cms area working group meeting

35
14/03/2007 [email protected] 1 CMS Area Working Group Meeting

Upload: catori

Post on 23-Jan-2016

37 views

Category:

Documents


0 download

DESCRIPTION

CMS Area Working Group Meeting. Installation schedule for coming months. CEMESTE / 105 : May 2 nd 2007 Agenda: Key milestones UXC55 Installation sequence of the cable chains +Z area installation YB0 installation schedule Impact on start of central beam pipe installation - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CMS Area Working  Group Meeting

14/03/2007 [email protected] 1

CMS Area Working Group Meeting

Page 2: CMS Area Working  Group Meeting

14/03/2007 [email protected] 2

Installation schedule for coming months

→CEMESTE/105 : May 2nd 2007

→Agenda:

→Key milestones →UXC55

→Installation sequence of the cable chains→+Z area installation →YB0 installation schedule

→Impact on start of central beam pipe installation→-Z area installation

→USC55→Electronics installation in Control area→LV system installation on top of By-pass→Magnet/Cryogenics area installation→TX54

Page 3: CMS Area Working  Group Meeting

14/03/2007 [email protected] 3

Nov2006 Dec2006 Feb2007 March2007 May2007

→Ready for crates with cooling in UXC55 X2 level

12/12/2006 27/02/2007 06/03/2007 17/04/2007 31/05/2007→Start pre-cabling of TK

15/05/2007→Ready to insert TK

28/08/2007→Ready to cool down magnet

31/08/2007→LV system ready to power YE+1

15/06/2007

Key milestones

Hardelec contract

Driven by TK piping and cable trays

Compatible with LHC deadline

Vacuum system & cryogenics

commissioned

Crucial for CMS commissioning

Page 4: CMS Area Working  Group Meeting

14/03/2007 [email protected] 4

Cable chains installation schedule

Page 5: CMS Area Working  Group Meeting

14/03/2007 [email protected] 5

TS LEA Work Packages almost completeFew pipes missing (compressed air)TS EL WPs all complete

ConnectCablesFrom

Patch pTo racks

On towers

Ready for fibres

Page 6: CMS Area Working  Group Meeting

14/03/2007 [email protected] 6

Very challenging task!!Planning/coordination effort on-going

ConnectCablesFrom

Patch pTo racks

On towers

Page 7: CMS Area Working  Group Meeting

14/03/2007 [email protected] 7

ID Task Name Duration Owner Contractor(s)

1546 NEAR Side 64.5 days

1547 Install HE fibre optics Near side 1 day PH-CMI HCAL

1548 Install CSC optical fibres Near Side 4 wks TS-EL MZ

1549 Install turbine Cables Near side 1 wk TS-LEA Cegelec

1550 Install gas control cables Near side 2 days TS-LEA Cegelec

1551 Start of CRIOTEC contract 0 days

1552 Install cooling/gas pipes in YE+1 towers Near side 1.2 wks TS-LEA CRIOTEC

1553 Install cooling/gas pipes in YE+2+3 towers Near side 1.2 wks TS-LEA CRIOTEC

1554 Install HV RPC YE+1 cables Near side 18 days PH-CMI Russia

1555 Install LV power & ctrl cables for subdetectors 1 wk TS-LEA Spie Cegelec

1556 Install HV CSC cables Near side 1 wk PH-CMI CSC

1557 Install DCS cables Near side 1 wk PH-CMI Russia

1558 Install safety cables (smoke) Near side 1 wk TS-CSE SOTEB

1559 Install RE Link boxes & cables Near Side 4 days PH-CMM Poland

1560 Install safety cables (RSS) Near side 2 days ? ?

1561 Install HV RPC YE+2 +3 cables Near side 2.5 days PH-CMI Russia

1562 Install mini Cable chains to YE+2 16 days

1565 Install mini Cable chains to YE+3 2 days

02/03 02/0302/03 02/03

23/03 23/0423/03 23/04

19/03 23/03

19/03 20/03

26/03

26/03 02/04

15/05 23/05

03/04 30/04

02/05 08/05

09/05 15/05

16/05 23/05

24/05 31/05

23/04 26/04

01/06 04/06

05/06 07/06

Jan Feb Mar Apr May Jun Jul AugQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007

YE+1 Draft schedule

→ TS-LEA: Criotec contract→ Behind schedule… Short notice holidays…→ More crews have been requested as from 07/05 to try and catch up→ Lack of execution drawings but lots of on site coordination

Page 8: CMS Area Working  Group Meeting

14/03/2007 [email protected] 8

YE+1: very challenging environment

Pipe, cables and fibres have to be organised

Page 9: CMS Area Working  Group Meeting

14/03/2007 [email protected] 9

ID Task Name Duration Owner Contractor(s)

1546 NEAR Side 64.5 days

1547 Install HE fibre optics Near side 1 day PH-CMI HCAL

1548 Install CSC optical fibres Near Side 4 wks TS-EL MZ

1549 Install turbine Cables Near side 1 wk TS-LEA Cegelec

1550 Install gas control cables Near side 2 days TS-LEA Cegelec

1551 Start of CRIOTEC contract 0 days

1552 Install cooling/gas pipes in YE+1 towers Near side 1.2 wks TS-LEA CRIOTEC

1553 Install cooling/gas pipes in YE+2+3 towers Near side 1.2 wks TS-LEA CRIOTEC

1554 Install HV RPC YE+1 cables Near side 18 days PH-CMI Russia

1555 Install LV power & ctrl cables for subdetectors 1 wk TS-LEA Spie Cegelec

1556 Install HV CSC cables Near side 1 wk PH-CMI CSC

1557 Install DCS cables Near side 1 wk PH-CMI Russia

1558 Install safety cables (smoke) Near side 1 wk TS-CSE SOTEB

1559 Install RE Link boxes & cables Near Side 4 days PH-CMM Poland

1560 Install safety cables (RSS) Near side 2 days ? ?

1561 Install HV RPC YE+2 +3 cables Near side 2.5 days PH-CMI Russia

1562 Install mini Cable chains to YE+2 16 days

1565 Install mini Cable chains to YE+3 2 days

02/03 02/0302/03 02/03

23/03 23/0423/03 23/04

19/03 23/03

19/03 20/03

26/03

26/03 02/04

15/05 23/05

03/04 30/04

02/05 08/05

09/05 15/05

16/05 23/05

24/05 31/05

23/04 26/04

01/06 04/06

05/06 07/06

Jan Feb Mar Apr May Jun Jul AugQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007

YE+1 Draft schedule

→ TS-LEA: Spie Cegelec contract→ In charge of on-detector cabling for both turbines and LV→ Work in YEs towers between patch panels and racks→ No proper execution drawings but supports from TS-EL and S Lusin→ Activity very much on the critical path

Page 10: CMS Area Working  Group Meeting

14/03/2007 [email protected] 10

UXC55: Racks installation

Page 11: CMS Area Working  Group Meeting

14/03/2007 [email protected] 11

ID Task Name Duration Owner Contractor(s)

926 Level X2 263 days

927 Near Side 263 days

928 Cooling plants 174 days

941 Ready for racks 0 days

942 Install racks 1 wk TS-IC-HM DBS

943 Weld racks on to structures 3.4 wks PH-CMI

944 Install racks side panels 4 wks PH-CMI

945 Equip racks with manifolds and heat exchangers 1 wk PH-CMI

946 Install ECAL cables between cooling plant and USC55/S2 2 days TS-EL Hadrelec

947 Perform pressure tests 2 days PH-CMI

948 Install LV power supply units 4 wks PH-CME

949 Install cables for turbines 2 wks TS-EL Hadrelec

950 Install cables for LV power distribution 4 wks TS-EL INEO

951 Connect and configure DSS system in USC55 4 wks PH-CMI

952 Ready for crates 0 days

29/09

02/10 06/10

30/10 21/1130/10 21/11

08/01 02/0208/01 02/02

05/02 09/0205/02 09/02

08/03 09/0308/03 09/03

26/04 27/0426/04 27/04

30/04 30/0530/04 30/05

16/05 31/0516/05 31/05

01/06 28/0601/06 28/06

08/06 05/0708/06 05/07

14/06

Jan Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007

→ TS-EL: Install cables for turbines→ Start 16/05 for 2 weeks→ Hadrelec→ Far side completed first, missing cable trays have to be installed

UXC55: Racks installation – Near side

Page 12: CMS Area Working  Group Meeting

14/03/2007 [email protected] 12

ID Task Name Duration Owner Contractor(s)

926 Level X2 263 days

927 Near Side 263 days

928 Cooling plants 174 days

941 Ready for racks 0 days

942 Install racks 1 wk TS-IC-HM DBS

943 Weld racks on to structures 3.4 wks PH-CMI

944 Install racks side panels 4 wks PH-CMI

945 Equip racks with manifolds and heat exchangers 1 wk PH-CMI

946 Install ECAL cables between cooling plant and USC55/S2 2 days TS-EL Hadrelec

947 Perform pressure tests 2 days PH-CMI

948 Install LV power supply units 4 wks PH-CME

949 Install cables for turbines 2 wks TS-EL Hadrelec

950 Install cables for LV power distribution 4 wks TS-EL INEO

951 Connect and configure DSS system in USC55 4 wks PH-CMI

952 Ready for crates 0 days

29/09

02/10 06/10

30/10 21/1130/10 21/11

08/01 02/0208/01 02/02

05/02 09/0205/02 09/02

08/03 09/0308/03 09/03

26/04 27/0426/04 27/04

30/04 30/0530/04 30/05

16/05 31/0516/05 31/05

01/06 28/0601/06 28/06

08/06 05/0708/06 05/07

14/06

Jan Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007

→ TS-EL: Install cables for LV power distribution→ Start 01/06 for 4 weeks→ INEO→ Routing to be provided by S Bally (nothing available at TS-EL)

UXC55: Racks installation – Near side

Page 13: CMS Area Working  Group Meeting

14/03/2007 [email protected] 13

YB0 project

eighth iteration

→Optimised schedule version 5:→Milestone summary: Keys date to keep in mind

Page 14: CMS Area Working  Group Meeting

14/03/2007 [email protected] 14

YB0 +Z sideID Task Name Duration

1265 +Z side 118 days

1266 Weld PP1 and ECAL fixation studs 1 wk

1267 Install water detection cable 1 day

1268 Install PP1s + HCAL source driver + laser box 3 days

1269 Perform photogrametry 1 day

1270 Install VT+ scaffolding 7 days

1271 Install Surkov platform inside VacT 1 day

1272 Install TK pipes supports 11 days

1283 Weld ECAL tubes + weld ECAL cooling fittings + pipe squeezing 12 days

1284 Install cooling pipes for TK PP1 to PP2 + insulation 4 wks

1285 Install support beam on X4 for PP2s 2 days

1286 Install PP2s 4 days

1287 Install TK cable trays (radial + outside Vac Tank) 19 days

1288 Delivery of cable trays for Sector 1 0 days

1289 Install TK cable trays for Sector 1 1 wk

1290 Delivery of cable trays for all remaining sectors 0 days

1291 Install TK cable trays for remaining sectors 2 wks

1292 Install ECAL/HCAL (TO MODULES) cable trays inside VacT 2 wks

1293 Install peripheral ECAL cable trays outside Vac Tank 1 wk

1294 Install LV ECAL cables from PP2 to towers 2 wks

1295 Install cooling pipes for TK PP2 to Plant + insulation 5 wks

1296 Install TK cables 15 days

1301 Modify scaffolding, remove Surkov platf and install enfourneur 1 wk

1302 Install 18 ECAL supermodules 14 days

1303 Remove Enfourneur 2 days

1304 EB-HB services 25 days

1314 Install TK optical fibres 1 wk

1315 Install cable/pipe channels between TK and PP1 (inside VacT) 1 wk

1316 Install TK heating wires 1 wk

1317 Install tooling for TK 5 days

1318 +Z side ready for TK insertion 0 days

1319 Insert TK 2 wks

23/03 29/03

23/03 23/03

03/04 05/04

03/04 03/04

05/04 17/04

16/04 16/04

18/04 03/05

07/05 23/05

18/04 14/05

20/04 23/0420/04 23/04

07/05 10/05

10/05 07/06

10/05

10/05 16/05

24/05

24/05 07/06

23/04 07/05

30/04 07/05

29/05 11/06

15/05 20/06

15/05 06/06

07/06 13/06

14/06 29/06

02/07 03/07

08/08 14/08

15/08 21/08

15/08 21/08

22/08 28/08

28/08

29/08 12/09

Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007

CosmiAhead of schedule

Page 15: CMS Area Working  Group Meeting

14/03/2007 [email protected] 15

YB0 +Z sideID Task Name Duration

1265 +Z side 118 days

1266 Weld PP1 and ECAL fixation studs 1 wk

1267 Install water detection cable 1 day

1268 Install PP1s + HCAL source driver + laser box 3 days

1269 Perform photogrametry 1 day

1270 Install VT+ scaffolding 7 days

1271 Install Surkov platform inside VacT 1 day

1272 Install TK pipes supports 11 days

1283 Weld ECAL tubes + weld ECAL cooling fittings + pipe squeezing 12 days

1284 Install cooling pipes for TK PP1 to PP2 + insulation 4 wks

1285 Install support beam on X4 for PP2s 2 days

1286 Install PP2s 4 days

1287 Install TK cable trays (radial + outside Vac Tank) 19 days

1288 Delivery of cable trays for Sector 1 0 days

1289 Install TK cable trays for Sector 1 1 wk

1290 Delivery of cable trays for all remaining sectors 0 days

1291 Install TK cable trays for remaining sectors 2 wks

1292 Install ECAL/HCAL (TO MODULES) cable trays inside VacT 2 wks

1293 Install peripheral ECAL cable trays outside Vac Tank 1 wk

1294 Install LV ECAL cables from PP2 to towers 2 wks

1295 Install cooling pipes for TK PP2 to Plant + insulation 5 wks

1296 Install TK cables 15 days

1301 Modify scaffolding, remove Surkov platf and install enfourneur 1 wk

1302 Install 18 ECAL supermodules 14 days

1303 Remove Enfourneur 2 days

1304 EB-HB services 25 days

1314 Install TK optical fibres 1 wk

1315 Install cable/pipe channels between TK and PP1 (inside VacT) 1 wk

1316 Install TK heating wires 1 wk

1317 Install tooling for TK 5 days

1318 +Z side ready for TK insertion 0 days

1319 Insert TK 2 wks

23/03 29/03

23/03 23/03

03/04 05/04

03/04 03/04

05/04 17/04

16/04 16/04

18/04 03/05

07/05 23/05

18/04 14/05

20/04 23/0420/04 23/04

07/05 10/05

10/05 07/06

10/05

10/05 16/05

24/05

24/05 07/06

23/04 07/05

30/04 07/05

29/05 11/06

15/05 20/06

15/05 06/06

07/06 13/06

14/06 29/06

02/07 03/07

08/08 14/08

15/08 21/08

15/08 21/08

22/08 28/08

28/08

29/08 12/09

Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007

Very aggressiveProcurement and assembly of cable trays will

drive the sequence

Target date

Page 16: CMS Area Working  Group Meeting

14/03/2007 [email protected] 16

YB0 -Z side

ID Task Name Duration

1321 -Z end 103 days

1322 Perform photogrametry 1 day

1323 Weld PP1 and ECAL ducts fixation studs 9 days

1324 Install VT- scaffolding 10 days

1325 Install water detection cable 1 day

1326 Setup enfourneur -Z side 4 days

1327 Weld ECAL tubes + weld ECAL cooling fittings + pipe squeezing 12 days

1328 Install PP2s 4 days

1329 Install 18 ECAL Super modules 22 days

1330 Lift up enfourneur to SX5 1 day

1331 Install PP1s + HCAL source driver + laser box + ECAL ducts (HB edge Vac Tank)5 days

1332 Install TK pipe supports outside Vac tank 1 wk

1333 Install HCAL layer 0 3 days

1334 Install Surkov platform inside VacT 1 day

1335 Install cooling pipes for TK PP1 to PP2 + insulation 3 wks

1336 Install radial TK cable trays (cooling + LV) outside Vac Tank 1 wk

1337 Install ECAL/HCAL (TO MODULES) cable trays inside Vac Tank 1 wk

1338 Install peripheral ECAL cable trays outside Vac Tank 1 wk

1339 Install LV ECAL cables from PP2 to towers 2 wks

1340 Install cooling pipes for TK PP2 to Plant + insulation 5 wks

1341 Install TK cables 18 days

1346 EB-HB services 22 days

1354 Install cable/pipe channels between TK and PP1 (inside VacT) 1 wk

1355 Install TK heating wires 1 wk

1356 Install TK optical fibres 1 wk

1357 Install tooling for TK 5 days

1358 -Z side ready for TK insertion 0 days

04/04 04/04

30/03 13/04

05/04 20/04

30/03 30/03

16/04 19/0416/04 19/04

07/05 23/05

11/05 16/05

23/04 21/05

22/05 22/05

17/04 23/04

27/04 04/05

23/05 25/05

29/05 29/05

15/05 06/06

31/05 06/06

31/05 06/06

30/04 07/05

23/05 06/06

07/06 11/07

07/06 02/07

02/08 08/08

02/08 08/08

15/08 21/08

22/08 28/08

28/08

Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007

Can only start once +Z complete

Slower than expected insertion

rate

Page 17: CMS Area Working  Group Meeting

14/03/2007 [email protected] 17Design by CMS Integration group, April 2005.

-Z Area installation

FIN 56 installedFew more days needed for final alignmentNext activity: Install forward beam pipe

Page 18: CMS Area Working  Group Meeting

14/03/2007 [email protected] 18

USC55 : TX54 shielding

Page 19: CMS Area Working  Group Meeting

14/03/2007 [email protected] 19

ID Task Name Duration Owner Contractor(s)

426 TX54 installation 58 days

427 Delivery of TX54 shielding wall 0 days

428 Install steel plates for TX54 sliding system 1 wk TS-LEA Workshop

429 Assemble TX54 frame and install rails 2 wks TS-LEA Pakistan

430 Create anchor points in walls and floor 2 days TS-CE Forebeton

431 Equip frame with compressed infrastructure 3 days PH-CMI

432 Concrete TX54 frame 1 day TS-CE Losinger

433 Install concrete blocks 3 days TS-IC-HM DBS

434 Install 2 remaining concrete blocks 1 day TS-IC-HM DBS

435 TX54 installed 0 days

02/04

10/04 16/04

07/05 18/05

27/04 30/0427/04 30/04

19/05 22/0519/05 22/05

23/05 23/0523/05 23/05

24/05 26/0524/05 26/05

18/06 18/0618/06 18/06

18/06

Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007

USC55 : TX54 shielding

→ Delivery from Pakistan: 30/03→ All material need to be cleared from the area→ Tremie to be opened on 07/05, implications for lowering in USC55?

→ Safety barriers at the outline of the shaft in S2 should be removed when no load is lowered. This will facilitate the flow of personnel

→ Need to fill the gap between the 2 rows of plates→ More steel plates needed→ Budget code?

Page 20: CMS Area Working  Group Meeting

14/03/2007 [email protected] 20

USC55 : Control Area – CMS Electronics S2 (-1)

Page 21: CMS Area Working  Group Meeting

14/03/2007 [email protected] 21

DSS commissioning in S2: start 10-11/05 Impact on Global run scheduled for 25/05

UPS supported

Page 22: CMS Area Working  Group Meeting

14/03/2007 [email protected] 22

USC55 : Control Area – CMS Electronics S1 (-2)

Page 23: CMS Area Working  Group Meeting

14/03/2007 [email protected] 23

Services interruption→ CV:

→ Cooling water:→ Ventilation:

→ EL:→ HV Power:→ LV Power:

→ CSE:→ Smoke detection: off in service area

→ HM:→ TAIM cranes:→ SDX5 crane:→ UXC55 crane: AT-ECR works on transfer line during W16

→ DSS:→ Tests: S1 S2 start 21-22/05

→ IT:→ Network:→ WiFi:

Page 24: CMS Area Working  Group Meeting

14/03/2007 [email protected] 24

Turbines cabinets: 2 installed 4 more to come

UPS supported

Die

se

l C

an

ali

s

New request from TK: accepted

DSS commissioning in S1: 21-22/05

Page 25: CMS Area Working  Group Meeting

14/03/2007 [email protected] 25

USC55 : CMS Electronics –Temporary Ctrl room

Partition walls erectedGeneral services doneTemporary access ctrl installedIT services installedBusy area already

Page 26: CMS Area Working  Group Meeting

14/03/2007 [email protected] 26

USC55 : Control Area – CMS Electronics S1 (-2)

Page 27: CMS Area Working  Group Meeting

14/03/2007 [email protected] 27

Turbines racks: 2nd to be installed this week

UPS supported

Die

se

l C

an

ali

s

New request from TK: acceptedMore requests are being considered

Page 28: CMS Area Working  Group Meeting

14/03/2007 [email protected] 28

Low-Voltage system

USC55 – top of bypass

Page 29: CMS Area Working  Group Meeting

14/03/2007 [email protected] 29

ID Task Name Duration Owner Contractor(s)

64 SDX5 717 days

99 Install LV room for detector 249 days PH-CME

103 Install cables for UPSs 7 wks TS-EL Hadrelec

104 Start up system UPSs 1 wk TS-EL Hadrelec

106 Install auxiliary cables for UPSs 2 wks TS-EL Hadrelec

107 Start up UPSs 1 wk TS-EL Hadrelec

108 Install network infrastructure for access control 2 wks IT-CS Hadrelec

109 PM54 733 days

230 USC55 848 days?

231 USC55 Control Area 848 days?

436 USC55 Service Area 848 days

437 Infrastructure installation 508 days

477 Top of CV Room installation 416 days

497 EL Safe Room 444 days

507 Magnet Power area 65 days

510 Install HV power connections 2 wks TS-EL Hadrelec

513 Top of Bypass 614 days

515 General services + cable trays 4.4 wks TS-EL Hadrelec

517 Install IT infrastructure 3 wks IT-CS Hadrelec

522 Cable 6 isolation power transformers 4 wks TS-EL Hadrelec

527 Sort cables for 2 LV cabinets 2.6 wks TS-EL Hadrelec

532 Install 6 TEK and 7 compensator modules in chassis 4 wks TS-EL Hadrelec

533 Install power cables from transformer to LV cabinets 4 wks TS-EL Hadrelec

534 Connect Turbine switchboard 4 wks TS-EL Hadrelec

535 Install cables from LV racks to LV cabinets 4 wks TS-EL Hadrelec

539 Install canalis for Wiener and TS racks 2 wks TS-EL Hadrelec

30/10 15/1230/10 15/12

18/12 22/1218/12 22/12

16/04 27/0416/04 27/04

30/04 07/0530/04 07/05

07/05 21/0507/05 21/05

02/04 17/0402/04 17/04

06/11 01/1206/11 01/12

08/03 26/0308/03 26/03

09/05 07/0609/05 07/06

09/05 07/0609/05 07/06

09/05 07/0609/05 07/06

08/06 05/0708/06 05/07

10/04 23/0410/04 23/04

Feb Mar Apr May Jun Jul Aug SepQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007

USC55 –LV system installation

Crucial for commissioning

Page 30: CMS Area Working  Group Meeting

14/03/2007 [email protected] 30

Installation of Magnet areaA project in itself!

→Sequence has been under intensive review

→Baseline available

→Actors from 3 departments (AT-PH-TS)

Page 31: CMS Area Working  Group Meeting

14/03/2007 [email protected] 31

16 racks

Discharge lines supports(design to be reviewed)

CP1 & CP2

DCCT

Transfer line

Cold Box

Cryo cabinets

Page 32: CMS Area Working  Group Meeting

14/03/2007 [email protected] 32

ID Task Name Duration Owner Contractor(s)

568 Install 200 control cables USC55 only 4 wks TS-EL INEO

569 Position TBT batteries 1 day AT-ECR DBS

570 Position Cryo electrical cabinets + atmospheric exchanger 1 day AT-ECR DBS

571 Reinstall false floor 3 wks TS-IC COSMI

572 Install 5 CR control cables 1 wk TS-EL INEO

573 Install metallic structures for discharge lines on top of racks 2 days PH-CME

574 Install discharge lines 5 days PH-CMI

575 Install cables between UXC55 and USC55 through wall 10 wks TS-EL INEO

576 Install false floor 1 wk TS-IC COSMI

577 Connect MSS, MCS, CDS, vacuum cables to racks 14 wks TS-EL INEO

578 Commission Magnet ctrl and safety systems 4 wks PH-CMI

579 Install scaffolding for transfer line installation 2 days AT-ECR DeMaCo

580 Install last section of Transfer lines 2 wks AT-ECR DeMaCo

581 Remove scaffolding 1 day PH-CMI MADA

582 Reinstall scaffolding 1 day PH-CMI MADA

583 Install Vacuum pipe 3 wks PH-CMI

584 Weld warm pipes to Cold box 1 wk AT-ECR DeMaCo

585 Connect water pipes to pumps 1 wk PH-CMI

586 Dismantle scaffolding for transfer line installation 1 day AT-ECR DeMaCo

587 Install instrumentation and control cables for cold box 3 wks AT-ECR Dauphelec

588 Lower and Install UPSs 2 wks PH-CMI

589 Perform synchronization tests 1 wk AT-ECR

590 Commission cold box 4 wks PH-CMI

591 Ready to start vacuum 0 days

592 Cryogenics system ready to cool down coil 0 days

26/03 24/0426/03 24/04

05/04 05/0405/04 05/04

29/03 29/0329/03 29/03

26/03 17/0426/03 17/04

10/04 16/0410/04 16/04

02/05 03/0502/05 03/05

04/05 10/0504/05 10/05

11/05 23/0711/05 23/07

24/07 30/0724/07 30/07

25/04 03/0825/04 03/08

06/08 31/0806/08 31/08

06/03 07/03

12/03 23/03

23/03 23/0323/03 23/03

18/04 18/0418/04 18/04

23/04 14/0523/04 14/05

08/05 14/05

15/05 22/05

23/05 23/05

30/03 23/04

24/05 07/0624/05 07/06

24/04 30/04

24/05 21/0624/05 21/06

31/08

21/06

Jan Feb Mar Apr May Jun Jul Aug Sep Oct NovQtr 1, 2007 Qtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007

USC55- Magnet area

→PH-CMI: Install support structure for transfer lines→No coactivity possible in the same area

Page 33: CMS Area Working  Group Meeting

14/03/2007 [email protected] 33

New items where scheduling effort is needed

Design by CMS Integration group, April 2005.

Areas where more scheduling effort is needed

Page 34: CMS Area Working  Group Meeting

14/03/2007 [email protected] 34

Very preliminary scheduleID Task Name Duration

896 UXC55 963 days?

1050 -Z side 912 days?

1128 CMS 912 days?

1200 YBs -Z side 845 days

1202 Lower Barrel YB-1 2 days

1203 Install YB-1 in temporary position 1 day

1204 Lower Barrel YB-2 2 days

1205 Install 8 missing muon chambers YB-1 3 days

1206 Install 8 missing muon chambers YB-2 3 days

1207 Position Barrel YB-1 on YB0 2 days

1208 Connect Patch Panel on YB-1 (mechanics) 1 day

1209 Position Barrel YB-2 2 days

1210 Connect Patch Panel on YB-2 (mechanics) 1 day

1211 Close Barrel wheels 2 days

1213 YEs -Z side 36 days

1214 Lower End Cap YE-1 1 day

1215 Move YE-1 out of shaft area 2 days

1216 Connect Patch Panel on YE-1 (mechanics) 2 days

1217 Lower End Cap YE-2 1 day

1218 Position YE-2 against YE-1 temporary 1 day

1219 Lower End Cap YE-3 1 day

1220 Position YE-3 against FIN 1 day

1221 Move YE-1 against barrel 2 days

1222 Chim and align YE-1 2 days

1223 Beam pipe 20 days

1224 Install central beam pipe 4 wks

1227 YB0 area 897 days

1265 YBO Services installation (under construction) 897 days

1266 +Z side 120 days

1319 +Z side ready for TK insertion 0 days

1320 Insert TK 12 days

1326 Connect TK to PP1 30 days

11/06 12/0611/06 12/06

13/06 13/0613/06 13/06

21/06 22/0621/06 22/06

25/06 27/0625/06 27/06

28/06 02/0728/06 02/07

22/08 23/0822/08 23/08

22/08 22/0822/08 22/08

24/08 27/0824/08 27/08

24/08 24/0824/08 24/08

27/08 28/0827/08 28/08

29/08 29/0829/08 29/08

17/09 18/09

19/09 20/0919/09 20/09

19/09 19/0919/09 19/09

20/09 20/0920/09 20/09

21/09 21/0921/09 21/09

24/09 24/0924/09 24/09

15/10 16/10

17/10 18/10

17/09 12/10

28/08

29/08 14/09

01/10 09/11

Apr May Jun Jul Aug Sep Oct Nov Dec JanQtr 2, 2007 Qtr 3, 2007 Qtr 4, 2007 Qtr 1, 2008

Position against YB0 once scaffolding

removed

Lot more work

needed

Page 35: CMS Area Working  Group Meeting

14/03/2007 [email protected] 35

Detailed studies on going….Dates are not relevant the focus is on the sequence

ID Task Name Duration

1367 CMS closure 118 days

1368 YBs positioned on YB0 0 days

1369 Central beam pipe installed 0 days

1370 Install intermediate beam pipe on -Z 2 days

1371 Install Pixel detector 4 wks

1372 Install BCM 1 wk

1373 Position YEs against YBs 1 wk

1374 Rise HFs 2 wks

1375 CMS closed and ready for Cosmics 0 days

1376 Perform Cosmic data taking 2 wks

1377 EE installation 31 days

1378 Delivery of 2nd D for EE 0 days

1379 Open YEs 3 days

1380 Install 1st D on -Z Far side 1 wk

1381 Install 2nd D on -Z Near side 1 wk

1382 Close CMS 3 days

1383 1st EE installed on -Z side 0 days

1384 Perform Cosmic data taking 2 wks

28/08

12/10

15/10 16/10

17/10 13/11

14/11 20/11

21/11 27/11

28/11 11/12

11/12

12/12 25/12

17/12

07/01 09/01

10/01 16/01

17/01 23/01

24/01 28/01

23/01

29/01 11/02

Jul Aug Sep Oct Nov Dec Jan Feb Mar AprQtr 3, 2007 Qtr 4, 2007 Qtr 1, 2008 Qtr 2, 2008

→Areas where more work in needed to understand the sequence