clean watersheds for a clean bay (cw4cb) task 5 individual ...basmaa.org/portals/0/documents/project...
TRANSCRIPT
Clean Watersheds for a Clean Bay (CW4CB)
Task 5 Individual Retrofit Pilot Project Report
Ettie Street Pump Station Media Filter Project
Alameda County, Oakland, California
Prepared for
Alameda Countywide Clean Water Program
Prepared by
1111 Broadway, 6th Floor
Oakland, California 94607
August 2016
i
TABLE OF CONTENTS
1. INTRODUCTION AND BACKGROUND ......................................................... 1
2. PROJECT LOCATION ........................................................................................ 1
3. TREATMENT CONTROL MEASURE .............................................................. 1
4. CONSTRUCTION PROCESS ............................................................................. 2
5. COST SUMMARY .............................................................................................. 2
6. MONITORING DATA ........................................................................................ 2
7. PROJECT OUTCOMES AND LESSONS LEARNED ....................................... 2
8. REFERENCES ..................................................................................................... 3
ii
LIST OF TABLES
Table 1. Cost Summary .................................................................................................... 2
LIST OF FIGURES
Figure 1: Ettie Street Pump Station Project Map
LIST OF APPENDICES
Appendix A: Ettie Street Pump Station Project – Conceptual Design
Appendix B: Ettie Street Pump Station Project – 100% Draft Engineer’s Estimate
Appendix C: Ettie Street Pump Station Project – 100% Plans
Ettie Street Pump Station Project Report
1
1. INTRODUCTION AND BACKGROUND
The Bay Area Stormwater Management Agencies Association (BASMAA) Clean Watersheds
for a Clean Bay (CW4CB) project evaluated a variety of potential control options to reduce mass
loadings of polychlorinated biphenyls (PCBs) and mercury in urban stormwater runoff to San
Francisco Bay.
The primary objective of CW4CB Task 5 was to select and implement representative urban
stormwater treatment retrofit projects. This objective coincided with Municipal Regional
Stormwater NPDES Permit (MRP, Order R2-2009-0074) Provision C.12.e, which required the
MRP Permittees to identify and conduct on-site pilot treatment projects in ten locations during
the MRP term and to document the knowledge and experience gained to provide a basis for
determining the scope of implementation of treatment retrofits in subsequent permit terms.
This report presents results of the Ettie Street Pump Station (ESPS) Media Filter Project in
Oakland, California and includes descriptions of the project location, treatment measure,
planning and design process, construction process and schedule, cost summary, monitoring plan,
and challenges and lessons learned.
2. PROJECT LOCATION
The Ettie Street Pump Station (ESPS) Media Filter Project is located in West Oakland,
California at 3465 Ettie Street, adjacent to MacArthur Freeway to the north and Nimitz Freeway
to the west. The ESPS is an Alameda County Flood Control and Water Conservation District
(ACFCWCD) facility that collects and pumps stormwater runoff to San Francisco Bay. The
ESPS watershed comprises approximately 1180 acres in West Oakland and includes
approximately 42% residential, 38% industrial, and 20% commercial land use areas. The
proposed stormwater treatment measure is a media filter system with two parallel filter beds
containing different media. The project location and watershed are shown on Figure 1.
The stormwater program representative for the project is Arleen Feng with the Alameda
Countywide Clean Water Program (ACCWP).
3. TREATMENT CONTROL MEASURE
The primary stormwater treatment measure consists of installing two parallel media filter beds to
treat PCBs and mercury that enter the ESPS from the watershed. The design media filter flow
capacity for both filters is limited to approximately 30 gpm. The media filter system will be
located at grade outside the ESPS building and will include a pump and pretreatment storage
tank. The pump will draw water up from one of the two forebays into the pretreatment storage
tank, which is designed to settle out the fine and coarse particulates. Pumping will be triggered
during storm events by elevated turbidity readings from a real-time turbidity sensor in the
forebay. The flows will then be evenly split between each media bed using flow control valves.
One filter bed will contain rhyolite sand and the second bed will contain a mix of media types,
Ettie Street Pump Station Project Report
2
including rhyolite sand, zeolite, and granulated active carbon (GAC). The discharges from the
media beds will be combined before returning to the forebay.
4. CONSTRUCTION PROCESS
ACFCWCD and BASMAA entered into a contract in October 2012. WRECO completed the
100% design in December 2013. Appendix A contains the WECO Conceptual Design Memo,
Appendix B contains the latest cost estimate dated December 31, 2013, and Appendix C contains
the 100% Design Plans. The project has not yet received approval from the Oakland City
Council and is currently on hold. At this time, a bid has not been put out and there is no
estimated start date for construction.
5. COST SUMMARY
Table 1. Cost Summary
Project Phase Description
Individual
Cost
($)
Total
Cost
($) Notes
Design Total 31,610 31,610 WRECO Invoice Summary.
Construction Management Unknown
72,200
Project has not gone out to bid.
Estimate based on WRECO’s Draft
Engineer’s Estimate dated December
31, 2013. Other Unknown
O&M Annual Unknown Unknown
Total Cost Total 103,810 The total estimated cost does not
include the annual O&M costs.
The total catchment area is 1,180 acres. The total estimated design and construction cost of the
project is $103,810. The estimated total cost per unit area is $88 per acre.
6. MONITORING DATA
As the project has not yet been constructed, no monitoring has been conducted to date.
7. PROJECT OUTCOMES AND LESSONS LEARNED
The one major lesson learned at this time is that the permitting and approval process can
significantly delay a project.
Ettie Street Pump Station Project Report
3
8. REFERENCES
BASMAA, 2012. Quality Assurance Project Plan: Clean Watersheds for a Clean Bay –
Implementing the San Francisco Bay’s PCBs and Mercury TMDLs with a Focus on Urban
Runoff, EPA San Francisco Bay Water Quality Improvement Fund Grant No. CFDA 66.202.
Prepared by Applied Marine Sciences, Inc. FINAL. 12 September 12.
BASMAA, 2013a. BASMAA Sampling and Analysis Plan, Clean Watersheds for a Clean Bay –
Implementing the San Francisco Bay’s PCBs and Mercury TMDLs with a Focus on Urban
Runoff, Task 5 Phase I, EPA San Francisco Bay Water Quality Improvement Fund Grant #
CFDA66.202. Prepared by Applied Marine Sciences. 5 March.
BASMAA 2013b. Clean Watersheds for a Clean Bay (CW4CB) Retrofit Pilot Study Plan.
Prepared by Brian Currier at the California State University Sacramento Office of Water
Programs. 22 October.
BASMAA, 2013c. BASMAA Sampling and Analysis Plan, Clean Watersheds for a Clean Bay –
Implementing the San Francisco Bay’s PCBs and Mercury TMDLs with a Focus on Urban
Runoff, Task 5 Phase II, EPA San Francisco Bay Water Quality Improvement Fund Grant #
CFDA66.202. Prepared by Applied Marine Sciences. 24 October.
BASMAA, 2013d. Integrated Monitoring Report Part B: PCBs and Mercury Loads Avoided and
Reduced via Stormwater Control Measures. Prepared by Geosyntec Consultants and EOA
Inc. 12 December.
BASMAA, in preparation. Clean Watersheds for a Clean Bay (CW4CB) Final Project Report.
WRECO, 2013. Ettie Street Pump Station Retrofit Project – Conceptual Design, 30% Design
Memorandum. Prepared by WRECO for the Alameda Countywide Clean Water Program. 2
July.
FIGURES
P:\GIS\Ala m eda Countywide Clea n Wa ter Progra m (ACCWP)\Ta sk 5\Project\ESPS.m xd
")
HAWTHORN E AV
TOL LPL AZA
JACKSON ST
WATTS ST
MARITIME ST
SY CAMORE ST
EB WGRAN D
OFFRP AV
14TH ST
Y ERBABU EN A AV
WB MARKETOFFRP ST
EB 11TH
OFFRP ST
HARL ANST
MAGNOLIA ST
WB 27TH OFFRP ST
FRANKLIN ST
HOL L IS ST
MAN DELA PKWY
ANDOV ER
ST
EB MACARTHU RON RP BL
3RD ST
BEACH ST
FRON TAGE RD
BROADWAY
23RD ST
N B U N IONON RP ST
MARKET ST
ETTIE ST
BRU SH ST
29TH ST
5TH ST
WB 52N D
ONRP ST
ADELIN E ST
WB 18TH
OFFRP ST
27TH ST
GRAN D AV
WEBSTER ST
39TH ST
THOMAS L .BERKL EY WY
31ST ST
CAMPBEL L
V ILL AGE CT
10TH ST
SB U N IONOFFRP ST
19TH ST
PAL M CT
V IL L AGECIR
HARRISON ST
EB 51ST OFFRP ST
37TH ST
EB 17TH OFFRP ST
33RD STHEN RY ST
VAL DEZ ST
ELM ST
TU LAGI ST
9TH ST
WEST11TH ST
JEFFERSON ST
VAL LEY ST
ZEPHY R DR
APGAR ST
LOU ISE ST
CURTIS ST
CASTRO ST
WB 12TH/14TH
OFFRP ST
21ST ST
EB 12TH ON RP ST
CLAY ST
AMBL ER L N
N ORTHGATE AV
N B MARKETOFFRP ST
WEST ST
CEN TER ST
PRESERV ATION
PARK WY
WIL L OW ST
EB W GRAN DCOL L AV AV
BU N AST
EAL ING LN
24TH ST
CHESTER ST
28TH ST
34TH ST
16TH ST
FITZGERAL D ST
36TH ST
26TH ST
ALICE ST
HORTON ST
SANPABL O AV
W MACARTHU RBL V D
7TH ST
MCELROY ST
8TH ST
WOOD ST
TELEGRAPH AV
PINE ST
11TH ST
KAISER
PLZ
6TH ST
W GRAN D AV
MACARTHU RBL V D
AL ASKA ST
FRAN K HOGAWA PL Z
MYRTL E ST
22N D ST
MARTIN
L UTHER
KING JR WY
12TH ST 17TH ST
WB 17TH
ONRP ST
18TH ST
LEWIS ST
EB 27TH
ONRP ST
13TH STU NION ST
AL ICIAST
GOSS ST
BU RMA RD
20TH ST
15TH ST
CHASE ST
SB ADEL IN E ON RP ST
SUMMIT ST
MCCLU RE
ST
CHESTNU T ST
WB 11TH
ONRP ST
HEL EN ST
30TH ST
EB MACARTHU R OFFRP BL
WB 12TH
OFFRP ST
CAMPBEL L ST
POPLAR ST
FILBERT ST
LINDEN ST
COV EN T
L N
PERALTA ST
MERRIMACST
KIRKHAM ST
HAN N AH ST
KIRKHAM CT
POPLAR CT
MILTON ST
32N D ST
BROCKHU RST ST
EB 18TH
ONRP ST
MEAD AV
ISABEL L A ST
ACCESS
WIL L IAM ST
25TH ST
35TH ST
WEST 14TH ST ATHEN S AV
WAKE AV
U KRAIN E ST
WEST 15TH ST
WEST 19TH ST
N B 7TH OFFRP ST
WEST 20TH ST
WEST 17TH ST
SB 7TH
ON RP ST
WEST 21ST ST
WEST 18TH ST
EN GIN EER RD
³ 0 1,000 2,000Feet
Figure1WW2053 July 2016
CW4CB Task 5Ettie Street Pump Station Media Filter Project Map
Legend") Ettie St. Pum p Sta tion (ESPS)
ESPS Wa tershed
Roa dsStorm Drains (Diameter)
≤36"
>36"
Source: Esri, Digita lGlobe, GeoEye, Ea rthsta r Geogra phics, CN ES/Airbus DS, U SDA, U SGS, AEX,Getm a pping, Aerogrid, IGN , IGP, swisstopo, a nd the GIS U ser Com m unity
Ala m eda County, CA
Project L oca tion
APPENDIX A: Ettie Street Pump Station Project –
Conceptual Design
1243 Alpine Road, Suite 108 Walnut Creek, CA 94596
Phone: 925.941.0017 Fax: 925.941.0018 www.wreco.com
| Civil Engineering | Water Resources | Environmental Compliance | Geotechnical Engineering | 1
Memorandum Date: July 2, 2013
To: Arleen Feng – ACPWA
From: Analette Ochoa / Jennifer Abrams – WRECO
Subject: Ettie Street Pump Station Retrofit Project – Conceptual Design
Introduction
The Ettie Street pump station in the City of Oakland is identified as one of the sites selected by the Bay Area Stormwater Management Agencies Association (BASMAA) as part of the Clean Watersheds for a Clean Bay Implementation Plan. The objective of this Plan is to select and implement representative urban stormwater treatment retrofit projects that can be used to evaluate potential polychlorinated biphenyls (PCBs) load reductions in urban stormwater runoff to the Bay. The purpose of this memorandum is to present a conceptual design for the treatment Best Management Practice (BMP) at the Ettie Street pump station site. The proposed stormwater treatment measure for the project is a media filter system with two separate filter beds containing different media.
Project Location and Existing Site Condition
The Ettie Street Pump Station Retrofit Project is located in West Oakland at the northernmost end of Ettie Street, adjacent to MacArthur Freeway to the north and Nimitz Freeway to the west (Figure 1). The Ettie Street Pump Station is an Alameda County Flood Control and Water Conservation District facility that collects and pumps stormwater runoff to the San Francisco Bay. The Ettie Street pump station receives stormwater runoff from approximately 2,000 acres of West Oakland. This watershed is composed of approximately 42% residential, 38% industrial, and 20% commercial land uses. PCB congeners have been measured in the pump station effluent during dry weather, first flush, and wet weather events.
The existing site layout is shown in Figure 2. Aboveground, the existing pump station consists of a building containing the pump and engine room and the auxiliaries and office. Outside of the building, there is a paved driveway and parking area, with a 6-foot by 25-foot access grate to the forebay below. There are two large vents adjacent to the west side of the access grate. At the northern corner of the property, a 600 gallon constant head tank has been constructed. The tank receives water pumped out of the pump station’s sump. Adjacent to this tank there is a planting area to the west, a gate and a PG&E gas utility access hole to the north, fence to the east, and the access grate and vents to the south. A controller is also located near the tank.
1243 Alpine Road, Suite 108 Walnut Creek, CA 94596
Phone: 925.941.0017 Fax: 925.941.0018 www.wreco.com
| Civil Engineering | Water Resources | Environmental Compliance | Geotechnical Engineering | 2
Figure 1. Project Location Map
Source: Google
Project Site
No Scale
N San Francisco Bay
Oakland
1243 Alpine Road, Suite 108 Walnut Creek, CA 94596
Phone: 925.941.0017 Fax: 925.941.0018 www.wreco.com
| Civil Engineering | Water Resources | Environmental Compliance | Geotechnical Engineering | 3
Figure 2. Existing Site Layout
Source: Google
Design Concept
The Project would install two media filter beds to treat PCBs and mercury (Hg) that enter the Ettie Street pump station from the Ettie Street drainage catchment. A schematic of the Project layout is included in Figure 3. The two media filters would operate in parallel, allowing samples to be taken to compare the performance of the two types of filter media. The media filters would be located at grade outside the pump station building. Each filter would have a 4-foot by 12-foot footprint. The filters would have covers to prevent rain from entering the system. Water from the existing storage tank would be pumped up to a sufficient elevation, then split and conveyed to each tank containing the filter media. Water would be directed over a weir onto the
No Scale
N
1243 Alpine Road, Suite 108 Walnut Creek, CA 94596
Phone: 925.941.0017 Fax: 925.941.0018 www.wreco.com
| Civil Engineering | Water Resources | Environmental Compliance | Geotechnical Engineering | 4
surface of the media filter bed where it would infiltrate down through the 2.5-foot thick filter media to an underdrain. One filter bed would contain rhyolite, and the second bed would contain a mix of media types, including 50% rhyolite, 30% zeolite, and 20% granulated active carbon. The discharge from the filter media would be collected in a 2-inch slotted pipe underdrain running the length of each tank. The pipe would be surrounded by a rock blanket and the bottom of the filter bed would be sloped for drainage. Each filter bed would discharge to a non-perforated PVC pipe, which would combine before reentering the wet well. Water quality sampling ports would be located just downstream of the storage tank and at the downstream ends of each filter bed. Flow control valves and backflow preventer valves would be located at the upstream and downstream ends of the filter beds to regulate the flow.
Figure 3. Proposed System Schematic
No Scale
1243 Alpine Road, Suite 108 Walnut Creek, CA 94596
Phone: 925.941.0017 Fax: 925.941.0018 www.wreco.com
| Civil Engineering | Water Resources | Environmental Compliance | Geotechnical Engineering | 5
Cost Information Cost data was obtained from manufacturers and RSMeans. The detailed estimate is included in the Attachments. The total cost of construction was estimated to be $53,800.
References
California Regional Water Quality Control Board San Francisco Bay Region. (April 2006). Fact Sheet PCBs in the Ettie Street Pump Station Watershed. <http://www2.oaklandnet.com/oakca1/groups/pwa/documents/report/oak026315.pdf> [Last accessed: June 28, 2013].
Google. Google Earth. Version 7.0.3.8542. [Last accessed: June 28, 2013]. RSMeans. (2008.) Heavy Construction Cost Data 22nd Annual Edition.
1243 Alpine Road, Suite 108 Walnut Creek, CA 94596
Phone: 925.941.0017 Fax: 925.941.0018 www.wreco.com
| Civil Engineering | Water Resources | Environmental Compliance | Geotechnical Engineering | 6
Attachments
Item No.
Item Description Unit of MeasureTotal
Estimated Quantity
Unit Price Item Total
1 Fiberglass Tank (12 ft x 4 ft x 5 ft deep) with Lid EA 2 $16,280.00 $32,560
2 5 GPM Pump (1-5 GPM range) EA 1 $1,100.00 $1,100
3 Flow Control Valves (2 GPM) EA 4 $300.00 $1,200
4 Flow Meter (1.2 to 12 GPM) EA 3 $800.00 $2,400
5 Check Valves EA 4 $32.00 $130
6 Weir EA 2 $500.00 $1,000
7 Media (Blended and Placed) CY 9 $265.00 $2,390
8 Filter Fabric SY 14 $2.00 $30
9 Underdrain Pea Gravel CY 1 $28.00 $30
10 Underdrain (2" Sch 40 Perforated PVC Pipe) LF 24 $1.26 $30
11 Inlet/Outlet Piping (4" Sch 40 PVC Pipe) LF 75 $4.00 $300
12 Inlet/Outlet Piping 90 degree Elbow (4" Sch 40 PVC Pipe) EA 4 $64.00 $260
13 Inlet/Outlet Piping Tee (4" Sch 40 PVC Pipe) EA 2 $125.00 $250
$41,680
1 Laborer HR 80 $70.00 $5,600
2 Operator HR 40 $100.00 $4,000
$9,600
$51,2805% CONTINGENCY $2,564TOTAL $53,800
SUBTOTAL
Construction: Materials
Materials Subtotal
Construction: Labor
Labor Subtotal
Etty Road Conceptual Treatment Cost EstimateOakland, CA
7/2/2013
APPENDIX B: Ettie Street Pump Station Project –100% Draft Engineer’s Estimate
Item No.
Item Description Unit of MeasureTotal
Estimated Quantity
Unit Price Item Total
1 Water Pollution Control Work LS 100% $1,000.00 $1,000
2 Construction Site Management LS 100% $2,000.00 $2,000
3 Concrete Removal CY 2 $1,000.00 $1,000
4 Structural Concrete CY 5 $5,000.00 $25,000
5 Bar Reinforcing Steel LB 640 $5.00 $3,200
6 Miscellaneous Iron and Steel LB 1,140 $5.00 $5,700
7 Flow Meter EA 4 $850.00 $3,400
8 Flow Control Valve EA 5 $500.00 $2,500
9 Sampling Port EA 3 $250.00 $750
10 Filter Media Type 1 CY 4 $450.00 $1,800
11 Filter Media Type 2 CY 4 $450.00 $1,800
12 Class 2 Permeable Material CY 2 $100.00 $200
13 1" PVC Pipe LF 6 $65.00 $390
14 2" PVC Pipe LF 100 $75.00 $7,500
15 2" x 1" PVC Pipe Reducer EA 8 $150.00 $1,200
16 2" PVC 90° Elbow EA 17 $150.00 $2,550
17 2" PVC Tee EA 7 $250.00 $1,750
18 2" PVC Corner Tee EA 1 $350.00 $350
19 2" PVC Terminal Riser EA 2 $500.00 $1,000
20 2" Perforated PVC Pipe LF 45 $35.00 $1,580
21 Cleaning Site and Miscellaneous Things LS 100% $1,000.00 $1,000
$65,67010% CONTINGENCY $6,567TOTAL $72,200
SUBTOTAL
Etty Street Pump Station Retrofit ProjectOakland, CA
Draft Engineer's EstimateDecember 30, 2013
12/30/2013
APPENDIX C: Ettie Street Pump Station Project –
100% Plans
71
LOCATION MAP
INDEX OF SHEETS
NO.SHEET DESCRIPTION
PROJECT LOCATION
VICINITY MAPALAMEDA COUNTY, CALIFORNIA
MAY 2006STANDARD PLANS
CALTRANS
ETTIE STREET PUMP STATION
ZONE NO. 12 PROJECT
ALAMEDA COUNTY, CALIFORNIAOAKLAND
(ADV) MONTH, YEAR
ALAMEDA COUNTY FLOOD CONTROLAND WATER CONSERVATION DISTRICT
IMPROVEMENTS AT THE
AT 3465 ETTIE STREET
CONVENTIONAL SYMBOLS
CB-###
PROJECT LOCATION
TITL
E SH
EET
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT
2 7
POLL
UTI
ON
PR
EVEN
TIO
N
concrete pavement.
or creeks. Collect sand and return it to the
stockpile, or dispose of it as trash.
from sand sealing into gutters, storm drains,
Comply with Alameda County Ordinances for recycling construction materials, wood,
gyp board, pipe, etc.
Runoff from streets and other paved areas is a major source of pollution and damage to creeks and the San
Francisco Bay. Construction activities can directly affect the health of creeks and the Bay unless contractors
and crews plan ahead to keep dirt, debris, and other construction waste away from storm drains and local
creeks. Following these guidelines and the project specifications will ensure your compliance with County of
Alameda requirements.
Storm drain polluters may be liable for fines of $10,000 or more per day!
Make sure your crews and subs do the job right!
Pollution Prevention - It's Part of the Plan
what should be done, and manage disposal of cntaminated soil according to their instructions.
underground tanks or pipes, or buried debris), call the Engineer for help in determining
If you suspect contamination (from site history, discoloration, odor, texture, abandoned
fiber rolls down-slope until soil is secure.
growing grasses as soon as possible. Place
erosion control fabric, or seed with fast-
prevent erosion by securing the soil with
If you disturb a slope during construction,
existing vegetation whenever possible.
erosion control. Minimize disturbance to
Mature vegetation is the best form of
Inspector in the Field.
by permit and as approved by the County
are only allowed during dry weather
Earth moving activities
Do not use water to wash down fresh asphalt
Do not sweep or wash down excess sand
with sand/gravel bags, or earthen berms.
Protect gutters, ditches, and drainage courses
slurry seal, or fog seal.
when paving or applying seal coat, tack coat,
Always cover storm drain inlets and manholes
If saw cut slurry enters a catch basin, clean it up immediately.
are finished in one location or at the end of each work day (whichever is sooner!).
Shovel, absorb, or vacuum saw-cut slurry and pick up all waste as soon as you
Use plastic sheeting (Visqueen) to keep slurry out of the storm drain system.
Always completely cover and barricade storm drain inlets when saw cutting.
Saw cutting
Paving/asphalt work
off the site.
Use fiber rolls, silt fences, or other control measures to minimize the flow of silt
Transfer to dump trucks should take place on the site, not in the street.
Keep excavated soil on the site where it will not collect in the street.
Earthwork & contaminated soils
Contaminated groundwater must be treated or hauled off-site for proper disposal.
Consult with the Engineer to determine what testing is required and how to interpret results.
In areas of known contamination, testing is required prior to reuse or discharge of groundwater.
or storm drain. Filtration or diversion through a basin, tank, or sediment trap may be required.
Be sure to notify and obtain approval from the Engineer before discharging water to a street, gutter,
extent possible.
or another on-site purpose to the greatest
Reuse water for dust control, irrigation,
Dewatering operations
steam cleaning equipment, etc.
on-site using soaps, solvents, degreasers,
Do not clean vehicles or equipment
storm drains, or creeks.
rinse water to run into gutters, streets,
bermed area that will not allow
on site, clean with water only in a
If you must clean vehicles or equipment
is big enough to prevent runoff.
in a bermed area or over a drip pan that
Fuel and maintain vehicles on site only
promptly.
until repairs are made; repair leaks
frequently. Use drip pans to catch leaks
Inspect vehicles and equipment for leaks
maintenance & cleaning
Vehicle and equipment
County Public Works Agency dispatch at (510) 670-5500
Report any hazardous materials spills immediately! Dial 911 or Alameda
Never wash spilled material into a gutter, street, storm drain, or creek!
to prevent leaks and spills from reaching the gutter, street, or storm drain.
When spills or leaks occur, contain them immediately and be particularly careful
the construction site at all times.
Keep a stockpile of spill cleanup materials (rags, absorbents, etc. ) available at
Spill prevention and control
Be sure to arrange for appropriate disposal of all hazardous wastes.
rain is forecasted within 24 hours.
careful not to use more than necessary. Do not apply chemicals outdoors when
Follow manufacturer's application instructions for hazardous materials and be
Store hazardous materials and wastes in water tight containers, store in
and federal regulations.
thinners, solvents, fuel, oil, and antifreeze) in accordance with city, county, state,
Label all hazardous materials and hazardous wastes (such as pesticides, paints,
Hazardous materials management
Repair or replace leaking dumpsters promptly. Check dumpsters regularly for leaks and to make sure they are not overfilled.
Recycle all asphalt, concrete, and aggregate base material from demolition activities.
work areas with water!
Sweep or vacuum streets and other paved areas daily. Do not wash down streets or
Use (but don't overuse) reclaimed water for dust control as needed.
catch basins. All construction material must be covered with a tarp and contained
Sand, dirt, and similar materials must be stored at least 10 feet (3 meters) from
Non-hazardous materials management
Materials storage & spill cleanup
hazardous waste.
Dispose of oil-based paint sludge and unusable thinner as
Filter paint thinners and solvents for reuse whenever possible.
Paint out excess oil-based
rollers, or containers in a sink.
paint before rinsing brushes,
Paint out excess water-based
materials in a gutter or street!
Never rinse paint brushes or
Painting
disposal off site.
remove it for appropriate
aggregate concrete and
from washing exposed
Collect the wash water
or onto the surrounding areas.
areas that will not allow discharge of wash water onto the underlying soil
Wash out concrete equipment/trucks off-site or into contained washout
storm drain.
and away from drainage areas. These materials must never reach a
Store concrete, grout, and mortar under cover, on pallets,
storage & waste disposal
Concrete, grout, and mortar
For references and more detailed information:
www.cleanwaterprogram.org
www.cabmphandbooks.com
Dispose of all containment and cleanup materials properly.
to prevent further tracking.
Sweep or vacuum any street tracking immediately and secure sediment source
entrances and exits to sufficiently control erosion and sediment discharges from site
Establish and maintain effective perimeter controls and stabilize all construction
Construction Entrances and Perimeter
and tracking off site.
or during wet weather or when rain is forecasted.
appropriate secondary containment, and cover them at the end of every work day
Cover all dumpsters with a tarp at the end of every work day or during wet weather.
with a perimeter control during wet weather or when rain is forecasted or when
not actively being used within 14 days.
the site. Run-on from off site shall be directed
within the site, and all runoff that discharges from
Effectively manage all run-on, all runoff
away from all disturbed areas or shall collectively
be in compliance.
within 2 days of forecasted rain and during wet weather.
Discontinue the application of any erodible landscape material
rain is forecasted or when not actively being used within 14 days.
materials (mulch, compost, fertilizers, etc.) during wet weather or when
Contain, cover, and store on pallets all stockpiled landscape
Landscape Materials
paint before cleaning brushes
in thinner.
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT
CB-###
3 6
NO
TES
AN
D A
BB
REV
IATI
ON
S
GENERAL NOTES: ABBREVIATIONS
1-
3A
CB-###
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT
61
LAYO
UT
4 7CB-###
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT
ETTIE STREET
NOTES:
D6 6D
62
6E
6E
E6
E6
62
PIPI
NG
SYS
TEM
LA
YOU
T
5 7CB-###
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT
DISTRIBUTION PIPING SYSTEM LAYOUT DETAIL COLLECTION PIPING SYSTEM LAYOUT DETAIL
NOTES:
LEGEND
A-
SECTION
41FIBERGLASS TANK DETAIL
B-
SECTION
C-
SECTION
D5
SECTION
A- -A
- CC-
-B B
-
PLAN
QUANTITIES
E5
SECTION
25
FLOW METER PIPING TYPICAL DETAIL
DISTRIBUTION PIPING
COLLECTION PIPING
4
47
7
DET
AIL
S A
ND
QU
AN
TITI
ES
6 7CB-###
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT
NOTES:
-A
-A
TANK PLAN
TOP COVER PLAN VIEW
-
B
-
B
B-
SECTION
A-
SECTION
-C
-C
-1
-2
1-DETAIL
2-
DETAIL
3-
DETAIL
46
DETAIL
STANDARD BAR HOOKS AND BENDS
90° BEND180° BENDMAX. OFFSET BEND
-3
C-
SECTION
NOTE:
GENERAL NOTES:
APPLICABLE CODE:
SEISMIC DESIGN CRITERA:
CONCRETE:
EXPANSION JOINT DETAIL
PLATE LIFTING LUG DETAIL
STR
UC
TUR
AL
DET
AIL
S
7 7CB-###
ZON
E N
O. 1
2 PR
OJE
CT
ETTI
E ST
REE
T PU
MP
STA
TIO
NR
ETR
OFI
T PR
OJE
CT