CITY OF SAVANNAHCapital Improvement Program

Review

11/20/2018

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 2: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

CAPITAL IMPROVEMENT PROGRAM OVERVIEW

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

362 Projects

55 Project Managers

CPM Team:

6 Project Managers (Including Director and Special Projects

Coordinator)

Cemetery3%

Civic Center4% Community

Development4%

Drainage3%

Other12%

Park and Recreation

12%

Public Building

11%Sanitation0%

Sewer 15%

Squares and Monuments

6%

Street7%

Traffic Engineering

7%

Water16%

Page 3: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

Q3 CAPITAL PROJECTS PROGRESS

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

27

16

10

6

0

5

10

15

20

25

30

Page 4: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

OFFICE OF CAPITAL PROJECT MANAGEMENT

6 Project Managers

59 Active Projects

$72.5 million

Total Project Budget

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 5: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018 LARGE PROJECT HIGHLIGHTSProject Funding Sources Estimated Completion

Cultural Arts CenterSPLOST 4, 5, 6 General FundDistrict Funds

January 2019

Bilbo Canal SPLOST 5 and 6 March 2019

Pennsylvania Avenue Family Resource Center

SPLOST 6 April 2019

Central PrecinctSPLOST 5

General FundJune 2019

Sweetwater Fire StationSPLOST 6

General FundCompleted 2018

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 6: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 7: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

SCOPE

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

New permanent fire station serving the Sweetwater Station area and southwest Savannah, replacing temporary facility on ChevisRoad.

Replication of prototype building design constructed at Bradley Pointe.

Built to meet Critical Facility standards for use in disaster events.

Page 8: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

LOCATION

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

1751 Grove Point Road

Page 9: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

PROJECT TEAM

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Consultant: Kern & Co., LLC

Contractor: Dabbs-Williams General Contractors, LLC

Test Lab: Whitaker Laboratories, Inc.

Owner: City of Savannah

Page 10: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

DESIGN

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 11: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2017- AUGUST

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 12: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2017- SEPTEMBER

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 13: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2017- OCTOBER

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 14: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2017- NOVEMBER

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 15: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018- FEBRUARY

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 16: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018- FEBRUARY

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 17: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018- FEBRUARY

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 18: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018- MARCH

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 19: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018- JULY

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 20: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

2018- NOVEMBER

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Page 21: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

SUMMARY TIMELINE

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

2012/June – Property purchased for $225,035

2015/February – Funding provided from SPLOST 6

2015/August – Design kick-off• Design Schedule: 8 months• Delays: 10 months

• Negotiations with Chatham County• Awaiting wetland permit from U.S. Army Corps of

Engineers

2017/January – Advertised for Construction• Delays (during bidding and contract execution):

• Georgia Power Encroachment Agreement requirements• Wetland mitigation• Adjustments to construction documents

Page 22: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

SUMMARY TIMELINE

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

2017/June – Construction Start• Construction Schedule: 12 months• Delays:

• Rain• Tropical Storm Irma• Remediation of adverse soil conditions• Snow and cold weather conditions• Special Inspections requirements• Extended punch list period

2018/September – Substantial Completion Inspections

2018/October – Building acceptance• Certificate of Occupancy: October 18• Fire operations commenced: October 22

Page 23: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

PROJECT COSTS

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

BUDGETED: $ 3,515,000

ACTUAL (ESTIMATED): $ 3,345,000

BALANCE: $ 170,000

Page 24: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

Grand Opening Ceremony

December 7th, 2:00pm

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

Welcome!

Page 25: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

DISTRICT SPECIFIC PROJECTS

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

DISTRICT PROJECT Q2 Q3

District 1

Ald. Johnson

Basketball Resurfacing Complete N/A

Brickyard Concrete Pad Pre-constructionPre-construction

(waiting on FEMA)

Grant Center Conceptual/Planning Conceptual/Planning

Woodville Community Sign - Complete

Highlands Park Development* - Conceptual/Planning

District 2

Ald. Durrence

Central Precinct Implementation/ Construction Implementation/ Construction

Caretaker's Cottage Restoration - Design/Pre-construction

Waters Avenue Corridor

Improvement*Design/Pre-construction (Phase 2) Design/Pre-construction (Phase 2)

District 3

Ald. Hall

Treat Park Design/Pre-construction Complete

Holly Heights Park* Design Design/Permitting

Twickenham/Pine Garden Sign Design/Pre-construction Complete

Parkwood Sign - Construction

* District projects highlighted in presentation

Page 26: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

DISTRICT SPECIFIC PROJECTS

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

DISTRICT PROJECT Q2 Q3

District 4

Ald. Miller

Atwood Park Design/Pre-construction Design/Pre-construction (waiting on FEMA)

Sheridan Circle Design/Pre-construction Design/Pre-construction (waiting on FEMA)

Washington Avenue Median

Improvements -Conceptual/ Planning

Washington Avenue Tree Lawn Protection - Conceptual/ Planning

Atlantic Park Improvements - Conceptual/ Planning

Sidewalk Repairs - Ongoing

Cedar Street Improvements* - Design

Jan Street Park - Conceptual/ Planning

Kensington Park Improvements - Design/Pre-construction

Montgomery & Skidaway Lighting - Conceptual/ Planning

Irrigation Improvements - Conceptual/ Planning

District 5

Ald. Shabazz

Sylvan Terrace Passive Park Ongoing Construction Ongoing Construction

Cann Park Sidewalks* Design/PermittingPre-construction (On the agenda. Shovel

ready)

Leedsgate Gazebo Pre-design Pre-design (waiting on FEMA)

Summerside Park Improvements Design/Pre-construction Design/Pre-construction (on the agenda)

Basketball Resurfacing - Cann Park resurfacing completed

Feiler Terrace Park Improvements Conceptual/ Planning Conceptual/ Planning

Poplar Place - Conceptual/ Planning

District 6

Ald. Thomas

Mohawk Park* Master Plan Completed Design/Pre-construction

Veterans Park Flagpole installedSidewalks, crosswalks and parking

completed

Windsor Neighborhood Park Construction Complete

Joe Tribble Park Improvements Parking Improvements Completed Complete

Thomas Bolton Park - Complete

Cedar Grove Nature Park - Complete

* District projects highlighted in presentation

Page 27: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

UPCOMING PROJECTSLOOKING AHEAD TO 2019

Project Funding Sources Estimated Start

Waters Avenue Streetscapes Phase 2SPLOST 4 & 6General Fund

Q1 2019

Broughton Street Streetscapes Bonds Q2 2019

Whitaker Street Sidewalk Improvements

Parking Services Fund

Q1 2019

Augusta Avenue StreetscapesSPLOST 4 & 6General Fund

Q2 2019

Savannah Shines Neighborhood Improvements – Edgemere Sackville

SPLOST 4General Fund

Q2 2019

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

NOTE: Not all upcoming projects are included in this presentation

Page 28: CITY OF SAVANNAH Capital Improvement Program Reviewagenda.savannahga.gov/content/files/112018-3rd-quarter-capital... · City of Savannah / Office of Infrastructure & Development

UPCOMING PROJECTSLOOKING AHEAD TO 2019

Project Funding Sources Estimated Start

Summerside Park SPLOST 5 Q2 2019

Bonaventure Cemetery Restrooms General Fund Q2 2019

Holly Heights Park General Fund Q1 2019

Stratford ParkSPLOST 4 & 6General Fund

Q2 2019

Highlands Fire Station SPLOST 6 Q3 2019

Mohawk ParkSPLOST 6

General FundQ3 2019

City Facilities at Interchange Court SPLOST 5 & 6 Q2 2019

City of Savannah / Office of Infrastructure & Development/ Capital Improvement Program Review

NOTE: Not all upcoming projects are included in this presentation