cms area working group meeting
DESCRIPTION
CMS Area Working Group Meeting. Installation schedule for coming months. CEMESTE / 105 : May 2 nd 2007 Agenda: Key milestones UXC55 Installation sequence of the cable chains +Z area installation YB0 installation schedule Impact on start of central beam pipe installation - PowerPoint PPT PresentationTRANSCRIPT
14/03/2007 [email protected] 1
CMS Area Working Group Meeting
14/03/2007 [email protected] 2
Installation schedule for coming months
→CEMESTE/105 : May 2nd 2007
→Agenda:
→Key milestones →UXC55
→Installation sequence of the cable chains→+Z area installation →YB0 installation schedule
→Impact on start of central beam pipe installation→-Z area installation
→USC55→Electronics installation in Control area→LV system installation on top of By-pass→Magnet/Cryogenics area installation→TX54
14/03/2007 [email protected] 3
Nov2006 Dec2006 Feb2007 March2007 May2007
→Ready for crates with cooling in UXC55 X2 level
12/12/2006 27/02/2007 06/03/2007 17/04/2007 31/05/2007→Start pre-cabling of TK
15/05/2007→Ready to insert TK
28/08/2007→Ready to cool down magnet
31/08/2007→LV system ready to power YE+1
15/06/2007
Key milestones
Hardelec contract
Driven by TK piping and cable trays
Compatible with LHC deadline
Vacuum system & cryogenics
commissioned
Crucial for CMS commissioning
14/03/2007 [email protected] 4
Cable chains installation schedule
14/03/2007 [email protected] 5
TS LEA Work Packages almost completeFew pipes missing (compressed air)TS EL WPs all complete
ConnectCablesFrom
Patch pTo racks
On towers
Ready for fibres
14/03/2007 [email protected] 6
Very challenging task!!Planning/coordination effort on-going
ConnectCablesFrom
Patch pTo racks
On towers
14/03/2007 [email protected] 7
ID Task Name Duration Owner Contractor(s)
1546 NEAR Side 64.5 days
1547 Install HE fibre optics Near side 1 day PH-CMI HCAL
1548 Install CSC optical fibres Near Side 4 wks TS-EL MZ
1549 Install turbine Cables Near side 1 wk TS-LEA Cegelec
1550 Install gas control cables Near side 2 days TS-LEA Cegelec
1551 Start of CRIOTEC contract 0 days
1552 Install cooling/gas pipes in YE+1 towers Near side 1.2 wks TS-LEA CRIOTEC
1553 Install cooling/gas pipes in YE+2+3 towers Near side 1.2 wks TS-LEA CRIOTEC
1554 Install HV RPC YE+1 cables Near side 18 days PH-CMI Russia
1555 Install LV power & ctrl cables for subdetectors 1 wk TS-LEA Spie Cegelec
1556 Install HV CSC cables Near side 1 wk PH-CMI CSC
1557 Install DCS cables Near side 1 wk PH-CMI Russia
1558 Install safety cables (smoke) Near side 1 wk TS-CSE SOTEB
1559 Install RE Link boxes & cables Near Side 4 days PH-CMM Poland
1560 Install safety cables (RSS) Near side 2 days ? ?
1561 Install HV RPC YE+2 +3 cables Near side 2.5 days PH-CMI Russia
1562 Install mini Cable chains to YE+2 16 days
1565 Install mini Cable chains to YE+3 2 days
02/03 02/0302/03 02/03
23/03 23/0423/03 23/04
19/03 23/03
19/03 20/03
26/03
26/03 02/04
15/05 23/05
03/04 30/04
02/05 08/05
09/05 15/05
16/05 23/05
24/05 31/05
23/04 26/04
01/06 04/06
05/06 07/06
Jan Feb Mar Apr May Jun Jul AugQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007
YE+1 Draft schedule
→ TS-LEA: Criotec contract→ Behind schedule… Short notice holidays…→ More crews have been requested as from 07/05 to try and catch up→ Lack of execution drawings but lots of on site coordination
14/03/2007 [email protected] 8
YE+1: very challenging environment
Pipe, cables and fibres have to be organised
14/03/2007 [email protected] 9
ID Task Name Duration Owner Contractor(s)
1546 NEAR Side 64.5 days
1547 Install HE fibre optics Near side 1 day PH-CMI HCAL
1548 Install CSC optical fibres Near Side 4 wks TS-EL MZ
1549 Install turbine Cables Near side 1 wk TS-LEA Cegelec
1550 Install gas control cables Near side 2 days TS-LEA Cegelec
1551 Start of CRIOTEC contract 0 days
1552 Install cooling/gas pipes in YE+1 towers Near side 1.2 wks TS-LEA CRIOTEC
1553 Install cooling/gas pipes in YE+2+3 towers Near side 1.2 wks TS-LEA CRIOTEC
1554 Install HV RPC YE+1 cables Near side 18 days PH-CMI Russia
1555 Install LV power & ctrl cables for subdetectors 1 wk TS-LEA Spie Cegelec
1556 Install HV CSC cables Near side 1 wk PH-CMI CSC
1557 Install DCS cables Near side 1 wk PH-CMI Russia
1558 Install safety cables (smoke) Near side 1 wk TS-CSE SOTEB
1559 Install RE Link boxes & cables Near Side 4 days PH-CMM Poland
1560 Install safety cables (RSS) Near side 2 days ? ?
1561 Install HV RPC YE+2 +3 cables Near side 2.5 days PH-CMI Russia
1562 Install mini Cable chains to YE+2 16 days
1565 Install mini Cable chains to YE+3 2 days
02/03 02/0302/03 02/03
23/03 23/0423/03 23/04
19/03 23/03
19/03 20/03
26/03
26/03 02/04
15/05 23/05
03/04 30/04
02/05 08/05
09/05 15/05
16/05 23/05
24/05 31/05
23/04 26/04
01/06 04/06
05/06 07/06
Jan Feb Mar Apr May Jun Jul AugQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007
YE+1 Draft schedule
→ TS-LEA: Spie Cegelec contract→ In charge of on-detector cabling for both turbines and LV→ Work in YEs towers between patch panels and racks→ No proper execution drawings but supports from TS-EL and S Lusin→ Activity very much on the critical path
14/03/2007 [email protected] 10
UXC55: Racks installation
14/03/2007 [email protected] 11
ID Task Name Duration Owner Contractor(s)
926 Level X2 263 days
927 Near Side 263 days
928 Cooling plants 174 days
941 Ready for racks 0 days
942 Install racks 1 wk TS-IC-HM DBS
943 Weld racks on to structures 3.4 wks PH-CMI
944 Install racks side panels 4 wks PH-CMI
945 Equip racks with manifolds and heat exchangers 1 wk PH-CMI
946 Install ECAL cables between cooling plant and USC55/S2 2 days TS-EL Hadrelec
947 Perform pressure tests 2 days PH-CMI
948 Install LV power supply units 4 wks PH-CME
949 Install cables for turbines 2 wks TS-EL Hadrelec
950 Install cables for LV power distribution 4 wks TS-EL INEO
951 Connect and configure DSS system in USC55 4 wks PH-CMI
952 Ready for crates 0 days
29/09
02/10 06/10
30/10 21/1130/10 21/11
08/01 02/0208/01 02/02
05/02 09/0205/02 09/02
08/03 09/0308/03 09/03
26/04 27/0426/04 27/04
30/04 30/0530/04 30/05
16/05 31/0516/05 31/05
01/06 28/0601/06 28/06
08/06 05/0708/06 05/07
14/06
Jan Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007
→ TS-EL: Install cables for turbines→ Start 16/05 for 2 weeks→ Hadrelec→ Far side completed first, missing cable trays have to be installed
UXC55: Racks installation – Near side
14/03/2007 [email protected] 12
ID Task Name Duration Owner Contractor(s)
926 Level X2 263 days
927 Near Side 263 days
928 Cooling plants 174 days
941 Ready for racks 0 days
942 Install racks 1 wk TS-IC-HM DBS
943 Weld racks on to structures 3.4 wks PH-CMI
944 Install racks side panels 4 wks PH-CMI
945 Equip racks with manifolds and heat exchangers 1 wk PH-CMI
946 Install ECAL cables between cooling plant and USC55/S2 2 days TS-EL Hadrelec
947 Perform pressure tests 2 days PH-CMI
948 Install LV power supply units 4 wks PH-CME
949 Install cables for turbines 2 wks TS-EL Hadrelec
950 Install cables for LV power distribution 4 wks TS-EL INEO
951 Connect and configure DSS system in USC55 4 wks PH-CMI
952 Ready for crates 0 days
29/09
02/10 06/10
30/10 21/1130/10 21/11
08/01 02/0208/01 02/02
05/02 09/0205/02 09/02
08/03 09/0308/03 09/03
26/04 27/0426/04 27/04
30/04 30/0530/04 30/05
16/05 31/0516/05 31/05
01/06 28/0601/06 28/06
08/06 05/0708/06 05/07
14/06
Jan Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007
→ TS-EL: Install cables for LV power distribution→ Start 01/06 for 4 weeks→ INEO→ Routing to be provided by S Bally (nothing available at TS-EL)
UXC55: Racks installation – Near side
14/03/2007 [email protected] 13
YB0 project
eighth iteration
→Optimised schedule version 5:→Milestone summary: Keys date to keep in mind
14/03/2007 [email protected] 14
YB0 +Z sideID Task Name Duration
1265 +Z side 118 days
1266 Weld PP1 and ECAL fixation studs 1 wk
1267 Install water detection cable 1 day
1268 Install PP1s + HCAL source driver + laser box 3 days
1269 Perform photogrametry 1 day
1270 Install VT+ scaffolding 7 days
1271 Install Surkov platform inside VacT 1 day
1272 Install TK pipes supports 11 days
1283 Weld ECAL tubes + weld ECAL cooling fittings + pipe squeezing 12 days
1284 Install cooling pipes for TK PP1 to PP2 + insulation 4 wks
1285 Install support beam on X4 for PP2s 2 days
1286 Install PP2s 4 days
1287 Install TK cable trays (radial + outside Vac Tank) 19 days
1288 Delivery of cable trays for Sector 1 0 days
1289 Install TK cable trays for Sector 1 1 wk
1290 Delivery of cable trays for all remaining sectors 0 days
1291 Install TK cable trays for remaining sectors 2 wks
1292 Install ECAL/HCAL (TO MODULES) cable trays inside VacT 2 wks
1293 Install peripheral ECAL cable trays outside Vac Tank 1 wk
1294 Install LV ECAL cables from PP2 to towers 2 wks
1295 Install cooling pipes for TK PP2 to Plant + insulation 5 wks
1296 Install TK cables 15 days
1301 Modify scaffolding, remove Surkov platf and install enfourneur 1 wk
1302 Install 18 ECAL supermodules 14 days
1303 Remove Enfourneur 2 days
1304 EB-HB services 25 days
1314 Install TK optical fibres 1 wk
1315 Install cable/pipe channels between TK and PP1 (inside VacT) 1 wk
1316 Install TK heating wires 1 wk
1317 Install tooling for TK 5 days
1318 +Z side ready for TK insertion 0 days
1319 Insert TK 2 wks
23/03 29/03
23/03 23/03
03/04 05/04
03/04 03/04
05/04 17/04
16/04 16/04
18/04 03/05
07/05 23/05
18/04 14/05
20/04 23/0420/04 23/04
07/05 10/05
10/05 07/06
10/05
10/05 16/05
24/05
24/05 07/06
23/04 07/05
30/04 07/05
29/05 11/06
15/05 20/06
15/05 06/06
07/06 13/06
14/06 29/06
02/07 03/07
08/08 14/08
15/08 21/08
15/08 21/08
22/08 28/08
28/08
29/08 12/09
Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007
CosmiAhead of schedule
14/03/2007 [email protected] 15
YB0 +Z sideID Task Name Duration
1265 +Z side 118 days
1266 Weld PP1 and ECAL fixation studs 1 wk
1267 Install water detection cable 1 day
1268 Install PP1s + HCAL source driver + laser box 3 days
1269 Perform photogrametry 1 day
1270 Install VT+ scaffolding 7 days
1271 Install Surkov platform inside VacT 1 day
1272 Install TK pipes supports 11 days
1283 Weld ECAL tubes + weld ECAL cooling fittings + pipe squeezing 12 days
1284 Install cooling pipes for TK PP1 to PP2 + insulation 4 wks
1285 Install support beam on X4 for PP2s 2 days
1286 Install PP2s 4 days
1287 Install TK cable trays (radial + outside Vac Tank) 19 days
1288 Delivery of cable trays for Sector 1 0 days
1289 Install TK cable trays for Sector 1 1 wk
1290 Delivery of cable trays for all remaining sectors 0 days
1291 Install TK cable trays for remaining sectors 2 wks
1292 Install ECAL/HCAL (TO MODULES) cable trays inside VacT 2 wks
1293 Install peripheral ECAL cable trays outside Vac Tank 1 wk
1294 Install LV ECAL cables from PP2 to towers 2 wks
1295 Install cooling pipes for TK PP2 to Plant + insulation 5 wks
1296 Install TK cables 15 days
1301 Modify scaffolding, remove Surkov platf and install enfourneur 1 wk
1302 Install 18 ECAL supermodules 14 days
1303 Remove Enfourneur 2 days
1304 EB-HB services 25 days
1314 Install TK optical fibres 1 wk
1315 Install cable/pipe channels between TK and PP1 (inside VacT) 1 wk
1316 Install TK heating wires 1 wk
1317 Install tooling for TK 5 days
1318 +Z side ready for TK insertion 0 days
1319 Insert TK 2 wks
23/03 29/03
23/03 23/03
03/04 05/04
03/04 03/04
05/04 17/04
16/04 16/04
18/04 03/05
07/05 23/05
18/04 14/05
20/04 23/0420/04 23/04
07/05 10/05
10/05 07/06
10/05
10/05 16/05
24/05
24/05 07/06
23/04 07/05
30/04 07/05
29/05 11/06
15/05 20/06
15/05 06/06
07/06 13/06
14/06 29/06
02/07 03/07
08/08 14/08
15/08 21/08
15/08 21/08
22/08 28/08
28/08
29/08 12/09
Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007
Very aggressiveProcurement and assembly of cable trays will
drive the sequence
Target date
14/03/2007 [email protected] 16
YB0 -Z side
ID Task Name Duration
1321 -Z end 103 days
1322 Perform photogrametry 1 day
1323 Weld PP1 and ECAL ducts fixation studs 9 days
1324 Install VT- scaffolding 10 days
1325 Install water detection cable 1 day
1326 Setup enfourneur -Z side 4 days
1327 Weld ECAL tubes + weld ECAL cooling fittings + pipe squeezing 12 days
1328 Install PP2s 4 days
1329 Install 18 ECAL Super modules 22 days
1330 Lift up enfourneur to SX5 1 day
1331 Install PP1s + HCAL source driver + laser box + ECAL ducts (HB edge Vac Tank)5 days
1332 Install TK pipe supports outside Vac tank 1 wk
1333 Install HCAL layer 0 3 days
1334 Install Surkov platform inside VacT 1 day
1335 Install cooling pipes for TK PP1 to PP2 + insulation 3 wks
1336 Install radial TK cable trays (cooling + LV) outside Vac Tank 1 wk
1337 Install ECAL/HCAL (TO MODULES) cable trays inside Vac Tank 1 wk
1338 Install peripheral ECAL cable trays outside Vac Tank 1 wk
1339 Install LV ECAL cables from PP2 to towers 2 wks
1340 Install cooling pipes for TK PP2 to Plant + insulation 5 wks
1341 Install TK cables 18 days
1346 EB-HB services 22 days
1354 Install cable/pipe channels between TK and PP1 (inside VacT) 1 wk
1355 Install TK heating wires 1 wk
1356 Install TK optical fibres 1 wk
1357 Install tooling for TK 5 days
1358 -Z side ready for TK insertion 0 days
04/04 04/04
30/03 13/04
05/04 20/04
30/03 30/03
16/04 19/0416/04 19/04
07/05 23/05
11/05 16/05
23/04 21/05
22/05 22/05
17/04 23/04
27/04 04/05
23/05 25/05
29/05 29/05
15/05 06/06
31/05 06/06
31/05 06/06
30/04 07/05
23/05 06/06
07/06 11/07
07/06 02/07
02/08 08/08
02/08 08/08
15/08 21/08
22/08 28/08
28/08
Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007
Can only start once +Z complete
Slower than expected insertion
rate
14/03/2007 [email protected] 17Design by CMS Integration group, April 2005.
-Z Area installation
FIN 56 installedFew more days needed for final alignmentNext activity: Install forward beam pipe
14/03/2007 [email protected] 18
USC55 : TX54 shielding
14/03/2007 [email protected] 19
ID Task Name Duration Owner Contractor(s)
426 TX54 installation 58 days
427 Delivery of TX54 shielding wall 0 days
428 Install steel plates for TX54 sliding system 1 wk TS-LEA Workshop
429 Assemble TX54 frame and install rails 2 wks TS-LEA Pakistan
430 Create anchor points in walls and floor 2 days TS-CE Forebeton
431 Equip frame with compressed infrastructure 3 days PH-CMI
432 Concrete TX54 frame 1 day TS-CE Losinger
433 Install concrete blocks 3 days TS-IC-HM DBS
434 Install 2 remaining concrete blocks 1 day TS-IC-HM DBS
435 TX54 installed 0 days
02/04
10/04 16/04
07/05 18/05
27/04 30/0427/04 30/04
19/05 22/0519/05 22/05
23/05 23/0523/05 23/05
24/05 26/0524/05 26/05
18/06 18/0618/06 18/06
18/06
Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007
USC55 : TX54 shielding
→ Delivery from Pakistan: 30/03→ All material need to be cleared from the area→ Tremie to be opened on 07/05, implications for lowering in USC55?
→ Safety barriers at the outline of the shaft in S2 should be removed when no load is lowered. This will facilitate the flow of personnel
→ Need to fill the gap between the 2 rows of plates→ More steel plates needed→ Budget code?
14/03/2007 [email protected] 20
USC55 : Control Area – CMS Electronics S2 (-1)
14/03/2007 [email protected] 21
DSS commissioning in S2: start 10-11/05 Impact on Global run scheduled for 25/05
UPS supported
14/03/2007 [email protected] 22
USC55 : Control Area – CMS Electronics S1 (-2)
14/03/2007 [email protected] 23
Services interruption→ CV:
→ Cooling water:→ Ventilation:
→ EL:→ HV Power:→ LV Power:
→ CSE:→ Smoke detection: off in service area
→ HM:→ TAIM cranes:→ SDX5 crane:→ UXC55 crane: AT-ECR works on transfer line during W16
→ DSS:→ Tests: S1 S2 start 21-22/05
→ IT:→ Network:→ WiFi:
14/03/2007 [email protected] 24
Turbines cabinets: 2 installed 4 more to come
UPS supported
Die
se
l C
an
ali
s
New request from TK: accepted
DSS commissioning in S1: 21-22/05
14/03/2007 [email protected] 25
USC55 : CMS Electronics –Temporary Ctrl room
Partition walls erectedGeneral services doneTemporary access ctrl installedIT services installedBusy area already
14/03/2007 [email protected] 26
USC55 : Control Area – CMS Electronics S1 (-2)
14/03/2007 [email protected] 27
Turbines racks: 2nd to be installed this week
UPS supported
Die
se
l C
an
ali
s
New request from TK: acceptedMore requests are being considered
14/03/2007 [email protected] 29
ID Task Name Duration Owner Contractor(s)
64 SDX5 717 days
99 Install LV room for detector 249 days PH-CME
103 Install cables for UPSs 7 wks TS-EL Hadrelec
104 Start up system UPSs 1 wk TS-EL Hadrelec
106 Install auxiliary cables for UPSs 2 wks TS-EL Hadrelec
107 Start up UPSs 1 wk TS-EL Hadrelec
108 Install network infrastructure for access control 2 wks IT-CS Hadrelec
109 PM54 733 days
230 USC55 848 days?
231 USC55 Control Area 848 days?
436 USC55 Service Area 848 days
437 Infrastructure installation 508 days
477 Top of CV Room installation 416 days
497 EL Safe Room 444 days
507 Magnet Power area 65 days
510 Install HV power connections 2 wks TS-EL Hadrelec
513 Top of Bypass 614 days
515 General services + cable trays 4.4 wks TS-EL Hadrelec
517 Install IT infrastructure 3 wks IT-CS Hadrelec
522 Cable 6 isolation power transformers 4 wks TS-EL Hadrelec
527 Sort cables for 2 LV cabinets 2.6 wks TS-EL Hadrelec
532 Install 6 TEK and 7 compensator modules in chassis 4 wks TS-EL Hadrelec
533 Install power cables from transformer to LV cabinets 4 wks TS-EL Hadrelec
534 Connect Turbine switchboard 4 wks TS-EL Hadrelec
535 Install cables from LV racks to LV cabinets 4 wks TS-EL Hadrelec
539 Install canalis for Wiener and TS racks 2 wks TS-EL Hadrelec
30/10 15/1230/10 15/12
18/12 22/1218/12 22/12
16/04 27/0416/04 27/04
30/04 07/0530/04 07/05
07/05 21/0507/05 21/05
02/04 17/0402/04 17/04
06/11 01/1206/11 01/12
08/03 26/0308/03 26/03
09/05 07/0609/05 07/06
09/05 07/0609/05 07/06
09/05 07/0609/05 07/06
08/06 05/0708/06 05/07
10/04 23/0410/04 23/04
Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007
USC55 –LV system installation
Crucial for commissioning
14/03/2007 [email protected] 30
Installation of Magnet areaA project in itself!
→Sequence has been under intensive review
→Baseline available
→Actors from 3 departments (AT-PH-TS)
14/03/2007 [email protected] 31
16 racks
Discharge lines supports(design to be reviewed)
CP1 & CP2
DCCT
Transfer line
Cold Box
Cryo cabinets
14/03/2007 [email protected] 32
ID Task Name Duration Owner Contractor(s)
568 Install 200 control cables USC55 only 4 wks TS-EL INEO
569 Position TBT batteries 1 day AT-ECR DBS
570 Position Cryo electrical cabinets + atmospheric exchanger 1 day AT-ECR DBS
571 Reinstall false floor 3 wks TS-IC COSMI
572 Install 5 CR control cables 1 wk TS-EL INEO
573 Install metallic structures for discharge lines on top of racks 2 days PH-CME
574 Install discharge lines 5 days PH-CMI
575 Install cables between UXC55 and USC55 through wall 10 wks TS-EL INEO
576 Install false floor 1 wk TS-IC COSMI
577 Connect MSS, MCS, CDS, vacuum cables to racks 14 wks TS-EL INEO
578 Commission Magnet ctrl and safety systems 4 wks PH-CMI
579 Install scaffolding for transfer line installation 2 days AT-ECR DeMaCo
580 Install last section of Transfer lines 2 wks AT-ECR DeMaCo
581 Remove scaffolding 1 day PH-CMI MADA
582 Reinstall scaffolding 1 day PH-CMI MADA
583 Install Vacuum pipe 3 wks PH-CMI
584 Weld warm pipes to Cold box 1 wk AT-ECR DeMaCo
585 Connect water pipes to pumps 1 wk PH-CMI
586 Dismantle scaffolding for transfer line installation 1 day AT-ECR DeMaCo
587 Install instrumentation and control cables for cold box 3 wks AT-ECR Dauphelec
588 Lower and Install UPSs 2 wks PH-CMI
589 Perform synchronization tests 1 wk AT-ECR
590 Commission cold box 4 wks PH-CMI
591 Ready to start vacuum 0 days
592 Cryogenics system ready to cool down coil 0 days
26/03 24/0426/03 24/04
05/04 05/0405/04 05/04
29/03 29/0329/03 29/03
26/03 17/0426/03 17/04
10/04 16/0410/04 16/04
02/05 03/0502/05 03/05
04/05 10/0504/05 10/05
11/05 23/0711/05 23/07
24/07 30/0724/07 30/07
25/04 03/0825/04 03/08
06/08 31/0806/08 31/08
06/03 07/03
12/03 23/03
23/03 23/0323/03 23/03
18/04 18/0418/04 18/04
23/04 14/0523/04 14/05
08/05 14/05
15/05 22/05
23/05 23/05
30/03 23/04
24/05 07/0624/05 07/06
24/04 30/04
24/05 21/0624/05 21/06
31/08
21/06
Jan Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007
USC55- Magnet area
→PH-CMI: Install support structure for transfer lines→No coactivity possible in the same area
14/03/2007 [email protected] 33
New items where scheduling effort is needed
Design by CMS Integration group, April 2005.
Areas where more scheduling effort is needed
14/03/2007 [email protected] 34
Very preliminary scheduleID Task Name Duration
896 UXC55 963 days?
1050 -Z side 912 days?
1128 CMS 912 days?
1200 YBs -Z side 845 days
1202 Lower Barrel YB-1 2 days
1203 Install YB-1 in temporary position 1 day
1204 Lower Barrel YB-2 2 days
1205 Install 8 missing muon chambers YB-1 3 days
1206 Install 8 missing muon chambers YB-2 3 days
1207 Position Barrel YB-1 on YB0 2 days
1208 Connect Patch Panel on YB-1 (mechanics) 1 day
1209 Position Barrel YB-2 2 days
1210 Connect Patch Panel on YB-2 (mechanics) 1 day
1211 Close Barrel wheels 2 days
1213 YEs -Z side 36 days
1214 Lower End Cap YE-1 1 day
1215 Move YE-1 out of shaft area 2 days
1216 Connect Patch Panel on YE-1 (mechanics) 2 days
1217 Lower End Cap YE-2 1 day
1218 Position YE-2 against YE-1 temporary 1 day
1219 Lower End Cap YE-3 1 day
1220 Position YE-3 against FIN 1 day
1221 Move YE-1 against barrel 2 days
1222 Chim and align YE-1 2 days
1223 Beam pipe 20 days
1224 Install central beam pipe 4 wks
1227 YB0 area 897 days
1265 YBO Services installation (under construction) 897 days
1266 +Z side 120 days
1319 +Z side ready for TK insertion 0 days
1320 Insert TK 12 days
1326 Connect TK to PP1 30 days
11/06 12/0611/06 12/06
13/06 13/0613/06 13/06
21/06 22/0621/06 22/06
25/06 27/0625/06 27/06
28/06 02/0728/06 02/07
22/08 23/0822/08 23/08
22/08 22/0822/08 22/08
24/08 27/0824/08 27/08
24/08 24/0824/08 24/08
27/08 28/0827/08 28/08
29/08 29/0829/08 29/08
17/09 18/09
19/09 20/0919/09 20/09
19/09 19/0919/09 19/09
20/09 20/0920/09 20/09
21/09 21/0921/09 21/09
24/09 24/0924/09 24/09
15/10 16/10
17/10 18/10
17/09 12/10
28/08
29/08 14/09
01/10 09/11
Apr May Jun Jul Aug Sep Oct Nov Dec JanQtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007 Qtr 1, 2008
Position against YB0 once scaffolding
removed
Lot more work
needed
14/03/2007 [email protected] 35
Detailed studies on going….Dates are not relevant the focus is on the sequence
ID Task Name Duration
1367 CMS closure 118 days
1368 YBs positioned on YB0 0 days
1369 Central beam pipe installed 0 days
1370 Install intermediate beam pipe on -Z 2 days
1371 Install Pixel detector 4 wks
1372 Install BCM 1 wk
1373 Position YEs against YBs 1 wk
1374 Rise HFs 2 wks
1375 CMS closed and ready for Cosmics 0 days
1376 Perform Cosmic data taking 2 wks
1377 EE installation 31 days
1378 Delivery of 2nd D for EE 0 days
1379 Open YEs 3 days
1380 Install 1st D on -Z Far side 1 wk
1381 Install 2nd D on -Z Near side 1 wk
1382 Close CMS 3 days
1383 1st EE installed on -Z side 0 days
1384 Perform Cosmic data taking 2 wks
28/08
12/10
15/10 16/10
17/10 13/11
14/11 20/11
21/11 27/11
28/11 11/12
11/12
12/12 25/12
17/12
07/01 09/01
10/01 16/01
17/01 23/01
24/01 28/01
23/01
29/01 11/02
Jul Aug Sep Oct Nov Dec Jan Feb Mar AprQtr 3, 2007 Qtr 4, 2007 Qtr 1, 2008 Qtr 2, 2008
→Areas where more work in needed to understand the sequence