COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY

Upload: others

Post on 18-Aug-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

COCO PALMS

SITE SAFETY PRACTICES

WORK AT HEIGHT SAFETY

Page 2: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Project Brief:

Project Scale : 12 blocks / 12 to 16 storeys building with 2

basement car parks

Total Units : 944 Units, 6 Ancillary Commercial Units

Site Area : 41,514 sqm (or approximate 446,857 sqft)

Contract Commencement Date : 10th July 2014

Contract Completion Date Phase 1 : 09th Oct 2017 – (39 months)

Contract Completion Date Phase 2 : 09th Jan 2018 – (42 months)

Page 3: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Project Team:

Developer/Owner : Hong Realty (Private) Limited

Project Manager : CDL Management Services Pte Ltd

Architect / QP For Building Plan : Axis Architects Planners Pte Ltd

Structural Engineer : Parsons Brinckerhoff Pte Ltd

Quantity Surveyor : Langdon & Seah Singapore Pte Ltd

M&E : Meinhardt (Singapore) Pte Ltd

Interior Designer : Axis ID Pte Ltd

Landscape Consultant : Tinderbox Pte Ltd

Builder : Woh Hup (Private) Limited

Page 4: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

CCP WSHE ORGANIZATION CHART

Roy ChiaConstruction Manager

Tang Chun KeatSite Manager

Tan Ee PongSite Manager

Scaffold Team Scaffold Sup – Sekar

Scaffold Erector – 16Blk 3-4

Padmanaban

Blk 1-2Paulo

Lifting TeamLifting Sup – Dinesh

Sig/Rig - 18

Mohd FadzliWSHEO

Blk 5-6Shanmugam

Blk 9-10Tan Siang Weng

Blk 7-8Ganesh

Blk 11-12Suresh

Page 5: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WH’s Safety Awards Achieved For The Past 3 Years

Page 6: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WOH HUP 2015 EHS ACHIEVEMENTS

RoSPA Gold Award

RoSPA Guardian Angel Award 2015

RoSPA Ocupational Safety Award

Winner of the Housebuilding & Property Development Sector

SCAL WSH Innovation Convention

Silver – WSHE Team

Bronze – Corals At Keppel bay

MOM WSH SHARP Award

MOM WSH Award For Supervisor

Happy Toilet 5 Star Award

Page 7: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

COCO PALMS EHS ACHIEVEMENTS

RoSPA Gold Award 2014

RoSPA Gold Award 2015

MOM SHARP Award 2014

MOM SHARP Award 2015

Happy Toilet 5 Star Award 2014

Happy Toilet 5 Star Award 2015

CDL 5 STAR AWARDS

Page 8: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

• WH Management’s Top-Down Driven Safety Culture

• WH’s Internal Monthly Housekeeping Audits

• External Safety Audits on site’s safety standards

• CDL quarterly 5 Stars Audits

Page 9: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to
Page 10: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WORK AT HEIGHT

SAFETY

TOPICS FOR THE DAY

WORK AT HEIGHT

SAFETY

Page 11: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WORK AT HEIGHT (WAH) SAFETY

Page 12: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WAH SAFETYFall Prevention Plan

Page 13: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WAH SAFETYFall Prevention Plan – Structural Stage

External Safety Screen

External Gap CoveringFormwork Edge Railings

Floor Opening

Cover

Rigid Barricade

Lift Shaft Jump Form Access to Construction Floor Formwork Edge Railings

Detachable Barricade External scaffold

Page 14: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WAH SAFETYFall Prevention Plan – Finishing Stage

Lift Shaft Fencing

External Safety Screen Catch Screen Opening Cover

Staircase Railings

Drop Down Lifeline External Gap Covering Rigid Barricade External scaffold

Bay Window Barricade

Page 16: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Installation of MLP

1

2

Dropdown lifeline pre

installed for user to

anchor on during the

shifting of MLP.

Dropdown lifeline pre

installed for user to

anchor on during the

shifting of MLP.

Page 17: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Installation of MLP

3

4

MLP door hinge is

provided with a knob to

prevent it from dislodge

during operation or

lifting.

MLP door hinge is

provided with a knob to

prevent it from dislodge

during operation or

lifting.

Page 18: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

3

4

Safe working load

(SWP) to be displayed

for user awareness.

Lifting point for MLP

Installation of MLP

Page 19: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

AC ledgeInstallation of barricade

Horizontal

GI pipe

Vertical GI

pipe

1m GI pipe

2.5m GI

pipe

AC Ledge

Base plate

Legend:Drop down lifeline

Steps:

1)Drill 10mm hole to

the ac ledge.

2) Insert 10mm wall

plug into the hole.

3)Install the GI

column pipe and

screw in with 10mm

bolt.

4) Complete with 5

layer horizontal

guardrail and

toeboard

Toeboard

Page 20: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Planter boxInstallation of barricade

Planter

Horizontal GI

pipe

Vertical GI pipe

0.5m GI pipe

1m GI pipe

1.5m GI pipe

Base plate

Legend:Drop down lifeline

Steps:

1)Drill 10mm hole to

the planter box.

2) Insert 10mm wall

plug into the hole.

3)Install the GI column

pipe plate and screw in

with 10mm bolt.

4) Complete with 3

layer horizontal

guardrail without

toeboard.

Page 21: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

StaircaseInstallation of barricade

Legend:Drop down lifeline

Staircase mid landing

Horizontal GI

pipe

Vertical GI pipe

0.5m GI pipe

1m GI pipe

1.5m GI pipe

Base

plate

Steps:

1)Drill 10mm hole

to the staircase

midlanding and

200mm away from

the edge.

2) Insert 10mm wall

plug into the hole.

3)Install the GI

column pipe plate

and screw in with

10mm bolt.

4) Complete with 3

layer horizontal

guardrail with

toeboard.200mm

Toeboard

Page 22: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

INSTALLATION OF WINDOW FRAME

1

3

Rope will be used

to secure the

window frame

and the other end

to the safety

barricade.

4

2 Worker will hook his

harness to the

safety barricade or

the dropdown

lifeline when

slotting the window

frame into its

position.

Using an explosive powered tools,

worker will then secured the window

frame to the concrete surface.

Once window frame installed,

barricades will be transferred to the

window frame itself.

Page 23: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Installation of precast finwallPrecast Finwall – Installation sequence

High detachable barricade in

placed prior precast Finwall is

installed.

4 5

Lifting gear released after tie

back is installed and secured.

Page 24: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

1. Brickcage to be installed at the exterior façade

of the work area

A

Layering AAC block or installing Acotec panel at the edge of the building

1. Brickcage will be shifted up to the next level for

the following level (Common staircase area)

B

Page 25: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

1. Brickcage to be installed at the exterior façade

of the work area (Planter area)

C

Layering AAC block or install Acotec panel at the edge of the building

Page 26: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Tower Crane Operator AccessTypical erection of tower crane access

1

2

3

4

1 2

43

Page 27: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

1

2

3

4

Tower Crane Operator AccessTypical erected of tower crane access

1

43

2

Page 28: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Passenger HoistLocation of passenger hoist

Page 29: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Site AccessPerimeter access

Site perimeter access to be clean. Any deviation in the

height of the walkway needs to be mark with a visible sign.

Page 30: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Site AccessAccess to higher slab

Steps access provided for personnel to cross higher slab

area

Page 31: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Site AccessAccess to formwork areas

Access provided to formwork

areas.

Page 32: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Internal In House TrainingJoint training between Woh Hup & Subcontractors - Classroom

Page 33: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

Internal In House TrainingJoint training between Woh Hup & Subcontractors – On Site Training

Page 34: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WAH SAFETYCompetency of WAH

Worker Supervisor

Assessor Manager

WAH

Page 35: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

WAH SAFETYEmergency Response

Rescue Kits

Page 36: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

SITE WALK

Page 37: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

SITE WALK ROUTEG2Site Office

Page 38: COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY · 2016. 11. 25. · COCO PALMS SITE SAFETY PRACTICES WORK AT HEIGHT SAFETY. Project Brief: Project Scale : 12 blocks / 12 to

THANK YOU