city council may 15, 2012 hickory update
DESCRIPTION
TRANSCRIPT
Progress Report
May 15, 2012
San Angelo City Council
2
Agenda
1. Overall project progress
2. Groundwater (GW) Treatment & Disposal Alternatives
3. Surface Water Treatment Plant Assessment
4. Updated treatment costs & schedule
5. Questions
3
Well Field Piping
Completed design: June 28, 2011 Bids Received: August 12, 2011 Contractor: Price Construction, LTD NTP: October 4, 2011 Current Status: Construction is 95% complete
4
Transmission Main
Completed design: August 12, 2011 Bids Received: September 23, 2012 Contractor: Oscar Renda Contracting Delay in approval and release of funds by TWDB NTP: January 23, 2012 Current status: Construction activities are
underway
5
Booster Pump Station & Well Field
Completed design: February 29, 2012 Design approved by TCEQ & TWDB: April 2012 Bids Received: May 1, 2012 Contractor: Archer Western Construction LLC Status: COSA Approval NTP: June 11, 2012 pending final approval and
release of funds by TWDB
6
Groundwater Treatment
Ion Exchange (IX) pilot testing 100% completeReverse Osmosis (RO) pilot testing 95% complete
Surface Water Treatment Plant Assessment completed for incorporation of new facilities
Final design will commence upon selection of treatment/disposal alternative
7
Groundwater Treatment Background
Single-use Ion Exchange (IX)• Previous pilot testing for groundwater indicated that
single use ion exchange is a viable technology for removing radium
• Pilot tests showed that O&M costs were higher than what was suggested by the manufacturers
• Results suggested evaluating other treatment technologies like RO
Reverse Osmosis • Pilot Plant investigations started in January 2012
8
Treatment Alternative 1: Single-Use Ion Exchange (IX)
Pretreatment
Finished Water(99% Recovery)
GranularMediaFilter
Well
Ion Exchange (IX)
SpentResin
Disposal to Licensed Facility
Phosphate
9
Treatment Alternative 2: Reverse Osmosis (RO)
Finished Water (90% Recovery)
Excellent Water Quality
GranularMediaFilter
Pretreatment
Well
CartridgeFilters
Post Treatment3-Stage RO
AirStripper
Brine to Treatment/Disposal
CalciteContactor
CO2
Acid Antiscalant
10
Preliminary RO Results Summary
Excellent membrane performance All three (3) RO membranes tested produced
good results which allows good competition All membranes tested maintained radium
below 1 pCi/L in the treated water
11
Comparison of Radium at the Point of Entry Using RO and Single-Use IX
Combined Ra
(pCi/L)
Time
5TCEQ Limit
RO Effluent
IX Effluent
0
12
GW Treatment/Disposal Alternatives
1. Single-Use Ion Exchange (IX) with spent media to an approved landfill
2. Reverse Osmosis (RO) with Brine to:a. Deep well injection
b. Land application (mixing with WWTP Effluent)
c. Single-Use Ion Exchange (IX)
2a. Brine Disposal/ Deep Well Injection
Inject RO brine into deep underground aquifer Location of injection wells needs to be identified Test well needs to be constructed and piloted at anticipated
full scale capacity prior to approval (approx 18 months)
2b. Brine Disposal / Land Application
Brine is pumped to storage pond at wastewater treatment plant (WWTP)
Brine blended with WWTP effluent Mixture is land applied
2c. Brine Disposal/ IX Brine Treatment
Single-use IX used to treat RO brine Treated concentrate sent to sewer Resin disposed of at a low-level radioactive waste site
16
Incorporation of Hickory GW into Existing SWTP Investigated incorporation of Groundwater Treatment
Facilities to expedite design once a treatment alternative is selected
Evaluated existing plant conditions with respect to regulations, reliability, performance & hydraulics
Conducted a blending study to investigate compatibility of the Surface Water & Ground Water
Estimated Construction Costs Comparison for a Treatment Capacity of 6 mgd
Alternative
1. IX2a. RO / Deep
Well Inj.2b. RO / Land Application
2c. RO/IX
Capital Cost(millions) $23.4 $61.0 $65.0 $39.8
Annual O&M(millions) $3.3 $2.4 $1.8 $2.2
NPV O&M Costs(millions) $92.3 $68.5 $51.1 $62.2
Total NPV Cost(millions) $115.7 $129.5 $116.1 $102.0
Note: Costs in millions and are for 2012 dollars, assuming a discount rate of 3% and a project life of 30 years starting in 2014, with a capacity of 6 mgd and no expansions.
18
IX RO/ Deep Well
RO / Land Applicatio
nRO / IX
Anticipated Start June 2012
Deep Well Full Scale Pilot Design & Operation (Approval needed by TCEQ, TWDB) --- 18 --- ---
Design (Expedited) 8 11 11 9
TCEQ / TWDB Review 2 2 2 2
Bid/Award/NTP 2 2 2 2
Construction 12 – 15 15 - 18 15 - 18 15 - 18
Total time 24 - 28 months
48 - 51 months
30 - 33 months
28 - 31 months
Anticipated Schedule
Ion Exchange (IX)
Reverse Osmosis with
Brine (IX) Treatment
Capital costs ✓
Annual O&M ✓
Net present value ✓ ✓
Schedule ✓ ✓
Treated water quality ✓
Water recovery ✓
Price fluctuations/competition ✓
Treatment Alternative Evaluation Summary
Questions?
May 15, 2012
San Angelo City Council
EXTRA SLIDES
Capital Cost to Add 3 MGD Capacity in 2014
Ion ExchangeReverse Osmosis with
IX of Brine
Additional Wells, piping, civil, electrical etc $14.5 $14.5
Booster Pump Station Upgrade $0.4 $0.4
Treatment $6.0 $11.1
Total Cost $20.9 $26.0
Note: Estimates are given in millions for 2012 dollars. Additional engineering & management is estimated at 12% and is included in the estimate
23
Recommended SWTP Improvements
Chemical storage and feed facilities for joint use between GW and SW facilities
New clearwell as the existing clearwell is reaching its service life
Facilities to recycle filter backwash washwater to the head of the surface WTP will conserve an average of 0.3 MGD (100 MG/year)
Raw water blending and flow split structure to handle the different source waters
Costs for Major Recommended SWTP Improvement
AlternativeEstimated Costs
Clearwell $3.9
Backwash handling facilities $3.4
Flow blending split structure $2.9
New control/lab building $2.4
Note: Estimates are given in millions for 2012 dollars. Additional engineering & management is estimated at 15% and is included in the estimate