CLINTON KEITH ROADURBAN ARTERIAL
EXTENSION PROJECT
(Whitewood Road to Leon Road)
![Page 2: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/2.jpg)
Building a 4 Lane Urban Arterial With Ultimate Buildout to 6 Lanes as Funds Become Available
Improvements Between Whitewood Road and Leon Road
Contract Bid Amount: $23,441,273
Construction Starts March 2016
Work Will Continue For 18 to 24 Months Weather Permitting
![Page 3: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/3.jpg)
![Page 4: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/4.jpg)
![Page 5: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/5.jpg)
![Page 6: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/6.jpg)
![Page 7: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/7.jpg)
![Page 8: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/8.jpg)
Wildlife Crossing
![Page 9: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/9.jpg)
![Page 10: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/10.jpg)
County workforce completed grading for Edison pole relocation during Fall of 2015
Edison relocation work has started and will continue during construction of the road.
![Page 11: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/11.jpg)
LIVE GOATS were being used
as an environmentally
friendly way to clear
vegetation within the project
limits
This method reduced the
impacts to the community
while also encouraging birds
to nest in other locations
Goats completed their task
in March 2016.
![Page 12: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/12.jpg)
Sukut Construction – Santa Ana, CA
18 to 24 Month Construction Schedule
Work hours 7 am – 6 pm M-F
◦ No weekend work anticipated at this time
![Page 13: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/13.jpg)
Access will be provided for residents via Greenberg Place, Arendt Lane, AvenidaManana
Roads will be graded at Arendt Lane and Greenberg Place to provide access to Whitewood Road (signalized intersection)
Local residents will have access to Los Alamos via Menifee Road
![Page 14: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/14.jpg)
![Page 15: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/15.jpg)
A portion of the job may require the
contractor to perform blast excavation
Similar process was used on SR-79 in the
Winchester area
Emergency responders will be positioned
during blast operations to reduce response
time
Notices will be distributed to the school and
residents prior to each blast event
![Page 16: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/16.jpg)
Stakeholders / First Responders, School District Transportation and local transit were briefed prior to the utility relocation work
Public meetings were held prior to the start of construction
Regular meetings / briefings will be held as necessary to keep all apprised of project milestones
Ongoing coordination will take place between the City of Murrieta, the County of Riverside, School District Management, and Emergency Services
![Page 17: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/17.jpg)
Website RCProjects.org will be updated and maintained
Collateral material will be distributed to communities impacted by the project
Hotline number 877-672-7765 will be distributed
All calls will be returned by the close of the next business day
Project information will be disseminated to local media
![Page 18: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/18.jpg)
Slow Down!
Obey Speed Laws
Allow Extra Time for Commute
Pay Attention to Construction Signs
Obey the Directions of the Flaggers
Visit rcprojects.org
Toll Free Hotline 877-672-7765
![Page 19: CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECTrcprojects.org/wp-content/uploads/2016/04/Clinton_Keith... · CLINTON KEITH ROAD URBAN ARTERIAL EXTENSION PROJECT (Whitewood Road](https://reader031.vdocuments.mx/reader031/viewer/2022022607/5b86b88d7f8b9a8f318d12b1/html5/thumbnails/19.jpg)
Thank you!