cleaner production - region2.dost.gov.ph€¦ · project at amulung, cagayan gina tumanguil pdo ii-...
TRANSCRIPT
-
Cleaner Production
QUEBRAL Piggery
Farm
Aglipay Quirino
MARCH 15, 2017
Agriculture -The firm is maintaining 30 sow level and 50
fattening
-Planning to expand up to 100 heads fattening and
50-60 sow levels
--Recommended to install about 50 cu. Meter biogas
digester.
LOVELY PRINCESS
PIGGERY FARM
Aglipay, Quirino
March 16, 2017
Agriculture - The firm is planning to expand the piggery up to
200 head of hog
- Recommended to install biogas digester of about
50 Cu. Meter
BJ Farm Supply
BJ Te
Sta Maria, Isabela
April 28, 2017
Agriculture - Conducted Biogas System lay-outing
- Started Construction of 16 cu. Meter Biogas Digester
-
Cleaner Production
GEMCEl Hog
Raising
Luzviminda B.
Gecha
Ivana, Batanes
April 20, 2017
Agriculture -The firm is maintaining 10 sow level and 20
fattening
-Planning to expand up to 15 sow level and 30
fattening
-Recommended to install about 30 cu. Meter biogas
digester.
Felix Lechuga
Basco, Batanes
April 21, 2017
Agriculture - The firm is planning to expand the piggery up to
200 head of hog
- Recommended to install biogas digester of about
50 Cu. Meter
C Square Farm
Ivana, Batanes
April 21, 2017
Agriculture - Farm is on Livestock production (Poultry both
Laying and Growing and Piggery
- Maintaining about 15,000 heads of birds and
about 50 heads of hog
- Recommended to install biogas digester for waste
utilization and minimization
- Recommended further to used Effective Micro
Organism (EMO) to minimize odor.
-
Cleaner Production
DSWD R02
Sustainable
Livelihood
Project at
Amulung, Cagayan
GINA TUMANGUIL
PDO II- Amulung
June 13, 2017
Agriculture -Three (3) associations maintaining about 22 heads of
hog and one (1) Association has 15 heads
-Provided estimate capacity of biogas digester as
basis for the SLP proposal in Amulung 4P’s
Beneficiaries
-Estimated biogas capacity are 6 cu meters and 4 cu
meters
-
Cleaner Production
CAVADECO,
Alicia Isabela
September 28,
2017
Cooperative
-Biogas site validation and assessment
-Recommended to install about 50 cu. Meter
biogas digester.
-provided design compliment the on-going
construction
JOHN UY
Integrated
Farm
San Vicente,
Tumauini, Isabela
December 05, 2017
Agriculture
-Biogas site validation and assessment
-Recommended to install about 100 cu. Meter
biogas digester.
-provided design
-started land excavation and willing to apply for
SETUP Program
-recommended to reactivate and retrofit the 5
unit existing biogas digester
-
CAVADECO
-
Photo during the site
assessment at JOHN UY
Integrated Farm at San
Vicente, Tumauini, ISabela
-
IDEA Team of
DOST R02,
conducting initial
testing of the
equipment
deployed for
food processing
Testing of equipment in Barangay
Dibulo, Dinapigue, Isabela
April 07, 2017
1 IDEA TEAM
-
DMJ Palay and Corn Buying Station
DARIUS CUSTUDIO
Ugad, Tumauini, Isabela
-Inspection of Rice milling equipment and accessories
-equipment lay-outing with the contractor (paddy de-husker, Paddy separator,
Stoner, Rice polisher/whitener, Mist polisher)
-Monitoring of equipment installation
-Energized last December 15, 2017, on-going test run
Isabela Seed Producer
Francisco Agornia
Sillawit, Cauayan City, Isabela
-Inspection of grain drying facility and accessories
-Testing/performance evaluation of equipment with the fabricator
-Equipment is now in operation
3
2 IDEA TEAM
-
CAJ Food Products
Luzviminda B. Gecha
Basco, Batanes
April 20, 2017
Food OBSERVATIONS:
-Renovation of production center on – going,
planning to reconstruct the ruined production center
caused by TY Ferdie.
- PSTC Batanes to check the proposed production
layout in compliant to the FDA requirement to
include electrical lay-outing.
- Equipment are operational, production capacity is
limited to 4 kg per batch.
- Requesting for the realignment of SETUP Fund for
the purchase of Dough Sheeting Machine with Cutter.
(PSTC Batanes to provides possible supplier)
- Proper raw materials stocking to avoid pest
contamination.
IAM J Printing
Jaycy S. Alina
Basco, Batanes
April 20, 2017
ICT OBSERVATIONS
- Equipment are operational
- There a need to expand the production
center to maximize operation, limited
production/printing
4
5
IDEA TEAM
-
Khims
Canteen and
Variety Store
Victoria
Ebalin
Uyugan,
Batanes
April 21, 2017
Food OBSERVATIONS
-Required re-layouting of Production
area, the proponent is planning to
expand the area for wider operation.
-Recommended to install exhaust fan
along the oven to reduced heat at the
baking area
Jojo A. Jose Motors
Jojo A. Jose
Basco, Batanes
April 20, 2017
Metals and
Engineering
OBSERVATIONS:
- Equipment are operational (Hydraulic Press, motor lifter,
hand drill, Crocodile jack, Sheet Bender)
- Solar Power was blown by TY Ferdie.
- Firm is highly recommended for MPEX, 5S training and
Operational Safety and Health Training
- Scattered Scraps are filed inside the Production Center, as
per owner schedule of disposal will be done by month of May
depending on the price of scrap metal
- Recommended to designate tool keeper to ensure availability
of tools at all time.
- Recommended to have container for used oil to avoid oil
spillage at the production area
6
7
IDEA TEAM
-
MENGAL
WOMEN
FOOD
PROCESSING
CENTER
Food -Conducted on-site assessment of
existing processing area (LGU Canteen)
-Provide production floor layout for the
proposed Mengal Women Food
Processing Center
-Conducted Periodic visit and
constructions monitoring
TUMAUINI
MANGO
PROCESSING
PLANT
FOOD -On site assessment of the proposed Mango
Processing Plant of Tumauini
-Provide production floor layout for the proposed
Mango Processing Plant.
8
9
IDEA TEAM
-
EA
1 ROMLYN BAKERY Capellan, City of
Ilagan, Isabela
Food -Conduct equipment re-lay
outing with proper electric
layout.
TRADERS DESIGN
San Fermin,
Cauayan City,
Isabela
Furniture -Conduct motor assessment for the proposed
purchased of transformer to accommodate the
load of the new equipment
-assisted in the conduct of equipment re-lay
outing for the utilization of new macbhines
GSD Enterprises
Bantug Highway, Roxas, Isabela
Metals and
Engineering
-Conduct motor assessment
and operational safety assessment
-Recommended to install exhaust fan at
the production area.
-recommended for CAMPI and 5’s
Training
2
3
-
EA
4
SOMAI JUAN EXPRESS
District 1, San Manuel,
Isabela
Food -Conduct equipment re-lay
outing with electrical
recommendation
-recommended for FOOD
Safety Assessment and
Consultancy
JJMK Furniture
Shop
Furniture -Conduct motor assessment
and operational safety assessment
-recommended to realign motors and avoid
on/off operation of equipment
-elevating motor baseplate to avoid short
circuit 5
-
EA
MANDAC
Furniture
Shop
Furniture -Conduct motor assessment
and operational safety assessment
-recommended to realign motors and avoid
on/off operation of equipment
-elevating motor baseplate to avoid short
circuit caused by motor immersion during
rainy day
CACAYAN
FURNITURE SHOP
Aglipay Quirino
Furniture -Conduct motor
assessment
and operational safety
assessment
-Recommended for electrical
relay-outing
6
7
-
MRB
Ricemill
Diffun,
Quirino
Food -Conduct equipment assessment and operational
safety assessment
-ongoing construction of mechanical dryer
-on-going repair of old rice mill facility,
recommended to conduct periodic maintenance
thru regular belt adjustment and greasing of
bearing
8
ER Welding Shop
La Paz, Saguday,
Quirino
Metals and
Engineering
-Conduct equipment assessment and
operational safety assessment
-poor electrical lay-outing causing high electric
consumption
-recommended electric relay-outing and
installation of individual circuit
breakers/switches
B-dict Machine
and Welding Shop
Saguday, Quirino
Metals and
Engineering
-Conduct equipment assessment and operational safety
operation
-observed proper electrical lay-outing and firm is paying
minimal electric bill
-each equipment has their own circuit breaker
-recommended to avoid using breaker as file cabinet.
9
10
EA
-
PHOTOS
OCM furniture’s ½ hp lathe machine motor:
As seen in these photo, motor wirings must at
least be protected by metal conduit, its
wirings are also exposed to sharp and heavy
raw materials that can cut open the wire.
Motor electrical box must also be kept close.
OCM furniture’s Table Saw
The V belt of the Table Saw is starting
to worn out, it is observed that its V
belt is not properly aligned.
-
PHOTOS
ER Welding and Machine Shop Panel 2 for lathe machine, welding machine, and temporary extension
convenience outlet.
-
PSTC Quirino personnel Provincial Director Mr Lucio G. Calimag and Mr
Nelson Calimag with Engr Rogelio J. Bulusan Jr and Engr Rafael B.
Tumaliuan (on camera) observing the operational safety of the firm. Mr
Danilo R. Veirnes in red shirt is the owner of the B-dict Welding and
Machine Shop
Main panel and Sub-panels for lathe machine, driller press, and portable welding
machine
PHOTOS
-
PHOTOS
No machine guarding installed for
the V-belt of the Rice mill facilities,
rotating parts, and other parts that
has a direct contact with the
worker.
The new facilities for MRB rice mill has separate circuit protection per equipment, however it is
not specified the branch distribution.