cmpc project cok+fbl – 1 st align meeting august, 6 - 2013
TRANSCRIPT
CMPC ProjectCOK+FBL – 1st Align Meeting
August, 6 - 2013
© Metso2
CMPC Project - COK+FBL 1st Align MeetingAgenda
1. Scope of Supply
2. Project organization
3. Time schedule
4. Milestones – first critical 90 days
5. Project manpower chart – whole project
6. What’s new ?a) Is anything bigger than ever running before ?b) Has anything been redesigned from anything running ?c) Is anything brand new and never been running ?
7. Are there any open scope issues remaining ?
© Metso3
CMPC Project - COK+FBL 1st Align MeetingScope of Supply
• Cooking: 5.100 ADMt/d
Two vessel steam-liquor phase
digester for Concurrent
Compact Cooking™ G2 (CoC G2);
• Fiberline: 4.750 ADt/d
O2 - Dht – EP- D1,
bleaching sequence;
EPC Project, including the core and non core equipment, installation materials, supervision and site works as MEI erection, commissioning and start up.
© Metso4
CMPC Project - COK+FBL 1st Align MeetingScope of Supply
DC
S +
AP
C +
OT
S
© Metso5
CMPC Project - COK+FBL 1st Align Meeting Project Organization - Araucária
© Metso 2013-05-29 T. Jacobsson6
Support functions-technical
TECHNOLOGY MANAGER – NA
INSTALLATION ENGINEER - NA
SPARE PARTS ENGINEER – Susanne Sandgren
PROJECT MANAGER
Torbjörn Jacobsson
START UP MGR - NA
TRAINING MGR - Mona BergströmSITE MANAGER - NA
PROCESS CONTROL
Rune Lindström
EL & INSTRUMENT
Peter Dahlin
TANK & VESSEL
Stefan G Jonsson
PLANT DESIGN
Tommy H Karlsson
MACHINE DESIGN
NA
HSEQ coordinator
Niklas Castenäs
PROCESS DESIGN
Jörgen Tegner
(Andreas Engelfeldt)
Support functions-administration
PROJECT SECRETARY – Carin Öberg
CUSTOMER DOCUMENTATION ENG. – Marie Almkvist
PROJECT PURCHASE MGR – Fredrik Åström
QC MANAGER. – Peter Strömberg
FORWARDER – TBN
PROJECT SCHEDULER – NA
COST CONTROLLER - NA
Lead Project Engineer Team
CMPC Project - COK+FBL 1st Align Meeting Project Organization - Sundsvall
© Metso 2013-05-29 T. Jacobsson7
CMPC Project - COK+FBL 1st Align Meeting Project Organization - Karlstad
Support functions-technical
TECHNOLOGY MANAGER – Recaust Magnus Ingelman
Cooking: Jonas Saetheråsen
INSTALLATION ENGINEER – Mattias Carlsson
SPARE PARTS ENGINEER – Truls Snedsböl
PROJECT MANAGER
Jan-Åke Larsson
LPE
EL & INSTRUMENT
Cooking Gunnar Rutquist
Recaust Tommy Höök
LPE
TANK & VESSEL
Kenneth Persson
LPE
PLANT DESIGN
Stefan Wessmark
QEHS coordinator
Carina Törngren
LPE
PROCESS DESIGN
Cooking: Jonas Saetheråsen
Recaust Magnus Ingelman
Project Team
START UP MGR -
TRAINING MGR - Mona BergströmSITE MANAGER –
Support functions-administration
PROJECT SECRETARY – Carin Sonesson
CUSTOMER DOCUMENTATION ENG. – Catarina Melin/Ann Arnell
PROJECT PURCHASE MGR – Cooking – Greger Andersson
Recaust - Sten Leandersson
TECHNICAL PURCHASE SUPPORT – Anders Holmberg
QC MANAGER. – Stefan Bergman
FORWARDER – Margareta Sjöman
PROJECT SCHEDULER – Fredrik Sundell
PROJECT CONTROLLER – Anna Gydemo-Berg
© Metso8
CMPC Project - COK+FBL 1st Align Meeting Time Schedule
Digester and Impbin Manufac. Sep.2013
Civil Work Aug.2013
Start UpMay 2015
Erection Start Jan.2014
CommissioningFeb. 2015
© Metso9
CMPC Project - COK+FBL 1st Align Meeting Time Schedule
Project schedule
• 03/May/2013 Contract effective date
• 18/Aug/2013 Site establishment 22/Jul/2013
• 18/Sep/2013 Civil Works 09/Aug/2013
• 18/Jan/2014 Start of erection works
• 18/Jun/2014 Electrical Room Release
• 03/Oct/2014 FAT start date
• 30/Oct/2014 Power on (electrical room)
• 03/Jan/2015 Training
• 03/Jan/2015 DCS loaded
• 03/Feb/2015 Comissioning phase
• 03/Feb/2015 Digester Hydrotest
• 03/May/2015 ECA / Start-up
© Metso10
CMPC Project - COK+FBL 1st Align Meeting General – S Curve
Jun/13 Jul/13 Ago/13 Sep/13
Prev. 1,67 1,96 2,14 2,33
Real. 1,67 1,98
© Metso11
CMPC Project -COK+FBL 1st Align MeetingMilestones, first critical 90 days
Engineering
• Kick off meetings with CMPC & with Metso's technology center
• Flowsheet and Lay-out in advanced status;
• Finish specifications for all core equipment, towers & tanks, pumps, ejectors, agitators, heat exchangers, electrical system are completed;
• Engineering documentation according to App.4
• Started Piping Detail Engineering;
• Time schedule in approving phase;
•Soil investigation – civil engineering on going
© Metso12
CMPC Project - COK+FBL 1st Align Meeting Milestones, first critical 90 daysProcurement - Purchase process completed
• Core equipment: Digester, ImpBin, HPF, Twinroll Presses, Mixers, MC Pumps
• Main Tanks & Towers
• Steel Structure;
• Electrical system;
• Civil Engineering & Construction;
• Plant Design Engineering
• Centrifugal pumps
Civil Construction Steel Structure
Tanks & Towers Tanks & Towers
Tanks & Towers
Plant Design
Presses & Mixers
Electrical system
© Metso13
Sweden
ShanghaiShanghai
Zhongshan
+ Mixers+ Pulp Distributor TMC-60+ Flow Scrapers SA+ DeltaCombi DC16
Vadodara
+ Liquor Screen L8+ Delta Screens D10 e D4+ Coarse Screen KFA-75+ Tail Screen TS-75+ Delta Knotter K8
RS
Steel Structures
RS
ES
RS
ES
PR
Centrifugal pumps
© Metso14
CMPC Project - COK+FBL 1st Align MeetingMilestone, first critical 90 days
IntecnialMetso Sundsvall
Nova JVA KingSun
Morimatsu
Imetame
© Metso15
CMPC Project - COK+FBL 1st Align MeetingProject manpower chart – Site Activities
Peak: 1000 p
© Metso16
CMPC Project - COK+FBL 1st Align Meeting What’s new ?
MC PumpCM 4030
© Metso17
CMPC Project - COK+FBL 1st Align Meeting Are there any open scope issues remaining ?