  • Cincinnati Dayton Rd

    Widening

  • Project Overview

    Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane

    Realignment of Station Rd

    Widening of bridge on Cincinnati Dayton Rd; Replacement of bridge on Station Rd

    New sidewalk and decorative lighting along corridor

    New closed storm system

    New mid-block crosswalks

    Includes rectangular rapid flashing beacons

  • Rectangular rapid

    flashing beacon: Corridor lighting:

  • Mid-block crosswalks

    Cincinnati Dayton Rd Bridge

  • Mid-block crosswalks

    Cincinnati Dayton Rd

    Boys & Girls Club

  • Cincinnati Dayton Rd

    Interstate 75 >>> Post Office

  • Standing at the Intersection of Station Rd and

    Cincinnati Dayton Rd Looking north

    Existing Proposed

  • Standing south of the Cincinnati Dayton Rd bridge

    Looking south

    Existing Proposed

  • Tentative Project Schedule

    Right-of-Way Acquisition Complete End of 2017

    Utility Relocations Ongoing

    Contract Sell Date Spring, 2018

    Construction Start Date Spring, 2018

    Construction Completion Date Summer, 2019

  • General Construction Notes

    Operating hours: 7:00AM 9:00PM Monday through Saturday

    1:00PM 9:00PM Sunday

    Lane restrictions allowed Monday-Friday during non-peak

    hours Peak hours: (7:00AM 8:30AM & 4:30PM 6:30PM)

    Lane restrictions will be allowed on weekends

    Pile driving for the Cincinnati Dayton Rd bridge will be

    restricted to the weekday hours of 8:00AM 4:00PM

  • Construction Sequence

    2018:

    Phase 1

    Phase 2

    Phase 3

    2019:

    Phase 4

    Phase 5

    Phase 6

  • Phase 1 Construction - 2018

    Phase 1 construction begins in Spring, 2018

    Construct temporary pavement on west side of Cincinnati Dayton Rd between Seminary St and I-75

    Permanently widen east side of Cincinnati Dayton Rd bridge

    Permanently widen east side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement

  • Phase 1 Construction - 2018

  • Phase 1 Construction - 2018

    West Chester

    Presbyterian Church

  • Phase 1 Construction - 2018

    Lesourd

    svill

    e

    West C

    heste

    r R

    d

  • Phase 1 Construction - 2018 Seminary St

    You are Here

  • Phase 1 Construction - 2018 Boys & Girls Club

    Cresthaven Ave

  • Phase 2 construction will close Station Rd from May 14th, 2018 through July 23rd, 2018 (10 weeks).

    Realign Station Rd with the intersection of Cincinnati Dayton Rd and Lesourdsville West Chester Rd.

    Complete construction up to the intermediate pavement and open Station Rd on July 23rd, 2018.

    This schedule was implemented to avoid detours during the St. Johns festival (August 3-5, 2018).

    Phase 2 Construction 2018 (Realignment of Station Rd)

  • Station Road Official Detour

    Station Rd Closed

    Official Detour (Trucks)

  • Phase 3 construction begins after the completion of Phase 1 (Phase 2 is independent of other phases)

    Shift traffic to completed east side of Cincinnati Dayton Rd

    Permanently widen west side of Cincinnati Dayton Rd between the Cin Day bridge and I-75 up to the intermediate pavement

    All roadway widening north of the Cincinnati Dayton Rd bridge will be complete up to the intermediate pavement by Winter, 2018

    Phase 3 Construction - 2018

  • Phase 3 Construction - 2018

    West Chester

    Presbyterian Church

  • Phase 3 Construction - 2018

    Lesourd

    svill

    e

    West

    Cheste

    r R

    d

  • Phase 3 Construction - 2018 Seminary St

    You are Here

  • Phase 3 Construction - 2018 Boys & Girls Club Cresthaven Ave

  • Phase 4 construction begins in Spring, 2019

    Permanently widen the west side of the bridge on Cincinnati Dayton Rd

    Permanently widen the west side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cin Day bridge

    Phase 4 Construction 2019 (South of Cin Day Bridge)

  • Phase 4 Construction - 2019

    Locust S

    t

  • Phase 4 Construction - 2019

    St. John Entrance

  • Phase 5 construction will begin after the completion of phase 4

    Permanently widen the east side of Cincinnati Dayton Rd up to the intermediate pavement between West Chester Rd and the Cincinnati Dayton Rd bridge

    This is the final phase of widening construction. Will be completed by Summer, 2019.

    Phase 5 Construction 2019 (South of Cin Day Bridge)

  • Phase 5 Construction - 2019

    Locust S

    t

  • Phase 5 Construction - 2019

    St. John Entrance

  • Phase 6 construction will begin once all widening

    phases are complete

    Pave the final asphalt surface course through the

    entire project

    Apply all final pavement markings

    Final completion date: Summer, 2019

    Phase 6 (Final) Construction - 2019

  • West C

    heste

    r R

    d

  • Cincinnati Dayton Rd

    Boys & Girls Club

  • Cincinnati Dayton Rd

    Post Office

  • Questions?