  • HomelandSecurity

    United StatesCoast Guard

    Consolidated Station Facility Woods HoleWoods Hole

    Town of Falmouth Public MeetingFebruary 2, 2016

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center1

  • HomelandSecurity

    United StatesCoast GuardINTRODUCTIONS

    Ground Rules for Questions

    Meeting Overview / AgendaCAPT John Kondratowicz SEC SENE 5 mins

    Will be addressed upon conclusion of the presentation

    CAPT John Kondratowicz SEC SENE 5 mins Welcome Introductions Ground Rules About SENE

    If you have question / comment pertaining to a particular, please

    CAPT John Healy, PE FDCC 5 mins Meeting Purpose Current Update

    Mr. Santora McKinney, RA FDCC 20 mins Revised Concept Design Solutions

    reference the slide number.

    Revised Concept Design Solutions

    Public Comment 45 mins

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center2

  • HomelandSecurity

    United StatesCoast Guard

    SEC SENE

    CAPT JOHN KONDRATOWICZ

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center3

  • HomelandSecurity

    United StatesCoast GuardUNIT DESCRIPTION

    About SENE Created 2006

    Coast Guard Sector Southeastern

    Responsible for over 600 miles of coastline

    110 Sector Personnel

    Sector Southeastern New England

    (SENE) 110 Sector Personnel Assets include:

    8 Multi-Mission Stations & 1 Seasonal4 Patrol Boats

    (SENE)

    4 Patrol Boats 2 Aids to Navigation Teams 2 Marine Safety Detachments TOTAL PERSONNEL ASSIGNED 575

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center4 4

  • HomelandSecurity

    United StatesCoast GuardUnits at Woods Hole

    Station Woods Hole 43 Person Unit 3 Response boats Area of Responsibility; Vineyard Area of Responsibility; Vineyard

    Sound, Nantucket Sound & Buzzards Bay

    17 P U it

    Aids to NavigationTeam Woods Hole

    17 Person Unit 2 Buoy service boats Responsible for 770+ Federal

    navigation aids in Vineyard Sound, N t k t S d & B d BNantucket Sound & Buzzards Bay

    CGC TYBEECGC SANIBEL

    11-18 Persons/Unit each (total 44) Homeported in Woods HoleCGC SANIBEL

    CGC HAMMERHEADHomeported in Woods Hole

    Area of Responsibility: Maine to New York, extending 200 miles off-shore

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center5

  • HomelandSecurity

    United StatesCoast Guard

    CG FDCC

    CAPT JOHN HEALY

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center6

  • HomelandSecurity

    United StatesCoast GuardMeeting Purpose

    1. Provide status of Section 106 process.

    2 U d t F l th it f t l h2. Update Falmouth community of conceptual changes made based on public input and CGs project refinement since Sept 2015.

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center7

  • HomelandSecurity

    United StatesCoast Guard

    Review of Last Meetingg

    Need for new WPB/ANT/STA buildings that supported CG Mission $23M Appropriated

    Section 106 Process Section 106 Process ANT Bldg could not be economically maintained for any CG Mission and is

    targeted for demolition. Mr Rick Hylton explained the Section 106 ProcessMr. Rick Hylton explained the Section 106 Process MOA Status

    Signed by MASHPO (Signatory) Historic Districts Commission & Historical Commission (Concurring Signatories)Historic Districts Commission & Historical Commission (Concurring Signatories)

    Preliminary Conceptual Design CGs intent is to construct a building that was in harmony w/community and

    stakeholders Goal was to hear communitys concerns and adjudicate rub points

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center8

  • HomelandSecurity

    United StatesCoast Guard

    Community Concerns voiced 9/16/2015

    Historical Concerns with Demolition of ANT ANT Bldg does not currently meet the CGs mission requirements at Woods

    H l it b i ll t fitt d t t i i i tHole, nor can it be economically retrofitted to meet our mission requirements. The MOA provides direction on documenting and remembering its history.

    Design / Constructability of new buildingM i d Si Massing and Size

    Viewsheds from nearby homes & street / Light pollution Materials chosen (Falmouth Historic District Design Review Guidelines)

    C t ti i /t ffi / ib ti & ti i / F P j t Construction noise/traffic/vibrations & timing w/ Ferry Project Now at 95% Conceptual Design

    Purpose of this meeting is to reengage w/ community Address any loose ends, if possible, before releasing Request for

    Proposal (RFP) to Industry

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center9

  • HomelandSecurity

    United StatesCoast Guard

    REVISEDREVISED CONCEPTUAL

    DESIGNMr. Santora McKinney, R.A.

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center10

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    Project Goals: Construct consolidate station

    Project Considerations: Building resiliency to flooding

    that meets the needs of: Station Woods Hole ANT (Aids to Navigation Team)

    WPB (P t l B t )

    g y g Building aesthetics which

    compliment Service Building and nearby residences

    WPB (Patrol Boats)y

    View obstructions to nearby neighbors

    Parking impacts on baseParking impacts on base Remove temporary trailer and

    sheds where possibleProvide sustainable facility Provide sustainable facility which meets LEED requirements

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center11

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    INITIAL SITE PLAN (SEPT/2015)

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center12

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED SITE PLANA

    B

    C

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center13

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    VIEW A TO BE MAINTAINED / IMPROVED

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center14

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    VIEW B TO BE MAINTAINED

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center15

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED SITE PLAN

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center16

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    PREVIOUS FIRST FLOOR PLAN CONSOLIDATED STATION / ANT (SEPT/2015)

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center17

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED GROUND FLOOR PLAN CONSOLIDATED STATION

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center18

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED FIRST FLOOR PLAN CONSOLIDATED STATION

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center19

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED SECOND FLOOR PLAN CONSOLIDATED STATION

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center20

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    PREVIOUS ELEVATION CONSOLIDATED STATION /ANT BLDG (SEPT/2015)EAST ELEVATION

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center21

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED EAST ELEVATION CONSOLIDATED STATION /ANT BLDG

    ORTHOGONAL VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center22

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED EAST ELEVATION CONSOLIDATED STATION BUILDING

    PERSPECTIVE VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center23

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    PREVIOUS ELEVATION CONSOLIDATED STATION /ANT BLDG (SEPT/2015)WEST ELEVATION

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center24

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED WEST ELEVATION CONSOLIDATED STATION BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center25

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    PREVIOUS NORTH ELEVATION CONSOLIDATED STATION BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center26

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED NORTH ELEVATION CONSOLIDATED STATION BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center27

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    CONSOLIDATED STATION BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center28

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    INITIAL SITE PLAN (SEPT/2015)

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center29

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED SITE PLAN

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center30

  • HomelandSecurity

    United StatesCoast Guard

    95%CONCEPTUAL DESIGN

    REVISED GROUND FLOOR PLAN ANT / WPB BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center31

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED FIRST FLOOR PLAN ANT / WPB BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center32

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    REVISED SECOND FLOOR PLAN ANT / WPB BUILDING

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center33

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    SOUTH ELEVATIONS ANT / WPB BUILDING

    ORTHOGONAL VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center34

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    SOUTH ELEVATIONS ANT / WPB BUILDING

    PERSPECTIVE VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center35

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    EAST ELEVATIONS ANT / WPB BUILDING

    PERSPECTIVE VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center36

  • HomelandSecurity

    United StatesCoast Guard

    95% CONCEPTUAL DESIGN

    WEST ANT / WPB BUILDING

    PERSPECTIVE VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center37

  • HomelandSecurity

    United StatesCoast Guard

    PRELIMINARY CONCEPTUAL DESIGN

    ANT / WPB BUILDING

    PERSPECTIVE VIEW

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center38

  • HomelandSecurity

    United StatesCoast GuardNEXT STEPS

    Feb 2016 MOA signed by MA SHPO and Falmouth Historic Districts Commission (awaitingHistoric Districts Commission (awaiting Falmouth Historical Commission)

    M 2016 R l R t f P l (RFP fMar 2016 Release Request for Proposal (RFP for Solicitation. (Design / Build IDIQ contract)

    Aug 2016 Award ProjectJan 2017 Design CompleteSpring 2017 Mobilize

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center39

  • HomelandSecurity

    United StatesCoast Guard

    QUESTIONS &QUESTIONS & COMMENTS

    Shore Infrastructure Logistics Center

    Facilities Design & Construction Center40