CAPABILITY MATURITY MODEL

for Software (CMM) Version 1.1

Maturity Level – 2 (Repeatable Level)Maturity Level – 2 (Repeatable Level)

Page 2: Cmm Level2

Characteristics of Level2 Characteristics of Level2 organizationsorganizations

• Planning and managing projects is based on experience with similar projects

• Software project management processes are documented and followed

• Organizational policies guide the projects in establishing management processes

• Successful practices developed on earlier projects can be repeated

• Data available are primarily related to size, effort and schedule which are shared across projects through informal practices

Page 3: Cmm Level2

Key process areas - level 2Key process areas - level 2

Requirements management (RM)Requirements management (RM)

Software project planning (SPP)Software project planning (SPP)

Software project tracking and oversight (SPTO)Software project tracking and oversight (SPTO)

Software subcontract management (SSCM)Software subcontract management (SSCM)

Software quality assurance (SQA)Software quality assurance (SQA)

Software configuration management (SCM)Software configuration management (SCM)

Page 4: Cmm Level2

Requirements ManagementRequirements Management

Purpose Establish a common understanding between

customer requirements and software project This agreement with the customer is the basis for

planning the software project. Following an effective change control process

RM involves Document and control of customer requirements

(technical and non-technical) Keeping plans, products, and activities consistent

with the requirements Reviewing the initial and revised system requirements

allocated (Note : customer can be system engineering group,

marketing group, another internal organization, or an external organization.)

Page 5: Cmm Level2

RM Goals & ActivitiesRM Goals & Activities

• Goal 1 - allocated requirements are controlled to establish baseline– Software engineering group reviews allocated

requirements before they are incorporated into the project

• Goal 2 - software plans, products, activities are kept consistent with the allocated requirements – Software engineering group uses the allocated

requirements as the basis for software plans, work products and activities.

– Changes to the allocated requirements are reviewed and incorporated into the software project

Page 6: Cmm Level2

RM Common FeaturesRM Common Features

• Commitment Written organizational policy for managing system

requirements• Ability

For each project, responsibility is established for analyzing documenting requirements

Allocated requirements are documented Adequate resources and funding are provided for

managing the allocated requirements Members of the software engineering group and other

software related groups are trained to perform their RM activities

• Measurements Measurements are made and used to determine the

status of the activities for managing the allocated requirements

Page 7: Cmm Level2

Software Project PlanningSoftware Project Planning

• Purpose is to establish reasonable plans for performing the software engineering and for managing the software project

• Involves– Developing estimates(size, cost, effort, schedule &

resources) for the work to be performed– Establishing the necessary commitments– Defining the plan to perform the work– Using the plan as the basis for performing and

managing project’s activities– Assessing the risks

Page 8: Cmm Level2

SPP Common FeaturesSPP Common Features

• Commitments– A project software manager is designated to be

responsible for project activities– Written organizational policy for planning a software

project• Ability

– Approved statement of work– Responsibilities for developing software

development plan– Resources and funding– Training on software estimation and planning

• Measurements– To determine status of activities pertaining to

software planning

Page 9: Cmm Level2

SPP Goals & ActivitiesSPP Goals & Activities

• Software estimates are documented for use in planning and tracking of software projects.– Estimates for size (or changes to size), effort and

cost, critical computer resources, software schedule are derived according to a documented procedure.

– Software planning data are recorded.• Software project activities and commitments are

planned and documented.– Project planning is initiated in the early stages– A software life cycle with predefined stages of

manageable size is defined– Software development plan is defined according to a

documented procedure and documented– Software work products are identified

Page 10: Cmm Level2

SPP Goals & ActivitiesSPP Goals & Activities

• Software project activities and commitments are planned and documented.– Risks associated with cost, resource, schedule and

technical aspects of the software project are identified, assessed and documented.

– Plan for software engineering facilities and support tools are prepared

• Affected groups and individuals agree to their commitments Related to the software project.– Software engineering group participates in the

project proposal team and with other groups in the overall project planning.

– Project commitments made to individuals and groups external / internal to the organization are reviewed with senior management according to a documented procedure

Page 11: Cmm Level2

Software Project Tracking Software Project Tracking and Oversightand Oversight

• Purpose is to provide adequate visibility into actual progress so that management can take effective actions when performance deviates significantly from the plan.

• Involves– Tracking and reviewing software accomplishments

and results against documented estimates, commitments, and plans.

– Adjusting plans based on actual accomplishments and results.

– When plans are not being met, take corrective actions by re-planning or taking actions to improve the performance

Page 12: Cmm Level2

SPTO - Common FeaturesSPTO - Common Features• Commitment

– Project software manager is designated to be responsible for the projects activities and results.

– Written organizational policy for managing software projects

• Ability– Software development plan is documented and

approved– Responsibility for every work product is assigned

explicitly– Resources and funding for tracking– Training on technical and personnel on software

project– Orientation on technical aspects of the project for

software managers.• Measurements

– To determine the status of project tracking activities

Page 13: Cmm Level2

SPTO Goals & ActivitiesSPTO Goals & Activities• Actual results and performances are tracked against the

software plans.– A documented SDP is used– The size of the work product, effort and cost, critical

computer resources, software schedule, software engineering and technical activities are tracked and corrective action taken when necessary.

– Risks associated with cost, resource, schedule and technical aspects are tracked

– Actual measurement data and re-planning data are recorded

– Software engineering group conducts periodic internal reviews and track technical progress, plan, performance, and issues against the software development plan.

– Formal reviews to address the accomplishments and results of the project are conducted at selected project milestones according to a doc.Proc

Page 14: Cmm Level2

• Corrective actions are taken and managed to closure when actual results and performance deviate significantly from the software plans.– The project’s software development plan is revised – The size of the work products, changes to size, effort and

costs, critical computer resources, software schedule and engineering technical activities are tracked and corrective actions are taken as necessary.

– Actual measurement data and re-planning data for the software project are recorded.

• Changes to software commitments are agreed to by the affected groups and individuals.– Software project commitments and changes to commitments

made to individuals and groups external to the organization are reviewed with senior management

– Approved changes to commitments that affect the software project are communicated to the members of the SEG and other software related groups.

SPTO Goals & ActivitiesSPTO Goals & Activities

Page 15: Cmm Level2

• Changes to software commitments are agreed to by the affected groups and individuals.– Software project commitments and changes to

commitments made to individuals and groups external to the organization are reviewed with senior management according to a documented procedure.

– Approved changes to commitments that affect the software project are communicated to the members of the software engineering group and other software related groups.

SPTO Goals & ActivitiesSPTO Goals & Activities

Page 16: Cmm Level2

Software S/C ManagementSoftware S/C Management

• Purpose is to select qualified software subcontractors and manage them effectively

• Involves– Selecting a software subcontractor.– Establishing plans, requirements , standards and

commitments with the subcontractor.– Tracking and reviewing the subcontractor’s

performance and result.– Managing a software sub contractor and managing the

software component that is sub contracted which includes software and hardware.

– Performing tracking and oversight activities for the subcontracted work.

– Ensuring that the software products delivered by the subcontractor satisfy the acceptance criteria.

Page 17: Cmm Level2

SSM - Common FeaturesSSM - Common Features

• Commitment– Written organizational policy for managing the

software sub contract.– A sub contract manager is designated to be

responsible for establishing and managing the software sub contract.

• Ability– Adequate resources and funding– Training for those who manage sub contract activity

on performing sub contract related activities and technical aspects.

• Measurements– To determine the status of the activities for

managing the software sub contract.

Page 18: Cmm Level2

SSM - ActivitiesSSM - Activities

• The prime contractor selects qualified software sub contractors– The work to be sub contracted is defined and planned

according to a documented procedure.– The software subcontractor is selected, based on an

evaluation of the subcontract bidders’ ability to perform the work, according to a documented procedure.

• The prime contractor and the software subcontractor agree to their commitments to each other– The contractual agreement between the prime

contractor and the software subcontractor is used as the basis for managing the subcontract.

– A documented subcontractor’s software development plan is reviewed and approved by the prime contractor

Page 19: Cmm Level2

• Prime contractor and the software subcontractor agree to their commitments to each other.– Changes to the software subcontractor’s statement

of work, subcontract terms and conditions and other commitments are resolved according to a documented procedure

• The prime contractor and the software subcontractor maintain ongoing communications.– The prime contractor's management conducts

periodic status/ coordination reviews with the software subcontractor’s management

– Periodic technical reviews and interchanges are held with the software subcontractor.

SSM - ActivitiesSSM - Activities

Page 20: Cmm Level2

Software Quality AssuranceSoftware Quality Assurance

• Purpose is to provide management with appropriate visibility into the process being used and the products being built.

• Involves– Establishing a quality assurance group who has

required independence.– Participation of SQA in establishing the plans,

standards and procedures for the project. – Reviewing and auditing the software products and

activities to ensure that they comply with the applicable procedures and standards.

– Providing the software project and other appropriate managers with the results of those reviews and audits.

– Escalating unresolved issues to an appropriate level of management.

Page 21: Cmm Level2

SQA - Common FeaturesSQA - Common Features

• Commitment– Written organizational policy for implementing software

quality assurance• Ability

– A group that is responsible for coordinating and implementing SQA for the project exists

– Adequate resources and funding– Members of SQA group are trained to perform their SQA

activities.– Orientation to members of the projects on SQA activities

and roles and responsibilities• Measurement

– To determine the status, cost and schedule of SQA activities.

• Verification– Experts independent of the SQA group periodically review

the activities of SQA group

Page 22: Cmm Level2

SQA Goals & ActivitiesSQA Goals & Activities• Software quality Assurance activities are planned

– A SQA plan is prepared for the software project according to a documented procedure.

– The SQA group’s activities are performed in accordance with the SQA plan.

• Adherence of software products and activities to be applicable standards, procedures, and requirements is verified objectively.– The SQA group’s activities are performed in accordance

with the SQA plan– The SQA group participates in the preparation and review of

the project’s software development plan, standards and procedures.

– The SQA group reviews the software engineering activities to verify compliance

– The SQA group audits designated software work products to verify compliance.

Page 23: Cmm Level2

SQA Goals & ActivitiesSQA Goals & Activities

• Affected groups and individuals are informed of software quality assurance activities and results.– The SQA group periodically reports the results of its

activities to the software engineering group.– Deviations identified in the software activities and

software work products are documented and handled according to a documented procedure.

– The SQA group conducts periodic reviews of its activities and findings with customers SQA personnel, as appropriate.

Page 24: Cmm Level2

Software Configuration Software Configuration ManagementManagement

• Purpose is to establish and maintain the integrity of the products of the software project throughout the software life cycle.

• Involves– Establishing a group for managing configuration

management activities for a project.– Identifying configuration items/units.– Establishing baselines as they are developed.– Systematically controlling changes through change

control and baseline audits.– Maintaining integrity and traceability of the

configuration throughout the software life cycle.

Page 25: Cmm Level2

SCM Common FeaturesSCM Common Features

• Commitment– A written organizational policy for implementing

SCM.• Ability

– A software configuration control board exists.– SCM group for a project exist– Adequate resources and funding– Training to SCM group on objectives, procedures

and methods of performing SCM activities.– Training to software engineering group to perform

SCM activities• Measurements

– To determine the status of the SCM activities

Page 26: Cmm Level2

SCM Goals & ActivitiesSCM Goals & Activities

• Software configuration management activities are planned.– A SCM plan is prepared for each software project according to

a documented procedure. (Part of SDP in Tarang)– A documented and approved SCM plan is used as the basis

for performing the SCM activities.• Selected software work products are identified, controlled,

and available.– A documented and approved SCM plan is used as the basis

for performing the SCM activities.– A configuration management library system is established as

a repository for the software baselines.– The software work products to be placed under configuration

management are identified.– Products from the software baseline library are created and

their release is controlled according to a documented procedure

Page 27: Cmm Level2

SCM Goals & ActivitiesSCM Goals & Activities

• Changes to identified software work products are controlled.– Change requests and problem reports for all configuration

items/units are initiated, recorded, reviewed, approved, and tracked according to a documented procedure.

– Changes to baselines are controlled according to a documented procedure.

• Affected groups and individuals are informed of the status and content of software baselines.– The status of configuration items/units is recorded according

to a documented procedure.– Standard reports documenting the SCM activities and the

contents of the software baseline are developed and made available to affected groups and individuals.

– Software baseline audits are conducted according to a documented procedure.

Page 28: Cmm Level2

End of Repeatable Level (L2) KPAsEnd of Repeatable Level (L2) KPAs