coastal regulation zonemesasmabi.com/wp-content/uploads/2018/12/crz-ppt.pdf · development in crz -...

20
Coastal Regulation Zone 1

Upload: others

Post on 16-Mar-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Coastal Regulation Zone

1

Definition of HTLQ.1 What is High Tide Line ?

Line up to which the highest water line reaches during the spring tide.

Q.2 What is Coastal Regulation zone ?

Coastal stretches of Sea, Bays, Estuaries, Creeks, Rivers and Backwaters which are influenced by the tidal action.

Area between LTL & HTL.

Area upto 500m from HTL

2

Landward limit of CRZ in creeksC.R.Z is extended up to what point inside landward direction,in cases of Rivers, Creeks and Backwaters?

Distance upto which tidal effects are experienced

Concentration levels of five parts per 1000.

3

Width of CRZ belt in creeksWhat is the width of Coastal Regulation zone in case of sea and in case of creeks and rivers and backwaters ?

for sea is 500mt. from the High Tide Line.

for Creeks and backwaters

4

Width of creek Width of CRZ belt

100m or less Up to 100m or less

100-350m 100m

>350m 150m

Prohibited activities in CRZ Prohibited activities in CRZ areas.

Setting up and expansion of existing industries,

Discharging of untreated waste,

Dumping of waste by land filling,

Land reclamation or bunding,

Construction activity in CRZ - I in between Low Tide Line & High Tide Line,

Alteration of sand dunes etc.

5

CRZ - I What are the different zone in Coastal Regulation

zone?

Coastal Regulation zone-I(i)

Areas that are ecological sensitive such as Marine Park, Mangroves, Coral Riffs, etc.

Coastal Regulation zone-I(ii)

Area between the Low Tide Line & High Tide Line.

6

Development in CRZ - I No new construction in Coastal Regulation zone-I

Projects of Department of atomic Energy, Pipelines, Transmission Lines are permitted

In CRZ- I (ii)

which are not ecological sensitive exploration and extraction of natural gas, salt harvesting permitted.

7

CRZ - II Coastal Regulation Zone - II

Developed areas close to the shore line,

Substantially built up areas within legally designated urban areas.

Infrastructure facilities provided.

8

Development in CRZ - II Development permissibility in CRZ - II

Buildings permitted only on

land ward side of existing road or

landward side of existing authorized structure or on

landward side of proposed roads in approved CZMP.

Such bldgs as per existing FSI/FAR norms

9

10

Landward Side of Road

Existing Road

C.R.Z (II)500 M

Sea

High tide Line

500M Control Line

Plot

11

Plot

ExistingBldg.

Sea

CRZ (II)

Land Ward Side of Existing Authorised Building

Development in CRZ - II Reconstruction permitted subject to existing FSI

*(Floor Space Index)/FAR (Floor Area Ratio)norms without change in use

Bldgs. Consistent with surrounding urban landscape & architecture.

Certain relaxations given in latest amendment to Redevelopment of Cessed Structures / MHADA Projects.

12

CRZ - III Coastal Regulation zone - III

Relatively undisturbed & undeveloped areas

Rural areas within municipal limit which are not substantially built up

13

Development in CRZ - III Development permissibility in CRZ - III

0-200m No construction except repairs of authorized structures public utility facilities allowed with permission of state CZMP.

200-500m Development of vacant plots for Hotels /beach resorts with prior approval from MoEF.

Construction / reconstruction of dwelling units within ambit of tradition of rights and customary use such as fishing, villages and gaothans etc.

14

15

Sea

0 –200 MTS. No. Dev. Zone of CRZ - III

200 TO 500 MTS. in N CRZ - III

HTL of Sea

CRZ - IV Coastal Regulation Zone - IV

Applicable only for Andaman & Nicobar Islands.

16

C.Z.M.P.What is Costal Zone Management Plan?

Identifying coastal stretches & classifying them in different CRZ areas.

Integrated development of these areas.

State level coastal management authority responsible for monitoring

17

Coastal Zone Management Plan for Greater Mumbai

18

N

Combined CZMP for Greater Mumbai

submitted to MoEF by GoM Wide letter

No. CS/TPB. 4396/12/CR-

263/96/UD-11 Dated 25th Nov. 1998

& approved by MoEF letter No. J-

17011/8/95-1A .III Dated 19th Jan 2000.

CRZ - I

CRZ - II

CRZ -III

Existing Roads shown as CZMP Roads

Proposed Roads on Land (Not Passing Trough

CRZ) shown as proposed CZMP Roads

Extent of CRZ in Mumbai The approximate areas of CRZ

CRZ – I 146 sq. kms

CRZ - II 42.7 sq. kms

CRZ - III 13.82 sq. kms.

19

20

Thank You