimination of material in the air: - 200 CFM ( 340 M3/Hr) = 4.3 minutes

http://www.elitecabs.com/index.php/cab-designs/elite-cab-design1205/freight-and-s?fID=65

Exhaust Fan

Presenter
Presentation Notes
Luke
Page 45: COMMERCIAL BUILDING DESIGN FOR COVID -19 & BEYOND library/technical...fy2018 business plan 01 commercial building design for covid -19 & beyond june 18th, 2020. luke leung, pe, p eng,

#

ELEVATORS

1. Prolong exposure – 15 minutes

2. Turn on elevator lift ventilation fan- 6’x6’x8’- 95% Elimination of material in the air: - 200 CFM ( 340 M3/Hr) = 4.3 minutes

3. Consider portable cleaner with HEPA filter

4. Open every doorhttp://www.elitecabs.com/index.php/cab-designs/elite-cab-design1205/freight-and-s?fID=65