City of Eugene Certification Project Case Study

Upload: kalyn-chambliss

Post on 14-Dec-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

City of Eugene

Certification Project Case Study

Page 2: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Why Did Eugene Get Certified?

• Can’t do fund exchange

• ODOT's Local Agency Program

• More project control– Doesn’t have to be the “ODOT Way”– Could use City’s policies, procedures and

processes after ODOT reviewed for compliance with ODOT/FHWA scheme.

Page 3: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Eugene Conditional Certification

• Design

• Consultant Selection

• Advertise, Bid & Award

• Construction Administration

Page 4: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Current Test Projects• Roosevelt Blvd Pavement Preservation

Page 5: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Current Test Projects

• North Game Farm Rd

Page 6: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Current Test Projects

• Chad Drive Extension

Page 7: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Current Test Projects

• West Bank Trail

Page 8: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Getting Started

Page 9: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Design (PE) Phase

• Receive written authorization from ODOT to proceed with design.

• Continue environmental documentation outlined in the Part 3 of the Prospectus

• ODOT Reviews & Approvals of Design

• Final PS&E

Page 10: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

ODOT Reviews

• Design Approval (60%)– LAG Manual Section C, Chapter 10– Prospectus/Design Report

• Advanced PS&E (95%)– Verify environmental clearance– Right of Way Certification– Obtain civil rights requirements– Verify design exceptions & public interest findings

Page 11: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Design Standards

Master Certification Agreement outlines the standards to be used.

– Public Improvement Design Standards (PIDS) Manual

– AASHTO– Oregon-APWA

Specifications & Amendments

– LAG Manual, Section C, Chapters 9, 10, 11

Page 12: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Design Exceptions

• Any deviations from City, AASHTO or other required standards must be documented and approved

• City Approval by City Engineer for City standard only or City funded only

• City & ODOT Approval for AASHTO standard on federally-funded project

Page 13: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

DesignRoosevelt Blvd Pavement Preservation

Page 14: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Design Roosevelt Blvd Pavement Preservation

• ADA Ramps

Page 15: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Consultant Selection

• Procedures:Use City’s Public Contracting RegulationsLAG Manual Section C, Chapter 12 with

Appendices

Page 16: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Consultant Selection• From the LAG Manual, need to include:

Civil Rights (Title VI) information about filing complaints regarding discrimination

Lobbying Prohibition

Page 17: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Consultant Selection

Example:

Roosevelt Blvd Archeological Services (PA

Memo)

Page 18: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Advertise, Bid & Award

• Non-Certified Agency projects are advertised by ODOT (or another local agency certified in advertising, bid and award).– LAG Manual Section B, Chapter 15– ODOT’s Office of Project Letting– ODOT’s Project Delivery Guidebook

Page 19: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Advertise, Bid & Award

• Certified Agency projects are advertised by the local agency.– Use City procedures for advertising, bidding

and contract award. (3 week minimum advertisement period)

– Use ODOT Civil Rights Office to provide for DBE, EEO and OJT requirements.

– Allow 6 weeks for authorization from FHWA to proceed with advertisement.

Page 20: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Pre-Advertisement Timelines

• Environmental Clearance (min. 3-4 weeks prior to advertisement)

• ODOT/FHWA Construction Authorization (allow 4-6 weeks prior to advertisement)

• ODOT PS&E Completeness Checklist

Page 21: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Advertise Bid & Award Roosevelt Blvd Pavement Preservation

• Received authorization July 24, 2008.• Project began advertisement August 5,

opened bids August 29.• Issued one addendum to clarify a

materials specification and a payment specification, and revise some bid quantities. The bid opening was postponed in order to issue the addendum.

Page 22: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Construction

• Non-Certified Agencies– LAG Manual Section B, Chapter 16– ODOT holds the construction contract

• Local agency staff can assign a project manager to work under ODOT oversight

• Local agency may hire a consultant to be the project manager with ODOT oversight

Page 23: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Construction

• Certified Agencies– LAG Manual Section C, Chapter 16– City holds the construction contract and is

responsible for all aspects of contract administration and construction engineering.

Page 24: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Construction• Eugene Certified Construction Contract

Administration– Eugene Project Manager’s Manual– Eugene Inspection Manual– Eugene Field Tested Materials Acceptance

Guide– Oregon Standard Specifications for

Construction (with Eugene Amendments)

Page 25: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Changes

ODOT approval is needed for changes affecting:• Environmental mitigation, classification or

commitments• Scope of work• State facilities• DBE goals, requirements and/or aspirational

targets• Traffic mobility on the state system• AASHTO requirements, such that the change is

below the minimum AASHTO standards

Page 26: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

ConstructionN Game Farm Road

• Jurisdictions of multiple agencies overlapping.

• Overlapping projects (ODOT & City of Eugene)

Page 27: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

ConstructionN Game Farm Road

• Simplified documentation using City process.

• Daily Inspection Reports documenting daily quantities and quality of work.

Page 28: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

ConstructionN Game Farm Road

• Reimbursed for contractor progress payments within 10 days.

• At least one documentation review by Region RAS during the work.

Page 29: City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control

Certification“Pros and Cons”

• Have not found there to be any “cons” in certification.

• Immediate and significant benefits– Design – Consultant selection – Advertise, bid and award

• Realized benefits in all areas due to simplified documentation