CIM Use at CenterPoint Energy CIM Use at CenterPoint Energy CIM Use at CenterPoint Energy September 2010 September 2010 Kevin Ding, Valentine Emesih Kevin Ding, Valentine Emesih Control Systems, CenterPoint Energy Control Systems, CenterPoint Energy “Confidential & Proprietary Information – CEII”

Upload: doandieu

Post on 15-Apr-2018

218 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

CIM Use at CenterPoint Energy CIM Use at CenterPoint Energy CIM Use at CenterPoint Energy 

September 2010September 2010

Kevin Ding, Valentine EmesihKevin Ding, Valentine EmesihControl Systems, CenterPoint EnergyControl Systems, CenterPoint Energy

“Confidential & Proprietary  Information – CEII”

Page 2: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

–Company Introduction

–CIM Modeling

–Auto‐Generated One‐lines

– Future Plan

2

Outlines

“Confidential & Proprietary  Information – CEII”

Page 3: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

3

Company Introduction

“Confidential & Proprietary  Information – CEII”

Page 4: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

4

Company Introduction

“Confidential & Proprietary  Information – CEII”

CenterPoint Energy (CNP) Houston Electric

• About 25% of ERCOT load;

• 5,000 square‐mile electric 

service territory serving 2+ 

million customers;

• Own and maintain the 

power lines and electric 

distribution system;

• Installing 2+ million smart 

meters.

Page 5: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

Main reasons to use Common Information  Modeling (CIM) at CenterPoint Energy:

1.

Texas Nodal protocol requirement

2.

Model exchangeable with ERCOT entities, 

3.

Model exchangeable between internal 

applications; 

4.

To Standardize a way exchanging messages.

5

CIM Modeling

“Confidential & Proprietary  Information – CEII”

Page 6: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

Timeline:

6

CIM Modeling

“Confidential & Proprietary  Information – CEII”

2005 Initial efforts to convert CNP EMS model to CIM/XML.

2006 ERCOT initiated its NMMS project in 2006.

2007 Contracted to purchase a Common Modeling 

Management (CMM) System.

1/2009 CNP CMM system in production.

9/2009 ERCOT implemented Single Entry Modeling in NMMS

Present Incremental Model files are exchangeable between 

ERCOT and CenterPoint Energy.

Page 7: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

CenterPoint Energy CMM systemProduction System: Redundant setup

Development System: Single server setup

Currently we are using CMM to1.

Exchange incremental model files with ERCOT 

Nodal Model Management System

2.

Update CNP Network Applications Model

3.

Generate Common models for other applications, 

potentially DMS

4.

Test auto‐layout substation one‐lines

7

CIM Modeling

“Confidential & Proprietary  Information – CEII”

System and Processes:

Page 8: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

Positives– One Common Model (ERCOT and CNP)

– Fewer application interfaces (e.g., substation model for 

DMS)

– Graphic user interface to edit model changes

– Easy access to ERCOT models

– Time‐based model changes

Challenges– Heavy dependency on ERCOT defined schema

– Managing attributes in different namespaces

– Ever‐changing model schema initiated by ERCOT

– Restrictive rules from downstream applications

8

CIM Modeling

“Confidential & Proprietary  Information – CEII”

Page 9: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

• No text‐file

editing anymore

LINE 2 5 2  0.0001  0.0005  1000 1200 …

Model changes will be done in CMM.

9

CIM Modeling

“Confidential & Proprietary  Information – CEII”

Model update example

Page 10: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

Dynamic external modeling

10

CIM Modeling

“Confidential & Proprietary  Information – CEII”

Page 11: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

11

Auto‐Generated One‐lines

“Confidential & Proprietary  Information – CEII”

Use XML model file to automatically generate One‐lines 

Page 12: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

12

Auto‐Generated One‐lines

“Confidential & Proprietary  Information – CEII”

Page 13: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

13

Future Plan

“Confidential & Proprietary  Information – CEII”

CIM/XML models are used in our Network Applications

CNP Network Applications =

Time‐based CIM/XML models + Time‐based auto‐generated one‐lines + Time‐base PI Historian data + Applications

Page 14: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

14

Future Plan

“Confidential & Proprietary  Information – CEII”

CMM

As-built CIM model

Project CIM model 1 (with NOMCR 1 …i)

Project CIM model k (with NOMCR j …m)

As-built NA database

Project NA database 1

Project NA database k

NA Database Server

Page 15: CIM Use at CenterPoint Energy - EPRImydocs.epri.com/.../1009/4ZNAVE2TN5E/E234888_2_4_… ·  · 2010-09-15CIM Use at CenterPoint Energy ... ERCOT implemented Single Entry Modeling

15

Future Plan

“Confidential & Proprietary  Information – CEII”

As-built NA database

Project NA database 1

Project NA database k

Real-time SCADA data

Historical data

NA functions

User Consoles

Real-time Operations

R-T Operations Planning

Foren

sic

Inve

stiga

tion