Fishbeck, Thompson, Carr & Huber Inc. Engineers | Architects | Scientists | Constructors Providing services for over 50 years. City of Rochester AIN STREET M AKEOVER Michigan Department of Transportation Contractor Angelo Iafrate Construction Co. NCI Engineering Hubbell Roth & Clark Inc. City of Rochester Rochester DDA Design Engineers Owners Construction Engineer W HAT WAS DONE ? Reconstruction of downtown Main Street between the Clinton River Bridge and Paint Creek Bridge. Water main replacement and utility upgrades. Traffic signal and sign upgrades. Streetscape and lighting improvements. Questions? Jaymes Vettraino City Manager [email protected] 248.609.0606 Tom Gray II, P.E. Vice President/Senior Civil Engineer [email protected] 248.324.2133

Upload: fishbeck-thompson-carr-and-huber

Post on 06-May-2015

183 views

Category:

Design


0 download

DESCRIPTION

A timeline of the reconstruction of downtown Main Street between the Clinton River Bridge and Paint Creek Bridge.

TRANSCRIPT

Page 1: City of Rochester, Main Street Makeover

P R O J E C T T E A M

Fishbeck, Thompson, Carr & Huber Inc. Engineers | Architects | Scientists | Constructors

Providing services for over 50 years.

City of Rochester AIN STREET MAKEOVER

Michigan Department of Transportation

Contractor

Angelo Iafrate Construction Co. NCI EngineeringHubbell Roth & Clark Inc.

City of Rochester Rochester DDA

Design Engineers

Owners

Construction Engineer

What Was done?

•Reconstruction of downtown Main Street

between the Clinton River Bridge and Paint

Creek Bridge.

•Water main replacement and utility upgrades.

•Traffic signal and sign upgrades.

•Streetscape and lighting improvements.

Questions?Jaymes VettrainoCity [email protected]

Tom Gray II, P.E.Vice President/Senior Civil [email protected]

Page 2: City of Rochester, Main Street Makeover

05.15 06.04 07.1708.02

09.2706.01 07.09

Exposed aggregate sidewalk construction begins.

Placement of concrete pavement is completed.

Exposed aggregate sidewalk complete.

Water main complete.

•Full closure opened to traffic. •One lane of traffic in each direction and a center

turn lane is opened to traffic between Second Street and University Drive.

•Single lane closures begin along NB and SB M-150.

•Pavement removal begins•Sidewalk removal begins.•Pedestrian traffic is maintained

along sidewalk adjacent to building using temporary fence.

Full closure starts between Second Street and University Drive.

10.15

M-150RECONSTRUCTION

STA

RT

04.22

04.24

Water main installation begins. Human remains discovered in front of Home Bakery at the NE corner of Third Street and Main Street.

Human remains discovered in front of bridal shop at the SE corner of Third Street and Main Street.

11.17

PROJECT OPENTO TRAFFIC

11.21Concrete paving begins.