CLIC TBM Prototype T0@CLEX Integration. Inventory. Planning Report - March 2014. Dmitry Gudkov. CONTENTS. 2D layout Inputs Supporting elements for CLEX components in the working area Integration Inventory Integration of TBM and modification of CLEX components. Drive beam - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

1[19-Mar-2014] «BE/RF»

CLIC TBM Prototype T0@CLEX

Integration. Inventory. Planning

Report - March 2014

Dmitry Gudkov

1

Page 2: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

2[19-Mar-2014] [CMWG Meeting] «BE/RF» 2

CONTENTS

2D layout

Inputs

Supporting elements for CLEX components in the working area• Integration• Inventory

Integration of TBM and modification of CLEX components. Drive beam

Integration of TBM and modification of CLEX components. Probe beam

Inventory of the CLEX components (working area, preliminary)

Status of components production for TBM

Planning for the TBM installation in CLEX

Documentation

Page 3: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

3[19-Mar-2014] [CMWG Meeting] «BE/RF» 3

TBM Prototype T0@CLEX. 2D Layout. Phase 1M

odul

e bo

rder

Module border

• 1 PETS and 1 SAS will be powered;• VGVs are installed on each extremity to

detach the test stand;• Engineering design and integration of

primary RF network is required.

2D layout is based on one presented by Igor on 3.04.2013LINK

Page 4: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

4[19-Mar-2014] [CMWG Meeting] «BE/RF» 4

INPUTS. Integration of TBM. Probe beam

3D model is based on the document prepared by Wilfrid Farabolini: EDMS 1366387

Are implemented in the drawing CLIATCIN0005 (under way):

Page 5: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

5[19-Mar-2014] [CMWG Meeting] «BE/RF» 5

INPUTS. Integration of TBM. Drive beam

Positions of the quadrupoles, input from Jacob Esberg: EDMS 136638821.33596587 '"QUADRUPOLE"' '"TL2.QDD10"' 0.575 UNCHANGED23.29201587 '"QUADRUPOLE"' '"CM.QFD0310"' 1.95605 UNCHANGED23.79201587 '"QUADRUPOLE"' '"CM.QDD0315"' 0.5 UNCHANGED24.29201587 '"QUADRUPOLE"' '"CM.QFD0320"' 0.5 UNCHANGED25.90225587 '"RFCAVITY"' '"P1"' 1.61024 UNCHANGED27.98793587 '"QUADRUPOLE"' '"CM.QFD0565A"' 2.08568 Has been increased28.39727587 '"QUADRUPOLE"' '"CM.QFD0565B"' 0.40934 Has been decreased

29.961016 '"RFCAVITY"' '"P2"' 1.56374 has been increased30.428016 '"QUADRUPOLE"' '"QTB1"' 0.467 0.467 As specified30.965016 '"RFCAVITY"' '"P3"' 0.537 0.537 As specified31.432016 '"QUADRUPOLE"' '"QTB2"' 0.467 0.467 As specified

33.19201587 '"QUADRUPOLE"' '"CM.QFD0560"' 1.76 1.76 As specified34.19201587 '"QUADRUPOLE"' '"CM.QFD0570"' 1 UNCHANGED37.19399775 '"RBEND"' '"CM.BHB0600"' 3.001982 UNCHANGED

Are implemented in the drawing CLIATCIN0005 (under way):

Page 6: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

6[19-Mar-2014] [CMWG Meeting] «BE/RF» 6

TBM implantation in CLEXTask Duration Date

1 Remove the safety barriers 0.5 days 1.06

2 Preparation of the storage tables inside CLEX 0.5 days 1.06

3 Radioprotection Survey Visit 1 day 2.06

4 Dismantling of the shielding blocks (to get the direct access for new equipment)

1 day 2.06

5 Organizing of free access to CLEX building 1day 3.06

storage

Page 7: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

7[19-Mar-2014] [CMWG Meeting] «BE/RF» 7

TBM implantation in CLEXTask Duration Date

6 Dismantling of TBTS PB and DB tanks- disconnection of electrical cables and water pipes

- disconnection and dismantling of RF network

6.5 days 02.0610.06

Page 8: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

8[19-Mar-2014] [CMWG Meeting] «BE/RF» 8

TBM implantation in CLEXTask Duration Date

7 - dismantling and transport of the TBTS PB Tank to the buffer zone 1 day 09.06

Page 9: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

9[19-Mar-2014] [CMWG Meeting] «BE/RF» 9

TBM implantation in CLEXTask Duration Date

8 - dismantling and transport of the TBTS DB Tank and transport to the storage

1 day 10.06

Page 10: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

10[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

9 - Disconnection of all cables (+ labelling) and pipes in the working area

4.5 days 11.0617.06

~14 meters

Page 11: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

11[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

10 - Removal of the equipment in the working area 4 days 12.0618.06Component Pic Quantity Component Pic Quantity

Quadrupoles 12 Supports 10

Correctors 10Sector

vacuum valves 4

BPMs and diagnostics chambers

8

Pumping ports

(including valves and

pumps)

5

Flashbox 1 Drift Tubes and bellows 20 + 22

Page 12: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

12[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

11 - Dismantling of the yellow girders and feet 3 days 18.0623.06

12 - Removal of the cooling distribution (central line) 3 days 23.0626.06

13 - Precise Floor marking before drilling of the holes for installation of the TBM supporting system: 32 holes in total

For dimensions: DRAWING CLIATCIN0004

1.5 days 26.0627.06

14 Drilling of the floor for all the supporting equipment 1.5 days 30.0601.07

Task Quantity

Feet to be removed from area 6

Feet to be replaced 2

Girders to be removed from area 6

Girders to be replaced 6

New girders to be manufactured(see on next slides)

3

Page 13: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

13[19-Mar-2014] [CMWG Meeting] «BE/RF»

Supporting Elements for TBM and CLEX Components

2 Feet to be reused in different place (8 holes to be drilled)

New girders (x3)

TBM supporting benches (24 holes to be drilled for installation)

• All green feet will not be moved• Green girders will be moved by several cm.

Page 14: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

14[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

15 - VACATIONS period time reservation 30 days 01.0731.07

16 - Installation of the supporting elements of the TBM and CLEX components

Installation of the new yellow supporting girders (1 day) Transport and Installation of the TBM extremity benches (1 day) Geometrical control of the extremity benches (3 days)

5 days 01.0807.08

17 - TBM installation and assemblySee next slides

26 days 08.0812.09

Page 15: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

15[19-Mar-2014] [CMWG Meeting] «BE/RF»

Installation of the TBM supporting system

Task Duration Date18 Installation of the TBM supporting system 5 days 08.08-14.0819 Geometrical control of the TBM supporting system 3 days 15.08-19.0820 Alignment of the girders (with respect to the existing beam) 1 day 20.0821 Installation of alignment’s device (wire, cable, sensors, data acquisition, …) 2 days 21.08-22.0822 Absolute measurement (cWPS sensors vs AT401 tracker) 1 day 25.0823 Test of actuators displacement on 1 mm range (girder unloaded) 1 day 26.0824 Test of the Articulation Point (girder unloaded) 1 day 27.08

Page 16: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

16[19-Mar-2014] [CMWG Meeting] «BE/RF»

Installation of the components of the TBM + alignment control

Task Duration Date25 Installation of the components of the TBM + alignment control + cooling test 5 days 28.08-03.0926 Cables for TBM routing and connection to the equipment in the external shelter 2 days 04.09-05.0927 Test of actuators displacement on 1 mm range (girder loaded) 1 day 08.0928 Test of the Articulation Point (girder loaded) 1 day 09.0929 Scanner 3D of the module 3 days 10.09-12.09

Page 17: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

17[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

30 Primary RF Network installation• Installation of the RF components on the TBTS tank (2 days)• Installation of the waveguides between TBTS tank and TBM Including supports, pumping port etc. (1 day)

3 days 28.0801.09

Page 18: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

18[19-Mar-2014] [CMWG Meeting] «BE/RF»

TBM implantation in CLEXTask Duration Date

31 Installation of CLEX components according to new configuration (not all the components are listed below, +5..10 components, final inventory under way)

12.5 days 04.0820.08

Component Pic Quantity Component Pic Quantity

Quadrupoles 12 Supports 18

Correctors 8Sector

vacuum valves 4

BPMs and diagnostics chambers

9

Pumping ports

(including valves and

pumps)

5

Flashbox 1 Drift Tubes and bellows 24 + 26

Page 19: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

19[19-Mar-2014] [CMWG Meeting] «BE/RF»

CLEX working area after installation of components

Page 20: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

20[19-Mar-2014] [CMWG Meeting] «BE/RF»

Final tests and cables reconnection

Task Duration DateLeaktightness test 2 days 15.09-16.09Final alignment tests 3 days 17.09-19.09Reconstruction of cable trays and cables pulling 5 days 17.09-23.09Reconnection of all cables (according to labelling) and pipes in the working area 2 days 24.09-25.09

Cooling system test 2 days 26.09-29.09Closing the shielding 1 day 15.09Safety chain test 1 day 30.09Commissioning 5 days 01.10-07.10

Page 21: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

21[19-Mar-2014] [CMWG Meeting] «BE/RF»

Status of components. TBM

Component Design Production Status Exp.

3D % 2D % Parts % Assembly

SAS 100 100 100 Brazing Mar’14

PETS 100 100 100 100 done

RF Network waveguides 100 100 100 brazing Apr’14

DB BPM 100 100 100 50 Apr’14

Vacuum minitanks and equipment 100 100 100 100 done

Vacuum drift tubes 100 100 0 0 Apr’14

RF Loads 100 100 Production, Ext. Comp. done

Directional Couplers 100 100 Production, Ext. Comp. done

Cooling tubes/fittings 100 90 0 - done

Supporting system 100 100 Test is under way done

U-clamps 100 100 50 0 Apr’14

Standard Supporting Frames 100 100 100 80 Apr’13

TBM ASSEMBLY May’13

Page 22: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

22[19-Mar-2014] [CMWG Meeting] «BE/RF»

Status of components. TBM. Primary RF Network

Component Design Production Status Expected

3D % 2D % Parts % Assembly

RF Network waveguides 100 100 100 50 Apr’14

Vacuum fittings 100 100 0 0 done

Supporting system elements 100 100 0 0 done

Standard Supporting Frames 100 100 0 0 done

Page 23: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

23[19-Mar-2014] [CMWG Meeting] «BE/RF»

Status of components. CLEX working area

Component Design Production Status Expected

3D % 2D % Parts % Assembly

Vacuum fittings and bellows (drift tubes)

100 - 0 0 Apr’14

Supporting girders 100 0 0 0 Apr’14

Implantation drawings (under way) 100 95 0 0 Mar’13

Cooling pipe

Page 24: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

24[19-Mar-2014] [CMWG Meeting] «BE/RF»

Resources

Cooling system: final integration is under way by Vadim Soldatov and Alexios Lorens Vamvakas

Installation: FSU108, Andrey Olyunin, Wilfrid Farabolini (CLEX equipment coordination)

Vacuum for CLEX: Esa Antero Paju

Fiducialization, alignment: ABP-SU

Special tasks: external companies or other groups of CERN are involved

Page 25: CLIC TBM  Prototype T0@CLEX  Integration. Inventory. Planning Report - March 2014

25[19-Mar-2014] [CMWG Meeting] «BE/RF»

Documentation

• EDMS 1366387 – INPUT. Integration of TBM in CLEX. Probe beam

• EDMS 1366388 – INPUT. Integration of TBM in CLEX. Drive beam

• CLIATCIN0004 (under way) – Integration of TBM in CLEX. Supporting system

• CLIATCIN0005 (under way) - Integration of TBM in CLEX. RF components

• EDMS 1366389 – TBM installation in CLEX. Detailed planning (preliminary)