August 3, 2020 Mr. Thomas Conboy Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362–9637 SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT – INTEGRATED INSPECTION REPORT 05000263/2020002 Dear Mr. Conboy: On June 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On July 7, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report. No findings or violations of more than minor significance were identified during this inspection. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, “Public Inspections, Exemptions, Requests for Withholding.” Sincerely, /RA/ Hironori Peterson, Chief Branch 3 Division of Reactor Projects Docket No. 05000263 License No. DPR-22 Enclosure: As stated cc w/ encl: Distribution via LISTSERV®

Upload: others

Post on 21-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

August 3, 2020 Mr. Thomas Conboy Site Vice President Monticello Nuclear Generating Plant Northern States Power Company, Minnesota 2807 West County Road 75 Monticello, MN 55362–9637 SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT – INTEGRATED INSPECTION

REPORT 05000263/2020002 Dear Mr. Conboy: On June 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On July 7, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report. No findings or violations of more than minor significance were identified during this inspection. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, “Public Inspections, Exemptions, Requests for Withholding.”

Sincerely, /RA/ Hironori Peterson, Chief Branch 3 Division of Reactor Projects

Docket No. 05000263 License No. DPR-22 Enclosure: As stated cc w/ encl: Distribution via LISTSERV®

Page 2: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

Letter to Thomas Conboy from Hironori Peterson dated August 3, 2020. SUBJECT: MONTICELLO NUCLEAR GENERATING PLANT – INTEGRATED INSPECTION

REPORT 05000263/2020002 DISTRIBUTION: Jessie Quichocho Elise Burket RidsNrrDorlLpl3 RidsNrrPMMonticello RidsNrrDroIrib Resource John Giessner Kenneth O’Brien Jamnes Cameron Allan Barker DRPIII DRSIII [email protected]

ADAMS ACCESSION NUMBER: ML20216A756

☒ SUNSI Review

☒ Non-Sensitive

Sensitive

☒ Publicly Available

Non-Publicly Available

OFFICE RIII RIII

NAME NShah:bw via email HPeterson via email

DATE 8/3/2020 8/3/2020

OFFICIAL RECORD COPY

Page 3: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION Inspection Report

Docket Number: 05000263 License Number: DPR-22 Report Number: 05000263/2020002 Enterprise Identifier: I-2020-002-0032 Licensee: Northern States Power Company, Minnesota Facility: Monticello Nuclear Generating Plant Location: Monticello, MN Inspection Dates: April 01, 2020 to June 30, 2020 Inspectors: R. Elliott, Acting Senior Resident Inspector N. Feliz-Adorno, Branch Chief T. Go, Health Physicist G. Hansen, Sr. Emergency Preparedness Inspector M. Holmberg, Senior Reactor Inspector D. Krause, Resident Inspector J. Robbins, Acting Sr. Resident Inspector N. Shah, Project Engineer A. Shaikh, Senior Reactor Inspector D. Szwarc, Senior Reactor Inspector J. Weigandt, Resident Inspector Approved By: Hironori Peterson, Chief

Branch 3 Division of Reactor Projects

Page 4: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

2

SUMMARY The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensee’s performance by conducting an integrated inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC’s program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000263/2020002-01 Partial Sample of FZ-08,

Cable Spreading Room Past Operability due to Installation of Heat Detectors with Incorrect Setpoint

71152 Open

Page 5: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

3

PLANT STATUS Monticello began the inspection period operating at approximately 100 percent power and, with the following exceptions, remained at that level throughout the inspection period. The plant reduced power to 75 percent, on June 17, 2020, for quarterly turbine valve testing and control rod drive scram insertion time testing, returning to 100 percent power prior to midnight. Monticello performed multiple flexible power operations over the quarter, for electric grid efficiencies in the early mornings, reducing power to approximately 80 percent then returning to 100 percent power. INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, “Light-Water Reactor Inspection Program - Operations Phase.” The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards. Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities; and completed on site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP. REACTOR SAFETY 71111.01 - Adverse Weather Protection Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness for seasonal extreme weather conditions. (1) Ice storm preparations

External Flooding Sample (IP Section 03.03) (1 Sample)

The inspectors evaluated site readiness to cope with external flooding due to forecast high river levels from spring ice melt and rain (1) Intake basin and discharge canal and circulating water (CW) water house, including

emergency service water, and diesel fire pump areas

Page 6: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

4

71111.04 - Equipment Alignment Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains: (1) 12 diesel generator emergency service water system - protected, on April 15, 2020 (2) Anticipated transient without scram inverter Division 1 - protected, on April 21, 2020 (3) Hardened pipe vent on May 4, 2020 (4) Circulating water bay traveling screens post diving activities on May 12, 2020

71111.05 - Fire Protection Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas: (1) Fire Zone (FZ) 09, control room, on April 10, 2020 (2) FZ-02-B, east HCU on June 30, 2020 (3) FZ-16, turbine building corridor east & west 911' & 931' on June 30, 2020 (4) FZ-17, turbine building north cable corridor on June 30, 2020 (5) FZ-19-C, feedwater pipe chase on June 30, 2020

71111.07A - Heat Sink Performance Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of: (1) 1136-01 [Residual Heat Removal] RHR Division 1 heat exchanger efficiency on

April 1, 2020

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

The inspectors observed and evaluated licensed operator performance in the control room during quarterly review of licensed operator requalification performance. (1) Downpower to 75 percent for quarterly turbine valve testing, reactivity maneuvering,

and control rod drive scram insertion time testing Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated Resident Inspector Quarterly Review of Licensed Operator Requalification:

Page 7: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

5

(1) Licensed operator requalification cycle MT-LOR-20C-001V simulator evolution on June 8, 2020

71111.12 - Maintenance Effectiveness Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function: (1) 4KV breaker performance/maintenance on June 12, 2020 (2) Residual heat removal on June 12, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed; (1) 15B feedwater heater transient on May 28, 2020 (2) Loss of 11 cooling tower fans on June 2, 2020 (3) 'C' main steam drain tank controller on June 3, 2020 (4) Division 1 RHR pump vibrations in alert range on June 9, 2020

71111.15 - Operability Determinations and Functionality Assessments Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments: (1) DPIS-2-129C, recirculation loop DP LPCI [low pressure coolant injection] loop select

interlock operability questioned on May 15, 2020 (2) CRD system anchor bolts loose or missing on May 29, 2020 (3) Weak link error, valve thrust assessment 10" anchor darling gate valves on

June 12, 2020 (4) 'A' RHR room cable trays not fastened per MPS-2096 on June 19, 2020

71111.18 - Plant Modifications Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample 1 Partial)

The inspectors evaluated the following temporary or permanent modifications: (1) Moisture separator high level trip SPV on June 12, 2020 (2) (Partial)

Remove RFP Start Interlock POS-2375 and POS-2376

Page 8: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

6

71111.19 - Post-Maintenance Testing Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality: (1) OPS-B2210, Perform V-EF-22 Reactor Building Main Exhaust Fan 480 VAC Supply

PMT on April 2, 2020 (2) OPS-DG-1/SSP1, 11 EDG Speed Sensing PMT on April 17, 2020 (3) OPS-B3105, C-93-11 EDG Control Panel PMT on April 17, 2020 (4) DG1-Gov-11, 11 EDG Control Panel PMT on April 17, 2020 (5) G-3A, 11 EDG PMT on April 17, 2020 (6) RV-1523, P-160A Discharge Relief Valve PMT on April 17, 2020 (7) Electric ATWS Inverter-B PMT on April 23, 2020 (8) P-202C - 13 RHR Pump PMT/RTS on June 9, 2020

71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests: Surveillance Tests (other) (IP Section 03.01) (4 Samples)

(1) 0032 [Emergency Core Cooling System] ECCS Pump Start Permissive Sensor Test

on April 2, 2020 (2) IC-PPS 0006 Scram Discharge Volume Hi Level Scram Tests on April 7, 2020 (3) 1052-05 Diesel Fuel Transfer Pump Quarterly Pump and Valve Test on April 14, 2020 (4) P-160A Diesel Fuel Transfer Pump Quarterly Pump and Valve Test on April 16, 2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) MO2061 and MO2062 Torus to [High Pressure Coolant Injection] HPCI Suction

Isolation Valves on March 23, 2020 RCS Leakage Detection Testing (IP Section 03.01) (1 Sample)

(1) B.04.01-05 H.4, Rise in Unidentified Leakage on June 19, 2020

FLEX Testing (IP Section 03.02) (1 Sample)

(1) OSP-FIR-0611, G-507 Flex Portable Diesel Generator Test on April 23, 2020

71114.02 - Alert and Notification System Testing Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and

notification system: • Annual siren inspection and maintenance records for the period from

May 2018 to May 2020

Page 9: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

7

• Monthly alert notification system (siren) tests for the period from May 2018 to May 2020

71114.03 - Emergency Response Organization Staffing and Augmentation System Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness

Organization

71114.05 - Maintenance of Emergency Preparedness Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the Emergency Preparedness Program

71114.06 - Drill Evaluation Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated: (1) Emergency Plan Table-top Drill coordinating Emergency Operations Facility,

Technical Support Center, and off-site organization on June 30, 2020

RADIATION SAFETY 71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation Waste Characterization and Classification (IP Section 03.03) (2 Samples)

(1) The inspectors evaluated the licensee’s characterization and classification of

radioactive waste shipment No. 20-32; Exclusive Use Shipment; UN-3321, LSA-II to UniTech Services, Oak Ridge, Tennessee.

(2) The inspectors evaluated the licensee’s characterization and classification of radioactive waste shipment No. 19-76; Exclusive Use Shipment; UN-3321; LSA-II to Energy Solution Clive Facility, Clive, Utah.

Shipping Records (IP Section 03.05) (5 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review: (1) Shipment No. 20-32; Exclusive Use Shipment; LSA-II, UN-3321, Dry Active Waste

(DAW) Plant Trash to UniTech Services, Waste Processor, Oak Ridge, Tennessee (2) Shipment No. 19-77; Exclusive Use Shipment; LSA-II, UN-3321, Condensate Resin

Liner to Energy Solution Clive Facility, Clive, Utah for Disposal (3) Shipment No. 19-75; Exclusive Use Shipment, LSA-II, UN-3321, Condensate Resin

Liner to Energy Solution Clive Facility, Clive, Utah for Disposal

Page 10: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

8

(4) Shipment No. 19-55; Exclusive Use Shipment; SCO-II, UN-2913, Westinghouse Equipment to Westinghouse Facility, Madison, Pennsylvania

(5) Shipment No. 19-74; Exclusive Use Shipment; LSA-II, UN-3321, Condensate Resin Liner to Energy Solution Clive Facility, Clive, Utah for Disposal

OTHER ACTIVITIES – BASELINE 71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below: EP01: Drill/Exercise Performance (IP Section 02.12) (1 Sample)

(1) Unit 1 (07/01/2019 - 03/31/2020)

EP02: ERO Drill Participation (IP Section 02.13) (1 Sample)

(1) Unit 1 (07/01/2019 - 03/31/2020)

EP03: Alert & Notification System Reliability (IP Section 02.14) (1 Sample)

(1) Unit 1 (07/01/2019 - 03/31/2020)

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

Safety System Functional Failures (SSFFs) (1) Unit 1 (April 2019 - March 2020)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) Unit 1 (01/01/2019 -12/31/2019)

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

RCS Leak Rate Sample (1) Unit 1 (April 2019 - March 2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Unit 1 (01/01/2019 - 12/31/2019)

71152 - Problem Identification and Resolution Annual Follow-up of Selected Issues (IP Section 02.03) (1 Partial)

The inspectors reviewed the licensee’s implementation of its corrective action program related to the following issues:

Page 11: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

9

(1) (Partial) FZ-08, Cable Spreading Room past Operability due to installation of heat detectors with incorrect setpoint

INSPECTION RESULTS

Unresolved Item (Open)

Partial Sample of FZ-08, Cable Spreading Room past operability due to installation of heat detectors with incorrect setpoint. URI 05000263/2020002-01

71152

Description: On March 5, 2020, the licensee identified that the set points for the cable spreading room fire detectors were incorrect. These detectors had been installed in 2018. The correct set point was 140 Fahrenheit (F), however, the licensee identified that the replaced detectors actually had a set point of 275 F. This would have resulted in a delayed response to a fire occurring in the room, potentially resulting in conditions outside the design basis analysis. The licensee’s preliminary investigation identified that the incorrect set point likely resulted from the wrong detectors being ordered from the supplier; however, this was still being confirmed through the investigation. Additionally, the licensee was still evaluating the actual impact to the design basis analysis. The inspectors were monitoring the licensee’s investigation including the actual risk impact. The licensee replaced the detectors with ones having the correct set point upon discovery and therefore the inspectors had no immediate safety concerns. This is considered a partial sample which is being continued in the third quarter. Planned Closure Actions: This finding was determined to require further risk evaluation and this evaluation continues into the third quarter. Licensee Actions: Cable Spreading Room (CSR) thermal detectors have been replaced with the correct setpoint detectors and an extent of conditions evaluation of other heat detectors has been performed. Corrective Action References: 501000038446, Replaced CSR Thermal Detector Issue

EXIT MEETINGS AND DEBRIEFS The inspectors verified no proprietary information was retained or documented in this report.

• On July 7, 2020, the inspectors presented the integrated inspection results to Mr. T. Conboy, Site Vice President and other members of the licensee staff.

• On May 21, 2020, the inspectors presented the Emergency Preparedness Inspection results to Mr. T. Conboy, Site Vice President and other members of the licensee staff.

• On June 12, 2020, the inspectors presented the Radiation Protection Baseline Inspection results to Ms. M. Kelly, Director Site Performance and Operation Support and other members of the licensee staff.

Page 12: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

10

DOCUMENTS REVIEWED Inspection Procedure

Type Designation Description or Title Revision or Date

71111.01 Procedures 1444 Pre and Post Severe Weather Inspection Checklist 20 A.6 Acts of Nature 2

71111.04 Drawings NF-36298 Electrical Load Flow One-Line Diagram 117 NX-16162-1-4 ATWS Elementary Diagram 77

Procedures B.08.01.02-05 Operations Manual EDG Emergency Service Water 23 C.5-3505 Venting Primary Containment 15 NH-116629 Hard Pipe Vent System P&ID 80 NH-36664 Service Water System & Make-Up Intake Structure P&ID 96 NH-36665 Service Water System and Make-Up Intake Structure P&ID 104

Work Orders 7000040127 Electric ATWS Inverter B 04/21/2020 71111.05 Fire Plans Fire Zone Strategy A.3-17, Cable Run Area 7

Fire Zone 16 Strategy A.3-16, Turbine Building Corridor East & West Elevations 911 & 931

18

Fire Zone 19-C Strategy A.3-19-C, Feedwater Pipe Chase 8 Fire Zone 2B Strategy A.3.02-B, East HCU Area 15 FZ- Strategy A.3-09

Control Room 10

71111.07A Procedures 1136 RHR Heat Exchanger Efficiency Test 37 Work Orders 7000040033 RHR Heat Exchanger Efficiency Test 03/28/2020

71111.11Q Corrective Action Documents

501000027283 HCU Position Indication Blank 0 501000041586 Delay Obtaining Scram Data for 1st Card 0

Miscellaneous 0081 Control Rod Drive Scram Insertion Time Test 81 2300 Reactivity Maneuvering Steps 06/17/2020

Procedures RQ-SS-181 MT Simulator Exercise, Cycle MT-LOR-20C-001V 0 71111.12 Corrective Action

Documents 500001195628 4kV BKR PM Interval may Exceed 125% of 4 0 500001309389 11 RFP Could not be Restarted 0 500001535749 CV-1995 Failed to Open when Required 0 500001547508 CV-1995 did not Open on a Shutdown of 12 0 500001556822 MO-2012 Margin Improvement 0 500001558431 MO-2012 Failed to Open during OSP-ECC-05 0 500001559586 MO-2030 Stall Event not Accounted For 0

Page 13: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

11

Inspection Procedure

Type Designation Description or Title Revision or Date

501000000863 4KVB-36 Main Secondary Contact Issue 0 501000001252 On 4KVB-36 - Closed Latch Spacer Missing 0 501000001705 Component Tagged for >70 Days 0 501000003335 Nonconserv Accept Criteria for RHR Hx Test 0 501000003461 MO-2012 Stroke Against High Differential 0 501000006230 4KVB-23 As-Found Reduced Volt Trip UNSAT 0 501000007176 Higher Ohms - Aux 4-4T Contact - 4KVB-24 0 501000007403 Question during Ops Deepdive 0 501000007485 4KVB-25 - Striker Plate Weld Cracked 0 501000007504 4KVB-24 Possible Interlock Roller Measure not SAT 0 501000007755 4KVB-25 Power Switch Resistance is High 0 501000008018 4KVB-25 Wire Strands Found Broken 0 501000008040 4KVB-24 Wire Strands Broken 0 501000008318 4KVB-31 - Half Voltage TRIO Test UNSAT 0 501000008340 4KVB-31 Driving Pawl Support Weld Crack 0 501000008732 4KVB-20 - MG Sec Disc Support Broken 0 501000008762 4KVB-20 Eccentric Roller Bearing UNSAT 0 501000009265 4KVB-20 Main Mechanism Cam Hub Cracked 0 501000009901 12 RHR Pump Motor Heater >550 Degrees Fahrenheit 0 501000011907 MO-2007 Failed to Close 0 501000013020 4KVB-19 As-Found Half Volt Testing UNSAT 0 501000013128 4KVB-19 Cracked Throat Baffle Found 0 501000013655 4KVB-30 'C' Arc Chute Buffer Bulk Cracked 0 501000013759 4KVB-30 As-Found 'A' Resistance High 0 501000013941 4KVB-32 Half Volt. Trip Test - UNSAT 0 501000014057 4KVB-32 Cam Set Screw Stripped 0 501000014186 4KVB-32 Charging MTR Mount Hole Stripped 0 501000014422 4KVB-32 Phase B Percent PF Test UNSAT 0 501000014461 4KVB-32 Closing Spring Mount Damaged 0 501000015314 4KVB-38 6 Lower Bushing Tested UNSAT 0 501000015383 4KVB-38 Lower Mechanism Found Misaligned 0 501000015743 4KVB-34 - All Primary Contacts Pitted 0 501000015847 4KVB-34 - Sec Pin MF-4 Support Cracked 0

Page 14: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

12

Inspection Procedure

Type Designation Description or Title Revision or Date

501000018660 11 EDG Failed to Load 0 501000019162 4KVB-52 B-Ph Top Bushing Doble UNSAT 0 501000019413 4KVB-52 Charging Motor Bolt Found Stripped 0 501000019657 4KVB-52 MG Secondary Disc Block 0 501000019681 4KBV-52 Broken Secondary Contacts 0 501000020431 4KVB-40 Half Volt Close Test - UNSAT 0 501000022322 MO-2012 Closed Bases 0 501000022899 4KVB-46 Eccentric Bearing Found Bad 0 501000022930 4KVB-46 Interlock Switch 152/IS UNSAT 0 501000025884 MO-2007 Trace Anomaly and Overthrust 0 501000025970 4KVB-02 Acrid Odor from Charging Motor 0 501000026915 4KVB-28 Roll Up of Minor 4858-PM 0 501000027372 4858-PM 4KVB-17 0 501000028145 POD Question with MO-2012 Closed 0 501000028281 PM Work Order was Incorrectly Cancelled 0 501000028904 Breaker not Charging When Expected 0 501000029125 MO-2012 Packing Leak 0 501000029629 4KVB-29 Bushing 1 Failed Dielectric Test 0 501000029958 4KVB-29 Limit Switch Failure 0 501000029965 4KVB-01 Limit Switch Failure 0 501000030066 Containment Spray Valves Thrust Exceeds Calculation 0 501000030175 4KVB-01 4858 AUX Contact Failed As-Found 0 501000030213 4KVB-01 Inner Latching Pawl Worn 0 501000030390 4KVB-26 4858 Major Roll Up 0 501000030831 4KVB-47 4858 Roll Up 0 501000031409 Rectifier Bad Cool Water 4KV Test Station 0 501000035294 Breaker 4KVB-27 Secondary Contact Broken 0 501000036403 Latch Check Switch Presence in 4KV Breakers 0 501000037673 MOV JOG Program COF Basis Lacking 0 501000037819 MO-2009 As-Found Test Anomaly 0 501000037836 MO-2009 Disconnected Motor Lead 0 501000037853 MO-2009 Preconditioning 0 501000037854 Degraded Parts Found on MO-2009 0

Page 15: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

13

Inspection Procedure

Type Designation Description or Title Revision or Date

501000037919 MOV Fatigue Life Cycling 0 Miscellaneous Plant Health

Report System Report - 4160-VAC Safety Related Sw. Gear 0

Plant Health Report

System Report - Residual Heat Removal 0

71111.13 Corrective Action Documents

105000041208 Loss of 11 Cooling Tower Fans 0 501000041038 15B Feedwater Heater / C Moisture Separator Drain Tank

Transient 0

501000041194 LT-1004 Error Message 0 501000041202 LT Fault Indication Improvement 0 501000041205 Wiring Connection Issue with LT-1004 0 501000041364 11 RHR Pump in the Alert Range 0 501000041366 13 RHR Pump Vibration in the Alert Range 0 501000041456 Plant Health Committee Risk Assessment Learning

Opportunity 0

Miscellaneous

11 Cooling Tower Fans ODMI Type 1 06/02/2020 ECR 601000002422

Add Out of Band Alarm to MSDT Level Control 0

Maintenance Rule Evaluation

LC-105 Transformer X50 06/08/2020

Work Orders 7000074991 X50 Transformer Test Cables N1N7-C-G 06/02/2020 700040746 13 RHR Motor Cooler Cleaning and Test 06/09/2020 700067587 RHR Pump and Motor Inspection 03/04/2020 700074888 Install Recorder on LC-1059 and IC-1058 05/28/2020 700074985 Replace LT-1004 Remote Head 06/02/2020

71111.15 Corrective Action Documents

501000037674 Substance Observed from DPIS-2-129C 0 501000038479, 'A' RHR Room Deep Dive - Tray Covers 0 501000039632 Weak Link Error 04/13/2020 501000040581 Unidentified Substance in DPIS-2-129C 0 501000041084 Anchor Bolt Issues - CRD System 0

Operability Evaluations

Prompt Operability Determination

DPIS-2-129C 0

Page 16: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

14

Inspection Procedure

Type Designation Description or Title Revision or Date

501000040581 Procedures 94-142 Valve Thrust Assessment 10" Anchor Darling Gate Valves:

MO-2020, MO-2021, MO-2022, and MO-2023 4

71111.18 Drawings NH- 36241 P&ID Nuclear Boiler System -Steam Supply 91 NH-36037 P&ID Condensate & Feedwater 93

Engineering Changes

ECR 601000000402

Remove RFP Start Interlock POS-2375 and POS-2376 0

Miscellaneous GEK 17954 Remote and Automatic Tripping October 1968

GEK-25425 Installation and Maintenance of Steam Separators GEK25504E Water Induction in Large Steam Turbines E GEK72223A Water Detection Thermocouples A GEK72285a Water Induction Operation and Testing March 2004 Letter General Electric Company from Bechtel Corporation -

Monticello Nuclear Generating Plant Unit 1, Northern States Power, Job No. 5828, Feedwater Piping Design Pressure

10/31/1967

MPS-1100 Specification for the Analysis of Piping and Piping Support Systems

11

SCR-18-0084 Removal of Feedwater Block Valve Pump Start Interlocks, 0 SI 5.01 Moisture Separator Drain System May 1996

Work Orders 601000000402 Remove RFP Start Interlock POS-2375 and POS-2376 0 71111.19 Work Orders 700008581 11 Emergency Diesel Generator (EDG) Return-to-Service

PMT 04/16/2020

700039966 Replace ESSB Speed Switch DG1/SSP1 PMT 04/16/2020 700040059 11 EDG Engine Control Panel 480V AC Supply PMT 04/16/2020 700040127 Electric ATWS Inverter B 04/21/2020 700040163 V-EF-22 - Reactor Building Main Exhaust Fan 480V AC

Supply PMT 04/02/2020

700040746 P-202C - 13 RHR Pump PMT/RTS 06/09/2020 700059828 11 EDG Governor PMT 04/16/2020 700065688 P-160A Discharge Relief Valve PMT 04/15/2020

71111.22 Corrective Action Documents

501000039095 Less-than-Adequate Extent-of-Condition Analysis on Quality Issue Management 50100039095 In-Service Test Position

0

Page 17: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

15

Inspection Procedure

Type Designation Description or Title Revision or Date

Indication Tests 501000039984 Cart Caddy in Flex Building not Working 0 501000041646 Slight Rise Drywell Unidentified Leakage 0

Miscellaneous

Drywell Gamma Atmosphere Analysis 06/19/2020 Drywell Floor Drain Sump Gross Beta Analysis 06/19/2020

Letter from Norther States Power Company to NRR

Supplemental Information Concerning Addendum No. 1 to License Amendment Request dated October 10, 1980

09/23/1982

Procedures B.04.01-05 H.4 Primary Containment Operation Manual - Rise in Unidentified Drywell Leakage

43

Work Orders 700039966 1052-05 Diesel Generator Speed Sensing Test 04/16/2020 700065937 G-507 Flex 480V Portable Diesel Generator Testing 04/23/2020 700066488 Scram Discharge Volume High Level Scram Test and

Calibration Procedure 04/07/2020

700067245 EDG Diesel Oil Pump Quarterly/Comprehensive Test 04/16/2020 700067408 ECCS Pump Start Permissive Sensor Test 04/02/2020 700071906 HPCI Torus Suction Inboard Isolation/HPCI Torus Suction

Outboard Isolation IST Position Indication Test 03/25/2020

71114.02 Corrective Action Documents

501000014921

MT EP Self-Assessment ANS Roll-up 07/27/2018

501000017988 Siren S-36 Indicated AC PWR Failure 10/03/2018 501000019659 Unexpected Siren Test Results 11/07/2018 501000023770 Notified by Vendor Siren S-47 is OOS 03/02/2019 501000026619 ANS Siren S-47 Failure 05/01/2019 501000027460 ANS Siren S-47 (047) Possible Failure 05/15/2019 501000028193 ANS Siren S-2, S-9, W-2, W-54 Possible Failure 06/05/2019 501000035361 ANS Siren S-9 and W 58 Failure 12/04/2019

Miscellaneous

Public Alert Notification Systems (PANS) Monthly Activation Test Records

05/01/2018 - 04/30/2020

Public Alert Notification Systems (PANS) Weekly Cancel Signal Test Records

05/01/2018 - 04/30/2020

Procedures ANS Alert and Notification System Design Report 4

Page 18: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

16

Inspection Procedure

Type Designation Description or Title Revision or Date

MNGP 1359 Public Alert Notification Systems (PANS) Weekly Cancel Signal Test and Monthly Activation Test

22

MNGP 1408 Annual PANS Performance Review 10 Work Orders 700035884-0010 Semi-Annual Auto-Dialing Telephone Notification System

Testing and Maintenance Verification 08/31/2018

700036414-0010 2018 Annual PANS Performance Review 01/24/2019 700040631-0010 Semi-Annual Auto-Dialing Telephone Notification System

Testing and Maintenance Verification 03/19/2019

700047004-0010 Semi-Annual Auto-Dialing Telephone Notification System Testing and Maintenance Verification

09/10/2019

WO 700047232-0010

2019 Annual PANS Performance Review 01/15/2020

WO 700056750-0010

Semi-Annual Auto-Dialing Telephone Notification System Testing and Maintenance Verification

03/03/2020

71114.03 Corrective Action Documents

501000016257 EP Drill-All Call Response at EOF 08/29/2018 501000016257 EP Drill-All Call response at EOF 08/29/2018 501000030363 ERO-RP Positions for Drill 08/05/2019 501000031680 EP Exercise - NUE Pager Activation Issue 09/10/2019 501000035399 EP DRILL-Untimely ERO Activation 12/06/2019 501000039152 ERO Pagers not Activated by Callout System

03/26/2020

501000039383 ERO Staffing Level of REC Position 04/03/2020 Miscellaneous

ERO Staff Training and Qualification Records (Sample) 05/20/2020 ERO Augmentation Drill Records 05/01/2018 –

04/30/2020 Monticello Nuclear Generating Plant On-Shift Staffing Analysis

5A

Procedures A.2-001 Emergency Organization 57 A.2-106 Activation and Operation of the TSC 43 A.2-107 Activation and Operation of the OSC 41 A.2-111 Activation and Operation of the Alternative Facilities During

a Security Threat 6

A.2-802 Activation and Operation of the EOF 26

Page 19: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

17

Inspection Procedure

Type Designation Description or Title Revision or Date

FL-BEP Fleet Emergency Plan Training Program Description 3 MNGP 1317 Emergency Alert Notification System Test 28 MT-BEP Monticello Emergency Plan Training Program Description 29

71114.05 Corrective Action Documents

501000016319 EP Drill - TSC Roll-Up CAP 08/30/2018 501000016943 EOF Dose Projection PC (EITER) 09/14/2018 501000021985 Condition Evaluation - Staffing of Shift Emergency

Communicator 03/31/2019

501000023637 Dose Projection Software Issue 02/27/2019 501000029895 EP Seal Broken in OSC 07/22/2019 501000030423 EP Drill OSC Computers 08/06/2019 501000030433 EP Drill - Exposure Authorization 08/06/2019 501000031659 EP Drill EOF Dosimetry 09/10/2019 501000031692 EP DRILL: Offsite Communication Procedures

09/10/2019

501000031710

EP Drill - Rad Protection Surveys

09/10/2019

501000033445

TSC PC Unable to Access SPDS

10/16/2019

501000035142

NOS: Monticello Fire Department Training

11/26/2019

Corrective Action Documents Resulting from Inspection

501000040846 EP Inspection NRC Comments/Observations 05/21/2020

Miscellaneous

2019 Monticello Emergency Planning Guide and Calendar 01/01/2019 2020 Emergency Planning Guide Brochure

01/01/2020

EP Critique Report –19A Table-Top Series Report 04/04/2019 EP Critique Report – June 25, 2019 OSC Tabletop Drill 07/25/2019 EP Critique Report – 29 August 2018 Full Scale Drill 09/10/2018 EP Critique Report – August 6, 2019 EP Full Scale Drill 08/29/2019 EP Critique Report – September 10, 2019 EP Exercise Drill 10/10/2019 EP Critique Report – 2019 EP Medical Drill 11/04/2019

Page 20: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

18

Inspection Procedure

Type Designation Description or Title Revision or Date

EP Critique Report – 2018 EP Medical Drill 11/08/2018 EP Critique Report - 28 May 2019 HP Mini Drill 06/27/2019 Monticello 8 Year EP Drill / Exercise Cycle Table 05/20/2020 Off-Site Response Organization Letters of Agreement - Current (LOAs / Memorandums of Understanding (MOUs)

A-EP-MNGP-2018-1

MNGP NOS Emergency Preparedness Audit – 2018 05/14/2018

A-EP-MNGP-2019-1

MNGP NOS Emergency Preparedness Audit – 2019 02/13/2019

KLD TR – 1040 Monticello Nuclear Generating Plant 2018 Population Update Analysis

10/29/2019

KLD TR – 1121 Monticello Nuclear Generating Plant 2019 Population Update Analysis

10/29/2019

KLD TR – 505 Monticello Nuclear Generating Plant Evacuation Time Estimate

1

MT-BEP-NOT-001L

Lesson Plan - Emergency Notifications 4

STP 1102 Emergency Equipment Inventory Records 04/30/2018-03/31/2020

STP 1125 Emergency Procedures Monthly Contact Verification Records

04/01/2018-03/31/2020

STP 1230 Emergency Response Facility Instrumentation Functional Test Records

04/01/2018-03/31/2020

Procedures

Monticello Nuclear Generating Plant Emergency Plan 53 FP-EP-SURV-05 Requirements for Annual Independent Review of EP

Program 3

71114.06 Miscellaneous

Emergency Plan Table-top DEP Drill Scenario 06/302020 71124.08 Corrective Action

Documents ACE 602000011898

Apparent Cause Evaluation Concerning Radioactive Shipment

0

CAP No. 501000041066

Radioactive Shipping Issue Concerning Waste Manifest Form-541

05/27/2020

Miscellaneous NSTS-2020 Verification/Validation Package Annual NSTS Inventory Reconciliation 2020 Monticello Nuclear Generating Plant

01/09/2020

Procedures R. 11.04 Waste Classification 13

Page 21: Code of Federal Regulations · OFFICIAL RECORD COPY . Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 05000263 ... Samples were declared ... OPS-DG-1/SSP1,

19

Inspection Procedure

Type Designation Description or Title Revision or Date

Shipping Records No. 19-55 Westinghouse Equipment to Westinghouse Facility 05/23/2019 No. 19-74 Condensate Resin Liner to Clive, Utah Facility 08/16/2019 No. 19-75 Condensate Resin Liner to Clive, Utah Facility 08/23/2019 No. 19-76 Resin Liner to Clive, Utah Facility 08/29/2019 No. 19-77 Resin Liner to Clive, Utah Facility 09/06/2019 No. 19-85 Plant Trash to UniTech, Oak Ridge, TN 09/20/2019 No. 20-18 Plant Laundry UN2912 to UniTech, Morris, IL 03/17/2020 No. 20-32 Scrap Metal Process to UniTech, Oak Ridge, TN 05/26/2020

71151 Miscellaneous

NRC Performance Indicator Data; Emergency Preparedness – ERO Readiness

07/01/2019 - 03/31/2020

NRC Performance Indicator Data; Emergency Preparedness – Alert and Notification System

07/01/2019 - 03/31/2020

MSPI Basis Document 12 Trend Date for the Period April 2019 - March 2020

NRC Performance Indicator Data; Emergency Preparedness – Drill/Exercise Performance

07/01/2019 - 03/31/2020

QF-0445 (Rev. 14)

NRC/INPO/WANO Data Collection and Submittal Form Fuel Performance (BWR)

01/01/2019-12/31/2019

QF-0445 (Rev. 14)

NRC/INPO/WANO Data Collection and Submittal Form Radiological Protection

01/01/2019-12/31/2019