cicpa updated schedule dtd 130816
TRANSCRIPT
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
CICPA Qusahwira Complex -MEP WORKS Recovery Program Updated As Of 6.02.2016, June 16 CompletionCICPA Qusahwira Complex -MEP WORKS Recovery Program Updated As Of 6.02.2016, June 16 Completion346 02-May-15 02-Jul-16 02-May-15 A 02-Jul-16 42.76% AED51,395,000 AED21,989,914
CICPA ProjectCICPA Project 346 02-May-15 02-Jul-16 02-May-15 A 02-Jul-16 42.76% AED51,395,000 AED21,989,914
GeneralGeneral 346 02-May-15 02-Jul-16 02-May-15 A 02-Jul-16 0% AED0 AED0
Contractual MilestonesContractual Milestones 346 02-May-15 02-Jul-16 02-May-15 A 02-Jul-16 0% AED0 AED0
A0005Effective Date of Start for MEP Works 0 02-May-15 02-May-15 A 100% AED0 AED0
A0011Project Contract & Novation Agreement Signing 0 02-May-15 02-May-15 A 100% AED0 AED0
A0055Project Completion 0 02-Jul-16 02-Jul-16* 0% AED0 AED0
Major MilestonesMajor Milestones 103 06-Feb-16 05-Jun-16 06-Feb-16 05-Jun-16 0% AED0 AED0
A51390All Shop Drawings Approval 0 10-Feb-16 10-Feb-16 0% AED0 AED0
A51400All Materials Approval 0 06-Feb-16 06-Feb-16 0% AED0 AED0
A51410MEP Works Completion - Administration Building 0 05-Jun-16 05-Jun-16 0% AED0 AED0
A51420MEP Works Completion - Accommodation Building 0 05-Jun-16 05-Jun-16 0% AED0 AED0
A51430MEP Works Completion- Substation 0 05-Jun-16 05-Jun-16 0% AED0 AED0
A51440MEP Works Completion-Service Yard 0 04-Jun-16 04-Jun-16 0% AED0 AED0
A51450MEP Works Completion-Maintenance Building 0 28-May-16 28-May-16 0% AED0 AED0
A51460MEP Works Completion- Gatehouse Building 0 04-Jun-16 04-Jun-16 0% AED0 AED0
A51470MEP Works Completion-Vehicle Washing Shed 0 01-Jun-16 01-Jun-16 0% AED0 AED0
A51480MEP Works Completion-Ammunition & Ligh weapon Sorgae 0 01-Jun-16 01-Jun-16 0% AED0 AED0
A51490MEP Works Completion-EXTERNAL Works 0 31-Mar-16 31-Mar-16 0% AED0 AED0
EngineeringEngineering 209 28-May-15 10-Feb-16 28-May-15 A 10-Feb-16 99.77% AED513,950 AED512,822
Shop DrawingsShop Drawings 209 28-May-15 10-Feb-16 28-May-15 A 10-Feb-16 99.77% AED513,950 AED512,822
MechanicalMechanical 203 28-May-15 03-Feb-16 28-May-15 A 03-Feb-16 A 100% AED171,317 AED171,317
Submittal 109 28-May-15 05-Oct-15 28-May-15 A 05-Oct-15 A 100% AED85,658 AED85,658
Mechanical Shopdrawing Submission Start 0 28-May-15 28-May-15 A 100% AED0 AED0
Mechanical Shopdrawing Submission Finish 0 05-Oct-15 05-Oct-15 A 100% AED0 AED0
Accomodation Building 50 28-May-15 30-Jul-15 28-May-15 A 30-Jul-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Submission 20 28-May-15 11-Jun-15 28-May-15 A 11-Jun-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Submission 20 20-Jun-15 22-Jun-15 20-Jun-15 A 22-Jun-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 07-Jul-15 30-Jul-15 07-Jul-15 A 30-Jul-15 A 100% AED4,508 AED4,508
Adminstrastion Building 105 02-Jun-15 29-Sep-15 02-Jun-15 A 29-Sep-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Submission 20 02-Jun-15 02-Aug-15 02-Jun-15 A 02-Aug-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Submission 20 20-Jul-15 11-Aug-15 20-Jul-15 A 11-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 19-Sep-15 29-Sep-15 19-Sep-15 A 29-Sep-15 A 100% AED4,508 AED4,508
Gate House Building 20 12-Aug-15 02-Sep-15 12-Aug-15 A 02-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 12-Aug-15 02-Sep-15 12-Aug-15 A 02-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 3 12-Aug-15 02-Sep-15 12-Aug-15 A 02-Sep-15 A 100% AED4,508 AED4,508
Substation Building 20 12-Jul-15 02-Sep-15 12-Jul-15 A 02-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 12-Jul-15 02-Sep-15 12-Jul-15 A 02-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 12-Jul-15 02-Sep-15 12-Jul-15 A 02-Sep-15 A 100% AED4,508 AED4,508
Service Yard 42 24-Aug-15 03-Oct-15 24-Aug-15 A 03-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Basement Floor Works Shopdrawing Submission 20 24-Aug-15 02-Sep-15 24-Aug-15 A 02-Sep-15 A 100% AED4,508 AED4,508
Ground Floor Works Shopdrawing Submission 20 10-Sep-15 22-Sep-15 10-Sep-15 A 22-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 19-Sep-15 03-Oct-15 19-Sep-15 A 03-Oct-15 A 100% AED4,508 AED4,508
Maintainance Building 30 25-Jul-15 08-Aug-15 25-Jul-15 A 08-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 25-Jul-15 27-Jul-15 25-Jul-15 A 27-Jul-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 05-Aug-15 08-Aug-15 05-Aug-15 A 08-Aug-15 A 100% AED4,508 AED4,508
Vehicle Washing Shed 21 21-Jul-15 15-Aug-15 21-Jul-15 A 15-Aug-15 A 100% AED9,017 AED9,017
2015 2016 2017
02-Jul-16, CICPA Qusahwira C
02-Jul-16, CICPA Project
02-Jul-16, General
02-Jul-16, Contractual Milestones
Effective Date of Start for MEP Works
Project Contract & Novation Agreement Signing
Project Completion
05-Jun-16, Major Milestones
All Shop Drawings Approval
All Materials Approval
MEP Works Completion - Adminis
MEP Works Completion - Accomm
MEP Works Completion- Substation
MEP Works Completion-Service Yard
MEP Works Completion-Maintenan
MEP Works Completion- Gatehou
MEP Works Completion-Vehicle W
MEP Works Completion-Ammunit
MEP Works Completion-EXTERNAL Works
10-Feb-16, Engineering
10-Feb-16, Shop Drawings
03-Feb-16 A, Mechanical
05-Oct-15 A, Submittal
Mechanical Shopdrawing Submission Start
Mechanical Shopdrawing Submission Finish
30-Jul-15 A, Accomodation Building
Builders Works & Ground Floor Works Shopdrawing Submission
First Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
29-Sep-15 A, Adminstrastion Building
Builders Works & Ground Floor Works Shopdrawing Submission
First Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
02-Sep-15 A, Gate House Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
02-Sep-15 A, Substation Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
03-Oct-15 A, Service Yard
Builders Works & Basement Floor Works Shopdrawing Submission
Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
08-Aug-15 A, Maintainance Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
15-Aug-15 A, Vehicle Washing Shed
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Builders Works & Ground Floor Works Shopdrawing Submission 20 21-Jul-15 15-Aug-15 21-Jul-15 A 15-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 22-Jul-15 15-Aug-15 22-Jul-15 A 15-Aug-15 A 100% AED4,508 AED4,508
Amunition & Light Weapon Storage 22 20-Jul-15 15-Aug-15 20-Jul-15 A 15-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 20-Jul-15 11-Aug-15 20-Jul-15 A 11-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 22-Jul-15 15-Aug-15 22-Jul-15 A 15-Aug-15 A 100% AED4,508 AED4,508
Approval 186 17-Jun-15 03-Feb-16 17-Jun-15 A 03-Feb-16 A 100% AED85,658 AED85,658
Mechanical Shopdrawing Approval Start 0 17-Jun-15 17-Jun-15 A 100% AED0 AED0
Mechanical Shopdrawing Approval Finish 0 03-Feb-16 03-Feb-16 A 100% AED0 AED0
Accomodation Building 39 28-Jul-15 28-Oct-15 28-Jul-15 A 28-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Approval 14 28-Jul-15 28-Oct-15 28-Jul-15 A 28-Oct-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Approval 14 28-Jul-15 19-Aug-15 28-Jul-15 A 19-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 26-Aug-15 10-Sep-15 26-Aug-15 A 10-Sep-15 A 100% AED4,508 AED4,508
Adminstrastion Building 64 20-Jun-15 15-Oct-15 20-Jun-15 A 15-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Approval 14 20-Jun-15 19-Aug-15 20-Jun-15 A 19-Aug-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Approval 14 26-Jul-15 10-Aug-15 26-Jul-15 A 10-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 26-Aug-15 15-Oct-15 26-Aug-15 A 15-Oct-15 A 100% AED4,508 AED4,508
Gate House Building 14 06-Aug-15 27-Sep-15 06-Aug-15 A 27-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 06-Aug-15 20-Sep-15 06-Aug-15 A 20-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 06-Aug-15 27-Sep-15 06-Aug-15 A 27-Sep-15 A 100% AED4,508 AED4,508
Substation Building 14 01-Aug-15 29-Aug-15 01-Aug-15 A 29-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 01-Aug-15 29-Aug-15 01-Aug-15 A 29-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 01-Aug-15 29-Aug-15 01-Aug-15 A 29-Aug-15 A 100% AED4,508 AED4,508
Service Yard 14 22-Jul-15 12-Oct-15 22-Jul-15 A 12-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Basement Floor Works Shopdrawing Approval 14 22-Jul-15 18-Aug-15 22-Jul-15 A 18-Aug-15 A 100% AED4,508 AED4,508
Ground Floor Works Shopdrawing Approval 14 22-Jul-15 12-Oct-15 22-Jul-15 A 12-Oct-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 22-Jul-15 12-Oct-15 22-Jul-15 A 12-Oct-15 A 100% AED4,508 AED4,508
Maintainance Building 14 28-Jul-15 29-Sep-15 28-Jul-15 A 29-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 28-Jul-15 26-Sep-15 28-Jul-15 A 26-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 28-Jul-15 29-Sep-15 28-Jul-15 A 29-Sep-15 A 100% AED4,508 AED4,508
Vehicle Washing Shed 14 06-Aug-15 26-Sep-15 06-Aug-15 A 26-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 06-Aug-15 20-Sep-15 06-Aug-15 A 20-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 06-Aug-15 26-Sep-15 06-Aug-15 A 26-Sep-15 A 100% AED4,508 AED4,508
Amunition & Light Weapon Storage 14 26-Jul-15 21-Sep-15 26-Jul-15 A 21-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 26-Jul-15 20-Sep-15 26-Jul-15 A 20-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 26-Jul-15 21-Sep-15 26-Jul-15 A 21-Sep-15 A 100% AED4,508 AED4,508
PlumbingPlumbing 184 20-Jun-15 03-Feb-16 20-Jun-15 A 03-Feb-16 A 100% AED171,317 AED171,317
Submittal 172 20-Jun-15 20-Jan-16 20-Jun-15 A 20-Jan-16 A 100% AED85,658 AED85,658
Plumbing Shopdrawing Submission Start 0 20-Jun-15 20-Jun-15 A 100% AED0 AED0
Plumbing Shopdrawing Submission Finish 0 20-Jan-16 20-Jan-16 A 100% AED0 AED0
Accomodation Building 69 20-Jun-15 28-Oct-15 20-Jun-15 A 28-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Submission 20 20-Jun-15 19-Aug-15 20-Jun-15 A 19-Aug-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Submission 20 01-Jul-15 20-Aug-15 01-Jul-15 A 20-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 25-Aug-15 28-Oct-15 25-Aug-15 A 28-Oct-15 A 100% AED4,508 AED4,508
Adminstrastion Building 61 24-Jun-15 28-Oct-15 24-Jun-15 A 28-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Submission 20 24-Jun-15 29-Aug-15 24-Jun-15 A 29-Aug-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Submission 20 01-Jul-15 29-Aug-15 01-Jul-15 A 29-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 19-Aug-15 28-Oct-15 19-Aug-15 A 28-Oct-15 A 100% AED4,508 AED4,508
Gate House Building 20 05-Aug-15 27-Aug-15 05-Aug-15 A 27-Aug-15 A 100% AED9,017 AED9,017
2015 2016 2017
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
15-Aug-15 A, Amunition & Light Weapon Storage
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
03-Feb-16 A, Approval
Mechanical Shopdrawing Approval Start
Mechanical Shopdrawing Approval Finish
28-Oct-15 A, Accomodation Building
Builders Works & Ground Floor Works Shopdrawing Approval
First Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
15-Oct-15 A, Adminstrastion Building
Builders Works & Ground Floor Works Shopdrawing Approval
First Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
27-Sep-15 A, Gate House Building
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
29-Aug-15 A, Substation Building
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
12-Oct-15 A, Service Yard
Builders Works & Basement Floor Works Shopdrawing Approval
Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
29-Sep-15 A, Maintainance Building
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
26-Sep-15 A, Vehicle Washing Shed
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
21-Sep-15 A, Amunition & Light Weapon Storage
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
03-Feb-16 A, Plumbing
20-Jan-16 A, Submittal
Plumbing Shopdrawing Submission Start
Plumbing Shopdrawing Submission Finish
28-Oct-15 A, Accomodation Building
Builders Works & Ground Floor Works Shopdrawing Submission
First Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
28-Oct-15 A, Adminstrastion Building
Builders Works & Ground Floor Works Shopdrawing Submission
First Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
27-Aug-15 A, Gate House Building
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Builders Works & Ground Floor Works Shopdrawing Submission 20 05-Aug-15 27-Aug-15 05-Aug-15 A 27-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 05-Aug-15 27-Aug-15 05-Aug-15 A 27-Aug-15 A 100% AED4,508 AED4,508
Substation Building 21 30-Jul-15 22-Aug-15 30-Jul-15 A 22-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 30-Jul-15 15-Aug-15 30-Jul-15 A 15-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 30-Jul-15 22-Aug-15 30-Jul-15 A 22-Aug-15 A 100% AED4,508 AED4,508
Service Yard 20 21-Jul-15 04-Nov-15 21-Jul-15 A 04-Nov-15 A 100% AED13,525 AED13,525
Builders Works & Basement Floor Works Shopdrawing Submission 20 21-Jul-15 02-Nov-15 21-Jul-15 A 02-Nov-15 A 100% AED4,508 AED4,508
Ground Floor Works Shopdrawing Submission 20 21-Jul-15 02-Nov-15 21-Jul-15 A 02-Nov-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 21-Jul-15 04-Nov-15 21-Jul-15 A 04-Nov-15 A 100% AED4,508 AED4,508
Maintainance Building 20 27-Jul-15 18-Aug-15 27-Jul-15 A 18-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 27-Jul-15 18-Aug-15 27-Jul-15 A 18-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 27-Jul-15 18-Aug-15 27-Jul-15 A 18-Aug-15 A 100% AED4,508 AED4,508
Vehicle Washing Shed 20 05-Aug-15 10-Aug-15 05-Aug-15 A 10-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 05-Aug-15 10-Aug-15 05-Aug-15 A 10-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 05-Aug-15 10-Aug-15 05-Aug-15 A 10-Aug-15 A 100% AED4,508 AED4,508
Amunition & Light Weapon Storage 20 26-Jul-15 17-Aug-15 26-Jul-15 A 17-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 26-Jul-15 10-Aug-15 26-Jul-15 A 10-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 26-Jul-15 17-Aug-15 26-Jul-15 A 17-Aug-15 A 100% AED4,508 AED4,508
Approval 184 20-Jun-15 03-Feb-16 20-Jun-15 A 03-Feb-16 A 100% AED85,658 AED85,658
Plumbing Shopdrawing Approval Start 0 30-Jun-15 30-Jun-15 A 100% AED0 AED0
Plumbing Shopdrawing Approval Finish 0 03-Feb-16 03-Feb-16 A 100% AED0 AED0
Accomodation Building 39 28-Jul-15 03-Feb-16 28-Jul-15 A 03-Feb-16 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Approval 14 28-Jul-15 29-Oct-15 28-Jul-15 A 29-Oct-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Approval 14 28-Jul-15 29-Oct-15 28-Jul-15 A 29-Oct-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 26-Aug-15 03-Feb-16 26-Aug-15 A 03-Feb-16 A 100% AED4,508 AED4,508
Adminstrastion Building 92 20-Jun-15 31-Jan-16 20-Jun-15 A 31-Jan-16 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Approval 14 20-Jun-15 19-Aug-15 20-Jun-15 A 19-Aug-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Approval 14 26-Jul-15 10-Aug-15 26-Jul-15 A 10-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 26-Aug-15 31-Jan-16 26-Aug-15 A 31-Jan-16 A 100% AED4,508 AED4,508
Gate House Building 14 06-Aug-15 27-Sep-15 06-Aug-15 A 27-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 06-Aug-15 20-Sep-15 06-Aug-15 A 20-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 06-Aug-15 27-Sep-15 06-Aug-15 A 27-Sep-15 A 100% AED4,508 AED4,508
Substation Building 14 01-Aug-15 16-Aug-15 01-Aug-15 A 16-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 01-Aug-15 16-Aug-15 01-Aug-15 A 16-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 01-Aug-15 16-Aug-15 01-Aug-15 A 16-Aug-15 A 100% AED4,508 AED4,508
Service Yard 14 22-Jul-15 19-Nov-15 22-Jul-15 A 19-Nov-15 A 100% AED13,525 AED13,525
Builders Works & Basement Floor Works Shopdrawing Approval 14 22-Jul-15 18-Nov-15 22-Jul-15 A 18-Nov-15 A 100% AED4,508 AED4,508
Ground Floor Works Shopdrawing Approval 14 22-Jul-15 19-Nov-15 22-Jul-15 A 19-Nov-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 22-Jul-15 19-Nov-15 22-Jul-15 A 19-Nov-15 A 100% AED4,508 AED4,508
Maintainance Building 14 28-Jul-15 12-Aug-15 28-Jul-15 A 12-Aug-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 28-Jul-15 12-Aug-15 28-Jul-15 A 12-Aug-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 28-Jul-15 12-Aug-15 28-Jul-15 A 12-Aug-15 A 100% AED4,508 AED4,508
Vehicle Washing Shed 14 06-Aug-15 21-Nov-15 06-Aug-15 A 21-Nov-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 14 06-Aug-15 18-Nov-15 06-Aug-15 A 18-Nov-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 06-Aug-15 21-Nov-15 06-Aug-15 A 21-Nov-15 A 100% AED4,508 AED4,508
Amunition & Light Weapon Storage 26 10-Aug-15 08-Sep-15 10-Aug-15 A 08-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Approval 26 10-Aug-15 08-Sep-15 10-Aug-15 A 08-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Approval 14 10-Aug-15 08-Sep-15 10-Aug-15 A 08-Sep-15 A 100% AED4,508 AED4,508
2015 2016 2017
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
22-Aug-15 A, Substation Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
04-Nov-15 A, Service Yard
Builders Works & Basement Floor Works Shopdrawing Submission
Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
18-Aug-15 A, Maintainance Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
10-Aug-15 A, Vehicle Washing Shed
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
17-Aug-15 A, Amunition & Light Weapon Storage
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
03-Feb-16 A, Approval
Plumbing Shopdrawing Approval Start
Plumbing Shopdrawing Approval Finish
03-Feb-16 A, Accomodation Building
Builders Works & Ground Floor Works Shopdrawing Approval
First Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
31-Jan-16 A, Adminstrastion Building
Builders Works & Ground Floor Works Shopdrawing Approval
First Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
27-Sep-15 A, Gate House Building
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
16-Aug-15 A, Substation Building
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
19-Nov-15 A, Service Yard
Builders Works & Basement Floor Works Shopdrawing Approval
Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
12-Aug-15 A, Maintainance Building
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
21-Nov-15 A, Vehicle Washing Shed
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
08-Sep-15 A, Amunition & Light Weapon Storage
Builders Works & Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 3 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
ElectricalElectrical 197 11-Jun-15 10-Feb-16 11-Jun-15 A 10-Feb-16 99.32% AED171,317 AED170,188
Submittal 196 11-Jun-15 09-Feb-16 11-Jun-15 A 09-Feb-16 100% AED85,658 AED85,658
Electrical Shopdrawing Submission Start 0 11-Jun-15 11-Jun-15 A 100% AED0 AED0
Electrical Shopdrawing Submission Finish 0 09-Feb-16 09-Feb-16 0% AED0 AED0
Accomodation Building 23 11-Jun-15 20-Oct-15 11-Jun-15 A 20-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Submission 20 11-Jun-15 20-Sep-15 11-Jun-15 A 20-Sep-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Submission 20 11-Jun-15 20-Oct-15 11-Jun-15 A 20-Oct-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 15-Jun-15 20-Oct-15 15-Jun-15 A 20-Oct-15 A 100% AED4,508 AED4,508
Adminstrastion Building 35 17-Jun-15 04-Feb-16 17-Jun-15 A 04-Feb-16 A 100% AED13,525 AED13,525
Builders Works & Ground Floor Works Shopdrawing Submission 20 17-Jun-15 03-Oct-15 17-Jun-15 A 03-Oct-15 A 100% AED4,508 AED4,508
First Floor Works Shopdrawing Submission 20 11-Jul-15 04-Feb-16 11-Jul-15 A 04-Feb-16 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 11-Jul-15 04-Feb-16 11-Jul-15 A 04-Feb-16 A 100% AED4,508 AED4,508
Gate House Building 20 25-Jun-15 30-Sep-15 25-Jun-15 A 30-Sep-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 25-Jun-15 30-Sep-15 25-Jun-15 A 30-Sep-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 25-Jun-15 30-Sep-15 25-Jun-15 A 30-Sep-15 A 100% AED4,508 AED4,508
Substation Building 20 08-Jul-15 15-Oct-15 08-Jul-15 A 15-Oct-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 08-Jul-15 15-Oct-15 08-Jul-15 A 15-Oct-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 08-Jul-15 15-Oct-15 08-Jul-15 A 15-Oct-15 A 100% AED4,508 AED4,508
Service Yard 20 05-Jul-15 05-Oct-15 05-Jul-15 A 05-Oct-15 A 100% AED13,525 AED13,525
Builders Works & Basement Floor Works Shopdrawing Submission 20 05-Jul-15 05-Oct-15 05-Jul-15 A 05-Oct-15 A 100% AED4,508 AED4,508
Ground Floor Works Shopdrawing Submission 20 05-Jul-15 05-Oct-15 05-Jul-15 A 05-Oct-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 05-Jul-15 05-Oct-15 05-Jul-15 A 05-Oct-15 A 100% AED4,508 AED4,508
Maintainance Building 20 20-Jul-15 04-Oct-15 20-Jul-15 A 04-Oct-15 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 20-Jul-15 04-Oct-15 20-Jul-15 A 04-Oct-15 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 20-Jul-15 04-Oct-15 20-Jul-15 A 04-Oct-15 A 100% AED4,508 AED4,508
Vehicle Washing Shed 20 21-Jul-15 03-Feb-16 21-Jul-15 A 03-Feb-16 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 21-Jul-15 03-Feb-16 21-Jul-15 A 03-Feb-16 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 21-Jul-15 03-Feb-16 21-Jul-15 A 03-Feb-16 A 100% AED4,508 AED4,508
Amunition & Light Weapon Storage 40 21-Jul-15 03-Feb-16 21-Jul-15 A 03-Feb-16 A 100% AED9,017 AED9,017
Builders Works & Ground Floor Works Shopdrawing Submission 20 21-Jul-15 03-Feb-16 21-Jul-15 A 03-Feb-16 A 100% AED4,508 AED4,508
Roof Works Shopdrawing Submission 20 09-Aug-15 03-Feb-16 09-Aug-15 A 03-Feb-16 A 100% AED4,508 AED4,508
Approval 178 08-Jul-15 10-Feb-16 08-Jul-15 A 10-Feb-16 98.63% AED85,658 AED84,530
Electrical Shopdrawing Approval Start 0 08-Jul-15 08-Jul-15 A 100% AED0 AED0
Electrical Shopdrawing Approval Finish 0 10-Feb-16 10-Feb-16 0% AED0 AED0
Accomodation Building 19 08-Jul-15 06-Feb-16 08-Jul-15 A 06-Feb-16 99% AED13,525 AED13,446
Builders Works & Ground Floor Works Shopdrawing Approval 14 08-Jul-15 06-Feb-16 08-Jul-15 A 06-Feb-16 99% AED4,508 AED4,482
First Floor Works Shopdrawing Approval 14 15-Jul-15 06-Feb-16 15-Jul-15 A 06-Feb-16 99% AED4,508 AED4,482
Roof Works Shopdrawing Approval 14 15-Jul-15 06-Feb-16 15-Jul-15 A 06-Feb-16 99% AED4,508 AED4,482
Adminstrastion Building 20 11-Jul-15 06-Feb-16 11-Jul-15 A 06-Feb-16 99% AED13,525 AED13,445
Builders Works & Ground Floor Works Shopdrawing Approval 14 11-Jul-15 06-Feb-16 11-Jul-15 A 06-Feb-16 99% AED4,508 AED4,482
First Floor Works Shopdrawing Approval 14 15-Jul-15 06-Feb-16 15-Jul-15 A 06-Feb-16 99% AED4,508 AED4,482
Roof Works Shopdrawing Approval 14 21-Jul-15 06-Feb-16 21-Jul-15 A 06-Feb-16 99% AED4,508 AED4,481
Gate House Building 37 11-Jul-15 06-Feb-16 11-Jul-15 A 06-Feb-16 98% AED9,017 AED8,603
Builders Works & Ground Floor Works Shopdrawing Approval 14 11-Jul-15 06-Feb-16 11-Jul-15 A 06-Feb-16 98% AED4,508 AED4,482
Roof Works Shopdrawing Approval 14 10-Aug-15 06-Feb-16 10-Aug-15 A 06-Feb-16 98% AED4,508 AED4,121
Substation Building 27 26-Jul-15 06-Feb-16 26-Jul-15 A 06-Feb-16 99% AED9,017 AED8,959
Builders Works & Ground Floor Works Shopdrawing Approval 14 26-Jul-15 06-Feb-16 26-Jul-15 A 06-Feb-16 99% AED4,508 AED4,481
Roof Works Shopdrawing Approval 14 10-Aug-15 06-Feb-16 10-Aug-15 A 06-Feb-16 99% AED4,508 AED4,478
2015 2016 2017
10-Feb-16, Electrical
09-Feb-16, Submittal
Electrical Shopdrawing Submission Start
Electrical Shopdrawing Submission Finish
20-Oct-15 A, Accomodation Building
Builders Works & Ground Floor Works Shopdrawing Submission
First Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
04-Feb-16 A, Adminstrastion Building
Builders Works & Ground Floor Works Shopdrawing Submission
First Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
30-Sep-15 A, Gate House Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
15-Oct-15 A, Substation Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
05-Oct-15 A, Service Yard
Builders Works & Basement Floor Works Shopdrawing Submission
Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
04-Oct-15 A, Maintainance Building
Builders Works & Ground Floor Works Shopdrawing Submission
Roof Works Shopdrawing Submission
03-Feb-16 A, Vehicle Washing Shed
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Submission
03-Feb-16 A, Amunition & Light Weapon Storage
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Submission
10-Feb-16, Approval
Electrical Shopdrawing Approval Start
Electrical Shopdrawing Approval Finish
06-Feb-16, Accomodation Building
Builders Works & Ground Floor Works Shopdra
First Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
06-Feb-16, Adminstrastion Building
Builders Works & Ground Floor Works Shopdra
First Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
06-Feb-16, Gate House Building
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Approval
06-Feb-16, Substation Building
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Approval
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 4 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Service Yard 27 26-Jul-15 06-Feb-16 26-Jul-15 A 06-Feb-16 98% AED13,525 AED13,440
Builders Works & Basement Floor Works Shopdrawing Approval 14 26-Jul-15 06-Feb-16 26-Jul-15 A 06-Feb-16 98% AED4,508 AED4,481
Ground Floor Works Shopdrawing Approval 14 26-Jul-15 06-Feb-16 26-Jul-15 A 06-Feb-16 98% AED4,508 AED4,481
Roof Works Shopdrawing Approval 14 10-Aug-15 06-Feb-16 10-Aug-15 A 06-Feb-16 98% AED4,508 AED4,478
Maintainance Building 20 03-Aug-15 06-Feb-16 03-Aug-15 A 06-Feb-16 98% AED9,017 AED8,958
Builders Works & Ground Floor Works Shopdrawing Approval 14 03-Aug-15 06-Feb-16 03-Aug-15 A 06-Feb-16 98% AED4,508 AED4,479
Roof Works Shopdrawing Approval 14 10-Aug-15 06-Feb-16 10-Aug-15 A 06-Feb-16 98% AED4,508 AED4,478
Vehicle Washing Shed 21 06-Aug-15 10-Feb-16 06-Aug-15 A 10-Feb-16 99% AED9,017 AED8,723
Builders Works & Ground Floor Works Shopdrawing Approval 14 06-Aug-15 10-Feb-16 06-Aug-15 A 10-Feb-16 99% AED4,508 AED4,365
Roof Works Shopdrawing Approval 14 15-Aug-15 10-Feb-16 15-Aug-15 A 10-Feb-16 99% AED4,508 AED4,358
Amunition & Light Weapon Storage 21 06-Aug-15 06-Feb-16 06-Aug-15 A 06-Feb-16 99% AED9,017 AED8,956
Builders Works & Ground Floor Works Shopdrawing Approval 14 06-Aug-15 06-Feb-16 06-Aug-15 A 06-Feb-16 99% AED4,508 AED4,479
Roof Works Shopdrawing Approval 14 15-Aug-15 06-Feb-16 15-Aug-15 A 06-Feb-16 99% AED4,508 AED4,477
Procurement ServicesProcurement Services 259 11-May-15 23-Apr-16 11-May-15 A 23-Apr-16 70.1% AED11,820,850 AED8,650,964
Material Submittal & Approval of Long Lead & Other MaterialsMaterial Submittal & Approval of Long Lead & Other Materials 196 11-May-15 29-Dec-15 11-May-15 A 29-Dec-15 A 100% AED640,294 AED640,294
SubmittalSubmittal 144 11-May-15 28-Oct-15 11-May-15 A 28-Oct-15 A 100% AED320,147 AED320,147
MEP 144 11-May-15 28-Oct-15 11-May-15 A 28-Oct-15 A 100% AED320,147 AED320,147
Material Submittal- HV Cable 14 07-Jul-15 01-Sep-15 07-Jul-15 A 01-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- SMDBs & DB's 14 19-Sep-15 05-Oct-15 19-Sep-15 A 05-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- IT, LAN and Telephone System 14 24-Aug-15 01-Sep-15 24-Aug-15 A 01-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Transformer 14 03-Aug-15 05-Sep-15 03-Aug-15 A 05-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- CCTV System 14 24-Aug-15 01-Sep-15 24-Aug-15 A 01-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Access Control System 14 24-Aug-15 01-Sep-15 24-Aug-15 A 01-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Central Battery System 14 21-Jul-15 05-Aug-15 21-Jul-15 A 05-Aug-15 A 100% AED8,209 AED8,209
Material Submittal- Light Fixtures 14 05-Sep-15 08-Sep-15 05-Sep-15 A 08-Sep-15 A 100% AED8,209 AED8,209
Material Submittal - Switch Gear / HV Panel 14 29-Aug-15 13-Sep-15 29-Aug-15 A 13-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Generators / UPS 14 22-Aug-15 10-Oct-15 22-Aug-15 A 10-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- MDBs & Capacitor Bank (LV Panels) 14 29-Aug-15 13-Sep-15 29-Aug-15 A 13-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- IBMS 14 16-Aug-15 31-Aug-15 16-Aug-15 A 31-Aug-15 A 100% AED8,209 AED8,209
Material Submittal- LV Cable 14 27-Jun-15 29-Jun-15 27-Jun-15 A 29-Jun-15 A 100% AED8,209 AED8,209
Material Submittal- Cable Trays 14 27-Jul-15 12-Aug-15 27-Jul-15 A 12-Aug-15 A 100% AED8,209 AED8,209
Material Submittal- Trunking 14 04-Jun-15 11-Jul-15 04-Jun-15 A 11-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- HVAC Ducts 14 23-May-15 07-Jun-15 23-May-15 A 07-Jun-15 A 100% AED8,209 AED8,209
Material Submittal- Chilled Water Pipes-Fittings-Valves 14 22-Jun-15 01-Jul-15 22-Jun-15 A 01-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Air Outlets 14 29-Jul-15 01-Sep-15 29-Jul-15 A 01-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- PPR Pipes -Fittings-Valves (Water) 14 11-May-15 01-Jul-15 11-May-15 A 01-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- UPVC Pipes-Fittings-Valves(Drainage) 14 11-May-15 01-Jul-15 11-May-15 A 01-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Fire Pipes-Fittings-Valves 14 01-Sep-15 15-Sep-15 01-Sep-15 A 15-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Fire Fighting Equipments 14 01-Sep-15 15-Sep-15 01-Sep-15 A 15-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Fire Alarm System 14 02-Jul-15 12-Jul-15 02-Jul-15 A 12-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Fire Fighting system Accessories 14 15-Sep-15 03-Oct-15 15-Sep-15 A 03-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- Filter Pump 14 05-Oct-15 21-Oct-15 05-Oct-15 A 21-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- AHU 14 25-Aug-15 09-Sep-15 25-Aug-15 A 09-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Package Unit 14 02-Jul-15 25-Jul-15 02-Jul-15 A 25-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Chiller 14 12-Jul-15 27-Jul-15 12-Jul-15 A 27-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Primary Chilled Water Pumps 14 04-Jul-15 11-Aug-15 04-Jul-15 A 11-Aug-15 A 100% AED8,209 AED8,209
Material Submittal- Fans 14 20-Jul-15 01-Sep-15 20-Jul-15 A 01-Sep-15 A 100% AED8,209 AED8,209
2015 2016 2017
06-Feb-16, Service Yard
Builders Works & Basement Floor Works Shopd
Ground Floor Works Shopdrawing Approval
Roof Works Shopdrawing Approval
06-Feb-16, Maintainance Building
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Approval
10-Feb-16, Vehicle Washing Shed
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Approval
06-Feb-16, Amunition & Light Weapon Storage
Builders Works & Ground Floor Works Shopdra
Roof Works Shopdrawing Approval
23-Apr-16, Procurement Services
29-Dec-15 A, Material Submittal & Approval of Long
28-Oct-15 A, Submittal
28-Oct-15 A, MEP
Material Submittal- HV Cable
Material Submittal- SMDBs & DB's
Material Submittal- IT, LAN and Telephone System
Material Submittal- Transformer
Material Submittal- CCTV System
Material Submittal- Access Control System
Material Submittal- Central Battery System
Material Submittal- Light Fixtures
Material Submittal - Switch Gear / HV Panel
Material Submittal- Generators / UPS
Material Submittal- MDBs & Capacitor Bank (LV Panels)
Material Submittal- IBMS
Material Submittal- LV Cable
Material Submittal- Cable Trays
Material Submittal- Trunking
Material Submittal- HVAC Ducts
Material Submittal- Chilled Water Pipes-Fittings-Valves
Material Submittal- Air Outlets
Material Submittal- PPR Pipes -Fittings-Valves (Water)
Material Submittal- UPVC Pipes-Fittings-Valves(Drainage)
Material Submittal- Fire Pipes-Fittings-Valves
Material Submittal- Fire Fighting Equipments
Material Submittal- Fire Alarm System
Material Submittal- Fire Fighting system Accessories
Material Submittal- Filter Pump
Material Submittal- AHU
Material Submittal- Package Unit
Material Submittal- Chiller
Material Submittal- Primary Chilled Water Pumps
Material Submittal- Fans
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 5 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Material Submittal- FCUs \ CCUs 14 12-Jul-15 27-Jul-15 12-Jul-15 A 27-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Sanitarywares 14 21-Jul-15 05-Aug-15 21-Jul-15 A 05-Aug-15 A 100% AED8,209 AED8,209
Material Submittal- Solar System 14 05-Jul-15 26-Jul-15 05-Jul-15 A 26-Jul-15 A 100% AED8,209 AED8,209
Material Submittal- Bulk Storage Fuel Tank 14 01-Oct-15 18-Oct-15 01-Oct-15 A 18-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- Fire Fighting Pump 14 24-Oct-15 28-Oct-15 24-Oct-15 A 28-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- Booster Pump 14 20-Aug-15 05-Sep-15 20-Aug-15 A 05-Sep-15 A 100% AED8,209 AED8,209
Material Submittal- Inergen Fire Protection System 14 07-Oct-15 24-Oct-15 07-Oct-15 A 24-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- Gate Barrier 14 10-Oct-15 26-Oct-15 10-Oct-15 A 26-Oct-15 A 100% AED8,209 AED8,209
Material Submittal- Lighting Control System 14 21-Jul-15 05-Aug-15 21-Jul-15 A 05-Aug-15 A 100% AED8,209 AED8,209
ApprovalApproval 176 04-Jun-15 29-Dec-15 04-Jun-15 A 29-Dec-15 A 100% AED320,147 AED320,147
MEP 176 04-Jun-15 29-Dec-15 04-Jun-15 A 29-Dec-15 A 100% AED320,147 AED320,147
Material Approval- LV Cable 14 29-Jun-15 21-Jul-15 29-Jun-15 A 21-Jul-15 A 100% AED8,209 AED8,209
Material Approval- Cable Trays 14 04-Jun-15 02-Sep-15 04-Jun-15 A 02-Sep-15 A 100% AED8,209 AED8,209
Material Approval- Trunking 14 04-Aug-15 02-Sep-15 04-Aug-15 A 02-Sep-15 A 100% AED8,209 AED8,209
Material Approval- HV Cable 14 08-Jul-15 17-Oct-15 08-Jul-15 A 17-Oct-15 A 100% AED8,209 AED8,209
Material Approval- SMDBs & DB's 14 12-Oct-15 14-Oct-15 12-Oct-15 A 14-Oct-15 A 100% AED8,209 AED8,209
Material Approval- IT, LAN and Telephone System 14 07-Oct-15 14-Oct-15 07-Oct-15 A 14-Oct-15 A 100% AED8,209 AED8,209
Material Approval - Transformer 14 20-Aug-15 03-Oct-15 20-Aug-15 A 03-Oct-15 A 100% AED8,209 AED8,209
Material Approval - CCTV System 14 10-Sep-15 12-Sep-15 10-Sep-15 A 12-Sep-15 A 100% AED8,209 AED8,209
Material Approval - Access Control System 14 14-Sep-15 16-Sep-15 14-Sep-15 A 16-Sep-15 A 100% AED8,209 AED8,209
Material Approval - Central Battery System 14 30-Jul-15 05-Sep-15 30-Jul-15 A 05-Sep-15 A 100% AED8,209 AED8,209
Material Approval - Light Fixtures 14 09-Sep-15 17-Sep-15 09-Sep-15 A 17-Sep-15 A 100% AED8,209 AED8,209
Material Approval - Switch Gear / HV Panel 14 12-Oct-15 14-Oct-15 12-Oct-15 A 14-Oct-15 A 100% AED8,209 AED8,209
Material Approval - Generators / UPS 14 03-Sep-15 05-Sep-15 03-Sep-15 A 05-Sep-15 A 100% AED8,209 AED8,209
Material Approval - MDBs & Capacitor Bank (LV Panels) 14 20-Aug-15 03-Oct-15 20-Aug-15 A 03-Oct-15 A 100% AED8,209 AED8,209
Material Approval - IBMS 14 06-Sep-15 10-Sep-15 06-Sep-15 A 10-Sep-15 A 100% AED8,209 AED8,209
Material Approval - Fans 14 29-Aug-15 14-Sep-15 29-Aug-15 A 14-Sep-15 A 100% AED8,209 AED8,209
Material Approval - FCUs \ CCUs 14 13-Jul-15 29-Aug-15 13-Jul-15 A 29-Aug-15 A 100% AED8,209 AED8,209
Material Approval - Sanitarywares 14 22-Jul-15 08-Aug-15 22-Jul-15 A 08-Aug-15 A 100% AED8,209 AED8,209
Material Approval - Solar System 14 20-Jul-15 17-Oct-15 20-Jul-15 A 17-Oct-15 A 100% AED8,209 AED8,209
Material Approval - Bulk Storage Fuel Tank 14 20-Jul-15 10-Oct-15 20-Jul-15 A 10-Oct-15 A 100% AED8,209 AED8,209
Material Approval - Fire Fighting Pump 14 14-Oct-15 11-Nov-15 14-Oct-15 A 11-Nov-15 A 100% AED8,209 AED8,209
Material Approval - Booster Pump 14 26-Dec-15 29-Dec-15 26-Dec-15 A 29-Dec-15 A 100% AED8,209 AED8,209
Material Approval - Inergen Fire Protection System 14 22-Nov-15 26-Nov-15 22-Nov-15 A 26-Nov-15 A 100% AED8,209 AED8,209
Material Approval - Lighting Control System 14 27-Jul-15 11-Aug-15 27-Jul-15 A 11-Aug-15 A 100% AED8,209 AED8,209
Material Approval- HVAC Ducts 14 13-Jul-15 15-Sep-15 13-Jul-15 A 15-Sep-15 A 100% AED8,209 AED8,209
Material Approval- Chilled Water Pipes-Fittings-Valves 14 15-Jul-15 29-Jul-15 15-Jul-15 A 29-Jul-15 A 100% AED8,209 AED8,209
Material Approval- Air Outlets 14 10-Aug-15 25-Aug-15 10-Aug-15 A 25-Aug-15 A 100% AED8,209 AED8,209
Material Approval- PPR Pipes -Fittings-Valves (Water) 14 01-Jul-15 15-Jul-15 01-Jul-15 A 15-Jul-15 A 100% AED8,209 AED8,209
Material Approval- UPVC Pipes-Fittings-Valves(Drainage) 14 02-Jul-15 25-Jul-15 02-Jul-15 A 25-Jul-15 A 100% AED8,209 AED8,209
Material Approval- Fire Pipes-Fittings-Valves 14 04-Oct-15 05-Nov-15 04-Oct-15 A 05-Nov-15 A 100% AED8,209 AED8,209
Material Approval- Fire Fighting Equipments 14 04-Oct-15 05-Nov-15 04-Oct-15 A 05-Nov-15 A 100% AED8,209 AED8,209
Material Approval- Fire Alarm System 14 12-Jul-15 26-Jul-15 12-Jul-15 A 26-Jul-15 A 100% AED8,209 AED8,209
Material Approval- Gate Barrier 14 20-Oct-15 04-Nov-15 20-Oct-15 A 04-Nov-15 A 100% AED8,209 AED8,209
Material Approval - Fire Fighting system Accessories 14 04-Oct-15 05-Nov-15 04-Oct-15 A 05-Nov-15 A 100% AED8,209 AED8,209
Material Approval - Filter Pump 14 26-Dec-15 28-Dec-15 26-Dec-15 A 28-Dec-15 A 100% AED8,209 AED8,209
Material Approval - AHU 14 26-Sep-15 28-Sep-15 26-Sep-15 A 28-Sep-15 A 100% AED8,209 AED8,209
2015 2016 2017
Material Submittal- FCUs \ CCUs
Material Submittal- Sanitarywares
Material Submittal- Solar System
Material Submittal- Bulk Storage Fuel Tank
Material Submittal- Fire Fighting Pump
Material Submittal- Booster Pump
Material Submittal- Inergen Fire Protection System
Material Submittal- Gate Barrier
Material Submittal- Lighting Control System
29-Dec-15 A, Approval
29-Dec-15 A, MEP
Material Approval- LV Cable
Material Approval- Cable Trays
Material Approval- Trunking
Material Approval- HV Cable
Material Approval- SMDBs & DB's
Material Approval- IT, LAN and Telephone System
Material Approval - Transformer
Material Approval - CCTV System
Material Approval - Access Control System
Material Approval - Central Battery System
Material Approval - Light Fixtures
Material Approval - Switch Gear / HV Panel
Material Approval - Generators / UPS
Material Approval - MDBs & Capacitor Bank (LV Panels)
Material Approval - IBMS
Material Approval - Fans
Material Approval - FCUs \ CCUs
Material Approval - Sanitarywares
Material Approval - Solar System
Material Approval - Bulk Storage Fuel Tank
Material Approval - Fire Fighting Pump
Material Approval - Booster Pump
Material Approval - Inergen Fire Protection System
Material Approval - Lighting Control System
Material Approval- HVAC Ducts
Material Approval- Chilled Water Pipes-Fittings-Valves
Material Approval- Air Outlets
Material Approval- PPR Pipes -Fittings-Valves (Water)
Material Approval- UPVC Pipes-Fittings-Valves(Drainage)
Material Approval- Fire Pipes-Fittings-Valves
Material Approval- Fire Fighting Equipments
Material Approval- Fire Alarm System
Material Approval- Gate Barrier
Material Approval - Fire Fighting system Accessories
Material Approval - Filter Pump
Material Approval - AHU
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 6 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Material Approval - Package Unit 14 25-Jul-15 29-Aug-15 25-Jul-15 A 29-Aug-15 A 100% AED8,209 AED8,209
Material Approval - Chiller 14 21-Jul-15 29-Aug-15 21-Jul-15 A 29-Aug-15 A 100% AED8,209 AED8,209
Material Approval - Primary Chilled Water Pumps 14 21-Jul-15 29-Aug-15 21-Jul-15 A 29-Aug-15 A 100% AED8,209 AED8,209
Domesic IemsDomesic Iems 180 27-Jul-15 28-Mar-16 27-Jul-15 A 28-Mar-16 96.86% AED3,497,001 AED3,435,372
Purchase order Domesic IemsPurchase order Domesic Iems 107 30-Jul-15 29-Nov-15 30-Jul-15 A 29-Nov-15 A 100% AED172,387 AED172,387
Electrical 107 30-Jul-15 28-Nov-15 30-Jul-15 A 28-Nov-15 A 100% AED106,716 AED106,716
Cable Trays - Cables 79 30-Jul-15 14-Nov-15 30-Jul-15 A 14-Nov-15 A 100% AED32,836 AED32,836
Purchase Order- LV Cable 7 26-Oct-15 26-Oct-15 26-Oct-15 A 26-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Cable Trays 7 30-Jul-15 30-Jul-15 30-Jul-15 A 30-Jul-15 A 100% AED8,209 AED8,209
Purchase Order- Trunking 7 30-Jul-15 30-Jul-15 30-Jul-15 A 30-Jul-15 A 100% AED8,209 AED8,209
Purchase Order- HV Cable 7 26-Oct-15 14-Nov-15 26-Oct-15 A 14-Nov-15 A 100% AED8,209 AED8,209
Electrical Equipments 37 24-Oct-15 28-Nov-15 24-Oct-15 A 28-Nov-15 A 100% AED73,880 AED73,880
Purchase Order- SMDBs & DB's 7 28-Nov-15 28-Nov-15 28-Nov-15 A 28-Nov-15 A 100% AED32,836 AED32,836
Purchase Order- IT, LAN and Telephone System 7 24-Oct-15 24-Oct-15 24-Oct-15 A 24-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Gate Barrier 7 01-Nov-15 02-Nov-15 01-Nov-15 A 02-Nov-15 A 100% AED32,836 AED32,836
Mechanical 96 12-Aug-15 29-Nov-15 12-Aug-15 A 29-Nov-15 A 100% AED65,671 AED65,671
HVAC 60 26-Sep-15 29-Nov-15 26-Sep-15 A 29-Nov-15 A 100% AED24,627 AED24,627
Purchase Order- HVAC Ducts 7 26-Sep-15 26-Sep-15 26-Sep-15 A 26-Sep-15 A 100% AED8,209 AED8,209
Purchase Order- Chilled Water Pipes-Fittings-Valves 7 01-Oct-15 12-Oct-15 01-Oct-15 A 12-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Air Outlets 7 28-Nov-15 29-Nov-15 28-Nov-15 A 29-Nov-15 A 100% AED8,209 AED8,209
Plumbing 36 12-Aug-15 19-Aug-15 12-Aug-15 A 19-Aug-15 A 100% AED16,418 AED16,418
Purchase Order- PPR Pipes -Fittings-Valves (Water) 7 12-Aug-15 15-Aug-15 12-Aug-15 A 15-Aug-15 A 100% AED8,209 AED8,209
Purchase Order- UPVC Pipes-Fittings-Valves(Drainage) 7 12-Aug-15 19-Aug-15 12-Aug-15 A 19-Aug-15 A 100% AED8,209 AED8,209
Fire Fighitng 43 19-Sep-15 03-Nov-15 19-Sep-15 A 03-Nov-15 A 100% AED24,627 AED24,627
Purchase Order- Fire Pipes-Fittings-Valves 7 03-Nov-15 03-Nov-15 03-Nov-15 A 03-Nov-15 A 100% AED8,209 AED8,209
Purchase Order- Fire Fighting Equipments 7 03-Nov-15 03-Nov-15 03-Nov-15 A 03-Nov-15 A 100% AED8,209 AED8,209
Purchase Order- Fire Alarm System 7 19-Sep-15 19-Sep-15 19-Sep-15 A 19-Sep-15 A 100% AED8,209 AED8,209
Manufacture Of Domestic ItemsManufacture Of Domestic Items 147 30-Jul-15 07-Feb-16 30-Jul-15 A 07-Feb-16 99% AED492,534 AED487,658
Mechanical 136 12-Aug-15 06-Feb-16 12-Aug-15 A 06-Feb-16 99% AED262,685 AED260,946
HVAC 100 26-Sep-15 06-Feb-16 26-Sep-15 A 06-Feb-16 99% AED98,507 AED97,769
Manufacture- HVAC Ducts 30 26-Sep-15 06-Feb-16 26-Sep-15 A 06-Feb-16 99% AED32,836 AED32,542
Manufacture- Chilled Water Pipes-Fittings-Valves 30 01-Oct-15 06-Feb-16 01-Oct-15 A 06-Feb-16 99% AED32,836 AED32,681
Manufacture- Air Outlets 45 30-Nov-15 06-Feb-16 30-Nov-15 A 06-Feb-16 99% AED32,836 AED32,545
Plumbing 30 12-Aug-15 06-Feb-16 12-Aug-15 A 06-Feb-16 99% AED65,671 AED65,449
Manufacture-PPR Pipes -Fittings-Valves (Water) 30 12-Aug-15 06-Feb-16 12-Aug-15 A 06-Feb-16 99% AED32,836 AED32,724
Manufacture- UPVC Pipes-Fittings-Valves(Drainage) 30 12-Aug-15 06-Feb-16 12-Aug-15 A 06-Feb-16 99% AED32,836 AED32,724
Fire Fighitng 81 19-Sep-15 06-Feb-16 19-Sep-15 A 06-Feb-16 99% AED98,507 AED97,729
Manufacture- Fire Pipes-Fittings-Valves 45 03-Nov-15 06-Feb-16 03-Nov-15 A 06-Feb-16 99% AED32,836 AED32,588
Manufacture- Fire Fighting Equipments 45 03-Nov-15 06-Feb-16 03-Nov-15 A 06-Feb-16 99% AED32,836 AED32,588
Manufacture- Fire Alarm System 45 19-Sep-15 06-Feb-16 19-Sep-15 A 06-Feb-16 99% AED32,836 AED32,553
Electrical 147 30-Jul-15 07-Feb-16 30-Jul-15 A 07-Feb-16 99% AED229,849 AED226,712
Cable Trays - Cables 117 30-Jul-15 06-Feb-16 30-Jul-15 A 06-Feb-16 99% AED131,342 AED130,257
Manufacture- LV Cable 45 26-Oct-15 06-Feb-16 26-Oct-15 A 06-Feb-16 99% AED32,836 AED32,458
Manufacture- Cable Trays 30 30-Jul-15 06-Feb-16 30-Jul-15 A 06-Feb-16 99% AED32,836 AED32,670
Manufacture- Trunking 30 30-Jul-15 06-Feb-16 30-Jul-15 A 06-Feb-16 99% AED32,836 AED32,670
Manufacture- HV Cable 45 26-Oct-15 06-Feb-16 26-Oct-15 A 06-Feb-16 99% AED32,836 AED32,458
Electrical Equipments 76 25-Oct-15 07-Feb-16 25-Oct-15 A 07-Feb-16 99% AED98,507 AED96,455
Manufacture- SMDBs & DB's 45 30-Nov-15 07-Feb-16 30-Nov-15 A 07-Feb-16 99% AED32,836 AED31,703
2015 2016 2017
Material Approval - Package Unit
Material Approval - Chiller
Material Approval - Primary Chilled Water Pumps
28-Mar-16, Domesic Iems
29-Nov-15 A, Purchase order Domesic Iems
28-Nov-15 A, Electrical
14-Nov-15 A, Cable Trays - Cables
Purchase Order- LV Cable
Purchase Order- Cable Trays
Purchase Order- Trunking
Purchase Order- HV Cable
28-Nov-15 A, Electrical Equipments
Purchase Order- SMDBs & DB's
Purchase Order- IT, LAN and Telephone System
Purchase Order- Gate Barrier
29-Nov-15 A, Mechanical
29-Nov-15 A, HVAC
Purchase Order- HVAC Ducts
Purchase Order- Chilled Water Pipes-Fittings-Valves
Purchase Order- Air Outlets
19-Aug-15 A, Plumbing
Purchase Order- PPR Pipes -Fittings-Valves (Water)
Purchase Order- UPVC Pipes-Fittings-Valves(Drainage)
03-Nov-15 A, Fire Fighitng
Purchase Order- Fire Pipes-Fittings-Valves
Purchase Order- Fire Fighting Equipments
Purchase Order- Fire Alarm System
07-Feb-16, Manufacture Of Domestic Items
06-Feb-16, Mechanical
06-Feb-16, HVAC
Manufacture- HVAC Ducts
Manufacture- Chilled Water Pipes-Fittings-Valves
Manufacture- Air Outlets
06-Feb-16, Plumbing
Manufacture-PPR Pipes -Fittings-Valves (Water)
Manufacture- UPVC Pipes-Fittings-Valves(Drainage)
06-Feb-16, Fire Fighitng
Manufacture- Fire Pipes-Fittings-Valves
Manufacture- Fire Fighting Equipments
Manufacture- Fire Alarm System
07-Feb-16, Electrical
06-Feb-16, Cable Trays - Cables
Manufacture- LV Cable
Manufacture- Cable Trays
Manufacture- Trunking
Manufacture- HV Cable
07-Feb-16, Electrical Equipments
Manufacture- SMDBs & DB's
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 7 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Manufacture- IT, LAN and Telephone System 45 25-Oct-15 07-Feb-16 25-Oct-15 A 07-Feb-16 99% AED32,836 AED32,098
Manufacture- Gate Barrier. 45 01-Nov-15 06-Feb-16 01-Nov-15 A 06-Feb-16 99% AED32,836 AED32,654
Delivery Of Domestic ItemsDelivery Of Domestic Items 180 27-Jul-15 28-Mar-16 27-Jul-15 A 28-Mar-16 96.29% AED2,832,081 AED2,775,327
Mechanical 177 27-Jul-15 28-Mar-16 27-Jul-15 A 28-Mar-16 96.8% AED1,420,145 AED1,408,699
HVAC 122 01-Oct-15 28-Mar-16 01-Oct-15 A 28-Mar-16 98% AED295,521 AED289,016
Delivery- Chilled Water Pipes-Fittings-Valves 30 19-Oct-15 06-Feb-16 19-Oct-15 A 06-Feb-16 98% AED279,104 AED277,595
Delivery- Air Outlets 45 02-Jan-16 28-Mar-16 02-Jan-16 A 28-Mar-16 98% AED8,209 AED3,251
Delivery- HVAC Ducts 30 01-Oct-15 06-Feb-16 01-Oct-15 A 06-Feb-16 98% AED8,209 AED8,170
Plumbing 64 27-Jul-15 06-Feb-16 27-Jul-15 A 06-Feb-16 98% AED558,207 AED556,249
Delivery-PPR Pipes -Fittings-Valves (Water) 30 05-Sep-15 06-Feb-16 05-Sep-15 A 06-Feb-16 98% AED279,104 AED278,009
Delivery- UPVC Pipes-Fittings-Valves(Drainage) 30 27-Jul-15 06-Feb-16 27-Jul-15 A 06-Feb-16 98% AED279,104 AED278,240
Fire Fighitng 105 04-Oct-15 06-Feb-16 04-Oct-15 A 06-Feb-16 95% AED566,416 AED563,435
Delivery- Fire Pipes-Fittings-Valves 45 19-Oct-15 06-Feb-16 19-Oct-15 A 06-Feb-16 95% AED279,104 AED277,595
Delivery- Fire Fighting Equipments 30 02-Jan-16 06-Feb-16 02-Jan-16 A 06-Feb-16 95% AED8,209 AED8,072
Delivery- Fire Alarm Devices 45 04-Oct-15 06-Feb-16 04-Oct-15 A 06-Feb-16 95% AED279,104 AED277,768
Electrical 128 28-Sep-15 10-Feb-16 28-Sep-15 A 10-Feb-16 95.78% AED1,411,936 AED1,366,628
Cable Trays - Cables 128 28-Sep-15 08-Feb-16 28-Sep-15 A 08-Feb-16 97.25% AED1,116,415 AED1,078,502
Delivery- LV Cable 45 17-Dec-15 06-Feb-16 17-Dec-15 A 06-Feb-16 95% AED279,104 AED272,613
Delivery- Cable Trays 45 28-Sep-15 06-Feb-16 28-Sep-15 A 06-Feb-16 98% AED279,104 AED277,829
Delivery- Trunking 45 28-Sep-15 06-Feb-16 28-Sep-15 A 06-Feb-16 98% AED279,104 AED277,829
Delivery- HV Cable 45 06-Jan-16 08-Feb-16 06-Jan-16 A 08-Feb-16 98% AED279,104 AED250,231
Electrical Equipments 54 07-Dec-15 10-Feb-16 07-Dec-15 A 10-Feb-16 90.22% AED295,521 AED288,126
Delivery- SMDBs & dB'S 45 07-Dec-15 10-Feb-16 07-Dec-15 A 10-Feb-16 90% AED8,209 AED7,476
Delivery- Gate Barrier. 30 04-Jan-16 06-Feb-16 04-Jan-16 A 06-Feb-16 98% AED8,209 AED8,037
Delivery- IT, LAN and Telephone System 45 17-Dec-15 06-Feb-16 17-Dec-15 A 06-Feb-16 90% AED279,104 AED272,613
Purchase order issuance of Long Lead & Other MaterialsPurchase order issuance of Long Lead & Other Materials 98 20-Sep-15 12-Jan-16 20-Sep-15 A 12-Jan-16 A 100% AED197,013 AED197,013
MEPMEP 98 20-Sep-15 12-Jan-16 20-Sep-15 A 12-Jan-16 A 100% AED197,013 AED197,013
Purchase Order- MDBs & Capacitor Bank (LV Panels) 7 26-Dec-15 28-Dec-15 26-Dec-15 A 28-Dec-15 A 100% AED8,209 AED8,209
Purchase Order- IBMS 7 28-Nov-15 29-Nov-15 28-Nov-15 A 29-Nov-15 A 100% AED8,209 AED8,209
Purchase Order- Transformer 7 26-Oct-15 26-Oct-15 26-Oct-15 A 26-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Generators / UPS 7 20-Sep-15 20-Sep-15 20-Sep-15 A 20-Sep-15 A 100% AED8,209 AED8,209
Purchase Order- CCTV System 7 01-Nov-15 01-Nov-15 01-Nov-15 A 01-Nov-15 A 100% AED8,209 AED8,209
Purchase Order- Access Control System 7 25-Oct-15 25-Oct-15 25-Oct-15 A 25-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Central Battery System 7 30-Sep-15 30-Sep-15 30-Sep-15 A 30-Sep-15 A 100% AED8,209 AED8,209
Purchase Order- Light Fixtures 7 22-Oct-15 22-Oct-15 22-Oct-15 A 22-Oct-15 A 100% AED8,209 AED8,209
Purchase Order - Switch Gear / HV Panel 7 10-Jan-16 12-Jan-16 10-Jan-16 A 12-Jan-16 A 100% AED8,209 AED8,209
Purchase Order- Fire Fighting system Accessories 7 18-Nov-15 19-Nov-15 18-Nov-15 A 19-Nov-15 A 100% AED8,209 AED8,209
Purchase Order- Filter Pump 7 27-Dec-15 28-Dec-15 27-Dec-15 A 28-Dec-15 A 100% AED8,209 AED8,209
Purchase Order- FCUs \ CCUs 7 26-Sep-15 26-Sep-15 26-Sep-15 A 26-Sep-15 A 100% AED8,209 AED8,209
Purchase Order- AHU 7 26-Oct-15 26-Oct-15 26-Oct-15 A 26-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Package Unit 7 22-Sep-15 22-Sep-15 22-Sep-15 A 22-Sep-15 A 100% AED8,209 AED8,209
Purchase Order- Chiller 7 11-Oct-15 11-Oct-15 11-Oct-15 A 11-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Primary Chilled Water Pumps 7 12-Oct-15 12-Oct-15 12-Oct-15 A 12-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Fans 7 11-Oct-15 11-Oct-15 11-Oct-15 A 11-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Sanitarywares 1 25-Oct-15 25-Oct-15 25-Oct-15 A 25-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Solar System 7 10-Jan-16 12-Jan-16 10-Jan-16 A 12-Jan-16 A 100% AED8,209 AED8,209
Purchase Order- Bulk Storage Fuel Tank 7 24-Oct-15 24-Oct-15 24-Oct-15 A 24-Oct-15 A 100% AED8,209 AED8,209
Purchase Order- Fire Fighting Pump 7 28-Nov-15 29-Nov-15 28-Nov-15 A 29-Nov-15 A 100% AED8,209 AED8,209
2015 2016 2017
Manufacture- IT, LAN and Telephone System
Manufacture- Gate Barrier.
28-Mar-16, Delivery Of Domestic Items
28-Mar-16, Mechanical
28-Mar-16, HVAC
Delivery- Chilled Water Pipes-Fittings-Valves
Delivery- Air Outlets
Delivery- HVAC Ducts
06-Feb-16, Plumbing
Delivery-PPR Pipes -Fittings-Valves (Water)
Delivery- UPVC Pipes-Fittings-Valves(Drainage)
06-Feb-16, Fire Fighitng
Delivery- Fire Pipes-Fittings-Valves
Delivery- Fire Fighting Equipments
Delivery- Fire Alarm Devices
10-Feb-16, Electrical
08-Feb-16, Cable Trays - Cables
Delivery- LV Cable
Delivery- Cable Trays
Delivery- Trunking
Delivery- HV Cable
10-Feb-16, Electrical Equipments
Delivery- SMDBs & dB'S
Delivery- Gate Barrier.
Delivery- IT, LAN and Telephone System
12-Jan-16 A, Purchase order issuance of Long Lea
12-Jan-16 A, MEP
Purchase Order- MDBs & Capacitor Bank (LV Panels)
Purchase Order- IBMS
Purchase Order- Transformer
Purchase Order- Generators / UPS
Purchase Order- CCTV System
Purchase Order- Access Control System
Purchase Order- Central Battery System
Purchase Order- Light Fixtures
Purchase Order - Switch Gear / HV Panel
Purchase Order- Fire Fighting system Accessories
Purchase Order- Filter Pump
Purchase Order- FCUs \ CCUs
Purchase Order- AHU
Purchase Order- Package Unit
Purchase Order- Chiller
Purchase Order- Primary Chilled Water Pumps
Purchase Order- Fans
Purchase Order- Sanitarywares
Purchase Order- Solar System
Purchase Order- Bulk Storage Fuel Tank
Purchase Order- Fire Fighting Pump
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 8 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Purchase Order- Booster Pump 7 27-Dec-15 29-Dec-15 27-Dec-15 A 29-Dec-15 A 100% AED8,209 AED8,209
Purchase Order- Inergen Fire Protection System 7 28-Nov-15 30-Nov-15 28-Nov-15 A 30-Nov-15 A 100% AED8,209 AED8,209
Purchase Order- Lighting Control System 7 28-Sep-15 28-Sep-15 28-Sep-15 A 28-Sep-15 A 100% AED8,209 AED8,209
Manufacturing of Long Lead and Other MaterialsManufacturing of Long Lead and Other Materials 135 20-Sep-15 08-Feb-16 20-Sep-15 A 08-Feb-16 95.75% AED788,054 AED763,484
MEPMEP 135 20-Sep-15 08-Feb-16 20-Sep-15 A 08-Feb-16 95.75% AED788,054 AED763,484
Manufacture- MDBs & Capacitor Bank (LV Panels) 40 29-Dec-15 07-Feb-16 29-Dec-15 A 07-Feb-16 95% AED32,836 AED30,959
Manufacture- IBMS 40 28-Nov-15 07-Feb-16 28-Nov-15 A 07-Feb-16 95% AED32,836 AED31,741
Manufacture- Transformer 40 26-Oct-15 07-Feb-16 26-Oct-15 A 07-Feb-16 95% AED32,836 AED32,089
Manufacture- Generators / UPS 40 20-Sep-15 07-Feb-16 20-Sep-15 A 07-Feb-16 95% AED32,836 AED32,269
Manufacture- Manufacturing- CCTV System 40 02-Nov-15 07-Feb-16 02-Nov-15 A 07-Feb-16 95% AED32,836 AED32,035
Manufacture- Access Control System 40 26-Oct-15 07-Feb-16 26-Oct-15 A 07-Feb-16 98% AED32,836 AED32,089
Manufacture- Central Battery System 40 30-Sep-15 01-Feb-16 30-Sep-15 A 01-Feb-16 A 100% AED32,836 AED32,836
Manufacture- Light Fixtures 40 22-Oct-15 31-Jan-16 22-Oct-15 A 31-Jan-16 A 100% AED32,836 AED32,836
Manufacture - Switch Gear / HV Panel 40 14-Jan-16 07-Feb-16 14-Jan-16 A 07-Feb-16 90% AED32,836 AED29,708
Manufacture- Fire Fighting system Accessories 40 01-Dec-15 07-Feb-16 01-Dec-15 A 07-Feb-16 90% AED32,836 AED31,683
Manufacture- Filter Pump 40 29-Dec-15 07-Feb-16 29-Dec-15 A 07-Feb-16 90% AED32,836 AED30,959
Manufacture- FCUs \ CCUs 40 26-Sep-15 10-Dec-15 26-Sep-15 A 10-Dec-15 A 100% AED32,836 AED32,836
Manufacture- AHU 40 26-Oct-15 07-Feb-16 26-Oct-15 A 07-Feb-16 95% AED32,836 AED32,089
Manufacture- Package Unit 40 22-Sep-15 31-Jan-16 22-Sep-15 A 31-Jan-16 A 100% AED32,836 AED32,836
Manufacture- Chiller 40 11-Oct-15 07-Feb-16 11-Oct-15 A 07-Feb-16 95% AED32,836 AED32,179
Manufacture- Primary Chilled Water Pump 40 12-Oct-15 07-Feb-16 12-Oct-15 A 07-Feb-16 95% AED32,836 AED32,172
Manufacture- Fans 40 11-Oct-15 31-Jan-16 11-Oct-15 A 31-Jan-16 A 100% AED32,836 AED32,836
Manufacture- Sanitarywares 40 26-Oct-15 07-Feb-16 26-Oct-15 A 07-Feb-16 95% AED32,836 AED32,089
Manufacture- Solar System 40 14-Jan-16 08-Feb-16 14-Jan-16 A 08-Feb-16 95% AED32,836 AED28,358
Manufacture- Bulk Storage Fuel Tank 40 25-Oct-15 07-Feb-16 25-Oct-15 A 07-Feb-16 95% AED32,836 AED32,098
Manufacture- Fire Fighting Pump 40 01-Dec-15 07-Feb-16 01-Dec-15 A 07-Feb-16 95% AED32,836 AED31,683
Manufacture- Booster Pump 40 29-Dec-15 07-Feb-16 29-Dec-15 A 07-Feb-16 95% AED32,836 AED30,959
Manufacture- Inergen Fire Protection System 40 19-Dec-15 07-Feb-16 19-Dec-15 A 07-Feb-16 95% AED32,836 AED31,308
Manufacture- Lighting Control System 40 28-Sep-15 01-Feb-16 28-Sep-15 A 01-Feb-16 A 100% AED32,836 AED32,836
Delivery of Long Lead & Other MaterialsDelivery of Long Lead & Other Materials 109 21-Nov-15 23-Apr-16 21-Nov-15 A 23-Apr-16 49.38% AED6,698,488 AED3,614,802
MEPMEP 109 21-Nov-15 23-Apr-16 21-Nov-15 A 23-Apr-16 49.38% AED6,698,488 AED3,614,802
Order&Delivery- MDBs & Capacitor Bank (LV Panels) 60 14-Jan-16 22-Mar-16 14-Jan-16 A 22-Mar-16 30% AED279,104 AED89,881
Order&Delivery- Central Battery System 60 16-Dec-15 16-Mar-16 16-Dec-15 A 16-Mar-16 95% AED279,104 AED153,865
Order&Delivery- CCTV System 60 16-Dec-15 05-Mar-16 16-Dec-15 A 05-Mar-16 90% AED279,104 AED176,492
Order&Delivery- Generators / UPS 60 16-Dec-15 16-Mar-16 16-Dec-15 A 16-Mar-16 30% AED279,104 AED153,865
Order&Delivery- Access Control System 60 16-Dec-15 05-Mar-16 16-Dec-15 A 05-Mar-16 50% AED279,104 AED176,492
Order&Delivery - Switch Gear / HV Panel 60 14-Jan-16 29-Mar-16 14-Jan-16 A 29-Mar-16 30% AED279,104 AED81,584
Order&Delivery- Transformer 60 16-Dec-15 28-Mar-16 16-Dec-15 A 28-Mar-16 30% AED279,104 AED136,380
Order&Delivery- Light Fixtures 60 16-Dec-15 29-Feb-16 16-Dec-15 A 29-Feb-16 90% AED279,104 AED187,523
Order&Delivery- IBMS 60 16-Dec-15 05-Mar-16 16-Dec-15 A 05-Mar-16 60% AED279,104 AED176,492
Order&Delivery- FCUs \ CCUs 60 21-Nov-15 16-Dec-15 21-Nov-15 A 16-Dec-15 A 100% AED279,104 AED279,104
Order&Delivery- Fire Fighting system Accessories 60 16-Dec-15 03-Apr-16 16-Dec-15 A 03-Apr-16 30% AED279,104 AED129,048
Order&Delivery- Bulk Storage Fuel Tank 60 16-Dec-15 22-Mar-16 16-Dec-15 A 22-Mar-16 25% AED279,104 AED144,596
Order&Delivery- Inergen Fire Protection System 60 16-Dec-15 10-Mar-16 16-Dec-15 A 10-Mar-16 30% AED279,104 AED164,404
Order&Delivery- Chiller 60 16-Dec-15 16-Mar-16 16-Dec-15 A 16-Mar-16 30% AED279,104 AED153,865
Order&Delivery- AHU 60 16-Dec-15 28-Mar-16 16-Dec-15 A 28-Mar-16 30% AED279,104 AED136,380
Order&Delivery- Fire Fighting Pump 60 16-Dec-15 23-Apr-16 16-Dec-15 A 23-Apr-16* 30% AED279,104 AED109,104
2015 2016 2017
Purchase Order- Booster Pump
Purchase Order- Inergen Fire Protection System
Purchase Order- Lighting Control System
08-Feb-16, Manufacturing of Long Lead and Ot
08-Feb-16, MEP
Manufacture- MDBs & Capacitor Bank (LV Panels)
Manufacture- IBMS
Manufacture- Transformer
Manufacture- Generators / UPS
Manufacture- Manufacturing- CCTV System
Manufacture- Access Control System
Manufacture- Central Battery System
Manufacture- Light Fixtures
Manufacture - Switch Gear / HV Panel
Manufacture- Fire Fighting system Accessories
Manufacture- Filter Pump
Manufacture- FCUs \ CCUs
Manufacture- AHU
Manufacture- Package Unit
Manufacture- Chiller
Manufacture- Primary Chilled Water Pump
Manufacture- Fans
Manufacture- Sanitarywares
Manufacture- Solar System
Manufacture- Bulk Storage Fuel Tank
Manufacture- Fire Fighting Pump
Manufacture- Booster Pump
Manufacture- Inergen Fire Protection System
Manufacture- Lighting Control System
23-Apr-16, Delivery of Long Lead & Ot
23-Apr-16, MEP
Order&Delivery- MDBs & Capacitor Bank (
Order&Delivery- Central Battery System
Order&Delivery- CCTV System
Order&Delivery- Generators / UPS
Order&Delivery- Access Control System
Order&Delivery - Switch Gear / HV Panel
Order&Delivery- Transformer
Order&Delivery- Light Fixtures
Order&Delivery- IBMS
Order&Delivery- FCUs \ CCUs
Order&Delivery- Fire Fighting system Accessories
Order&Delivery- Bulk Storage Fuel Tank
Order&Delivery- Inergen Fire Protection System
Order&Delivery- Chiller
Order&Delivery- AHU
Order&Delivery- Fire Fighting Pump
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 9 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Order&Delivery- Package Unit 60 16-Dec-15 08-Feb-16 16-Dec-15 A 08-Feb-16 A 100% AED279,104 AED279,104
Order&Delivery- Solar System 60 14-Jan-16 20-Apr-16 14-Jan-16 A 20-Apr-16 10% AED279,104 AED63,131
Order&Delivery- Sanitarywares 60 16-Dec-15 10-Mar-16 16-Dec-15 A 10-Mar-16 25% AED279,104 AED164,404
Order&Delivery- Fans 60 16-Dec-15 25-Feb-16 16-Dec-15 A 25-Feb-16 90% AED279,104 AED196,745
Order&Delivery- Booster Pump 60 14-Jan-16 28-Mar-16 14-Jan-16 A 28-Mar-16 30% AED279,104 AED82,859
Order&Delivery- Primary Chilled Water Pumps 60 16-Dec-15 23-Apr-16 16-Dec-15 A 23-Apr-16 30% AED279,104 AED109,104
Order&Delivery- Filter Pump 60 14-Jan-16 28-Mar-16 14-Jan-16 A 28-Mar-16 30% AED279,104 AED82,859
Order&Delivery- Lighting Contrrol System 60 16-Dec-15 29-Feb-16 16-Dec-15 A 29-Feb-16 90% AED279,104 AED187,523
Construction & PreCommissioning Of UnitsConstruction & PreCommissioning Of Units 298 01-Jul-15 02-Jul-16 01-Jul-15 A 02-Jul-16 33.73% AED39,060,199 AED12,826,128
Accomodation BuildingAccomodation Building 281 01-Jul-15 05-Jun-16 01-Jul-15 A 05-Jun-16 53.86% AED7,857,227 AED4,292,839
SkeletonSkeleton 141 01-Jul-15 22-Dec-15 01-Jul-15 A 22-Dec-15 A 100% AED113,702 AED113,702
Sub Structure 31 01-Jul-15 12-Aug-15 01-Jul-15 A 12-Aug-15 A 100% AED57,168 AED57,168
Part 1 18 01-Jul-15 28-Jul-15 01-Jul-15 A 28-Jul-15 A 100% AED14,292 AED14,292
Concrete Works 18 01-Jul-15 28-Jul-15 01-Jul-15 A 28-Jul-15 A 100% AED14,292 AED14,292
Accommodation-MEP Under Ground Services 2 01-Jul-15 05-Jul-15 01-Jul-15 A 05-Jul-15 A 100% AED2,319 AED2,319
Clearance for MEP Under ground Services 0 01-Jul-15 01-Jul-15 A 100% AED0 AED0
Accommodation-Grade Slab Rebar & MEP Services 2 26-Jul-15 28-Jul-15 26-Jul-15 A 28-Jul-15 A 100% AED11,973 AED11,973
Part 2 18 12-Jul-15 05-Aug-15 12-Jul-15 A 05-Aug-15 A 100% AED14,292 AED14,292
Concrete Works 18 12-Jul-15 05-Aug-15 12-Jul-15 A 05-Aug-15 A 100% AED14,292 AED14,292
Accommodation-MEP Under Ground Services 2 12-Jul-15 21-Jul-15 12-Jul-15 A 21-Jul-15 A 100% AED2,319 AED2,319
Accommodation-Grade Slab Rebar & MEP Services 2 03-Aug-15 05-Aug-15 03-Aug-15 A 05-Aug-15 A 100% AED11,973 AED11,973
Part 3 17 15-Jul-15 05-Aug-15 15-Jul-15 A 05-Aug-15 A 100% AED14,292 AED14,292
Concrete Works 17 15-Jul-15 05-Aug-15 15-Jul-15 A 05-Aug-15 A 100% AED14,292 AED14,292
Accommodation-MEP Under Ground Services 5 15-Jul-15 23-Jul-15 15-Jul-15 A 23-Jul-15 A 100% AED2,319 AED2,319
Accommodation-Grade Slab Rebar & MEP Services 3 03-Aug-15 05-Aug-15 03-Aug-15 A 05-Aug-15 A 100% AED11,973 AED11,973
Part 4 17 23-Jul-15 12-Aug-15 23-Jul-15 A 12-Aug-15 A 100% AED14,292 AED14,292
Concrete Works 17 23-Jul-15 12-Aug-15 23-Jul-15 A 12-Aug-15 A 100% AED14,292 AED14,292
Accommodation-MEP Under Ground Services 3 23-Jul-15 27-Jul-15 23-Jul-15 A 27-Jul-15 A 100% AED2,319 AED2,319
Accommodation-Grade Slab Rebar & MEP Services 2 10-Aug-15 12-Aug-15 10-Aug-15 A 12-Aug-15 A 100% AED11,973 AED11,973
Super Structure 99 25-Aug-15 22-Dec-15 25-Aug-15 A 22-Dec-15 A 100% AED56,534 AED56,534
Part 1 94 25-Aug-15 17-Dec-15 25-Aug-15 A 17-Dec-15 A 100% AED16,960 AED16,960
First Floor 2 25-Aug-15 27-Aug-15 25-Aug-15 A 27-Aug-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 2 25-Aug-15 27-Aug-15 25-Aug-15 A 27-Aug-15 A 100% AED5,653 AED5,653
Roof Floor 2 14-Oct-15 17-Oct-15 14-Oct-15 A 17-Oct-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 2 14-Oct-15 17-Oct-15 14-Oct-15 A 17-Oct-15 A 100% AED5,653 AED5,653
Top Roof Floor 2 15-Dec-15 17-Dec-15 15-Dec-15 A 17-Dec-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 2 15-Dec-15 17-Dec-15 15-Dec-15 A 17-Dec-15 A 100% AED5,653 AED5,653
Part 2 32 20-Sep-15 27-Oct-15 20-Sep-15 A 27-Oct-15 A 100% AED11,307 AED11,307
First Floor 4 20-Sep-15 22-Sep-15 20-Sep-15 A 22-Sep-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 20-Sep-15 22-Sep-15 20-Sep-15 A 22-Sep-15 A 100% AED5,653 AED5,653
Roof Floor 4 26-Oct-15 27-Oct-15 26-Oct-15 A 27-Oct-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 26-Oct-15 27-Oct-15 26-Oct-15 A 27-Oct-15 A 100% AED5,653 AED5,653
Part 3 11 26-Sep-15 10-Nov-15 26-Sep-15 A 10-Nov-15 A 100% AED11,307 AED11,307
First Floor 4 26-Sep-15 29-Sep-15 26-Sep-15 A 29-Sep-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 26-Sep-15 29-Sep-15 26-Sep-15 A 29-Sep-15 A 100% AED5,653 AED5,653
Roof Floor 4 04-Nov-15 10-Nov-15 04-Nov-15 A 10-Nov-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 04-Nov-15 10-Nov-15 04-Nov-15 A 10-Nov-15 A 100% AED5,653 AED5,653
Part 4 85 10-Oct-15 22-Dec-15 10-Oct-15 A 22-Dec-15 A 100% AED16,960 AED16,960
First Floor 4 10-Oct-15 14-Oct-15 10-Oct-15 A 14-Oct-15 A 100% AED5,653 AED5,653
2015 2016 2017
Order&Delivery- Package Unit
Order&Delivery- Solar System
Order&Delivery- Sanitarywares
Order&Delivery- Fans
Order&Delivery- Booster Pump
Order&Delivery- Primary Chilled Water Pumps
Order&Delivery- Filter Pump
Order&Delivery- Lighting Contrrol System
02-Jul-16, Construction & PreC
05-Jun-16, Accomodation Building
22-Dec-15 A, Skeleton
12-Aug-15 A, Sub Structure
28-Jul-15 A, Part 1
28-Jul-15 A, Concrete Works
Accommodation-MEP Under Ground Services
Clearance for MEP Under ground Services
Accommodation-Grade Slab Rebar & MEP Services
05-Aug-15 A, Part 2
05-Aug-15 A, Concrete Works
Accommodation-MEP Under Ground Services
Accommodation-Grade Slab Rebar & MEP Services
05-Aug-15 A, Part 3
05-Aug-15 A, Concrete Works
Accommodation-MEP Under Ground Services
Accommodation-Grade Slab Rebar & MEP Services
12-Aug-15 A, Part 4
12-Aug-15 A, Concrete Works
Accommodation-MEP Under Ground Services
Accommodation-Grade Slab Rebar & MEP Services
22-Dec-15 A, Super Structure
17-Dec-15 A, Part 1
27-Aug-15 A, First Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
17-Oct-15 A, Roof Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
17-Dec-15 A, Top Roof Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
27-Oct-15 A, Part 2
22-Sep-15 A, First Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
27-Oct-15 A, Roof Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
10-Nov-15 A, Part 3
29-Sep-15 A, First Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
10-Nov-15 A, Roof Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
22-Dec-15 A, Part 4
14-Oct-15 A, First Floor
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 10 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 10-Oct-15 14-Oct-15 10-Oct-15 A 14-Oct-15 A 100% AED5,653 AED5,653
Roof Floor 4 02-Nov-15 04-Nov-15 02-Nov-15 A 04-Nov-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 02-Nov-15 04-Nov-15 02-Nov-15 A 04-Nov-15 A 100% AED5,653 AED5,653
Top Roof Floor 4 19-Dec-15 22-Dec-15 19-Dec-15 A 22-Dec-15 A 100% AED5,653 AED5,653
Accommodation-MEP Conduits & Sleeves Inside The Slab 4 19-Dec-15 22-Dec-15 19-Dec-15 A 22-Dec-15 A 100% AED5,653 AED5,653
MEPMEP 195 04-Oct-15 22-May-16 04-Oct-15 A 22-May-16 56.13% AED7,336,618 AED4,179,137
Ground Floor 160 04-Oct-15 10-Apr-16 04-Oct-15 A 10-Apr-16 76.36% AED2,145,505 AED1,634,826
ZONE A 160 04-Oct-15 10-Apr-16 04-Oct-15 A 10-Apr-16 76.93% AED1,072,752 AED821,665
MEP 1st Fix 18 04-Oct-15 19-Nov-15 04-Oct-15 A 19-Nov-15 A 100% AED147,966 AED147,966
Accommodation-Civil clearance to Start 1st Fix 0 04-Oct-15 04-Oct-15 A 100% AED0 AED0
Accommodation-DRAINAGE PIPES ( IN WALLS) 8 04-Oct-15 19-Nov-15 04-Oct-15 A 19-Nov-15 A 100% AED49,322 AED49,322
Accommodation-WATER SUPPLY PIPES ( IN WALLS) 8 10-Oct-15 19-Nov-15 10-Oct-15 A 19-Nov-15 A 100% AED49,322 AED49,322
Accommodation-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 8 10-Oct-15 19-Nov-15 10-Oct-15 A 19-Nov-15 A 100% AED49,322 AED49,322
Accommodation-MEP clearance to Start Plaster 0 25-Oct-15 25-Oct-15 A 100% AED0 AED0
MEP 2nd Fix 92 15-Oct-15 06-Mar-16 15-Oct-15 A 06-Mar-16 99.87% AED665,848 AED665,478
Accommodation-DRAINAGE PIPES (HIGH L) 7 15-Oct-15 04-Nov-15 15-Oct-15 A 04-Nov-15 A 100% AED43,157 AED43,157
Accommodation-WATER SUPPLY PIPES (HIGH L) 7 18-Oct-15 04-Nov-15 18-Oct-15 A 04-Nov-15 A 100% AED43,157 AED43,157
Accommodation-GRAVITY TEST 4 19-Nov-15 26-Nov-15 19-Nov-15 A 26-Nov-15 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING PIPES(MAINS/BRANCHES) 7 19-Oct-15 11-Jan-16 19-Oct-15 A 11-Jan-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TESTING 4 02-Nov-15 11-Jan-16 02-Nov-15 A 11-Jan-16 A 100% AED24,661 AED24,661
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION 4 22-Dec-15 10-Jan-16 22-Dec-15 A 10-Jan-16 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING TESTING 4 24-Nov-15 25-Jan-16 24-Nov-15 A 25-Jan-16 A 100% AED24,661 AED24,661
Accommodation-VERTICAL SPRINKLER DROPS 4 14-Nov-15 16-Jan-16 14-Nov-15 A 16-Jan-16 A 100% AED24,661 AED24,661
Accommodation-WIRING FOR LIGHTING WORKS 7 15-Oct-15 10-Jan-16 15-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WIRING FOR POWER 7 17-Oct-15 10-Jan-16 17-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 7 15-Oct-15 11-Jan-16 15-Oct-15 A 11-Jan-16 A 100% AED43,157 AED43,157
Accommodation-CABLE TRAY / TRUNKING 7 15-Oct-15 10-Jan-16 15-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-STRUC&ELEC CABLING INCLUDING DRESSING 7 24-Nov-15 18-Jan-16 24-Nov-15 A 18-Jan-16 A 100% AED43,157 AED43,157
Accommodation-DUCTING WORK INCLUDING INSULATION 7 15-Oct-15 17-Jan-16 15-Oct-15 A 17-Jan-16 A 100% AED43,157 AED43,157
Accommodation-INSTALLATION OF FCUS & FANS 7 23-Nov-15 17-Dec-15 23-Nov-15 A 17-Dec-15 A 100% AED43,157 AED43,157
Accommodation-FINAL DUCT CONNECTION TO FANS 7 12-Dec-15 10-Jan-16 12-Dec-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TEST&INSULATION 4 15-Nov-15 11-Jan-16 15-Nov-15 A 11-Jan-16 A 100% AED24,661 AED24,661
Accommodation-MEP clearance to close Rooms ceilings 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
Accommodation-Civil clearance to Start 2nd Fix 0 15-Oct-15 15-Oct-15 A 100% AED0 AED0
Accommodation-MEP clearance to close corridors ceilings 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
Accommodation-CHILLED WATER PIPES (HIGH L) 7 01-Nov-15 06-Mar-16 01-Nov-15 A 06-Mar-16 98% AED43,157 AED42,787
MEP Final Fix 57 04-Feb-16 10-Apr-16 04-Feb-16 A 10-Apr-16 4.76% AED258,938 AED8,220
Accommodation-Civil Clearance to Start Final Fix 0 04-Feb-16 04-Feb-16 A 100% AED0 AED0
Accommodation-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 4 04-Apr-16 07-Apr-16 04-Apr-16 07-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF DBS 4 04-Feb-16 10-Mar-16 04-Feb-16 A 10-Mar-16 50% AED24,661 AED8,220
Accommodation-INSTALLATION OF PANELS / SMDBS 4 24-Mar-16 28-Mar-16 24-Mar-16 28-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF TELEPHONE SYSTEM 4 20-Mar-16 23-Mar-16 20-Mar-16 23-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF CCTV SYSTEM 4 12-Mar-16 15-Mar-16 12-Mar-16 15-Mar-16 0% AED24,661 AED0
Accommodation-TERMINATION & DRESSING OF DBS 4 06-Apr-16 10-Apr-16 06-Apr-16 10-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 4 24-Feb-16 28-Feb-16 24-Feb-16 28-Feb-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 06-Apr-16 10-Apr-16 06-Apr-16 10-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF WIRING ACCESSORIES 4 06-Mar-16 09-Mar-16 06-Mar-16 09-Mar-16 0% AED24,661 AED0
2015 2016 2017
Accommodation-MEP Conduits & Sleeves Inside The Slab
04-Nov-15 A, Roof Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
22-Dec-15 A, Top Roof Floor
Accommodation-MEP Conduits & Sleeves Inside The Slab
22-May-16, MEP
10-Apr-16, Ground Floor
10-Apr-16, ZONE A
19-Nov-15 A, MEP 1st Fix
Accommodation-Civil clearance to Start 1st Fix
Accommodation-DRAINAGE PIPES ( IN WALLS)
Accommodation-WATER SUPPLY PIPES ( IN WALLS)
Accommodation-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL
Accommodation-MEP clearance to Start Plaster
06-Mar-16, MEP 2nd Fix
Accommodation-DRAINAGE PIPES (HIGH L)
Accommodation-WATER SUPPLY PIPES (HIGH L)
Accommodation-GRAVITY TEST
Accommodation-FIRE FIGHTING PIPES(MAINS/B
Accommodation-PRESSURE TESTING
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION
Accommodation-FIRE FIGHTING TESTING
Accommodation-VERTICAL SPRINKLER DROPS
Accommodation-WIRING FOR LIGHTING WORKS
Accommodation-WIRING FOR POWER
Accommodation-WIRING FOR FIRE ALARM&LOW
Accommodation-CABLE TRAY / TRUNKING
Accommodation-STRUC&ELEC CABLING INCLU
Accommodation-DUCTING WORK INCLUDING I
Accommodation-INSTALLATION OF FCUS & FANS
Accommodation-FINAL DUCT CONNECTION TO FANS
Accommodation-PRESSURE TEST&INSULATION
Accommodation-MEP clearance to close Rooms ceilings
Accommodation-Civil clearance to Start 2nd Fix
Accommodation-MEP clearance to close corridors ceilings
Accommodation-CHILLED WATER PIPES (HIGH L)
10-Apr-16, MEP Final Fix
Accommodation-Civil Clearance to Start Final Fix
Accommodation-HOSE REEL&FIRE EXT
Accommodation-INSTALLATION OF DBS
Accommodation-INSTALLATION OF PAN
Accommodation-INSTALLATION OF TELE
Accommodation-INSTALLATION OF CCTV SYSTEM
Accommodation-TERMINATION & DRE
Accommodation-INSTALLATION OF FIRE AL
Accommodation-INSTALLATION OF LIG
Accommodation-INSTALLATION OF WIRIN
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 11 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Accommodation-INSTALLATION OF GRILLS&DIFFUSERS 4 29-Mar-16 02-Apr-16 29-Mar-16 02-Apr-16 0% AED24,661 AED0
Accommodation-THERMOSTAT FIXING 2 03-Apr-16 04-Apr-16 03-Apr-16 04-Apr-16 0% AED12,330 AED0
Accommodation-MEP Final Fix Clearance 0 10-Apr-16 10-Apr-16 0% AED0 AED0
Accommodation-INSTALLATION OF SANITARY WARES 12 12-Mar-16 24-Mar-16 12-Mar-16 24-Mar-16 0% AED0 AED0
ZONE B 139 29-Oct-15 10-Apr-16 29-Oct-15 A 10-Apr-16 75.78% AED1,072,752 AED813,161
MEP 1st Fix 19 29-Oct-15 30-Nov-15 29-Oct-15 A 30-Nov-15 A 100% AED147,966 AED147,966
Accommodation-Civil clearance to Start 1st Fix 0 29-Oct-15 29-Oct-15 A 100% AED0 AED0
Accommodation-DRAINAGE PIPES ( IN WALLS) 8 29-Oct-15 28-Nov-15 29-Oct-15 A 28-Nov-15 A 100% AED49,322 AED49,322
Accommodation-WATER SUPPLY PIPES ( IN WALLS) 8 29-Oct-15 26-Nov-15 29-Oct-15 A 26-Nov-15 A 100% AED49,322 AED49,322
Accommodation-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 8 29-Oct-15 30-Nov-15 29-Oct-15 A 30-Nov-15 A 100% AED49,322 AED49,322
Accommodation-MEP clearance to Start Plaster 0 19-Nov-15 19-Nov-15 A 100% AED0 AED0
MEP 2nd Fix 116 29-Oct-15 14-Mar-16 29-Oct-15 A 14-Mar-16 99.87% AED665,848 AED665,194
Accommodation-DRAINAGE PIPES (HIGH L) 7 29-Oct-15 26-Nov-15 29-Oct-15 A 26-Nov-15 A 100% AED43,157 AED43,157
Accommodation-WATER SUPPLY PIPES (HIGH L) 7 29-Oct-15 26-Nov-15 29-Oct-15 A 26-Nov-15 A 100% AED43,157 AED43,157
Accommodation-GRAVITY TEST 4 23-Nov-15 25-Nov-15 23-Nov-15 A 25-Nov-15 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING PIPES(MAINS/BRANCHES) 7 31-Oct-15 10-Jan-16 31-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TESTING 4 23-Nov-15 26-Nov-15 23-Nov-15 A 26-Nov-15 A 100% AED24,661 AED24,661
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION 4 22-Dec-15 12-Jan-16 22-Dec-15 A 12-Jan-16 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING TESTING 4 28-Nov-15 12-Jan-16 28-Nov-15 A 12-Jan-16 A 100% AED24,661 AED24,661
Accommodation-VERTICAL SPRINKLER DROPS 4 22-Nov-15 14-Jan-16 22-Nov-15 A 14-Jan-16 A 100% AED24,661 AED24,661
Accommodation-WIRING FOR LIGHTING WORKS 7 31-Oct-15 10-Jan-16 31-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WIRING FOR POWER 7 19-Nov-15 10-Jan-16 19-Nov-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 7 31-Oct-15 10-Jan-16 31-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-CABLE TRAY / TRUNKING 7 31-Oct-15 10-Jan-16 31-Oct-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-STRUC&ELEC CABLING INCLUDING DRESSING 7 10-Dec-15 10-Jan-16 10-Dec-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-DUCTING WORK INCLUDING INSULATION 7 29-Oct-15 17-Jan-16 29-Oct-15 A 17-Jan-16 A 100% AED43,157 AED43,157
Accommodation-INSTALLATION OF FCUS & FANS 7 16-Dec-15 19-Dec-15 16-Dec-15 A 19-Dec-15 A 100% AED43,157 AED43,157
Accommodation-FINAL DUCT CONNECTION TO FANS 7 12-Dec-15 10-Jan-16 12-Dec-15 A 10-Jan-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TEST&INSULATION 4 22-Nov-15 10-Jan-16 22-Nov-15 A 10-Jan-16 A 100% AED24,661 AED24,661
Accommodation-MEP clearance to close Rooms ceilings 0 07-Mar-16 07-Mar-16 0% AED0 AED0
Accommodation-Civil clearance to Start 2nd Fix 0 29-Oct-15 29-Oct-15 A 100% AED0 AED0
Accommodation-MEP clearance to close corridors ceilings 0 14-Mar-16 14-Mar-16 0% AED0 AED0
Accommodation-CHILLED WATER PIPES (HIGH L) 7 19-Nov-15 07-Mar-16 19-Nov-15 A 07-Mar-16 98% AED43,157 AED42,503
MEP Final Fix 56 04-Feb-16 10-Apr-16 04-Feb-16 A 10-Apr-16 0% AED258,938 AED0
Accommodation-Civil Clearance to Start Final Fix 0 04-Feb-16 04-Feb-16 A 100% AED0 AED0
Accommodation-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 4 23-Feb-16 27-Feb-16 23-Feb-16 27-Feb-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF DBS 4 23-Feb-16 27-Feb-16 23-Feb-16 27-Feb-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF PANELS / SMDBS 4 12-Mar-16 15-Mar-16 12-Mar-16 15-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF TELEPHONE SYSTEM 4 07-Mar-16 10-Mar-16 07-Mar-16 10-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF CCTV SYSTEM 4 07-Mar-16 10-Mar-16 07-Mar-16 10-Mar-16 0% AED24,661 AED0
Accommodation-TERMINATION & DRESSING OF DBS 4 16-Mar-16 20-Mar-16 16-Mar-16 20-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 4 23-Feb-16 27-Feb-16 23-Feb-16 27-Feb-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 24-Mar-16 28-Mar-16 24-Mar-16 28-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF WIRING ACCESSORIES 4 02-Apr-16 05-Apr-16 02-Apr-16 05-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF GRILLS&DIFFUSERS 4 14-Feb-16 17-Feb-16 14-Feb-16 17-Feb-16 0% AED24,661 AED0
Accommodation-THERMOSTAT FIXING 2 27-Feb-16 28-Feb-16 27-Feb-16 28-Feb-16 0% AED12,330 AED0
Accommodation-MEP Final Fix Clearance 0 10-Apr-16 10-Apr-16 0% AED0 AED0
2015 2016 2017
Accommodation-INSTALLATION OF GRI
Accommodation-THERMOSTAT FIXING
Accommodation-MEP Final Fix Clearance
Accommodation-INSTALLATION OF SANI
10-Apr-16, ZONE B
30-Nov-15 A, MEP 1st Fix
Accommodation-Civil clearance to Start 1st Fix
Accommodation-DRAINAGE PIPES ( IN WALLS)
Accommodation-WATER SUPPLY PIPES ( IN WALLS)
Accommodation-SLEEVES,CONDUITS,GI BOX,DB BO
Accommodation-MEP clearance to Start Plaster
14-Mar-16, MEP 2nd Fix
Accommodation-DRAINAGE PIPES (HIGH L)
Accommodation-WATER SUPPLY PIPES (HIGH L)
Accommodation-GRAVITY TEST
Accommodation-FIRE FIGHTING PIPES(MAINS/B
Accommodation-PRESSURE TESTING
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION
Accommodation-FIRE FIGHTING TESTING
Accommodation-VERTICAL SPRINKLER DROPS
Accommodation-WIRING FOR LIGHTING WORKS
Accommodation-WIRING FOR POWER
Accommodation-WIRING FOR FIRE ALARM&LOW
Accommodation-CABLE TRAY / TRUNKING
Accommodation-STRUC&ELEC CABLING INCLUD
Accommodation-DUCTING WORK INCLUDING IN
Accommodation-INSTALLATION OF FCUS & FANS
Accommodation-FINAL DUCT CONNECTION TO FANS
Accommodation-PRESSURE TEST&INSULATION
Accommodation-MEP clearance to close Ro
Accommodation-Civil clearance to Start 2nd Fix
Accommodation-MEP clearance to close co
Accommodation-CHILLED WATER PIPES (HIGH L)
10-Apr-16, MEP Final Fix
Accommodation-Civil Clearance to Start Final Fix
Accommodation-HOSE REEL&FIRE EXTING
Accommodation-INSTALLATION OF DBS
Accommodation-INSTALLATION OF PANE
Accommodation-INSTALLATION OF TELEP
Accommodation-INSTALLATION OF CCTV SYSTEM
Accommodation-TERMINATION & DRESS
Accommodation-INSTALLATION OF FIRE AL
Accommodation-INSTALLATION OF LIGH
Accommodation-INSTALLATION OF WIR
Accommodation-INSTALLATION OF GRILLS&
Accommodation-THERMOSTAT FIXING
Accommodation-MEP Final Fix Clearance
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 12 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Accommodation-INSTALLATION OF SANITARY WARES 8 12-Mar-16 20-Mar-16 12-Mar-16 20-Mar-16 0% AED0 AED0
1st Floor 150 05-Nov-15 30-Apr-16 05-Nov-15 A 30-Apr-16 75.14% AED2,145,482 AED1,599,530
ZONE A 150 05-Nov-15 30-Apr-16 05-Nov-15 A 30-Apr-16 75.44% AED1,072,752 AED804,357
MEP 1st Fix 55 05-Nov-15 10-Jan-16 05-Nov-15 A 10-Jan-16 A 100% AED147,966 AED147,966
Accommodation-Civil clearance to Start 1st Fix 0 05-Nov-15 05-Nov-15 A 100% AED0 AED0
Accommodation-DRAINAGE PIPES ( IN WALLS) 8 07-Nov-15 20-Dec-15 07-Nov-15 A 20-Dec-15 A 100% AED49,322 AED49,322
Accommodation-WATER SUPPLY PIPES ( IN WALLS) 8 07-Nov-15 20-Dec-15 07-Nov-15 A 20-Dec-15 A 100% AED49,322 AED49,322
Accommodation-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 8 07-Nov-15 20-Dec-15 07-Nov-15 A 20-Dec-15 A 100% AED49,322 AED49,322
Accommodation-MEP clearance to Start Plaster 0 10-Jan-16 10-Jan-16 A 100% AED0 AED0
MEP 2nd Fix 103 19-Nov-15 20-Mar-16 19-Nov-15 A 20-Mar-16 99.31% AED665,848 AED656,390
Accommodation-DRAINAGE PIPES (HIGH L) 7 19-Nov-15 18-Jan-16 19-Nov-15 A 18-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WATER SUPPLY PIPES (HIGH L) 7 19-Nov-15 18-Jan-16 19-Nov-15 A 18-Jan-16 A 100% AED43,157 AED43,157
Accommodation-GRAVITY TEST 4 16-Dec-15 16-Feb-16 16-Dec-15 A 16-Feb-16 98% AED24,661 AED22,562
Accommodation-FIRE FIGHTING PIPES(MAINS/BRANCHES) 7 19-Nov-15 19-Jan-16 19-Nov-15 A 19-Jan-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TESTING 4 16-Dec-15 16-Feb-16 16-Dec-15 A 16-Feb-16 98% AED24,661 AED22,562
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION 4 22-Dec-15 27-Dec-15 22-Dec-15 A 27-Dec-15 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING TESTING 4 17-Dec-15 04-Feb-16 17-Dec-15 A 04-Feb-16 A 100% AED24,661 AED24,661
Accommodation-VERTICAL SPRINKLER DROPS 4 16-Dec-15 03-Mar-16 16-Dec-15 A 03-Mar-16 98% AED24,661 AED22,562
Accommodation-WIRING FOR LIGHTING WORKS 7 25-Nov-15 19-Jan-16 25-Nov-15 A 19-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WIRING FOR POWER 7 25-Nov-15 19-Jan-16 25-Nov-15 A 19-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 7 24-Nov-15 19-Jan-16 24-Nov-15 A 19-Jan-16 A 100% AED43,157 AED43,157
Accommodation-CABLE TRAY / TRUNKING 7 24-Nov-15 17-Feb-16 24-Nov-15 A 17-Feb-16 98% AED43,157 AED41,787
Accommodation-STRUC&ELEC CABLING INCLUDING DRESSING 7 02-Jan-16 01-Feb-16 02-Jan-16 A 01-Feb-16 A 100% AED43,157 AED43,157
Accommodation-DUCTING WORK INCLUDING INSULATION 7 19-Nov-15 22-Feb-16 19-Nov-15 A 22-Feb-16 98% AED43,157 AED42,503
Accommodation-INSTALLATION OF FCUS & FANS 7 19-Dec-15 19-Dec-15 19-Dec-15 A 19-Dec-15 A 100% AED43,157 AED43,157
Accommodation-FINAL DUCT CONNECTION TO FANS 7 19-Dec-15 04-Feb-16 19-Dec-15 A 04-Feb-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TEST&INSULATION 4 08-Dec-15 22-Feb-16 08-Dec-15 A 22-Feb-16 98% AED24,661 AED24,177
Accommodation-MEP clearance to close Rooms ceilings 0 03-Mar-16 03-Mar-16 0% AED0 AED0
Accommodation-Civil clearance to Start 2nd Fix 0 06-Feb-16 06-Feb-16 0% AED0 AED0
Accommodation-MEP clearance to close corridors ceilings 0 20-Mar-16 20-Mar-16 0% AED0 AED0
Accommodation-CHILLED WATER PIPES (HIGH L) 7 19-Nov-15 28-Feb-16 19-Nov-15 A 28-Feb-16 98% AED43,157 AED42,503
MEP Final Fix 35 20-Mar-16 30-Apr-16 20-Mar-16 30-Apr-16 0% AED258,938 AED0
Accommodation-Civil Clearance to Start Final Fix 0 20-Mar-16 20-Mar-16 0% AED0 AED0
Accommodation-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 4 24-Mar-16 28-Mar-16 24-Mar-16 28-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF DBS 4 24-Mar-16 28-Mar-16 24-Mar-16 28-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF PANELS / SMDBS 4 28-Mar-16 31-Mar-16 28-Mar-16 31-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF TELEPHONE SYSTEM 4 06-Apr-16 10-Apr-16 06-Apr-16 10-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF CCTV SYSTEM 4 06-Apr-16 10-Apr-16 06-Apr-16 10-Apr-16 0% AED24,661 AED0
Accommodation-TERMINATION & DRESSING OF DBS 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 4 24-Mar-16 28-Mar-16 24-Mar-16 28-Mar-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 18-Apr-16 21-Apr-16 18-Apr-16 21-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF WIRING ACCESSORIES 4 26-Apr-16 30-Apr-16 26-Apr-16 30-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF GRILLS&DIFFUSERS 4 24-Mar-16 28-Mar-16 24-Mar-16 28-Mar-16 0% AED24,661 AED0
Accommodation-THERMOSTAT FIXING 2 06-Apr-16 07-Apr-16 06-Apr-16 07-Apr-16 0% AED12,330 AED0
Accommodation-MEP Final Fix Clearance 0 30-Apr-16 30-Apr-16 0% AED0 AED0
Accommodation-INSTALLATION OF SANITARY WARES 7 21-Mar-16 28-Mar-16 21-Mar-16 28-Mar-16 0% AED0 AED0
ZONE B 125 06-Dec-15 30-Apr-16 06-Dec-15 A 30-Apr-16 74.85% AED1,072,729 AED795,173
2015 2016 2017
Accommodation-INSTALLATION OF SANI
30-Apr-16, 1st Floor
30-Apr-16, ZONE A
10-Jan-16 A, MEP 1st Fix
Accommodation-Civil clearance to Start 1st Fix
Accommodation-DRAINAGE PIPES ( IN WALLS)
Accommodation-WATER SUPPLY PIPES ( IN WALLS)
Accommodation-SLEEVES,CONDUITS,GI BOX,DB B
Accommodation-MEP clearance to Start Plaster
20-Mar-16, MEP 2nd Fix
Accommodation-DRAINAGE PIPES (HIGH L)
Accommodation-WATER SUPPLY PIPES (HIGH L)
Accommodation-GRAVITY TEST
Accommodation-FIRE FIGHTING PIPES(MAINS/
Accommodation-PRESSURE TESTING
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION
Accommodation-FIRE FIGHTING TESTING
Accommodation-VERTICAL SPRINKLER DROPS
Accommodation-WIRING FOR LIGHTING WORKS
Accommodation-WIRING FOR POWER
Accommodation-WIRING FOR FIRE ALARM&LO
Accommodation-CABLE TRAY / TRUNKING
Accommodation-STRUC&ELEC CABLING INCL
Accommodation-DUCTING WORK INCLUDIN
Accommodation-INSTALLATION OF FCUS & FANS
Accommodation-FINAL DUCT CONNECTION TO FANS
Accommodation-PRESSURE TEST&INSULATION
Accommodation-MEP clearance to close Roo
Accommodation-Civil clearance to Start 2nd Fix
Accommodation-MEP clearance to close co
Accommodation-CHILLED WATER PIPES (HIGH L)
30-Apr-16, MEP Final Fix
Accommodation-Civil Clearance to Start Final Fix
Accommodation-HOSE REEL&FIRE EXT
Accommodation-INSTALLATION OF DBS
Accommodation-INSTALLATION OF PAN
Accommodation-INSTALLATION OF TE
Accommodation-INSTALLATION OF CC
Accommodation-TERMINATION & DRE
Accommodation-INSTALLATION OF FIRE
Accommodation-INSTALLATION OF LI
Accommodation-INSTALLATION OF W
Accommodation-INSTALLATION OF GRIL
Accommodation-THERMOSTAT FIXING
Accommodation-MEP Final Fix Clearance
Accommodation-INSTALLATION OF SAN
30-Apr-16, ZONE B
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 13 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
MEP 1st Fix 33 07-Dec-15 14-Jan-16 07-Dec-15 A 14-Jan-16 A 100% AED147,966 AED147,966
Accommodation-Civil clearance to Start 1st Fix 0 10-Dec-15 10-Dec-15 A 100% AED0 AED0
Accommodation-DRAINAGE PIPES ( IN WALLS) 8 07-Dec-15 26-Dec-15 07-Dec-15 A 26-Dec-15 A 100% AED49,322 AED49,322
Accommodation-WATER SUPPLY PIPES ( IN WALLS) 8 07-Dec-15 26-Dec-15 07-Dec-15 A 26-Dec-15 A 100% AED49,322 AED49,322
Accommodation-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 8 07-Dec-15 26-Dec-15 07-Dec-15 A 26-Dec-15 A 100% AED49,322 AED49,322
Accommodation-MEP clearance to Start Plaster 0 14-Jan-16 14-Jan-16 A 100% AED0 AED0
MEP 2nd Fix 98 06-Dec-15 29-Mar-16 06-Dec-15 A 29-Mar-16 98.37% AED665,825 AED647,206
Accommodation-DRAINAGE PIPES (HIGH L) 7 07-Dec-15 30-Jan-16 07-Dec-15 A 30-Jan-16 A 100% AED43,157 AED43,157
Accommodation-WATER SUPPLY PIPES (HIGH L) 7 16-Dec-15 30-Jan-16 16-Dec-15 A 30-Jan-16 A 100% AED43,157 AED43,157
Accommodation-GRAVITY TEST 4 22-Dec-15 30-Jan-16 22-Dec-15 A 30-Jan-16 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING PIPES(MAINS/BRANCHES) 7 06-Dec-15 30-Jan-16 06-Dec-15 A 30-Jan-16 A 100% AED43,157 AED43,157
Accommodation-PRESSURE TESTING 4 22-Dec-15 30-Jan-16 22-Dec-15 A 30-Jan-16 A 100% AED24,661 AED24,661
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION 4 22-Dec-15 27-Dec-15 22-Dec-15 A 27-Dec-15 A 100% AED24,661 AED24,661
Accommodation-FIRE FIGHTING TESTING 4 20-Dec-15 28-Dec-15 20-Dec-15 A 28-Dec-15 A 100% AED24,661 AED24,661
Accommodation-VERTICAL SPRINKLER DROPS 4 16-Dec-15 30-Jan-16 16-Dec-15 A 30-Jan-16 A 100% AED24,661 AED24,661
Accommodation-WIRING FOR LIGHTING WORKS 7 16-Dec-15 16-Feb-16 16-Dec-15 A 16-Feb-16 98% AED43,157 AED42,176
Accommodation-WIRING FOR POWER 7 16-Dec-15 05-Mar-16 16-Dec-15 A 05-Mar-16 98% AED43,157 AED42,176
Accommodation-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 7 06-Dec-15 05-Mar-16 06-Dec-15 A 05-Mar-16 98% AED43,157 AED42,343
Accommodation-CABLE TRAY / TRUNKING 7 16-Dec-15 05-Mar-16 16-Dec-15 A 05-Mar-16 98% AED43,157 AED42,176
Accommodation-STRUC&ELEC CABLING INCLUDING DRESSING 7 14-Jan-16 22-Mar-16 14-Jan-16 A 22-Mar-16 90% AED43,157 AED31,538
Accommodation-DUCTING WORK INCLUDING INSULATION 7 06-Dec-15 01-Mar-16 06-Dec-15 A 01-Mar-16 98% AED43,157 AED42,343
Accommodation-INSTALLATION OF FCUS & FANS 7 19-Dec-15 19-Dec-15 19-Dec-15 A 19-Dec-15 A 100% AED43,157 AED43,157
Accommodation-FINAL DUCT CONNECTION TO FANS 7 19-Dec-15 22-Feb-16 19-Dec-15 A 22-Feb-16 98% AED43,157 AED42,129
Accommodation-PRESSURE TEST&INSULATION 4 19-Dec-15 10-Mar-16 19-Dec-15 A 10-Mar-16 98% AED24,661 AED24,074
Accommodation-MEP clearance to close Rooms ceilings 0 22-Mar-16 22-Mar-16 0% AED0 AED0
Accommodation-Civil clearance to Start 2nd Fix 0 13-Feb-16 13-Feb-16 0% AED0 AED0
Accommodation-MEP clearance to close corridors ceilings 0 29-Mar-16 29-Mar-16 0% AED0 AED0
Accommodation-CHILLED WATER PIPES (HIGH L) 7 06-Dec-15 16-Feb-16 06-Dec-15 A 16-Feb-16 98% AED43,134 AED42,320
MEP Final Fix 22 04-Apr-16 30-Apr-16 04-Apr-16 30-Apr-16 0% AED258,938 AED0
Accommodation-Civil Clearance to Start Final Fix 0 04-Apr-16 04-Apr-16 0% AED0 AED0
Accommodation-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 4 05-Apr-16 09-Apr-16 05-Apr-16 09-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF DBS 4 05-Apr-16 09-Apr-16 05-Apr-16 09-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF PANELS / SMDBS 4 05-Apr-16 09-Apr-16 05-Apr-16 09-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF TELEPHONE SYSTEM 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF CCTV SYSTEM 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED24,661 AED0
Accommodation-TERMINATION & DRESSING OF DBS 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 4 05-Apr-16 09-Apr-16 05-Apr-16 09-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF WIRING ACCESSORIES 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF GRILLS&DIFFUSERS 4 05-Apr-16 09-Apr-16 05-Apr-16 09-Apr-16 0% AED24,661 AED0
Accommodation-THERMOSTAT FIXING 2 10-Apr-16 11-Apr-16 10-Apr-16 11-Apr-16 0% AED12,330 AED0
Accommodation-MEP Final Fix Clearance 0 30-Apr-16 30-Apr-16 0% AED0 AED0
Accommodation-INSTALLATION OF SANITARY WARES 7 05-Apr-16 12-Apr-16 05-Apr-16 12-Apr-16 0% AED0 AED0
Roof Floor 91 06-Feb-16 22-May-16 06-Feb-16 22-May-16 0% AED1,843,409 AED0
Civil Clearance for Roof floor Works - Mechanical Works 0 29-Feb-16 29-Feb-16 0% AED0 AED0
Civil Clearance for roof floor Works - Electrical Works 0 06-Feb-16 06-Feb-16 0% AED0 AED0
All Zones 76 23-Feb-16 22-May-16 23-Feb-16 22-May-16 0% AED1,843,409 AED0
2015 2016 2017
14-Jan-16 A, MEP 1st Fix
Accommodation-Civil clearance to Start 1st Fix
Accommodation-DRAINAGE PIPES ( IN WALLS)
Accommodation-WATER SUPPLY PIPES ( IN WALLS)
Accommodation-SLEEVES,CONDUITS,GI BOX,DB B
Accommodation-MEP clearance to Start Plaster
29-Mar-16, MEP 2nd Fix
Accommodation-DRAINAGE PIPES (HIGH L)
Accommodation-WATER SUPPLY PIPES (HIGH L)
Accommodation-GRAVITY TEST
Accommodation-FIRE FIGHTING PIPES(MAINS
Accommodation-PRESSURE TESTING
Accommodation-ACOUSTIC DRAINAGE PIPE INSULATION
Accommodation-FIRE FIGHTING TESTING
Accommodation-VERTICAL SPRINKLER DROPS
Accommodation-WIRING FOR LIGHTING WORKS
Accommodation-WIRING FOR POWER
Accommodation-WIRING FOR FIRE ALARM
Accommodation-CABLE TRAY / TRUNKING
Accommodation-STRUC&ELEC CABLING
Accommodation-DUCTING WORK INCLUDI
Accommodation-INSTALLATION OF FCUS & FANS
Accommodation-FINAL DUCT CONNECTION TO FANS
Accommodation-PRESSURE TEST&INSULATION
Accommodation-MEP clearance to close R
Accommodation-Civil clearance to Start 2nd Fix
Accommodation-MEP clearance to close c
Accommodation-CHILLED WATER PIPES (HIGH L)
30-Apr-16, MEP Final Fix
Accommodation-Civil Clearance to Start Final Fix
Accommodation-HOSE REEL&FIRE EX
Accommodation-INSTALLATION OF DBS
Accommodation-INSTALLATION OF PA
Accommodation-INSTALLATION OF TE
Accommodation-INSTALLATION OF CC
Accommodation-TERMINATION & DRE
Accommodation-INSTALLATION OF FIR
Accommodation-INSTALLATION OF LIG
Accommodation-INSTALLATION OF WI
Accommodation-INSTALLATION OF GR
Accommodation-THERMOSTAT FIXING
Accommodation-MEP Final Fix Clearance
Accommodation-INSTALLATION OF SA
22-May-16, Roof Floor
Civil Clearance for Roof floor Works - Mecha
Civil Clearance for roof floor Works - Electrical Works
22-May-16, All Zones
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 14 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Mechanical 70 29-Feb-16 21-May-16 29-Feb-16 21-May-16 0% AED1,097,413 AED0
SECOND FIX 53 29-Feb-16 30-Apr-16 29-Feb-16 30-Apr-16 0% AED900,125 AED0
Accommodation-PRESSURE TEST&INSULATION 10 11-Apr-16 21-Apr-16 11-Apr-16 21-Apr-16 0% AED24,661 AED0
Accommodation-SUPPORTS FOR DUCTING WORK 12 29-Feb-16 13-Mar-16 29-Feb-16 13-Mar-16 0% AED73,983 AED0
Accommodation-SUPPORTS FOR PIPING WORKS 12 06-Mar-16 19-Mar-16 06-Mar-16 19-Mar-16 0% AED73,983 AED0
Accommodation-DUCTING WORK ON ROOF 35 20-Mar-16 28-Apr-16 20-Mar-16 28-Apr-16 0% AED215,784 AED0
Accommodation-PIPING WORK ON ROOF 25 20-Mar-16 17-Apr-16 20-Mar-16 17-Apr-16 0% AED215,784 AED0
Accommodation-INSTALLATION OF FANS AND CONNECTION 24 03-Apr-16 30-Apr-16 03-Apr-16 30-Apr-16 0% AED147,966 AED0
Accommodation-INSTALLATION OF AHU AND VALVE PACKAGES 24 29-Mar-16 25-Apr-16 29-Mar-16 25-Apr-16 0% AED147,966 AED0
FINAL FIX 38 06-Apr-16 21-May-16 06-Apr-16 21-May-16 0% AED197,288 AED0
Accommodation-INSTALLATION OF CU's 14 06-Apr-16 21-Apr-16 06-Apr-16 21-Apr-16 0% AED86,313 AED0
Accommodation-CLADDING WORKS FOR DUCTS&PIPING 18 30-Apr-16 21-May-16 30-Apr-16 21-May-16 0% AED110,975 AED0
Electrical 76 23-Feb-16 22-May-16 23-Feb-16 22-May-16 0% AED376,081 AED0
FIRST FIX 6 23-Feb-16 29-Feb-16 23-Feb-16 29-Feb-16 0% AED36,992 AED0
Accommodation-SLEEVES,CONDUTES,GI BOX,DB BOX IN WALL 6 23-Feb-16 29-Feb-16 23-Feb-16 29-Feb-16 0% AED36,992 AED0
SECOND FIX 29 04-Apr-16 08-May-16 04-Apr-16 08-May-16 0% AED160,297 AED0
Accommodation-WIRING FOR LIGHTING & POWER 7 04-Apr-16 11-Apr-16 04-Apr-16 11-Apr-16 0% AED43,157 AED0
Accommodation-CABLE TRAY / TRUNKING 12 11-Apr-16 24-Apr-16 11-Apr-16 24-Apr-16 0% AED43,157 AED0
Accommodation-CABLING INCLUDING DRESSING OF CABLES 12 24-Apr-16 08-May-16 24-Apr-16 08-May-16 0% AED73,983 AED0
FINAL FIX 12 09-May-16 22-May-16 09-May-16 22-May-16 0% AED178,792 AED0
Accommodation-INSTILLATION OF PANELS / SMDBS /MCC 7 09-May-16 16-May-16 09-May-16 16-May-16 0% AED43,157 AED0
Accommodation-TERMINATION & DRESSING OF DBS 7 15-May-16 22-May-16 15-May-16 22-May-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF WIRING ACCESSORIES 7 09-May-16 16-May-16 09-May-16 16-May-16 0% AED24,661 AED0
Accommodation-INSTALLATION OF LIGHTING CONTROL SYSTEM 7 09-May-16 16-May-16 09-May-16 16-May-16 0% AED43,157 AED0
Accommodation-INSTALL OF LIGHT FITTING & E.M LIGHT 7 09-May-16 16-May-16 09-May-16 16-May-16 0% AED43,157 AED0
Plumbing 59 05-Mar-16 12-May-16 05-Mar-16 12-May-16 0% AED369,914 AED0
SECOND FIX 59 05-Mar-16 12-May-16 05-Mar-16 12-May-16 0% AED369,914 AED0
Accommodation-SOLAR WATER HEATERS 18 21-Apr-16 12-May-16 21-Apr-16 12-May-16 0% AED110,975 AED0
Accommodation-FIXING OF CIRCULATION PUMP 15 29-Mar-16 14-Apr-16 29-Mar-16 14-Apr-16 0% AED92,478 AED0
Accommodation-WATER SUPPLY & DRAINAGE PIPES ON ROOF 18 05-Mar-16 24-Mar-16 05-Mar-16 24-Mar-16 0% AED110,975 AED0
Accommodation-PRESSURE TESTING 5 26-Mar-16 30-Mar-16 26-Mar-16 30-Mar-16 0% AED24,661 AED0
Accommodation-PIPE INSULATION 5 16-Apr-16 20-Apr-16 16-Apr-16 20-Apr-16 0% AED30,826 AED0
All Floors 65 14-Dec-15 29-Feb-16 14-Dec-15 A 29-Feb-16 72.18% AED1,202,223 AED944,781
All Zones 65 14-Dec-15 29-Feb-16 14-Dec-15 A 29-Feb-16 72.18% AED1,202,223 AED944,781
Civil Clearance for Shaft Works 0 29-Feb-16 29-Feb-16 0% AED0 AED0
Mechanical Shafts 35 16-Dec-15 10-Feb-16 16-Dec-15 A 10-Feb-16 82.5% AED554,872 AED522,804
SECOND FIX 35 16-Dec-15 10-Feb-16 16-Dec-15 A 10-Feb-16 77.5% AED431,567 AED399,499
Accommodation-DUCT RISERS IN SHAFTS 35 16-Dec-15 07-Feb-16 16-Dec-15 A 07-Feb-16 95% AED215,784 AED206,193
Accommodation-PIPING IN SHAFTS 35 16-Dec-15 10-Feb-16 16-Dec-15 A 10-Feb-16 60% AED215,784 AED193,306
FINAL FIX 20 26-Dec-15 28-Dec-15 26-Dec-15 A 28-Dec-15 A 100% AED123,305 AED123,305
Accommodation-CLADDING WORK FOR DUCTS&PIPING 20 26-Dec-15 28-Dec-15 26-Dec-15 A 28-Dec-15 A 100% AED123,305 AED123,305
Electrical Shafts 55 16-Dec-15 18-Feb-16 16-Dec-15 A 18-Feb-16 45% AED431,567 AED206,193
SECOND FIX 55 16-Dec-15 18-Feb-16 16-Dec-15 A 18-Feb-16 45% AED431,567 AED206,193
Accommodation-CABLE TRAY 35 16-Dec-15 07-Feb-16 16-Dec-15 A 07-Feb-16 90% AED215,784 AED206,193
Accommodation-CABLE PULLING 8 10-Feb-16 18-Feb-16 10-Feb-16 18-Feb-16 0% AED215,784 AED0
Plumbing Shafts 35 14-Dec-15 21-Dec-15 14-Dec-15 A 21-Dec-15 A 100% AED215,784 AED215,784
SECOND FIX 35 14-Dec-15 21-Dec-15 14-Dec-15 A 21-Dec-15 A 100% AED215,784 AED215,784
Accommodation-SHAFTS DRAINAGE & PLUMBING PIPES 35 14-Dec-15 21-Dec-15 14-Dec-15 A 21-Dec-15 A 100% AED215,784 AED215,784
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 13 22-May-16 05-Jun-16 22-May-16 05-Jun-16 0% AED221,949 AED0
2015 2016 2017
21-May-16, Mechanical
30-Apr-16, SECOND FIX
Accommodation-PRESSURE TEST&IN
Accommodation-SUPPORTS FOR DUCTING WORK
Accommodation-SUPPORTS FOR PIPING WORKS
Accommodation-DUCTING WORK ON ROOF
Accommodation-PIPING WORK ON ROOF
Accommodation-INSTALLATION OF F
Accommodation-INSTALLATION OF A
21-May-16, FINAL FIX
Accommodation-INSTALLATION OF CU's
Accommodation-CLADDING WORK
22-May-16, Electrical
29-Feb-16, FIRST FIX
Accommodation-SLEEVES,CONDUTES,GI B
08-May-16, SECOND FIX
Accommodation-WIRING FOR LIGHTIN
Accommodation-CABLE TRAY / TRUNKING
Accommodation-CABLING INCLUDI
22-May-16, FINAL FIX
Accommodation-INSTILLATION OF
Accommodation-TERMINATION &
Accommodation-INSTALLATION OF
Accommodation-INSTALLATION OF
Accommodation-INSTALL OF LIGH
12-May-16, Plumbing
12-May-16, SECOND FIX
Accommodation-SOLAR WATER HEATERS
Accommodation-FIXING OF CIRCULAT
Accommodation-WATER SUPPLY & DRA
Accommodation-PRESSURE TESTING
Accommodation-PIPE INSULATION
29-Feb-16, All Floors
29-Feb-16, All Zones
Civil Clearance for Shaft Works
10-Feb-16, Mechanical Shafts
10-Feb-16, SECOND FIX
Accommodation-DUCT RISERS IN SHAFTS
Accommodation-PIPING IN SHAFTS
28-Dec-15 A, FINAL FIX
Accommodation-CLADDING WORK FOR DUCTS&PIPING
18-Feb-16, Electrical Shafts
18-Feb-16, SECOND FIX
Accommodation-CABLE TRAY
Accommodation-CABLE PULLING
21-Dec-15 A, Plumbing Shafts
21-Dec-15 A, SECOND FIX
Accommodation-SHAFTS DRAINAGE & PLUMBING PIPES
05-Jun-16, Preliminary Testing &
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 15 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
All Floors 13 22-May-16 05-Jun-16 22-May-16 05-Jun-16 0% AED221,949 AED0
All Zones 13 22-May-16 05-Jun-16 22-May-16 05-Jun-16 0% AED221,949 AED0
Accommodation-Electrical System Preliminary Testing & Commissioning 12 23-May-16 05-Jun-16 23-May-16 05-Jun-16 0% AED73,983 AED0
Accommodation-HVAC System Preliminary Testing & Commissioning 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED73,983 AED0
Accommodation-Plumbing System Preliminary Testing & Commissioning 12 23-May-16 05-Jun-16 23-May-16 05-Jun-16 0% AED73,983 AED0
House ConnectionsHouse Connections 51 29-Mar-16 28-May-16 29-Mar-16 28-May-16 0% AED184,959 AED0
All Floors 51 29-Mar-16 28-May-16 29-Mar-16 28-May-16 0% AED184,959 AED0
All Zones 51 29-Mar-16 28-May-16 29-Mar-16 28-May-16 0% AED184,959 AED0
Accommodation-Drainage House Connection 6 22-May-16 28-May-16 22-May-16 28-May-16 0% AED36,992 AED0
Accommodation-Water Supply House Connection 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED36,992 AED0
Accommodation-Chilled Water House Connection 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED36,992 AED0
Accommodation-Low Current House Connection 6 08-May-16 14-May-16 08-May-16 14-May-16 0% AED36,992 AED0
Accommodation-Electrical House Connection 6 29-Mar-16 04-Apr-16 29-Mar-16 04-Apr-16 0% AED36,992 AED0
Administration BuildingAdministration Building 240 24-Aug-15 05-Jun-16 24-Aug-15 A 05-Jun-16 21.05% AED9,117,104 AED1,965,913
SkeletonSkeleton 105 24-Aug-15 07-Jan-16 24-Aug-15 A 07-Jan-16 A 100% AED192,858 AED192,858
Sub Structure 65 24-Aug-15 28-Nov-15 24-Aug-15 A 28-Nov-15 A 100% AED144,182 AED144,182
Part 1 15 24-Aug-15 09-Sep-15 24-Aug-15 A 09-Sep-15 A 100% AED36,045 AED36,045
Concrete Works 15 24-Aug-15 09-Sep-15 24-Aug-15 A 09-Sep-15 A 100% AED36,045 AED36,045
Administration-Grade Slab Rebar & MEP Services 2 07-Sep-15 09-Sep-15 07-Sep-15 A 09-Sep-15 A 100% AED29,092 AED29,092
Administration-MEP Under Ground Services 1 24-Aug-15 25-Aug-15 24-Aug-15 A 25-Aug-15 A 100% AED6,954 AED6,954
Clearance for MEP Under ground Services 0 24-Aug-15 24-Aug-15 A 100% AED0 AED0
Part 2 13 02-Sep-15 16-Sep-15 02-Sep-15 A 16-Sep-15 A 100% AED36,045 AED36,045
Concrete Works 13 02-Sep-15 16-Sep-15 02-Sep-15 A 16-Sep-15 A 100% AED36,045 AED36,045
Administration-MEP Under Ground Services 5 02-Sep-15 07-Sep-15 02-Sep-15 A 07-Sep-15 A 100% AED6,954 AED6,954
Administration-Grade Slab Rebar & MEP Services 2 15-Sep-15 16-Sep-15 15-Sep-15 A 16-Sep-15 A 100% AED29,092 AED29,092
Part 3 53 02-Sep-15 28-Nov-15 02-Sep-15 A 28-Nov-15 A 100% AED36,045 AED36,045
Concrete Works 53 02-Sep-15 28-Nov-15 02-Sep-15 A 28-Nov-15 A 100% AED36,045 AED36,045
Administration-MEP Under Ground Services 2 02-Sep-15 03-Sep-15 02-Sep-15 A 03-Sep-15 A 100% AED6,954 AED6,954
Administration-Grade Slab Rebar & MEP Services 2 04-Nov-15 28-Nov-15 04-Nov-15 A 28-Nov-15 A 100% AED29,092 AED29,092
Part 4 50 10-Sep-15 28-Nov-15 10-Sep-15 A 28-Nov-15 A 100% AED36,045 AED36,045
Concrete Works 50 10-Sep-15 28-Nov-15 10-Sep-15 A 28-Nov-15 A 100% AED36,045 AED36,045
Administration-MEP Under Ground Services 4 10-Sep-15 14-Sep-15 10-Sep-15 A 14-Sep-15 A 100% AED6,954 AED6,954
Administration-Grade Slab Rebar & MEP Services 5 05-Nov-15 28-Nov-15 05-Nov-15 A 28-Nov-15 A 100% AED29,092 AED29,092
Super Structure 55 25-Oct-15 07-Jan-16 25-Oct-15 A 07-Jan-16 A 100% AED48,676 AED48,676
Part 1 26 18-Nov-15 19-Dec-15 18-Nov-15 A 19-Dec-15 A 100% AED20,861 AED20,861
First Floor 2 18-Nov-15 25-Nov-15 18-Nov-15 A 25-Nov-15 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 2 18-Nov-15 25-Nov-15 18-Nov-15 A 25-Nov-15 A 100% AED6,954 AED6,954
Roof Floor 2 16-Dec-15 17-Dec-15 16-Dec-15 A 17-Dec-15 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 2 16-Dec-15 17-Dec-15 16-Dec-15 A 17-Dec-15 A 100% AED6,954 AED6,954
Top Roof Floor 1 19-Dec-15 19-Dec-15 19-Dec-15 A 19-Dec-15 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 1 19-Dec-15 19-Dec-15 19-Dec-15 A 19-Dec-15 A 100% AED6,954 AED6,954
Part 2 4 25-Oct-15 28-Oct-15 25-Oct-15 A 28-Oct-15 A 100% AED6,954 AED6,954
First Floor 4 25-Oct-15 28-Oct-15 25-Oct-15 A 28-Oct-15 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 4 25-Oct-15 28-Oct-15 25-Oct-15 A 28-Oct-15 A 100% AED6,954 AED6,954
Part 3 20 26-Dec-15 07-Jan-16 26-Dec-15 A 07-Jan-16 A 100% AED13,907 AED13,907
First Floor 4 26-Dec-15 29-Dec-15 26-Dec-15 A 29-Dec-15 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 4 26-Dec-15 29-Dec-15 26-Dec-15 A 29-Dec-15 A 100% AED6,954 AED6,954
Roof Floor 2 06-Jan-16 07-Jan-16 06-Jan-16 A 07-Jan-16 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 2 06-Jan-16 07-Jan-16 06-Jan-16 A 07-Jan-16 A 100% AED6,954 AED6,954
Part 4 2 17-Dec-15 17-Dec-15 17-Dec-15 A 17-Dec-15 A 100% AED6,954 AED6,954
2015 2016 2017
05-Jun-16, All Floors
05-Jun-16, All Zones
Accommodation-Electrical System
Accommodation-HVAC System Pr
Accommodation-Plumbing System
28-May-16, House Connections
28-May-16, All Floors
28-May-16, All Zones
Accommodation-Drainage House Connection
Accommodation-Water Supply House
Accommodation-Chilled Water House
Accommodation-Low Current House
Accommodation-Electrical House Connection
05-Jun-16, Administration Building
07-Jan-16 A, Skeleton
28-Nov-15 A, Sub Structure
09-Sep-15 A, Part 1
09-Sep-15 A, Concrete Works
Administration-Grade Slab Rebar & MEP Services
Administration-MEP Under Ground Services
Clearance for MEP Under ground Services
16-Sep-15 A, Part 2
16-Sep-15 A, Concrete Works
Administration-MEP Under Ground Services
Administration-Grade Slab Rebar & MEP Services
28-Nov-15 A, Part 3
28-Nov-15 A, Concrete Works
Administration-MEP Under Ground Services
Administration-Grade Slab Rebar & MEP Services
28-Nov-15 A, Part 4
28-Nov-15 A, Concrete Works
Administration-MEP Under Ground Services
Administration-Grade Slab Rebar & MEP Services
07-Jan-16 A, Super Structure
19-Dec-15 A, Part 1
25-Nov-15 A, First Floor
Administration-MEP Conduits & Sleeves Inside The Slab
17-Dec-15 A, Roof Floor
Administration-MEP Conduits & Sleeves Inside The Slab
19-Dec-15 A, Top Roof Floor
Administration-MEP Conduits & Sleeves Inside The Slab
28-Oct-15 A, Part 2
28-Oct-15 A, First Floor
Administration-MEP Conduits & Sleeves Inside The Slab
07-Jan-16 A, Part 3
29-Dec-15 A, First Floor
Administration-MEP Conduits & Sleeves Inside The Slab
07-Jan-16 A, Roof Floor
Administration-MEP Conduits & Sleeves Inside The Slab
17-Dec-15 A, Part 4
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 16 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
First Floor 2 17-Dec-15 17-Dec-15 17-Dec-15 A 17-Dec-15 A 100% AED6,954 AED6,954
Administration-MEP Conduits & Sleeves Inside The Slab 2 17-Dec-15 17-Dec-15 17-Dec-15 A 17-Dec-15 A 100% AED6,954 AED6,954
MEPMEP 158 18-Nov-15 24-May-16 18-Nov-15 A 24-May-16 20.13% AED8,577,981 AED1,773,055
Ground Floor 138 18-Nov-15 30-Apr-16 18-Nov-15 A 30-Apr-16 44.05% AED2,901,377 AED1,356,175
ZONE A 138 18-Nov-15 30-Apr-16 18-Nov-15 A 30-Apr-16 54.01% AED1,489,475 AED827,049
MEP 1st Fix 32 14-Dec-15 24-Jan-16 14-Dec-15 A 24-Jan-16 A 100% AED204,265 AED204,265
Administration-Civil clearance to Start 1st Fix 0 14-Dec-15 14-Dec-15 A 100% AED0 AED0
Administration-DRAINAGE PIPES ( IN WALLS) 12 20-Dec-15 24-Jan-16 20-Dec-15 A 24-Jan-16 A 100% AED68,088 AED68,088
Administration-WATER SUPPLY PIPES ( IN WALLS) 12 20-Dec-15 24-Jan-16 20-Dec-15 A 24-Jan-16 A 100% AED68,088 AED68,088
Administration-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 12 14-Dec-15 24-Jan-16 14-Dec-15 A 24-Jan-16 A 100% AED68,088 AED68,088
Administration-MEP clearance to Start Plaster 0 20-Jan-16 20-Jan-16 A 100% AED0 AED0
MEP 2nd Fix 117 18-Nov-15 05-Apr-16 18-Nov-15 A 05-Apr-16 82.1% AED731,023 AED622,784
Administration-DRAINAGE PIPES (HIGH L) 14 19-Nov-15 07-Feb-16 19-Nov-15 A 07-Feb-16 95% AED38,223 AED37,082
Administration-WATER SUPPLY PIPES (HIGH L) 14 15-Dec-15 24-Feb-16 15-Dec-15 A 24-Feb-16 95% AED38,223 AED36,561
Administration-GRAVITY TEST 8 14-Dec-15 07-Mar-16 14-Dec-15 A 07-Mar-16 98% AED45,392 AED43,460
Administration-FIRE FIGHTING PIPES(MAINS/BRANCHES) 14 15-Dec-15 25-Feb-16 15-Dec-15 A 25-Feb-16 95% AED38,223 AED36,561
Administration-PRESSURE TESTING 8 14-Jan-16 09-Feb-16 14-Jan-16 A 09-Feb-16 60% AED45,392 AED37,322
Administration-ACOUSTIC DRAINAGE PIPE INSULATION 8 20-Jan-16 09-Mar-16 20-Jan-16 A 09-Mar-16 70% AED45,392 AED39,718
Administration-FIRE FIGHTING TESTING 8 10-Dec-15 05-Mar-16 10-Dec-15 A 05-Mar-16 95% AED45,392 AED43,576
Administration-VERTICAL SPRINKLER DROPS 8 20-Dec-15 07-Mar-16 20-Dec-15 A 07-Mar-16 95% AED45,392 AED43,230
Administration-WIRING FOR LIGHTING WORKS 14 20-Dec-15 22-Feb-16 20-Dec-15 A 22-Feb-16 95% AED38,223 AED36,402
Administration-WIRING FOR POWER 14 20-Dec-15 22-Mar-16 20-Dec-15 A 22-Mar-16 95% AED38,223 AED36,402
Administration-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 14 25-Nov-15 22-Mar-16 25-Nov-15 A 22-Mar-16 95% AED38,223 AED36,990
Administration-CABLE TRAY / TRUNKING 14 15-Dec-15 22-Feb-16 15-Dec-15 A 22-Feb-16 95% AED38,223 AED36,561
Administration-STRUC&ELEC CABLING INCLUDING DRESSING 14 06-Feb-16 22-Feb-16 06-Feb-16 22-Feb-16 0% AED38,223 AED0
Administration-DUCTING WORK INCLUDING INSULATION 14 19-Nov-15 07-Feb-16 19-Nov-15 A 07-Feb-16 90% AED38,223 AED37,082
Administration-INSTALLATION OF FCUS & FANS 14 15-Dec-15 19-Dec-15 15-Dec-15 A 19-Dec-15 A 100% AED38,223 AED38,223
Administration-FINAL DUCT CONNECTION TO FANS 12 06-Feb-16 18-Feb-16 06-Feb-16 18-Feb-16 0% AED38,223 AED0
Administration-PRESSURE TEST&INSULATION 8 16-Dec-15 27-Dec-15 16-Dec-15 A 27-Dec-15 A 100% AED45,392 AED45,392
Administration-MEP clearance to close Kitchen, Laundry & Gym ceilings 0 29-Mar-16 29-Mar-16 0% AED0 AED0
Administration-Civil clearance to Start 2nd Fix 0 18-Nov-15 18-Nov-15 A 100% AED0 AED0
Administration-MEP clearance to close Dining & Majlis ceilings 0 05-Apr-16 05-Apr-16 0% AED0 AED0
Administration-CHILD WATER PIPES (HIGH L) 14 14-Dec-15 19-Dec-15 14-Dec-15 A 19-Dec-15 A 100% AED38,223 AED38,223
MEP Final Fix 21 05-Apr-16 30-Apr-16 05-Apr-16 30-Apr-16 0% AED554,187 AED0
Administration-Civil Clearance to Start Final Fix 0 05-Apr-16 05-Apr-16 0% AED0 AED0
Administration-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 8 06-Apr-16 14-Apr-16 06-Apr-16 14-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF DBS 8 06-Apr-16 14-Apr-16 06-Apr-16 14-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF PANELS / SMDBS 8 06-Apr-16 14-Apr-16 06-Apr-16 14-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF TELEPHONE SYSTEM 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF CCTV SYSTEM 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-TERMINATION & DRESSING OF DBS 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 8 06-Apr-16 14-Apr-16 06-Apr-16 14-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF LIGHT FITTING & E.M LIGHT 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF WIRING ACCESSORIES 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF GRILLS&DIFFUSERS 8 06-Apr-16 14-Apr-16 06-Apr-16 14-Apr-16 0% AED45,392 AED0
Administration-THERMOSTAT FIXING 4 16-Apr-16 19-Apr-16 16-Apr-16 19-Apr-16 0% AED22,696 AED0
Administration-MEP Final Fix Clearance 0 30-Apr-16 30-Apr-16 0% AED0 AED0
2015 2016 2017
17-Dec-15 A, First Floor
Administration-MEP Conduits & Sleeves Inside The Slab
24-May-16, MEP
30-Apr-16, Ground Floor
30-Apr-16, ZONE A
24-Jan-16 A, MEP 1st Fix
Administration-Civil clearance to Start 1st Fix
Administration-DRAINAGE PIPES ( IN WALLS)
Administration-WATER SUPPLY PIPES ( IN WALLS)
Administration-SLEEVES,CONDUITS,GI BOX,DB
Administration-MEP clearance to Start Plaster
05-Apr-16, MEP 2nd Fix
Administration-DRAINAGE PIPES (HIGH L)
Administration-WATER SUPPLY PIPES (HIGH L)
Administration-GRAVITY TEST
Administration-FIRE FIGHTING PIPES(MAIN
Administration-PRESSURE TESTING
Administration-ACOUSTIC DRAINAGE PIPE
Administration-FIRE FIGHTING TESTING
Administration-VERTICAL SPRINKLER DROPS
Administration-WIRING FOR LIGHTING WORKS
Administration-WIRING FOR POWER
Administration-WIRING FOR FIRE ALARM
Administration-CABLE TRAY / TRUNKING
Administration-STRUC&ELEC CABLING INC
Administration-DUCTING WORK INCLUDING I
Administration-INSTALLATION OF FCUS & FANS
Administration-FINAL DUCT CONNECTION TO FANS
Administration-PRESSURE TEST&INSULATION
Administration-MEP clearance to close Kit
Administration-Civil clearance to Start 2nd Fix
Administration-MEP clearance to close D
Administration-CHILD WATER PIPES (HIGH L)
30-Apr-16, MEP Final Fix
Administration-Civil Clearance to Start Final Fix
Administration-HOSE REEL&FIRE EXT
Administration-INSTALLATION OF DBS
Administration-INSTALLATION OF PAN
Administration-INSTALLATION OF TEL
Administration-INSTALLATION OF CC
Administration-TERMINATION & DRES
Administration-INSTALLATION OF FIRE
Administration-INSTALLATION OF LIG
Administration-INSTALLATION OF WIR
Administration-INSTALLATION OF GRIL
Administration-THERMOSTAT FIXING
Administration-MEP Final Fix Clearance
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 17 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Administration- INSTALLA TION SANITARY WARES 12 06-Apr-16 19-Apr-16 06-Apr-16 19-Apr-16 0% AED77,572 AED0
ZONE B 101 04-Jan-16 30-Apr-16 04-Jan-16 A 30-Apr-16 33.55% AED1,411,903 AED529,126
MEP 1st Fix 25 04-Jan-16 07-Feb-16 04-Jan-16 A 07-Feb-16 90% AED204,265 AED190,647
Administration-Civil clearance to Start 1st Fix 0 04-Jan-16 04-Jan-16 A 100% AED0 AED0
Administration-DRAINAGE PIPES ( IN WALLS) 12 04-Jan-16 07-Feb-16 04-Jan-16 A 07-Feb-16 90% AED68,088 AED63,549
Administration-WATER SUPPLY PIPES ( IN WALLS) 12 04-Jan-16 07-Feb-16 04-Jan-16 A 07-Feb-16 90% AED68,088 AED63,549
Administration-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 12 04-Jan-16 07-Feb-16 04-Jan-16 A 07-Feb-16 90% AED68,088 AED63,549
Administration-MEP clearance to Start Plaster 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
MEP 2nd Fix 79 10-Jan-16 11-Apr-16 10-Jan-16 A 11-Apr-16 39.66% AED731,023 AED338,479
Administration-DRAINAGE PIPES (HIGH L) 14 17-Jan-16 20-Feb-16 17-Jan-16 A 20-Feb-16 70% AED38,223 AED30,942
Administration-WATER SUPPLY PIPES (HIGH L) 14 17-Jan-16 20-Feb-16 17-Jan-16 A 20-Feb-16 70% AED38,223 AED30,942
Administration-GRAVITY TEST 8 17-Jan-16 25-Feb-16 17-Jan-16 A 25-Feb-16 95% AED45,392 AED40,614
Administration-FIRE FIGHTING PIPES(MAINS/BRANCHES) 14 17-Jan-16 21-Feb-16 17-Jan-16 A 21-Feb-16 60% AED38,223 AED30,942
Administration-PRESSURE TESTING 8 21-Feb-16 29-Feb-16 21-Feb-16 29-Feb-16 0% AED45,392 AED0
Administration-ACOUSTIC DRAINAGE PIPE INSULATION 8 04-Feb-16 28-Feb-16 04-Feb-16 A 28-Feb-16 50% AED45,392 AED9,078
Administration-FIRE FIGHTING TESTING 8 15-Feb-16 23-Feb-16 15-Feb-16 23-Feb-16 0% AED45,392 AED0
Administration-VERTICAL SPRINKLER DROPS 8 26-Jan-16 25-Feb-16 26-Jan-16 A 25-Feb-16 60% AED45,392 AED37,139
Administration-WIRING FOR LIGHTING WORKS 14 26-Jan-16 13-Feb-16 26-Jan-16 A 13-Feb-16 60% AED38,223 AED31,273
Administration-WIRING FOR POWER 14 26-Jan-16 24-Feb-16 26-Jan-16 A 24-Feb-16 60% AED38,223 AED26,462
Administration-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 14 26-Jan-16 24-Feb-16 26-Jan-16 A 24-Feb-16 60% AED38,223 AED26,462
Administration-CABLE TRAY / TRUNKING 14 17-Jan-16 21-Feb-16 17-Jan-16 A 21-Feb-16 60% AED38,223 AED30,942
Administration-STRUC&ELEC CABLING INCLUDING DRESSING 14 22-Feb-16 08-Mar-16 22-Feb-16 08-Mar-16 0% AED38,223 AED0
Administration-DUCTING WORK INCLUDING INSULATION 14 17-Jan-16 20-Feb-16 17-Jan-16 A 20-Feb-16 50% AED38,223 AED30,942
Administration-INSTALLATION OF FCUS & FANS 14 06-Feb-16 21-Feb-16 06-Feb-16 21-Feb-16 0% AED38,223 AED0
Administration-FINAL DUCT CONNECTION TO FANS 14 06-Feb-16 21-Feb-16 06-Feb-16 21-Feb-16 0% AED38,223 AED0
Administration-PRESSURE TEST&INSULATION 8 21-Feb-16 29-Feb-16 21-Feb-16 29-Feb-16 0% AED45,392 AED0
Administration-MEP clearance to close Administration, Clinic, Mosque ceilings 0 29-Feb-16 29-Feb-16 0% AED0 AED0
Administration-Civil clearance to Start 2nd Fix 0 10-Jan-16 10-Jan-16 A 100% AED0 AED0
Administration-MEP clearance to close corridors ceilings 0 11-Apr-16 11-Apr-16 0% AED0 AED0
Administration-CHILD WATER PIPES (HIGH L) 14 30-Jan-16 20-Feb-16 30-Jan-16 A 20-Feb-16 25% AED38,223 AED12,741
MEP Final Fix 16 11-Apr-16 30-Apr-16 11-Apr-16 30-Apr-16 0% AED476,615 AED0
Administration-Civil Clearance to Start Final Fix 0 11-Apr-16 11-Apr-16 0% AED0 AED0
Administration-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 8 12-Apr-16 20-Apr-16 12-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF DBS 8 12-Apr-16 20-Apr-16 12-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF PANELS / SMDBS 8 12-Apr-16 20-Apr-16 12-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF TELEPHONE SYSTEM 8 21-Apr-16 30-Apr-16 21-Apr-16 30-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF CCTV SYSTEM 8 21-Apr-16 30-Apr-16 21-Apr-16 30-Apr-16 0% AED45,392 AED0
Administration-TERMINATION & DRESSING OF DBS 8 21-Apr-16 30-Apr-16 21-Apr-16 30-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 8 12-Apr-16 20-Apr-16 12-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF LIGHT FITTING & E.M LIGHT 8 21-Apr-16 30-Apr-16 21-Apr-16 30-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF WIRING ACCESSORIES 8 21-Apr-16 30-Apr-16 21-Apr-16 30-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF GRILLS&DIFFUSERS 8 12-Apr-16 20-Apr-16 12-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-THERMOSTAT FIXING 4 21-Apr-16 25-Apr-16 21-Apr-16 25-Apr-16 0% AED22,696 AED0
Administration-MEP Final Fix Clearance 0 30-Apr-16 30-Apr-16 0% AED0 AED0
Administration- INSTALLA TION SANITARY WARES 12 12-Apr-16 25-Apr-16 12-Apr-16 25-Apr-16 0% AED0 AED0
1st Floor 97 23-Jan-16 18-May-16 23-Jan-16 A 18-May-16 15.88% AED2,823,806 AED416,880
ZONE A 82 23-Jan-16 30-Apr-16 23-Jan-16 A 30-Apr-16 19.85% AED1,411,903 AED318,139
2015 2016 2017
Administration- INSTALLA TION SANIT
30-Apr-16, ZONE B
07-Feb-16, MEP 1st Fix
Administration-Civil clearance to Start 1st Fix
Administration-DRAINAGE PIPES ( IN WALLS)
Administration-WATER SUPPLY PIPES ( IN WALLS)
Administration-SLEEVES,CONDUITS,GI BOX,D
Administration-MEP clearance to Start Plaster
11-Apr-16, MEP 2nd Fix
Administration-DRAINAGE PIPES (HIGH L)
Administration-WATER SUPPLY PIPES (HIGH L)
Administration-GRAVITY TEST
Administration-FIRE FIGHTING PIPES(MAINS
Administration-PRESSURE TESTING
Administration-ACOUSTIC DRAINAGE PIPE
Administration-FIRE FIGHTING TESTING
Administration-VERTICAL SPRINKLER DROPS
Administration-WIRING FOR LIGHTING WORKS
Administration-WIRING FOR POWER
Administration-WIRING FOR FIRE ALARM&L
Administration-CABLE TRAY / TRUNKING
Administration-STRUC&ELEC CABLING IN
Administration-DUCTING WORK INCLUDING
Administration-INSTALLATION OF FCUS & FANS
Administration-FINAL DUCT CONNECTION TO FANS
Administration-PRESSURE TEST&INSULATION
Administration-MEP clearance to close Admin
Administration-Civil clearance to Start 2nd Fix
Administration-MEP clearance to close c
Administration-CHILD WATER PIPES (HIGH L)
30-Apr-16, MEP Final Fix
Administration-Civil Clearance to Start Final Fix
Administration-HOSE REEL&FIRE EXT
Administration-INSTALLATION OF DBS
Administration-INSTALLATION OF PAN
Administration-INSTALLATION OF TE
Administration-INSTALLATION OF CC
Administration-TERMINATION & DRE
Administration-INSTALLATION OF FIR
Administration-INSTALLATION OF LIG
Administration-INSTALLATION OF W
Administration-INSTALLATION OF GRI
Administration-THERMOSTAT FIXING
Administration-MEP Final Fix Clearance
Administration- INSTALLA TION SANIT
18-May-16, 1st Floor
30-Apr-16, ZONE A
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 18 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
MEP 1st Fix 8 01-Feb-16 09-Feb-16 01-Feb-16 A 09-Feb-16 0% AED204,265 AED0
Administration-Civil clearance to Start 1st Fix 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
Administration-DRAINAGE PIPES ( IN WALLS) 4 06-Feb-16 09-Feb-16 06-Feb-16 09-Feb-16 0% AED68,088 AED0
Administration-WATER SUPPLY PIPES ( IN WALLS) 4 06-Feb-16 09-Feb-16 06-Feb-16 09-Feb-16 0% AED68,088 AED0
Administration-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 4 06-Feb-16 09-Feb-16 06-Feb-16 09-Feb-16 0% AED68,088 AED0
Administration-MEP clearance to Start Plaster 0 09-Feb-16 09-Feb-16 0% AED0 AED0
MEP 2nd Fix 71 23-Jan-16 17-Apr-16 23-Jan-16 A 17-Apr-16 38.33% AED731,023 AED318,139
Administration-DRAINAGE PIPES (HIGH L) 6 28-Jan-16 18-Feb-16 28-Jan-16 A 18-Feb-16 90% AED38,223 AED33,445
Administration-WATER SUPPLY PIPES (HIGH L) 6 28-Jan-16 18-Feb-16 28-Jan-16 A 18-Feb-16 70% AED38,223 AED33,445
Administration-GRAVITY TEST 5 20-Feb-16 24-Feb-16 20-Feb-16 24-Feb-16 0% AED45,392 AED0
Administration-FIRE FIGHTING PIPES(MAINS/BRANCHES) 6 28-Jan-16 20-Feb-16 28-Jan-16 A 20-Feb-16 70% AED38,223 AED33,445
Administration-PRESSURE TESTING 5 20-Feb-16 24-Feb-16 20-Feb-16 24-Feb-16 0% AED45,392 AED0
Administration-ACOUSTIC DRAINAGE PIPE INSULATION 5 22-Feb-16 27-Feb-16 22-Feb-16 27-Feb-16 0% AED45,392 AED0
Administration-FIRE FIGHTING TESTING 5 17-Feb-16 22-Feb-16 17-Feb-16 22-Feb-16 0% AED45,392 AED0
Administration-VERTICAL SPRINKLER DROPS 5 28-Jan-16 24-Feb-16 28-Jan-16 A 24-Feb-16 70% AED45,392 AED39,718
Administration-WIRING FOR LIGHTING WORKS 6 28-Jan-16 18-Feb-16 28-Jan-16 A 18-Feb-16 70% AED38,223 AED33,445
Administration-WIRING FOR POWER 6 28-Jan-16 07-Mar-16 28-Jan-16 A 07-Mar-16 70% AED38,223 AED33,445
Administration-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 6 28-Jan-16 27-Feb-16 28-Jan-16 A 27-Feb-16 70% AED38,223 AED33,445
Administration-CABLE TRAY / TRUNKING 6 23-Jan-16 27-Feb-16 23-Jan-16 A 27-Feb-16 70% AED38,223 AED35,282
Administration-STRUC&ELEC CABLING INCLUDING DRESSING 6 21-Feb-16 27-Feb-16 21-Feb-16 27-Feb-16 0% AED38,223 AED0
Administration-DUCTING WORK INCLUDING INSULATION 6 04-Feb-16 18-Feb-16 04-Feb-16 A 18-Feb-16 70% AED38,223 AED12,741
Administration-INSTALLATION OF FCUS & FANS 6 13-Feb-16 18-Feb-16 13-Feb-16 18-Feb-16 0% AED38,223 AED0
Administration-FINAL DUCT CONNECTION TO FANS 6 13-Feb-16 18-Feb-16 13-Feb-16 18-Feb-16 0% AED38,223 AED0
Administration-PRESSURE TEST&INSULATION 5 14-Feb-16 18-Feb-16 14-Feb-16 18-Feb-16 0% AED45,392 AED0
Administration-MEP clearance to close Rooms ceilings 0 07-Mar-16 07-Mar-16 0% AED0 AED0
Administration-Civil clearance to Start 2nd Fix 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
Administration-MEP clearance to close corridors ceilings 0 17-Apr-16 17-Apr-16 0% AED0 AED0
Administration-CHILD WATER PIPES (HIGH L) 6 28-Jan-16 18-Feb-16 28-Jan-16 A 18-Feb-16 70% AED38,223 AED29,729
MEP Final Fix 11 17-Apr-16 30-Apr-16 17-Apr-16 30-Apr-16 0% AED476,615 AED0
Administration-Civil Clearance to Start Final Fix 0 17-Apr-16 17-Apr-16 0% AED0 AED0
Administration-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 3 18-Apr-16 20-Apr-16 18-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF DBS 3 18-Apr-16 20-Apr-16 18-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF PANELS / SMDBS 3 18-Apr-16 20-Apr-16 18-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF TELEPHONE SYSTEM 3 21-Apr-16 24-Apr-16 21-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF CCTV SYSTEM 3 21-Apr-16 24-Apr-16 21-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-TERMINATION & DRESSING OF DBS 3 21-Apr-16 24-Apr-16 21-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 3 18-Apr-16 20-Apr-16 18-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF LIGHT FITTING & E.M LIGHT 3 21-Apr-16 24-Apr-16 21-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF WIRING ACCESSORIES 3 21-Apr-16 24-Apr-16 21-Apr-16 24-Apr-16 0% AED45,392 AED0
Administration-INSTALLATION OF GRILLS&DIFFUSERS 3 18-Apr-16 20-Apr-16 18-Apr-16 20-Apr-16 0% AED45,392 AED0
Administration-THERMOSTAT FIXING 2 21-Apr-16 23-Apr-16 21-Apr-16 23-Apr-16 0% AED22,696 AED0
Administration-MEP Final Fix Clearance 0 30-Apr-16 30-Apr-16 0% AED0 AED0
Administration- INSTALLA TION SANITARY WARES 6 18-Apr-16 24-Apr-16 18-Apr-16 24-Apr-16 0% AED0 AED0
ZONE B 91 01-Feb-16 18-May-16 01-Feb-16 A 18-May-16 11.91% AED1,411,903 AED98,742
MEP 1st Fix 9 01-Feb-16 11-Feb-16 01-Feb-16 A 11-Feb-16 0% AED204,265 AED0
Administration-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 4 08-Feb-16 11-Feb-16 08-Feb-16 11-Feb-16 0% AED68,088 AED0
Administration-MEP clearance to Start Plaster 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
2015 2016 2017
09-Feb-16, MEP 1st Fix
Administration-Civil clearance to Start 1st Fix
Administration-DRAINAGE PIPES ( IN WALLS)
Administration-WATER SUPPLY PIPES ( IN WALLS)
Administration-SLEEVES,CONDUITS,GI BOX,D
Administration-MEP clearance to Start Plaster
17-Apr-16, MEP 2nd Fix
Administration-DRAINAGE PIPES (HIGH L)
Administration-WATER SUPPLY PIPES (HIGH L)
Administration-GRAVITY TEST
Administration-FIRE FIGHTING PIPES(MAINS
Administration-PRESSURE TESTING
Administration-ACOUSTIC DRAINAGE PIPE
Administration-FIRE FIGHTING TESTING
Administration-VERTICAL SPRINKLER DROPS
Administration-WIRING FOR LIGHTING WORKS
Administration-WIRING FOR POWER
Administration-WIRING FOR FIRE ALARM&L
Administration-CABLE TRAY / TRUNKING
Administration-STRUC&ELEC CABLING INC
Administration-DUCTING WORK INCLUDING
Administration-INSTALLATION OF FCUS & FANS
Administration-FINAL DUCT CONNECTION TO FANS
Administration-PRESSURE TEST&INSULATION
Administration-MEP clearance to close Rooms ceilings
Administration-Civil clearance to Start 2nd Fix
Administration-MEP clearance to close c
Administration-CHILD WATER PIPES (HIGH L)
30-Apr-16, MEP Final Fix
Administration-Civil Clearance to Start Final Fix
Administration-HOSE REEL&FIRE EXT
Administration-INSTALLATION OF DBS
Administration-INSTALLATION OF PAN
Administration-INSTALLATION OF TEL
Administration-INSTALLATION OF CC
Administration-TERMINATION & DRES
Administration-INSTALLATION OF FIR
Administration-INSTALLATION OF LIG
Administration-INSTALLATION OF WIR
Administration-INSTALLATION OF GRI
Administration-THERMOSTAT FIXING
Administration-MEP Final Fix Clearance
Administration- INSTALLA TION SANIT
18-May-16, ZONE B
11-Feb-16, MEP 1st Fix
Administration-SLEEVES,CONDUITS,GI BOX,D
Administration-MEP clearance to Start Plaster
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 19 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Administration-Civil clearance to Start 1st Fix 0 08-Feb-16 08-Feb-16 0% AED0 AED0
Administration-DRAINAGE PIPES ( IN WALLS) 4 08-Feb-16 11-Feb-16 08-Feb-16 11-Feb-16 0% AED68,088 AED0
Administration-WATER SUPPLY PIPES ( IN WALLS) 4 08-Feb-16 11-Feb-16 08-Feb-16 11-Feb-16 0% AED68,088 AED0
MEP 2nd Fix 70 01-Feb-16 23-Apr-16 01-Feb-16 A 23-Apr-16 23.01% AED731,023 AED98,742
Administration-DRAINAGE PIPES (HIGH L) 5 04-Feb-16 18-Feb-16 04-Feb-16 A 18-Feb-16 60% AED38,223 AED12,741
Administration-WATER SUPPLY PIPES (HIGH L) 5 04-Feb-16 18-Feb-16 04-Feb-16 A 18-Feb-16 60% AED38,223 AED12,741
Administration-GRAVITY TEST 3 20-Feb-16 22-Feb-16 20-Feb-16 22-Feb-16 0% AED45,392 AED0
Administration-FIRE FIGHTING PIPES(MAINS/BRANCHES) 5 04-Feb-16 20-Feb-16 04-Feb-16 A 20-Feb-16 60% AED38,223 AED12,741
Administration-PRESSURE TESTING 3 20-Feb-16 22-Feb-16 20-Feb-16 22-Feb-16 0% AED45,392 AED0
Administration-ACOUSTIC DRAINAGE PIPE INSULATION 3 22-Feb-16 24-Feb-16 22-Feb-16 24-Feb-16 0% AED45,392 AED0
Administration-FIRE FIGHTING TESTING 3 20-Feb-16 22-Feb-16 20-Feb-16 22-Feb-16 0% AED45,392 AED0
Administration-VERTICAL SPRINKLER DROPS 3 22-Feb-16 24-Feb-16 22-Feb-16 24-Feb-16 0% AED45,392 AED0
Administration-WIRING FOR LIGHTING WORKS 5 04-Feb-16 29-Feb-16 04-Feb-16 A 29-Feb-16 40% AED38,223 AED9,556
Administration-WIRING FOR POWER 5 04-Feb-16 17-Mar-16 04-Feb-16 A 17-Mar-16 40% AED38,223 AED9,556
Administration-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 5 04-Feb-16 17-Mar-16 04-Feb-16 A 17-Mar-16 40% AED38,223 AED9,556
Administration-CABLE TRAY / TRUNKING 5 04-Feb-16 17-Mar-16 04-Feb-16 A 17-Mar-16 60% AED38,223 AED12,741
Administration-STRUC&ELEC CABLING INCLUDING DRESSING 5 13-Mar-16 17-Mar-16 13-Mar-16 17-Mar-16 0% AED38,223 AED0
Administration-DUCTING WORK INCLUDING INSULATION 5 04-Feb-16 18-Feb-16 04-Feb-16 A 18-Feb-16 40% AED38,223 AED9,556
Administration-INSTALLATION OF FCUS & FANS 5 14-Feb-16 18-Feb-16 14-Feb-16 18-Feb-16 0% AED38,223 AED0
Administration-FINAL DUCT CONNECTION TO FANS 5 14-Feb-16 18-Feb-16 14-Feb-16 18-Feb-16 0% AED38,223 AED0
Administration-PRESSURE TEST&INSULATION 3 16-Feb-16 18-Feb-16 16-Feb-16 18-Feb-16 0% AED45,392 AED0
Administration-MEP clearance to close Rooms ceilings 0 17-Mar-16 17-Mar-16 0% AED0 AED0
Administration-Civil clearance to Start 2nd Fix 0 01-Feb-16 01-Feb-16 A 100% AED0 AED0
Administration-MEP clearance to close corridors ceilings 0 23-Apr-16 23-Apr-16 0% AED0 AED0
Administration-CHILD WATER PIPES (HIGH L) 5 04-Feb-16 18-Feb-16 04-Feb-16 A 18-Feb-16 40% AED38,223 AED9,556
MEP Final Fix 6 11-May-16 18-May-16 11-May-16 18-May-16 0% AED476,615 AED0
Administration-Civil Clearance to Start Final Fix 0 11-May-16 11-May-16 0% AED0 AED0
Administration-HOSE REEL&FIRE EXTINGUISHERS & SPRINKLERS 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF DBS 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF PANELS / SMDBS 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF TELEPHONE SYSTEM 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF CCTV SYSTEM 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-TERMINATION & DRESSING OF DBS 3 16-May-16 18-May-16 16-May-16 18-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF LIGHT FITTING & E.M LIGHT 3 16-May-16 18-May-16 16-May-16 18-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF WIRING ACCESSORIES 3 16-May-16 18-May-16 16-May-16 18-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF GRILLS&DIFFUSERS 3 12-May-16 15-May-16 12-May-16 15-May-16 0% AED45,392 AED0
Administration-THERMOSTAT FIXING 2 16-May-16 17-May-16 16-May-16 17-May-16 0% AED22,696 AED0
Administration-MEP Final Fix Clearance 0 18-May-16 18-May-16 0% AED0 AED0
Administration- INSTALLA TION SANITARY WARES 6 12-May-16 18-May-16 12-May-16 18-May-16 0% AED0 AED0
Roof Floor 93 06-Feb-16 24-May-16 06-Feb-16 24-May-16 0% AED1,405,920 AED0
All Zones 93 06-Feb-16 24-May-16 06-Feb-16 24-May-16 0% AED1,405,920 AED0
Civil Clearance for Roof floor Works - Electrical 0 21-Feb-16 21-Feb-16 0% AED0 AED0
Civil Clearance for Roof floor Works-Mechanical 0 06-Feb-16 06-Feb-16 0% AED0 AED0
Mechanical 71 24-Feb-16 17-May-16 24-Feb-16 17-May-16 0% AED482,551 AED0
SECOND FIX 57 24-Feb-16 30-Apr-16 24-Feb-16 30-Apr-16 0% AED300,982 AED0
Administration-PRESSURE TEST&INSULATION 10 19-Apr-16 30-Apr-16 19-Apr-16 30-Apr-16 0% AED45,392 AED0
2015 2016 2017
Administration-Civil clearance to Start 1st Fix
Administration-DRAINAGE PIPES ( IN WALLS)
Administration-WATER SUPPLY PIPES ( IN WALLS)
23-Apr-16, MEP 2nd Fix
Administration-DRAINAGE PIPES (HIGH L)
Administration-WATER SUPPLY PIPES (HIGH L)
Administration-GRAVITY TEST
Administration-FIRE FIGHTING PIPES(MAINS
Administration-PRESSURE TESTING
Administration-ACOUSTIC DRAINAGE PIPE
Administration-FIRE FIGHTING TESTING
Administration-VERTICAL SPRINKLER DROPS
Administration-WIRING FOR LIGHTING WORKS
Administration-WIRING FOR POWER
Administration-WIRING FOR FIRE ALARM
Administration-CABLE TRAY / TRUNKING
Administration-STRUC&ELEC CABLING IN
Administration-DUCTING WORK INCLUDING
Administration-INSTALLATION OF FCUS & FANS
Administration-FINAL DUCT CONNECTION TO FANS
Administration-PRESSURE TEST&INSULATION
Administration-MEP clearance to close Roo
Administration-Civil clearance to Start 2nd Fix
Administration-MEP clearance to close
Administration-CHILD WATER PIPES (HIGH L)
18-May-16, MEP Final Fix
Administration-Civil Clearance to Start Final Fix
Administration-HOSE REEL&FIRE E
Administration-INSTALLATION OF DBS
Administration-INSTALLATION OF P
Administration-INSTALLATION OF T
Administration-INSTALLATION OF C
Administration-TERMINATION & DR
Administration-INSTALLATION OF F
Administration-INSTALLATION OF L
Administration-INSTALLATION OF W
Administration-INSTALLATION OF G
Administration-THERMOSTAT FIXING
Administration-MEP Final Fix Clearance
Administration- INSTALLA TION SA
24-May-16, Roof Floor
24-May-16, All Zones
Civil Clearance for Roof floor Works - Electrical
Civil Clearance for Roof floor Works-Mechanical
17-May-16, Mechanical
30-Apr-16, SECOND FIX
Administration-PRESSURE TEST&INSULATION
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 20 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Administration-SUPPORTS FOR DUCTING WORK 18 24-Feb-16 15-Mar-16 24-Feb-16 15-Mar-16 0% AED33,443 AED0
Administration-SUPPORTS FOR PIPING WORKS 18 24-Feb-16 15-Mar-16 24-Feb-16 15-Mar-16 0% AED33,443 AED0
Administration-DUCTING WORK ON ROOF 35 16-Mar-16 25-Apr-16 16-Mar-16 25-Apr-16 0% AED61,211 AED0
Administration-PIPING WORK ON ROOF 35 16-Mar-16 25-Apr-16 16-Mar-16 25-Apr-16 0% AED61,211 AED0
Administration-INSTALLATION OF FANS AND CONNECTION 24 19-Mar-16 14-Apr-16 19-Mar-16 14-Apr-16 0% AED33,142 AED0
Administration-INSTALLATION OF AHU AND VALVE PACKAGES 24 14-Mar-16 10-Apr-16 14-Mar-16 10-Apr-16 0% AED33,142 AED0
FINAL FIX 38 03-Apr-16 17-May-16 03-Apr-16 17-May-16 0% AED181,569 AED0
Administration-INSTALLATION OF CU's 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED79,437 AED0
Administration-CLADDING WORKS FOR DUCTS&PIPING 18 26-Apr-16 17-May-16 26-Apr-16 17-May-16 0% AED102,132 AED0
Electrical 65 09-Mar-16 24-May-16 09-Mar-16 24-May-16 0% AED560,232 AED0
FIRST FIX 10 09-Mar-16 20-Mar-16 09-Mar-16 20-Mar-16 0% AED56,740 AED0
Administration-SLEEVES,CONDUTES,GI BOX,DB BOX IN WALL 10 09-Mar-16 20-Mar-16 09-Mar-16 20-Mar-16 0% AED56,740 AED0
SECOND FIX 31 21-Mar-16 25-Apr-16 21-Mar-16 25-Apr-16 0% AED208,443 AED0
Administration-WIRING FOR LIGHTING & POWER 12 21-Mar-16 03-Apr-16 21-Mar-16 03-Apr-16 0% AED68,088 AED0
Administration-CABLE TRAY / TRUNKING 18 28-Mar-16 17-Apr-16 28-Mar-16 17-Apr-16 0% AED38,223 AED0
Administration-CABLING INCLUDING DRESSING OF CABLES 18 05-Apr-16 25-Apr-16 05-Apr-16 25-Apr-16 0% AED102,132 AED0
FINAL FIX 24 26-Apr-16 24-May-16 26-Apr-16 24-May-16 0% AED295,048 AED0
Administration-INSTILLATION OF PANELS / SMDBS /MCC 12 26-Apr-16 10-May-16 26-Apr-16 10-May-16 0% AED68,088 AED0
Administration-TERMINATION & DRESSING OF DBS 12 11-May-16 24-May-16 11-May-16 24-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF WIRING ACCESSORIES 12 26-Apr-16 10-May-16 26-Apr-16 10-May-16 0% AED45,392 AED0
Administration-INSTALLATION OF LIGHTING CONTROL SYSTEM 12 26-Apr-16 10-May-16 26-Apr-16 10-May-16 0% AED68,088 AED0
Administration-INSTALL OF LIGHT FITTING & E.M LIGHT 12 26-Apr-16 10-May-16 26-Apr-16 10-May-16 0% AED68,088 AED0
Plumbing 38 23-Mar-16 07-May-16 23-Mar-16 07-May-16 0% AED363,137 AED0
SECOND FIX 38 23-Mar-16 07-May-16 23-Mar-16 07-May-16 0% AED363,137 AED0
Administration-SOLAR WATER HEATERS 18 23-Mar-16 13-Apr-16 23-Mar-16 13-Apr-16 0% AED102,132 AED0
Administration-FIXING OF CIRCULATION PUMP 15 13-Apr-16 30-Apr-16 13-Apr-16 30-Apr-16 0% AED85,110 AED0
Administration-WATER SUPPLY & DRAINAGE PIPES ON ROOF 18 23-Mar-16 13-Apr-16 23-Mar-16 13-Apr-16 0% AED102,132 AED0
Administration-PRESSURE TESTING 5 13-Apr-16 18-Apr-16 13-Apr-16 18-Apr-16 0% AED45,392 AED0
Administration-PIPE INSULATION 5 01-May-16 07-May-16 01-May-16 07-May-16 0% AED28,370 AED0
All Floors 89 06-Feb-16 19-May-16 06-Feb-16 19-May-16 0% AED1,446,878 AED0
All Zones 89 06-Feb-16 19-May-16 06-Feb-16 19-May-16 0% AED1,446,878 AED0
Shaft Clearance- Mechanical 0 06-Feb-16 06-Feb-16 06-Feb-16 06-Feb-16 0% AED0 AED0
Shaft Clearance- Electrical 0 21-Feb-16 21-Feb-16 21-Feb-16 21-Feb-16 0% AED0 AED0
Mechanical Shafts 82 14-Feb-16 19-May-16 14-Feb-16 19-May-16 0% AED680,884 AED0
SECOND FIX 52 14-Feb-16 13-Apr-16 14-Feb-16 13-Apr-16 0% AED510,663 AED0
Administration-DUCT RISERS IN SHAFTS 45 14-Feb-16 05-Apr-16 14-Feb-16 05-Apr-16 0% AED255,331 AED0
Administration-PIPING IN SHAFTS 45 22-Feb-16 13-Apr-16 22-Feb-16 13-Apr-16 0% AED255,331 AED0
FINAL FIX 30 14-Apr-16 19-May-16 14-Apr-16 19-May-16 0% AED170,221 AED0
Administration-CLADDING WORK FOR DUCTS&PIPING 30 14-Apr-16 19-May-16 14-Apr-16 19-May-16 0% AED170,221 AED0
Electrical Shafts 55 21-Feb-16 24-Apr-16 21-Feb-16 24-Apr-16 0% AED510,663 AED0
SECOND FIX 55 21-Feb-16 24-Apr-16 21-Feb-16 24-Apr-16 0% AED510,663 AED0
Administration-CABLE TRAY 45 21-Feb-16 12-Apr-16 21-Feb-16 12-Apr-16 0% AED255,331 AED0
Administration-CABLE PULLING 25 27-Mar-16 24-Apr-16 27-Mar-16 24-Apr-16 0% AED255,331 AED0
Plumbing Shafts 45 22-Feb-16 13-Apr-16 22-Feb-16 13-Apr-16 0% AED255,331 AED0
SECOND FIX 45 22-Feb-16 13-Apr-16 22-Feb-16 13-Apr-16 0% AED255,331 AED0
Administration-SHAFTS DRAINAGE & PLUMBING PIPES 45 22-Feb-16 13-Apr-16 22-Feb-16 13-Apr-16 0% AED255,331 AED0
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 14 21-May-16 05-Jun-16 21-May-16 05-Jun-16 0% AED230,844 AED0
All Floors 14 21-May-16 05-Jun-16 21-May-16 05-Jun-16 0% AED230,844 AED0
All Zones 14 21-May-16 05-Jun-16 21-May-16 05-Jun-16 0% AED230,844 AED0
2015 2016 2017
Administration-SUPPORTS FOR DUCTING WORK
Administration-SUPPORTS FOR PIPING WORKS
Administration-DUCTING WORK ON ROOF
Administration-PIPING WORK ON ROOF
Administration-INSTALLATION OF FAN
Administration-INSTALLATION OF AHU
17-May-16, FINAL FIX
Administration-INSTALLATION OF CU's
Administration-CLADDING WORKS
24-May-16, Electrical
20-Mar-16, FIRST FIX
Administration-SLEEVES,CONDUTES,GI B
25-Apr-16, SECOND FIX
Administration-WIRING FOR LIGHTING & POWER
Administration-CABLE TRAY / TRUNKING
Administration-CABLING INCLUDING
24-May-16, FINAL FIX
Administration-INSTILLATION OF PA
Administration-TERMINATION & D
Administration-INSTALLATION OF W
Administration-INSTALLATION OF L
Administration-INSTALL OF LIGHT F
07-May-16, Plumbing
07-May-16, SECOND FIX
Administration-SOLAR WATER HEATERS
Administration-FIXING OF CIRCULAT
Administration-WATER SUPPLY & DRA
Administration-PRESSURE TESTING
Administration-PIPE INSULATION
19-May-16, All Floors
19-May-16, All Zones
Shaft Clearance- Mechanical
Shaft Clearance- Electrical
19-May-16, Mechanical Shafts
13-Apr-16, SECOND FIX
Administration-DUCT RISERS IN SHAFTS
Administration-PIPING IN SHAFTS
19-May-16, FINAL FIX
Administration-CLADDING WORK F
24-Apr-16, Electrical Shafts
24-Apr-16, SECOND FIX
Administration-CABLE TRAY
Administration-CABLE PULLING
13-Apr-16, Plumbing Shafts
13-Apr-16, SECOND FIX
Administration-SHAFTS DRAINAGE & P
05-Jun-16, Preliminary Testing &
05-Jun-16, All Floors
05-Jun-16, All Zones
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 21 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Administration-Electrical System Preliminary Testing & Commissioning 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED76,948 AED0
Administration-HVAC System Preliminary Testing & Commissioning 14 21-May-16 05-Jun-16 21-May-16 05-Jun-16 0% AED76,948 AED0
Administration-Plumbing System Preliminary Testing & Commissioning 7 29-May-16 05-Jun-16 29-May-16 05-Jun-16 0% AED76,948 AED0
House ConnectionsHouse Connections 17 25-Apr-16 15-May-16 25-Apr-16 15-May-16 0% AED115,422 AED0
All Floors 17 25-Apr-16 15-May-16 25-Apr-16 15-May-16 0% AED115,422 AED0
All Zones 17 25-Apr-16 15-May-16 25-Apr-16 15-May-16 0% AED115,422 AED0
Administration-Drainage House Connection 5 10-May-16 15-May-16 10-May-16 15-May-16 0% AED23,084 AED0
Administration-Water Supply House Connection 5 25-Apr-16 30-Apr-16 25-Apr-16 30-Apr-16 0% AED23,084 AED0
Administration-Chilled Water House Connection 5 25-Apr-16 30-Apr-16 25-Apr-16 30-Apr-16 0% AED23,084 AED0
Administration-Low Current House Connection 5 08-May-16 12-May-16 08-May-16 12-May-16 0% AED23,084 AED0
Administration-Electrical House Connection 5 04-May-16 09-May-16 04-May-16 09-May-16 0% AED23,084 AED0
SubstationSubstation 225 10-Sep-15 05-Jun-16 10-Sep-15 A 05-Jun-16 18.33% AED3,171,732 AED585,240
SkeletonSkeleton 59 10-Sep-15 26-Nov-15 10-Sep-15 A 26-Nov-15 A 100% AED10,431 AED10,431
Sub Structure 3 10-Sep-15 19-Sep-15 10-Sep-15 A 19-Sep-15 A 100% AED3,477 AED3,477
All Zones 3 10-Sep-15 19-Sep-15 10-Sep-15 A 19-Sep-15 A 100% AED3,477 AED3,477
Concrete Works 3 10-Sep-15 19-Sep-15 10-Sep-15 A 19-Sep-15 A 100% AED3,477 AED3,477
Clearance for MEP Works 0 10-Sep-15 10-Sep-15 A 100% AED0 AED0
Substation-MEP Sleeves 3 10-Sep-15 19-Sep-15 10-Sep-15 A 19-Sep-15 A 100% AED3,477 AED3,477
Super Structure 3 18-Nov-15 26-Nov-15 18-Nov-15 A 26-Nov-15 A 100% AED6,954 AED6,954
All Zones 3 18-Nov-15 26-Nov-15 18-Nov-15 A 26-Nov-15 A 100% AED6,954 AED6,954
Roof Floor 3 18-Nov-15 26-Nov-15 18-Nov-15 A 26-Nov-15 A 100% AED6,954 AED6,954
Substation-MEP Conduits & Sleeves Inside The Slab 3 18-Nov-15 26-Nov-15 18-Nov-15 A 26-Nov-15 A 100% AED6,954 AED6,954
MEPMEP 137 14-Dec-15 23-May-16 14-Dec-15 A 23-May-16 19.01% AED3,004,213 AED574,810
Ground Floor 137 14-Dec-15 23-May-16 14-Dec-15 A 23-May-16 15.71% AED1,762,726 AED280,710
All Zones 137 14-Dec-15 23-May-16 14-Dec-15 A 23-May-16 15.71% AED1,762,726 AED280,710
MEP 1st Fix 11 14-Dec-15 28-Dec-15 14-Dec-15 A 28-Dec-15 A 100% AED50,417 AED50,417
Substation-Civil clearance to Start 1st Fix 0 28-Dec-15 28-Dec-15 A 100% AED0 AED0
Substation-SLEEVES,CONDUITS,GI BOX IN WALL 6 14-Dec-15 17-Dec-15 14-Dec-15 A 17-Dec-15 A 100% AED50,417 AED50,417
Substation-MEP clearance to Start Plaster 0 17-Dec-15 17-Dec-15 A 100% AED0 AED0
MEP 2nd Fix 100 19-Dec-15 13-Apr-16 19-Dec-15 A 13-Apr-16 37.96% AED596,601 AED230,293
Substation-FIRE PROTECTION "INERGEN SYSTEM" INSTALLATION 14 12-Mar-16 27-Mar-16 12-Mar-16 27-Mar-16 0% AED117,640 AED0
Substation-FIRE PROTECTION SYSTEM TESTING 4 26-Mar-16 29-Mar-16 26-Mar-16 29-Mar-16 0% AED33,612 AED0
Substation-WIRING FOR LIGHTING WORKS 7 06-Jan-16 21-Feb-16 06-Jan-16 A 21-Feb-16 95% AED58,820 AED57,277
Substation-WIRING FOR POWER 7 06-Jan-16 10-Mar-16 06-Jan-16 A 10-Mar-16 95% AED58,820 AED56,225
Substation-WIRING FOR FIRE ALARM \ LOW CURRENT 7 19-Dec-15 09-Mar-16 19-Dec-15 A 09-Mar-16 95% AED58,820 AED57,971
Substation-CABLE TRAY / TRUNKING 7 28-Feb-16 06-Mar-16 28-Feb-16 06-Mar-16 0% AED58,820 AED0
Substation-ELECTRICAL CABLING 18 24-Mar-16 13-Apr-16 24-Mar-16 13-Apr-16 0% AED151,251 AED0
Substation-DUCTING WORK INCLUDING INSULATION 7 20-Dec-15 26-Dec-15 20-Dec-15 A 26-Dec-15 A 100% AED58,820 AED58,820
Substation-MEP clearance To Start Paint Pre-Final Coats 0 13-Apr-16 13-Apr-16 0% AED0 AED0
Substation-Civil clearance to Start 2nd Fix 0 20-Dec-15 20-Dec-15 A 100% AED0 AED0
MEP Final Fix 32 14-Apr-16 23-May-16 14-Apr-16 23-May-16 0% AED1,115,708 AED0
Substation-Civil Clearance to Start Final Fix 0 14-Apr-16 14-Apr-16 0% AED0 AED0
Substation-FIRE EXTINGUISHERS LOCATING 4 19-May-16 23-May-16 19-May-16 23-May-16 0% AED33,612 AED0
Substation-INSTALLATION OF SWITCH GEARS 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Substation-INSTALLATION OF MDBs / SMDBs /DBs 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Substation-INSTALLATION OF TELEPHONE DATA POINTS ACCESSORIES 4 15-May-16 18-May-16 15-May-16 18-May-16 0% AED33,612 AED0
2015 2016 2017
Administration-Electrical System P
Administration-HVAC System Pre
Administration-Plumbing System P
15-May-16, House Connections
15-May-16, All Floors
15-May-16, All Zones
Administration-Drainage House Connection
Administration-Water Supply House Connection
Administration-Chilled Water House Connection
Administration-Low Current House Connection
Administration-Electrical House Connection
05-Jun-16, Substation
26-Nov-15 A, Skeleton
19-Sep-15 A, Sub Structure
19-Sep-15 A, All Zones
19-Sep-15 A, Concrete Works
Clearance for MEP Works
Substation-MEP Sleeves
26-Nov-15 A, Super Structure
26-Nov-15 A, All Zones
26-Nov-15 A, Roof Floor
Substation-MEP Conduits & Sleeves Inside The Slab
23-May-16, MEP
23-May-16, Ground Floor
23-May-16, All Zones
28-Dec-15 A, MEP 1st Fix
Substation-Civil clearance to Start 1st Fix
Substation-SLEEVES,CONDUITS,GI BOX IN WALL
Substation-MEP clearance to Start Plaster
13-Apr-16, MEP 2nd Fix
Substation-FIRE PROTECTION "INERGE
Substation-FIRE PROTECTION SYSTEM
Substation-WIRING FOR LIGHTING WORKS
Substation-WIRING FOR POWER
Substation-WIRING FOR FIRE ALARM \ LO
Substation-CABLE TRAY / TRUNKING
Substation-ELECTRICAL CABLING
Substation-DUCTING WORK INCLUDING INSULATION
Substation-MEP clearance To Start Pain
Substation-Civil clearance to Start 2nd Fix
23-May-16, MEP Final Fix
Substation-Civil Clearance to Start Final Fix
Substation-FIRE EXTINGUISHERS
Substation-INSTALLATION OF SWI
Substation-INSTALLATION OF MDB
Substation-INSTALLATION OF TEL
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 22 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Substation-INSTALLATION OF GENERATOR + TANK 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Substation-CABLES TERMINATION & DRESSING 4 15-May-16 18-May-16 15-May-16 18-May-16 0% AED33,612 AED0
Substation-INSTALLATION OF FIRE ALARM PANEL & ACCESSORIES 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Substation-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 15-May-16 18-May-16 15-May-16 18-May-16 0% AED33,612 AED0
Substation-INSTALLATION OF WIRING ACCESSORIES 4 15-May-16 18-May-16 15-May-16 18-May-16 0% AED33,612 AED0
Substation-INSTALLATION OF GRILLS&DIFFUSERS 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Substation-THERMOSTAT FIXING 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED16,806 AED0
Substation-MEP Final Fix Clearance 0 23-May-16 23-May-16 0% AED0 AED0
Substation-INSTALLATION OF CENTRAL BATTERY 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Substation-INSTALLATION OF TRANSFORMER 24 16-Apr-16 14-May-16 16-Apr-16 14-May-16 0% AED132,978 AED0
Roof Floor 75 06-Feb-16 02-May-16 06-Feb-16 02-May-16 0% AED947,388 AED0
All Zones 75 06-Feb-16 02-May-16 06-Feb-16 02-May-16 0% AED947,388 AED0
Civil clearance for Roof - Mechanical Works 0 06-Feb-16 06-Feb-16 0% AED0 AED0
Civil Clearance for Roof - Electrical Works 0 06-Feb-16 06-Feb-16 0% AED0 AED0
Mechanical 48 07-Mar-16 01-May-16 07-Mar-16 01-May-16 0% AED436,949 AED0
SECOND FIX 30 07-Mar-16 10-Apr-16 07-Mar-16 10-Apr-16 0% AED285,697 AED0
Substation-SUPPORTS FOR DUCTING WORK 6 07-Mar-16 13-Mar-16 07-Mar-16 13-Mar-16 0% AED50,417 AED0
Substation-DUCTING WORK ON ROOF 14 26-Mar-16 10-Apr-16 26-Mar-16 10-Apr-16 0% AED117,640 AED0
Substation-INSTALLATION OF PACKAGE UNIT & CONNECTIONS 14 10-Mar-16 26-Mar-16 10-Mar-16 26-Mar-16 0% AED117,640 AED0
FINAL FIX 18 11-Apr-16 01-May-16 11-Apr-16 01-May-16 0% AED151,251 AED0
Substation-CLADDING WORKS FOR DUCTS 18 11-Apr-16 01-May-16 11-Apr-16 01-May-16 0% AED151,251 AED0
Electrical 53 02-Mar-16 02-May-16 02-Mar-16 02-May-16 0% AED359,188 AED0
FIRST FIX 6 02-Mar-16 08-Mar-16 02-Mar-16 08-Mar-16 0% AED50,417 AED0
Substation-CONDUTES, BOXES, IN PARAPET 6 02-Mar-16 08-Mar-16 02-Mar-16 08-Mar-16 0% AED50,417 AED0
SECOND FIX 24 09-Mar-16 05-Apr-16 09-Mar-16 05-Apr-16 0% AED149,784 AED0
Substation-WIRING FOR LIGHTING & POWER 7 09-Mar-16 16-Mar-16 09-Mar-16 16-Mar-16 0% AED58,820 AED0
Substation-CABLE TRAY / TRUNKING 12 16-Mar-16 29-Mar-16 16-Mar-16 29-Mar-16 0% AED58,820 AED0
Substation-CABLING INCLUDING DRESSING OF CABLES 12 23-Mar-16 05-Apr-16 23-Mar-16 05-Apr-16 0% AED32,144 AED0
FINAL FIX 16 14-Apr-16 02-May-16 14-Apr-16 02-May-16 0% AED158,987 AED0
Substation-INSTILLATION OF PANELS / SMDBS /MCC 7 14-Apr-16 21-Apr-16 14-Apr-16 21-Apr-16 0% AED31,344 AED0
Substation-TERMINATION & DRESSING OF DBS 7 20-Apr-16 27-Apr-16 20-Apr-16 27-Apr-16 0% AED31,344 AED0
Substation-INSTALLATION OF WIRING ACCESSORIES 7 25-Apr-16 02-May-16 25-Apr-16 02-May-16 0% AED33,612 AED0
Substation-INSTALLATION OF LIGHTNING CONTROL SYSTEM 7 25-Apr-16 02-May-16 25-Apr-16 02-May-16 0% AED31,344 AED0
Substation-INSTALL OF LIGHT FITTING & E.M LIGHT 7 25-Apr-16 02-May-16 25-Apr-16 02-May-16 0% AED31,344 AED0
Plumbing 18 12-Mar-16 31-Mar-16 12-Mar-16 31-Mar-16 0% AED151,251 AED0
SECOND FIX 18 12-Mar-16 31-Mar-16 12-Mar-16 31-Mar-16 0% AED151,251 AED0
Substation-DRAINAGE PIPES ON ROOF 18 12-Mar-16 31-Mar-16 12-Mar-16 31-Mar-16 0% AED151,251 AED0
All Floors 45 14-Dec-15 06-Feb-16 14-Dec-15 A 06-Feb-16 100% AED294,099 AED294,099
All Zones 45 14-Dec-15 06-Feb-16 14-Dec-15 A 06-Feb-16 100% AED294,099 AED294,099
Civil clearance for Shafts 0 06-Feb-16 06-Feb-16 0% AED0 AED0
Plumbing Shafts 35 14-Dec-15 26-Dec-15 14-Dec-15 A 26-Dec-15 A 100% AED294,099 AED294,099
SECOND FIX 35 14-Dec-15 26-Dec-15 14-Dec-15 A 26-Dec-15 A 100% AED294,099 AED294,099
Substation-SHAFTS DRAINAGE PIPES 35 14-Dec-15 26-Dec-15 14-Dec-15 A 26-Dec-15 A 100% AED294,099 AED294,099
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED117,816 AED0
All Floors 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED117,816 AED0
All Zones 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED117,816 AED0
Substation-Electrical System Preliminary Testing & Commissioning 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED39,272 AED0
Substation-HVAC System Preliminary Testing & Commissioning 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED39,272 AED0
Substation-Plumbing System Preliminary Testing & Commissioning 10 25-May-16 05-Jun-16 25-May-16 05-Jun-16 0% AED39,272 AED0
2015 2016 2017
Substation-INSTALLATION OF GEN
Substation-CABLES TERMINATION
Substation-INSTALLATION OF FIRE
Substation-INSTALLATION OF LIGH
Substation-INSTALLATION OF WIR
Substation-INSTALLATION OF GRIL
Substation-THERMOSTAT FIXING
Substation-MEP Final Fix Clearance
Substation-INSTALLATION OF CEN
Substation-INSTALLATION OF TRA
02-May-16, Roof Floor
02-May-16, All Zones
Civil clearance for Roof - Mechanical Works
Civil Clearance for Roof - Electrical Works
01-May-16, Mechanical
10-Apr-16, SECOND FIX
Substation-SUPPORTS FOR DUCTING WORK
Substation-DUCTING WORK ON ROOF
Substation-INSTALLATION OF PACKAGE
01-May-16, FINAL FIX
Substation-CLADDING WORKS FOR DUCTS
02-May-16, Electrical
08-Mar-16, FIRST FIX
Substation-CONDUTES, BOXES, IN PARAPET
05-Apr-16, SECOND FIX
Substation-WIRING FOR LIGHTING & POWER
Substation-CABLE TRAY / TRUNKING
Substation-CABLING INCLUDING DRES
02-May-16, FINAL FIX
Substation-INSTILLATION OF PANELS
Substation-TERMINATION & DRESSI
Substation-INSTALLATION OF WIRIN
Substation-INSTALLATION OF LIGH
Substation-INSTALL OF LIGHT FITT
31-Mar-16, Plumbing
31-Mar-16, SECOND FIX
Substation-DRAINAGE PIPES ON ROOF
06-Feb-16, All Floors
06-Feb-16, All Zones
Civil clearance for Shafts
26-Dec-15 A, Plumbing Shafts
26-Dec-15 A, SECOND FIX
Substation-SHAFTS DRAINAGE PIPES
05-Jun-16, Preliminary Testing &
05-Jun-16, All Floors
05-Jun-16, All Zones
Substation-Electrical System Preli
Substation-HVAC System Prelimin
Substation-Plumbing System Prel
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 23 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
House ConnectionsHouse Connections 25 08-May-16 05-Jun-16 08-May-16 05-Jun-16 0% AED39,272 AED0
All Floors 25 08-May-16 05-Jun-16 08-May-16 05-Jun-16 0% AED39,272 AED0
All Zones 25 08-May-16 05-Jun-16 08-May-16 05-Jun-16 0% AED39,272 AED0
Substation-Low Current House Connection 6 08-May-16 14-May-16 08-May-16 14-May-16 0% AED39,272 AED0
Substation-Energization 0 05-Jun-16 05-Jun-16 0% AED0 AED0
Service YardService Yard 240 26-Aug-15 08-Jun-16 26-Aug-15 A 08-Jun-16 0.65% AED3,628,219 AED23,643
SkeletonSkeleton 120 26-Aug-15 18-Jan-16 26-Aug-15 A 18-Jan-16 A 100% AED23,643 AED23,643
Sub Structure 6 26-Aug-15 02-Sep-15 26-Aug-15 A 02-Sep-15 A 100% AED6,954 AED6,954
All Zones 6 26-Aug-15 02-Sep-15 26-Aug-15 A 02-Sep-15 A 100% AED6,954 AED6,954
Concrete Works 6 26-Aug-15 02-Sep-15 26-Aug-15 A 02-Sep-15 A 100% AED6,954 AED6,954
Clearance for MEP Works 0 26-Aug-15 26-Aug-15 A 100% AED0 AED0
Service Yard-MEP Services In Raft 6 26-Aug-15 02-Sep-15 26-Aug-15 A 02-Sep-15 A 100% AED6,954 AED6,954
Super Structure 43 28-Nov-15 18-Jan-16 28-Nov-15 A 18-Jan-16 A 100% AED16,689 AED16,689
All Zones 43 28-Nov-15 18-Jan-16 28-Nov-15 A 18-Jan-16 A 100% AED16,689 AED16,689
Ground Floor 4 28-Nov-15 05-Dec-15 28-Nov-15 A 05-Dec-15 A 100% AED8,344 AED8,344
Service Yard-MEP Conduits & Sleeves Inside The Slab 4 28-Nov-15 05-Dec-15 28-Nov-15 A 05-Dec-15 A 100% AED8,344 AED8,344
Roof Floor 3 16-Jan-16 18-Jan-16 16-Jan-16 A 18-Jan-16 A 100% AED8,344 AED8,344
Service Yard-MEP Conduits & Sleeves Inside The Slab 3 16-Jan-16 18-Jan-16 16-Jan-16 A 18-Jan-16 A 100% AED8,344 AED8,344
MEPMEP 68 02-Mar-16 22-May-16 02-Mar-16 22-May-16 0% AED3,450,453 AED0
Basement 68 02-Mar-16 22-May-16 02-Mar-16 22-May-16 0% AED1,488,845 AED0
All Zones 68 02-Mar-16 22-May-16 02-Mar-16 22-May-16 0% AED1,488,845 AED0
MEP 1st Fix 13 02-Mar-16 16-Mar-16 02-Mar-16 16-Mar-16 0% AED42,337 AED0
Service Yard-Civil clearance to Start 1st Fix 0 02-Mar-16 02-Mar-16 0% AED0 AED0
Service Yard-SLEEVES,CONDUITS,GI BOX IN WALL 6 10-Mar-16 16-Mar-16 10-Mar-16 16-Mar-16 0% AED42,337 AED0
Service Yard-MEP clearance to Start Plaster 0 16-Mar-16 16-Mar-16 0% AED0 AED0
MEP 2nd Fix 21 20-Mar-16 13-Apr-16 20-Mar-16 13-Apr-16 0% AED458,650 AED0
Service Yard-FIRE FIGHTING SYSTEM INSTALLATION 14 21-Mar-16 05-Apr-16 21-Mar-16 05-Apr-16 0% AED98,786 AED0
Service Yard-FIRE PROTECTION SYSTEM TESTING 4 04-Apr-16 07-Apr-16 04-Apr-16 07-Apr-16 0% AED28,225 AED0
Service Yard-WIRING FOR LIGHTING WORKS 7 22-Mar-16 29-Mar-16 22-Mar-16 29-Mar-16 0% AED49,393 AED0
Service Yard-WIRING FOR POWER 7 22-Mar-16 29-Mar-16 22-Mar-16 29-Mar-16 0% AED49,393 AED0
Service Yard-WIRING FOR FIRE ALARM \ LOW CURRENT 7 22-Mar-16 29-Mar-16 22-Mar-16 29-Mar-16 0% AED49,393 AED0
Service Yard-CABLE TRAY / TRUNKING 7 22-Mar-16 29-Mar-16 22-Mar-16 29-Mar-16 0% AED49,393 AED0
Service Yard-ELECTRICAL CABLING 12 30-Mar-16 12-Apr-16 30-Mar-16 12-Apr-16 0% AED84,674 AED0
Service Yard-CHILLED WATER PIPES INCLUDING INSULATION 7 22-Mar-16 29-Mar-16 22-Mar-16 29-Mar-16 0% AED49,393 AED0
Service Yard-MEP clearance To Start Paint Pre-Final Coats 0 13-Apr-16 13-Apr-16 0% AED0 AED0
Service Yard-Civil clearance to Start 2nd Fix 0 20-Mar-16 20-Mar-16 0% AED0 AED0
MEP Final Fix 31 13-Apr-16 22-May-16 13-Apr-16 22-May-16 0% AED987,858 AED0
Service Yard-Civil Clearance to Start Final Fix 0 13-Apr-16 13-Apr-16 0% AED0 AED0
Service Yard-FIRE EXTINGUISHERS LOCATING 4 19-Apr-16 23-Apr-16 19-Apr-16 23-Apr-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF WATER SUPPLY / SUMP PUMPS 24 14-Apr-16 12-May-16 14-Apr-16 12-May-16 0% AED169,347 AED0
Service Yard-INSTALLATION OF SMDBs /DBs 24 14-Apr-16 12-May-16 14-Apr-16 12-May-16 0% AED169,347 AED0
Service Yard-INSTALLATION OF DATA POINTS ACCESSORIES 4 24-Apr-16 27-Apr-16 24-Apr-16 27-Apr-16 0% AED28,225 AED0
Service Yard-CABLES TERMINATION & DRESSING 4 14-May-16 17-May-16 14-May-16 17-May-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF FIRE ALARM PANEL & ACCESSORIES 24 14-Apr-16 12-May-16 14-Apr-16 12-May-16 0% AED169,347 AED0
Service Yard-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 14-Apr-16 18-Apr-16 14-Apr-16 18-Apr-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF WIRING ACCESSORIES 4 19-Apr-16 23-Apr-16 19-Apr-16 23-Apr-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF FCU's 24 14-Apr-16 12-May-16 14-Apr-16 12-May-16 0% AED169,347 AED0
Service Yard-MEP Final Fix Clearance 0 22-May-16 22-May-16 0% AED0 AED0
Service Yard-INSTALLATION OF FIRE FIGHTING PUMPS 15 24-Apr-16 11-May-16 24-Apr-16 11-May-16 0% AED169,347 AED0
2015 2016 2017
05-Jun-16, House Connections
05-Jun-16, All Floors
05-Jun-16, All Zones
Substation-Low Current House Connection
Substation-Energization
08-Jun-16, Service Yard
18-Jan-16 A, Skeleton
02-Sep-15 A, Sub Structure
02-Sep-15 A, All Zones
02-Sep-15 A, Concrete Works
Clearance for MEP Works
Service Yard-MEP Services In Raft
18-Jan-16 A, Super Structure
18-Jan-16 A, All Zones
05-Dec-15 A, Ground Floor
Service Yard-MEP Conduits & Sleeves Inside The Slab
18-Jan-16 A, Roof Floor
Service Yard-MEP Conduits & Sleeves Inside The Slab
22-May-16, MEP
22-May-16, Basement
22-May-16, All Zones
16-Mar-16, MEP 1st Fix
Service Yard-Civil clearance to Start 1st Fix
Service Yard-SLEEVES,CONDUITS,GI BO
Service Yard-MEP clearance to Start Plaster
13-Apr-16, MEP 2nd Fix
Service Yard-FIRE FIGHTING SYSTEM
Service Yard-FIRE PROTECTION SYST
Service Yard-WIRING FOR LIGHTING WORKS
Service Yard-WIRING FOR POWER
Service Yard-WIRING FOR FIRE ALARM
Service Yard-CABLE TRAY / TRUNKING
Service Yard-ELECTRICAL CABLING
Service Yard-CHILLED WATER PIPES IN
Service Yard-MEP clearance To Start Pa
Service Yard-Civil clearance to Start 2nd Fix
22-May-16, MEP Final Fix
Service Yard-Civil Clearance to Start Final Fix
Service Yard-FIRE EXTINGUISHERS
Service Yard-INSTALLATION OF WA
Service Yard-INSTALLATION OF SMDBs /DBs
Service Yard-INSTALLATION OF DAT
Service Yard-CABLES TERMINATIO
Service Yard-INSTALLATION OF FIR
Service Yard-INSTALLATION OF LIGH
Service Yard-INSTALLATION OF WIR
Service Yard-INSTALLATION OF FCU's
Service Yard-MEP Final Fix Clearance
Service Yard-INSTALLATION OF FIR
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 24 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Ground Floor 59 13-Mar-16 22-May-16 13-Mar-16 22-May-16 0% AED1,488,845 AED0
All Zones 59 13-Mar-16 22-May-16 13-Mar-16 22-May-16 0% AED1,488,845 AED0
MEP 1st Fix 6 13-Mar-16 19-Mar-16 13-Mar-16 19-Mar-16 0% AED42,337 AED0
Service Yard-Civil clearance to Start 1st Fix 0 13-Mar-16 13-Mar-16 0% AED0 AED0
Service Yard-SLEEVES,CONDUITS,GI BOX IN WALL 6 13-Mar-16 19-Mar-16 13-Mar-16 19-Mar-16 0% AED42,337 AED0
Service Yard-MEP clearance to Start Plaster 0 19-Mar-16 19-Mar-16 0% AED0 AED0
MEP 2nd Fix 26 22-Mar-16 21-Apr-16 22-Mar-16 21-Apr-16 0% AED458,650 AED0
Service Yard-FIRE PROTECTION "INERGEN SYSTEM" INSTALLATION 14 23-Mar-16 07-Apr-16 23-Mar-16 07-Apr-16 0% AED98,786 AED0
Service Yard-FIRE PROTECTION SYSTEM TESTING 4 06-Apr-16 10-Apr-16 06-Apr-16 10-Apr-16 0% AED28,225 AED0
Service Yard-WIRING FOR LIGHTING WORKS 7 24-Mar-16 31-Mar-16 24-Mar-16 31-Mar-16 0% AED49,393 AED0
Service Yard-WIRING FOR POWER 7 24-Mar-16 31-Mar-16 24-Mar-16 31-Mar-16 0% AED49,393 AED0
Service Yard-WIRING FOR FIRE ALARM \ LOW CURRENT 7 24-Mar-16 31-Mar-16 24-Mar-16 31-Mar-16 0% AED49,393 AED0
Service Yard-CABLE TRAY / TRUNKING 7 24-Mar-16 31-Mar-16 24-Mar-16 31-Mar-16 0% AED49,393 AED0
Service Yard-ELECTRICAL CABLING 18 02-Apr-16 21-Apr-16 02-Apr-16 21-Apr-16 0% AED84,674 AED0
Service Yard-CHILLED WATER PIPING INCLUDING INSULATION 7 24-Mar-16 31-Mar-16 24-Mar-16 31-Mar-16 0% AED49,393 AED0
Service Yard-MEP clearance To Start Paint Pre-Final Coats 0 21-Apr-16 21-Apr-16 0% AED0 AED0
Service Yard-Civil clearance to Start 2nd Fix 0 22-Mar-16 22-Mar-16 0% AED0 AED0
MEP Final Fix 24 21-Apr-16 22-May-16 21-Apr-16 22-May-16 0% AED987,858 AED0
Service Yard-Civil Clearance to Start Final Fix 0 21-Apr-16 21-Apr-16 0% AED0 AED0
Service Yard-FIRE EXTINGUISHERS LOCATING 4 27-Apr-16 01-May-16 27-Apr-16 01-May-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF CHILLERS 20 23-Apr-16 16-May-16 23-Apr-16 16-May-16 0% AED169,347 AED0
Service Yard-INSTALLATION OF SMDBs /DBs 20 23-Apr-16 16-May-16 23-Apr-16 16-May-16 0% AED169,347 AED0
Service Yard-INSTALLATION OF IBMS / DATA POINTS ACCESSORIES 4 17-May-16 21-May-16 17-May-16 21-May-16 0% AED28,225 AED0
Service Yard-CABLES TERMINATION & DRESSING 4 17-May-16 21-May-16 17-May-16 21-May-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF FIRE ALARM PANEL & ACCESSORIES 24 23-Apr-16 21-May-16 23-Apr-16 21-May-16 0% AED169,347 AED0
Service Yard-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 23-Apr-16 26-Apr-16 23-Apr-16 26-Apr-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF WIRING ACCESSORIES 4 23-Apr-16 26-Apr-16 23-Apr-16 26-Apr-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF FCU's 24 23-Apr-16 21-May-16 23-Apr-16 21-May-16 0% AED169,347 AED0
Service Yard-MEP Final Fix Clearance 0 22-May-16 22-May-16 0% AED0 AED0
Service Yard-INSTALLATION OF CHILLED WATER PUMPS, PRESSURIZATION UNITS20 24-Apr-16 17-May-16 24-Apr-16 17-May-16 0% AED169,347 AED0
Roof Floor 56 05-Mar-16 09-May-16 05-Mar-16 09-May-16 0% AED423,370 AED0
All Zones 56 05-Mar-16 09-May-16 05-Mar-16 09-May-16 0% AED423,370 AED0
Civil Clearance for Mechanical Works 0 22-Mar-16 22-Mar-16 0% AED0 AED0
Civil Clearance for Electrical Works 0 05-Mar-16 05-Mar-16 0% AED0 AED0
Mechanical 26 22-Mar-16 20-Apr-16 22-Mar-16 20-Apr-16 0% AED112,899 AED0
SECOND FIX 22 22-Mar-16 16-Apr-16 22-Mar-16 16-Apr-16 0% AED84,674 AED0
Service Yard-INSTALLATION OF CONDENSATING UNITS 2 22-Mar-16 23-Mar-16 22-Mar-16 23-Mar-16 0% AED14,113 AED0
Service Yard-PIPING WORKS ON ROOF 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED28,225 AED0
Service Yard-FINAL CONNECTIONS 6 10-Apr-16 16-Apr-16 10-Apr-16 16-Apr-16 0% AED42,337 AED0
FINAL FIX 4 17-Apr-16 20-Apr-16 17-Apr-16 20-Apr-16 0% AED28,225 AED0
Service Yard-PIPES INSULATION 4 17-Apr-16 20-Apr-16 17-Apr-16 20-Apr-16 0% AED28,225 AED0
Electrical 56 05-Mar-16 09-May-16 05-Mar-16 09-May-16 0% AED261,078 AED0
FIRST FIX 6 05-Mar-16 10-Mar-16 05-Mar-16 10-Mar-16 0% AED42,337 AED0
Service Yard-CONDUTES, BOXES, IN PARAPET 6 05-Mar-16 10-Mar-16 05-Mar-16 10-Mar-16 0% AED42,337 AED0
SECOND FIX 18 10-Apr-16 30-Apr-16 10-Apr-16 30-Apr-16 0% AED91,730 AED0
Service Yard-WIRING FOR LIGHTING & POWER 7 10-Apr-16 17-Apr-16 10-Apr-16 17-Apr-16 0% AED49,393 AED0
Service Yard-CABLING INCLUDING DRESSING OF CABLES 6 24-Apr-16 30-Apr-16 24-Apr-16 30-Apr-16 0% AED42,337 AED0
FINAL FIX 7 01-May-16 09-May-16 01-May-16 09-May-16 0% AED127,011 AED0
2015 2016 2017
22-May-16, Ground Floor
22-May-16, All Zones
19-Mar-16, MEP 1st Fix
Service Yard-Civil clearance to Start 1st Fix
Service Yard-SLEEVES,CONDUITS,GI BO
Service Yard-MEP clearance to Start Plaster
21-Apr-16, MEP 2nd Fix
Service Yard-FIRE PROTECTION "INER
Service Yard-FIRE PROTECTION SYST
Service Yard-WIRING FOR LIGHTING WORKS
Service Yard-WIRING FOR POWER
Service Yard-WIRING FOR FIRE ALARM
Service Yard-CABLE TRAY / TRUNKING
Service Yard-ELECTRICAL CABLING
Service Yard-CHILLED WATER PIPING I
Service Yard-MEP clearance To Start P
Service Yard-Civil clearance to Start 2nd Fix
22-May-16, MEP Final Fix
Service Yard-Civil Clearance to Start Final Fix
Service Yard-FIRE EXTINGUISHERS
Service Yard-INSTALLATION OF CHILLERS
Service Yard-INSTALLATION OF SM
Service Yard-INSTALLATION OF IB
Service Yard-CABLES TERMINATI
Service Yard-INSTALLATION OF F
Service Yard-INSTALLATION OF LIGH
Service Yard-INSTALLATION OF WIR
Service Yard-INSTALLATION OF FCU's
Service Yard-MEP Final Fix Clearance
Service Yard-INSTALLATION OF CH
09-May-16, Roof Floor
09-May-16, All Zones
Civil Clearance for Mechanical Works
Civil Clearance for Electrical Works
20-Apr-16, Mechanical
16-Apr-16, SECOND FIX
Service Yard-INSTALLATION OF CONDEN
Service Yard-PIPING WORKS ON ROOF
Service Yard-FINAL CONNECTIONS
20-Apr-16, FINAL FIX
Service Yard-PIPES INSULATION
09-May-16, Electrical
10-Mar-16, FIRST FIX
Service Yard-CONDUTES, BOXES, IN PARAPET
30-Apr-16, SECOND FIX
Service Yard-WIRING FOR LIGHTING & POWER
Service Yard-CABLING INCLUDING D
09-May-16, FINAL FIX
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 25 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Service Yard-INSTALLATION OF WIRING ACCESSORIES 7 01-May-16 09-May-16 01-May-16 09-May-16 0% AED28,225 AED0
Service Yard-INSTALLATION OF LIGHTNING PROTECTION SYSTEM 7 01-May-16 09-May-16 01-May-16 09-May-16 0% AED49,393 AED0
Service Yard-INSTALL OF LIGHT FITTING & E.M LIGHT 7 01-May-16 09-May-16 01-May-16 09-May-16 0% AED49,393 AED0
Plumbing 7 17-Mar-16 24-Mar-16 17-Mar-16 24-Mar-16 0% AED49,393 AED0
SECOND FIX 7 17-Mar-16 24-Mar-16 17-Mar-16 24-Mar-16 0% AED49,393 AED0
Service Yard-DRAINAGE PIPES ON ROOF 7 17-Mar-16 24-Mar-16 17-Mar-16 24-Mar-16 0% AED49,393 AED0
All Floors 7 09-Mar-16 16-Mar-16 09-Mar-16 16-Mar-16 0% AED49,393 AED0
All Zones 7 09-Mar-16 16-Mar-16 09-Mar-16 16-Mar-16 0% AED49,393 AED0
Civil clearance plumbing Works 0 09-Mar-16 09-Mar-16 0% AED0 AED0
Plumbing Shafts 7 09-Mar-16 16-Mar-16 09-Mar-16 16-Mar-16 0% AED49,393 AED0
SECOND FIX 7 09-Mar-16 16-Mar-16 09-Mar-16 16-Mar-16 0% AED49,393 AED0
Service Yard-SHAFTS DRAINAGE PIPES 7 09-Mar-16 16-Mar-16 09-Mar-16 16-Mar-16 0% AED49,393 AED0
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED92,474 AED0
All Floors 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED92,474 AED0
All Zones 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED92,474 AED0
Service Yard-Electrical System Preliminary Testing & Commissioning 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED30,825 AED0
Service Yard-HVAC System Preliminary Testing & Commissioning 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED30,825 AED0
Service Yard-Plumbing System Preliminary Testing & Commissioning 12 22-May-16 04-Jun-16 22-May-16 04-Jun-16 0% AED30,825 AED0
House ConnectionsHouse Connections 27 08-May-16 08-Jun-16 08-May-16 08-Jun-16 0% AED61,649 AED0
All Floors 27 08-May-16 08-Jun-16 08-May-16 08-Jun-16 0% AED61,649 AED0
All Zones 27 08-May-16 08-Jun-16 08-May-16 08-Jun-16 0% AED61,649 AED0
Service Yard-Low Current House Connection 6 08-May-16 14-May-16 08-May-16 14-May-16 0% AED30,825 AED0
Service Yard-Electrical House Connection 6 01-Jun-16 08-Jun-16 01-Jun-16 08-Jun-16 0% AED30,825 AED0
Vehicle Washing ShedVehicle Washing Shed 52 31-Mar-16 01-Jun-16 31-Mar-16 01-Jun-16 0% AED256,642 AED0
SkeletonSkeleton 5 03-Apr-16 07-Apr-16 03-Apr-16 07-Apr-16 0% AED4,172 AED0
Sub Structure 2 03-Apr-16 04-Apr-16 03-Apr-16 04-Apr-16 0% AED2,086 AED0
All Zones 2 03-Apr-16 04-Apr-16 03-Apr-16 04-Apr-16 0% AED2,086 AED0
Concrete Works 2 03-Apr-16 04-Apr-16 03-Apr-16 04-Apr-16 0% AED2,086 AED0
Clearance for MEP Works - Vehicle Washing Shed 0 03-Apr-16 03-Apr-16 0% AED0 AED0
Vehicle Washing Shed-MEP Sleeves 2 03-Apr-16 04-Apr-16 03-Apr-16 04-Apr-16 0% AED2,086 AED0
Super Structure 3 05-Apr-16 07-Apr-16 05-Apr-16 07-Apr-16 0% AED2,086 AED0
All Zones 3 05-Apr-16 07-Apr-16 05-Apr-16 07-Apr-16 0% AED2,086 AED0
Roof Floor 3 05-Apr-16 07-Apr-16 05-Apr-16 07-Apr-16 0% AED2,086 AED0
Vehicle Washing Shed-MEP Conduits & Sleeves Inside The Slab 3 05-Apr-16 07-Apr-16 05-Apr-16 07-Apr-16 0% AED2,086 AED0
MEPMEP 40 31-Mar-16 18-May-16 31-Mar-16 18-May-16 0% AED241,672 AED0
Ground Floor 40 31-Mar-16 18-May-16 31-Mar-16 18-May-16 0% AED179,527 AED0
All Zones 40 31-Mar-16 18-May-16 31-Mar-16 18-May-16 0% AED179,527 AED0
MEP 1st Fix 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED9,207 AED0
Vehicle Washing Shed-Civil clearance to Start 1st Fix 0 10-Apr-16 10-Apr-16 0% AED0 AED0
Vehicle Washing Shed-SLEEVES,CONDUITS,GI BOX IN WALL 4 10-Apr-16 13-Apr-16 10-Apr-16 13-Apr-16 0% AED9,207 AED0
Vehicle Washing Shed-MEP clearance to Start Plaster 0 13-Apr-16 13-Apr-16 0% AED0 AED0
MEP 2nd Fix 20 31-Mar-16 24-Apr-16 31-Mar-16 24-Apr-16 0% AED59,841 AED0
Vehicle Washing Shed-WIRING FOR LIGHTING WORKS 7 14-Apr-16 21-Apr-16 14-Apr-16 21-Apr-16 0% AED16,111 AED0
Vehicle Washing Shed-WIRING FOR POWER 7 14-Apr-16 21-Apr-16 14-Apr-16 21-Apr-16 0% AED16,111 AED0
Vehicle Washing Shed-WIRING FOR FIRE ALARM \ LOW CURRENT 7 14-Apr-16 21-Apr-16 14-Apr-16 21-Apr-16 0% AED16,111 AED0
Vehicle Washing Shed-WATER SUPPLY PIPING 5 14-Apr-16 19-Apr-16 14-Apr-16 19-Apr-16 0% AED11,508 AED0
Vehicle Washing Shed-MEP clearance To Start Paint Pre-Final Coats 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Vehicle Washing Shed-Civil clearance to Start 2nd Fix 0 31-Mar-16 31-Mar-16 0% AED0 AED0
MEP Final Fix 20 24-Apr-16 18-May-16 24-Apr-16 18-May-16 0% AED110,480 AED0
2015 2016 2017
Service Yard-INSTALLATION OF WI
Service Yard-INSTALLATION OF LIG
Service Yard-INSTALL OF LIGHT FI
24-Mar-16, Plumbing
24-Mar-16, SECOND FIX
Service Yard-DRAINAGE PIPES ON ROOF
16-Mar-16, All Floors
16-Mar-16, All Zones
Civil clearance plumbing Works
16-Mar-16, Plumbing Shafts
16-Mar-16, SECOND FIX
Service Yard-SHAFTS DRAINAGE PIPES
04-Jun-16, Preliminary Testing & P
04-Jun-16, All Floors
04-Jun-16, All Zones
Service Yard-Electrical System Pre
Service Yard-HVAC System Prelim
Service Yard-Plumbing System Pr
08-Jun-16, House Connections
08-Jun-16, All Floors
08-Jun-16, All Zones
Service Yard-Low Current House Connection
Service Yard-Electrical House Connection
01-Jun-16, Vehicle Washing Shed
07-Apr-16, Skeleton
04-Apr-16, Sub Structure
04-Apr-16, All Zones
04-Apr-16, Concrete Works
Clearance for MEP Works - Vehicle Washing Shed
Vehicle Washing Shed-MEP Sleeves
07-Apr-16, Super Structure
07-Apr-16, All Zones
07-Apr-16, Roof Floor
Vehicle Washing Shed-MEP Conduits &
18-May-16, MEP
18-May-16, Ground Floor
18-May-16, All Zones
13-Apr-16, MEP 1st Fix
Vehicle Washing Shed-Civil clearance to
Vehicle Washing Shed-SLEEVES,COND
Vehicle Washing Shed-MEP clearance t
24-Apr-16, MEP 2nd Fix
Vehicle Washing Shed-WIRING FOR L
Vehicle Washing Shed-WIRING FOR POWER
Vehicle Washing Shed-WIRING FOR F
Vehicle Washing Shed-WATER SUPPLY PIPING
Vehicle Washing Shed-MEP clearance
Vehicle Washing Shed-Civil clearance to S
18-May-16, MEP Final Fix
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 26 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Vehicle Washing Shed-Civil Clearance to Start Final Fix 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Vehicle Washing Shed-FIRE EXTINGUISHERS LOCATING 4 15-May-16 18-May-16 15-May-16 18-May-16 0% AED9,207 AED0
Vehicle Washing Shed-INSTALLATION OF DBs / PANELS / EQUIPMENTS 12 25-Apr-16 09-May-16 25-Apr-16 09-May-16 0% AED27,620 AED0
Vehicle Washing Shed-INSTALLATION OF CCTV / SPEAKERS 4 25-Apr-16 28-Apr-16 25-Apr-16 28-Apr-16 0% AED9,207 AED0
Vehicle Washing Shed-CABLES TERMINATION & DRESSING 4 10-May-16 14-May-16 10-May-16 14-May-16 0% AED9,207 AED0
Vehicle Washing Shed-INSTALLATION OF FIRE ALARM PANEL & ACCESSORIES12 25-Apr-16 09-May-16 25-Apr-16 09-May-16 0% AED27,620 AED0
Vehicle Washing Shed-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 10-May-16 14-May-16 10-May-16 14-May-16 0% AED9,207 AED0
Vehicle Washing Shed-INSTALLATION OF WIRING ACCESSORIES 4 10-May-16 14-May-16 10-May-16 14-May-16 0% AED9,207 AED0
Vehicle Washing Shed-INSTALLATION OF DECORATIVE UNIT 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED4,603 AED0
Vehicle Washing Shed-INSTALLATION OF BIB TAPS / WATER SUPPLY OUTLETS2 25-Apr-16 26-Apr-16 25-Apr-16 26-Apr-16 0% AED4,603 AED0
Vehicle Washing Shed-MEP Final Fix Clearance 0 18-May-16 18-May-16 0% AED0 AED0
Roof Floor 28 13-Apr-16 16-May-16 13-Apr-16 16-May-16 0% AED57,541 AED0
All Zones 28 13-Apr-16 16-May-16 13-Apr-16 16-May-16 0% AED57,541 AED0
Civil Clearance - Electrical Works 0 18-Apr-16 18-Apr-16 0% AED0 AED0
Civil Clearance- Mechanical Works 0 15-May-16 15-May-16 0% AED0 AED0
Mechanical 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED9,207 AED0
SECOND FIX 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED4,603 AED0
Vehicle Washing Shed-INSTALLATION OF OUTDOOR UNIT 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED4,603 AED0
FINAL FIX 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED4,603 AED0
Vehicle Washing Shed-PIPING AND FINAL CONNECTIONS 2 15-May-16 16-May-16 15-May-16 16-May-16 0% AED4,603 AED0
Electrical 22 18-Apr-16 14-May-16 18-Apr-16 14-May-16 0% AED43,731 AED0
FIRST FIX 2 18-Apr-16 19-Apr-16 18-Apr-16 19-Apr-16 0% AED4,603 AED0
Vehicle Washing Shed-CONDUTES, BOXES, IN PARAPET 2 18-Apr-16 19-Apr-16 18-Apr-16 19-Apr-16 0% AED4,603 AED0
SECOND FIX 7 02-May-16 10-May-16 02-May-16 10-May-16 0% AED16,111 AED0
Vehicle Washing Shed-WIRING FOR LIGHTING & POWER 7 02-May-16 10-May-16 02-May-16 10-May-16 0% AED16,111 AED0
FINAL FIX 3 11-May-16 14-May-16 11-May-16 14-May-16 0% AED23,017 AED0
Vehicle Washing Shed-INSTALLATION OF WIRING ACCESSORIES 3 11-May-16 14-May-16 11-May-16 14-May-16 0% AED9,207 AED0
Vehicle Washing Shed-INSTALLATION OF LIGHTNING PROTECTION SYSTEM 3 11-May-16 14-May-16 11-May-16 14-May-16 0% AED6,905 AED0
Vehicle Washing Shed-INSTALL OF LIGHT FITTING 3 11-May-16 14-May-16 11-May-16 14-May-16 0% AED6,905 AED0
Plumbing 2 13-Apr-16 14-Apr-16 13-Apr-16 14-Apr-16 0% AED4,603 AED0
SECOND FIX 2 13-Apr-16 14-Apr-16 13-Apr-16 14-Apr-16 0% AED4,603 AED0
Vehicle Washing Shed-DRAINAGE PIPES ON ROOF 2 13-Apr-16 14-Apr-16 13-Apr-16 14-Apr-16 0% AED4,603 AED0
All Floors 4 13-Apr-16 17-Apr-16 13-Apr-16 17-Apr-16 0% AED4,603 AED0
All Zones 4 13-Apr-16 17-Apr-16 13-Apr-16 17-Apr-16 0% AED4,603 AED0
Clearance for Shaft Works 0 13-Apr-16 13-Apr-16 0% AED0 AED0
Plumbing Shafts 2 16-Apr-16 17-Apr-16 16-Apr-16 17-Apr-16 0% AED4,603 AED0
SECOND FIX 2 16-Apr-16 17-Apr-16 16-Apr-16 17-Apr-16 0% AED4,603 AED0
Vehicle Washing Shed-VERTICAL DRAINAGE PIPES 2 16-Apr-16 17-Apr-16 16-Apr-16 17-Apr-16 0% AED4,603 AED0
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED5,399 AED0
All Floors 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED5,399 AED0
All Zones 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED5,399 AED0
Vehicle Washing Shed-Electrical System Preliminary Testing & Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED1,800 AED0
Vehicle Washing Shed-HVAC System Preliminary Testing & Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED1,800 AED0
Vehicle Washing Shed-Plumbing System Preliminary Testing & Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED1,800 AED0
House ConnectionsHouse Connections 36 03-Apr-16 15-May-16 03-Apr-16 15-May-16 0% AED5,399 AED0
All Floors 36 03-Apr-16 15-May-16 03-Apr-16 15-May-16 0% AED5,399 AED0
All Zones 36 03-Apr-16 15-May-16 03-Apr-16 15-May-16 0% AED5,399 AED0
Vehicle Washing Shed-Water Supply House Connection 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED1,800 AED0
Vehicle Washing Shed-Electrical House Connection 6 03-Apr-16 09-Apr-16 03-Apr-16 09-Apr-16 0% AED1,800 AED0
2015 2016 2017
Vehicle Washing Shed-Civil Clearance
Vehicle Washing Shed-FIRE EXTIN
Vehicle Washing Shed-INSTALLATIO
Vehicle Washing Shed-INSTALLATION
Vehicle Washing Shed-CABLES TER
Vehicle Washing Shed-INSTALLATIO
Vehicle Washing Shed-INSTALLATIO
Vehicle Washing Shed-INSTALLATIO
Vehicle Washing Shed-INSTALLATI
Vehicle Washing Shed-INSTALLATION
Vehicle Washing Shed-MEP Final F
16-May-16, Roof Floor
16-May-16, All Zones
Civil Clearance - Electrical Works
Civil Clearance- Mechanical Works
16-May-16, Mechanical
16-May-16, SECOND FIX
Vehicle Washing Shed-INSTALLATI
16-May-16, FINAL FIX
Vehicle Washing Shed-PIPING AND
14-May-16, Electrical
19-Apr-16, FIRST FIX
Vehicle Washing Shed-CONDUTES, B
10-May-16, SECOND FIX
Vehicle Washing Shed-WIRING FOR
14-May-16, FINAL FIX
Vehicle Washing Shed-INSTALLATIO
Vehicle Washing Shed-INSTALLATIO
Vehicle Washing Shed-INSTALL OF
14-Apr-16, Plumbing
14-Apr-16, SECOND FIX
Vehicle Washing Shed-DRAINAGE PIPE
17-Apr-16, All Floors
17-Apr-16, All Zones
Clearance for Shaft Works
17-Apr-16, Plumbing Shafts
17-Apr-16, SECOND FIX
Vehicle Washing Shed-VERTICAL DRA
01-Jun-16, Preliminary Testing & P
01-Jun-16, All Floors
01-Jun-16, All Zones
Vehicle Washing Shed-Electrical S
Vehicle Washing Shed-HVAC Syst
Vehicle Washing Shed-Plumbing S
15-May-16, House Connections
15-May-16, All Floors
15-May-16, All Zones
Vehicle Washing Shed-Water Supply
Vehicle Washing Shed-Electrical House C
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 27 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Vehicle Washing Shed-Drainage House Connection 5 10-May-16 15-May-16 10-May-16 15-May-16 0% AED1,800 AED0
Maintainance BuildingMaintainance Building 96 06-Feb-16 28-May-16 06-Feb-16 28-May-16 0% AED718,585 AED0
SkeletonSkeleton 38 06-Feb-16 20-Mar-16 06-Feb-16 20-Mar-16 0% AED44,230 AED0
Sub Structure 29 06-Feb-16 09-Mar-16 06-Feb-16 09-Mar-16 0% AED34,495 AED0
All Zones 29 06-Feb-16 09-Mar-16 06-Feb-16 09-Mar-16 0% AED34,495 AED0
Concrete Works 29 06-Feb-16 09-Mar-16 06-Feb-16 09-Mar-16 0% AED34,495 AED0
Clearance for MEP Works - Maintenance Building 0 06-Feb-16 06-Feb-16 06-Feb-16 06-Feb-16 0% AED0 AED0
Maintenance Building-MEP Under Ground Services 4 01-Mar-16 05-Mar-16 01-Mar-16 05-Mar-16 0% AED10,431 AED0
Maintenance Building-Grade Slab Rebar & MEP Services 4 06-Mar-16 09-Mar-16 06-Mar-16 09-Mar-16 0% AED24,064 AED0
Super Structure 4 16-Mar-16 20-Mar-16 16-Mar-16 20-Mar-16 0% AED9,735 AED0
All Zones 4 16-Mar-16 20-Mar-16 16-Mar-16 20-Mar-16 0% AED9,735 AED0
First Floor 4 16-Mar-16 20-Mar-16 16-Mar-16 20-Mar-16 0% AED9,735 AED0
Maintenance Building-MEP Conduits & Sleeves Inside The Slab 4 16-Mar-16 20-Mar-16 16-Mar-16 20-Mar-16 0% AED9,735 AED0
MEPMEP 52 16-Mar-16 16-May-16 16-Mar-16 16-May-16 0% AED644,264 AED0
Ground Floor 42 21-Mar-16 09-May-16 21-Mar-16 09-May-16 0% AED329,518 AED0
All Zones 42 21-Mar-16 09-May-16 21-Mar-16 09-May-16 0% AED329,518 AED0
MEP 1st Fix 10 21-Mar-16 31-Mar-16 21-Mar-16 31-Mar-16 0% AED34,087 AED0
Maintenance Building-Civil clearance to Start 1st Fix 0 21-Mar-16 21-Mar-16 0% AED0 AED0
Maintenance Building-DRAINAGE PIPES ( IN WALLS) 10 21-Mar-16 31-Mar-16 21-Mar-16 31-Mar-16 0% AED11,362 AED0
Maintenance Building-WATER SUPPLY PIPES ( IN WALLS) 10 21-Mar-16 31-Mar-16 21-Mar-16 31-Mar-16 0% AED11,362 AED0
Maintenance Building-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 10 21-Mar-16 31-Mar-16 21-Mar-16 31-Mar-16 0% AED11,362 AED0
Maintenance Building-MEP clearance to Start Plaster 0 31-Mar-16 31-Mar-16 0% AED0 AED0
MEP 2nd Fix 20 31-Mar-16 24-Apr-16 31-Mar-16 24-Apr-16 0% AED224,984 AED0
Maintenance Building-DRAINAGE PIPES (HIGH L) 14 02-Apr-16 17-Apr-16 02-Apr-16 17-Apr-16 0% AED15,908 AED0
Maintenance Building-WATER SUPPLY PIPES \ WATER HEATERS (HIGH L) 14 02-Apr-16 17-Apr-16 02-Apr-16 17-Apr-16 0% AED15,908 AED0
Maintenance Building-GRAVITY TEST 6 18-Apr-16 24-Apr-16 18-Apr-16 24-Apr-16 0% AED6,817 AED0
Maintenance Building-FIRE FIGHTING PIPES 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-PRESSURE TESTING 6 18-Apr-16 24-Apr-16 18-Apr-16 24-Apr-16 0% AED6,817 AED0
Maintenance Building-ACOUSTIC DRAINAGE PIPE INSULATION 6 18-Apr-16 24-Apr-16 18-Apr-16 24-Apr-16 0% AED6,817 AED0
Maintenance Building-FIRE FIGHTING TESTING 6 14-Apr-16 20-Apr-16 14-Apr-16 20-Apr-16 0% AED6,817 AED0
Maintenance Building-WIRING FOR LIGHTING WORKS 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-WIRING FOR POWER 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-CABLE TRAY / TRUNKING 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-STRUC&ELEC CABLING INCLUDING DRESSING 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-DUCTING WORK INCLUDING INSULATION 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-INSTALLATION OF FANS 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-FINAL DUCT CONNECTION TO FANS 14 03-Apr-16 18-Apr-16 03-Apr-16 18-Apr-16 0% AED15,908 AED0
Maintenance Building-PRESSURE TEST&INSULATION 6 12-Apr-16 18-Apr-16 12-Apr-16 18-Apr-16 0% AED6,817 AED0
Maintenance Building-MEP clearance to close Administration ceilings 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Maintenance Building-Civil clearance to Start 2nd Fix 0 31-Mar-16 31-Mar-16 0% AED0 AED0
Maintenance Building-MEP clearance to close corridors ceilings 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Maintenance Building-CHILD WATER PIPES (HIGH L) 14 02-Apr-16 17-Apr-16 02-Apr-16 17-Apr-16 0% AED15,908 AED0
MEP Final Fix 12 24-Apr-16 09-May-16 24-Apr-16 09-May-16 0% AED70,447 AED0
Maintenance Building-Civil Clearance to Start Final Fix 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Maintenance Building-HOSE REEL&FIRE EXTINGUISHERS 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF DBS 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF PANELS / SMDBS 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED6,817 AED0
2015 2016 2017
Vehicle Washing Shed-Drainage Ho
28-May-16, Maintainance Building
20-Mar-16, Skeleton
09-Mar-16, Sub Structure
09-Mar-16, All Zones
09-Mar-16, Concrete Works
Clearance for MEP Works - Maintenance Building
Maintenance Building-MEP Under Ground Services
Maintenance Building-Grade Slab Rebar & M
20-Mar-16, Super Structure
20-Mar-16, All Zones
20-Mar-16, First Floor
Maintenance Building-MEP Conduits & Sle
16-May-16, MEP
09-May-16, Ground Floor
09-May-16, All Zones
31-Mar-16, MEP 1st Fix
Maintenance Building-Civil clearance to Start 1st Fix
Maintenance Building-DRAINAGE PIPES
Maintenance Building-WATER SUPPLY P
Maintenance Building-SLEEVES,CONDU
Maintenance Building-MEP clearance to S
24-Apr-16, MEP 2nd Fix
Maintenance Building-DRAINAGE PIPE
Maintenance Building-WATER SUPPLY
Maintenance Building-GRAVITY TEST
Maintenance Building-FIRE FIGHTING PIPES
Maintenance Building-PRESSURE TESTING
Maintenance Building-ACOUSTIC DRA
Maintenance Building-FIRE FIGHTING TESTING
Maintenance Building-WIRING FOR LIG
Maintenance Building-WIRING FOR POWER
Maintenance Building-WIRING FOR FI
Maintenance Building-CABLE TRAY / TRUNKING
Maintenance Building-STRUC&ELEC C
Maintenance Building-DUCTING WOR
Maintenance Building-INSTALLATION OF FANS
Maintenance Building-FINAL DUCT CO
Maintenance Building-PRESSURE TES
Maintenance Building-MEP clearance t
Maintenance Building-Civil clearance to S
Maintenance Building-MEP clearance t
Maintenance Building-CHILD WATER P
09-May-16, MEP Final Fix
Maintenance Building-Civil Clearance t
Maintenance Building-HOSE REEL&F
Maintenance Building-INSTALLATION OF DBS
Maintenance Building-INSTALLATION
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 28 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Maintenance Building-INSTALLATION OF TELEPHONE SYSTEM 6 02-May-16 09-May-16 02-May-16 09-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF CCTV SYSTEM 6 02-May-16 09-May-16 02-May-16 09-May-16 0% AED6,817 AED0
Maintenance Building-TERMINATION & DRESSING OF DBS 6 02-May-16 09-May-16 02-May-16 09-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF LIGHT FITTING & E.M LIGHT 6 02-May-16 09-May-16 02-May-16 09-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF WIRING ACCESSORIES 6 02-May-16 09-May-16 02-May-16 09-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF GRILLS&DIFFUSERS 6 25-Apr-16 01-May-16 25-Apr-16 01-May-16 0% AED6,817 AED0
Maintenance Building-THERMOSTAT FIXING 2 02-May-16 04-May-16 02-May-16 04-May-16 0% AED2,272 AED0
Maintenance Building-MEP Final Fix Clearance 0 09-May-16 09-May-16 0% AED0 AED0
Maintenance Building- Installation of Sanitary wares 7 25-Apr-16 02-May-16 25-Apr-16 02-May-16 0% AED0 AED0
Roof Floor 52 16-Mar-16 16-May-16 16-Mar-16 16-May-16 0% AED235,208 AED0
All Zones 52 16-Mar-16 16-May-16 16-Mar-16 16-May-16 0% AED235,208 AED0
Civil clearance for Roof - Mechanical Works 0 24-Mar-16 24-Mar-16 0% AED0 AED0
Civil clearance for Roof - Electrical Works 0 16-Mar-16 16-Mar-16 0% AED0 AED0
Mechanical 45 24-Mar-16 16-May-16 24-Mar-16 16-May-16 0% AED127,263 AED0
SECOND FIX 39 24-Mar-16 09-May-16 24-Mar-16 09-May-16 0% AED115,901 AED0
Maintenance Building-PRESSURE TEST&INSULATION 7 01-May-16 09-May-16 01-May-16 09-May-16 0% AED6,817 AED0
Maintenance Building-SUPPORTS FOR DUCTING WORK 12 24-Mar-16 06-Apr-16 24-Mar-16 06-Apr-16 0% AED13,636 AED0
Maintenance Building-SUPPORTS FOR PIPING WORKS 12 30-Mar-16 12-Apr-16 30-Mar-16 12-Apr-16 0% AED13,636 AED0
Maintenance Building-DUCTING WORK ON ROOF 18 13-Apr-16 04-May-16 13-Apr-16 04-May-16 0% AED20,453 AED0
Maintenance Building-PIPING WORK ON ROOF 18 13-Apr-16 04-May-16 13-Apr-16 04-May-16 0% AED20,453 AED0
Maintenance Building-INSTALLATION OF FANS AND CONNECTION 18 17-Apr-16 08-May-16 17-Apr-16 08-May-16 0% AED20,453 AED0
Maintenance Building-INSTALLATION OF AHU AND VALVE PACKAGES 18 12-Apr-16 02-May-16 12-Apr-16 02-May-16 0% AED20,453 AED0
FINAL FIX 10 05-May-16 16-May-16 05-May-16 16-May-16 0% AED11,362 AED0
Maintenance Building-CLADDING WORKS FOR DUCTS&PIPING 10 05-May-16 16-May-16 05-May-16 16-May-16 0% AED11,362 AED0
Electrical 41 17-Mar-16 04-May-16 17-Mar-16 04-May-16 0% AED88,629 AED0
FIRST FIX 7 17-Mar-16 24-Mar-16 17-Mar-16 24-Mar-16 0% AED7,954 AED0
Maintenance Building-SLEEVES,CONDUTES,GI BOX,DB BOX IN WALL 7 17-Mar-16 24-Mar-16 17-Mar-16 24-Mar-16 0% AED7,954 AED0
SECOND FIX 18 28-Mar-16 17-Apr-16 28-Mar-16 17-Apr-16 0% AED43,179 AED0
Maintenance Building-WIRING FOR LIGHTING & POWER 12 28-Mar-16 10-Apr-16 28-Mar-16 10-Apr-16 0% AED13,636 AED0
Maintenance Building-CABLE TRAY / TRUNKING 12 29-Mar-16 11-Apr-16 29-Mar-16 11-Apr-16 0% AED15,908 AED0
Maintenance Building-CABLING INCLUDING DRESSING OF CABLES 12 04-Apr-16 17-Apr-16 04-Apr-16 17-Apr-16 0% AED13,636 AED0
FINAL FIX 14 18-Apr-16 04-May-16 18-Apr-16 04-May-16 0% AED37,496 AED0
Maintenance Building-INSTILLATION OF PANELS / SMDBS /MCC 7 18-Apr-16 25-Apr-16 18-Apr-16 25-Apr-16 0% AED7,954 AED0
Maintenance Building-TERMINATION & DRESSING OF DBS 7 26-Apr-16 04-May-16 26-Apr-16 04-May-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF WIRING ACCESSORIES 7 18-Apr-16 25-Apr-16 18-Apr-16 25-Apr-16 0% AED6,817 AED0
Maintenance Building-INSTALLATION OF LIGHTING CONTROL SYSTEM\ 7 18-Apr-16 25-Apr-16 18-Apr-16 25-Apr-16 0% AED7,954 AED0
Maintenance Building-INSTALL OF LIGHT FITTING & E.M LIGHT 7 18-Apr-16 25-Apr-16 18-Apr-16 25-Apr-16 0% AED7,954 AED0
Plumbing 15 26-Mar-16 11-Apr-16 26-Mar-16 11-Apr-16 0% AED19,316 AED0
SECOND FIX 15 26-Mar-16 11-Apr-16 26-Mar-16 11-Apr-16 0% AED19,316 AED0
Maintenance Building-WATER SUPPLY & DRAINAGE PIPES ON ROOF 7 26-Mar-16 03-Apr-16 26-Mar-16 03-Apr-16 0% AED7,954 AED0
Maintenance Building-PRESSURE TESTING 4 03-Apr-16 06-Apr-16 03-Apr-16 06-Apr-16 0% AED6,817 AED0
Maintenance Building-BIB Taps / PIPE INSULATION 4 07-Apr-16 11-Apr-16 07-Apr-16 11-Apr-16 0% AED4,545 AED0
All Floors 32 26-Mar-16 01-May-16 26-Mar-16 01-May-16 0% AED79,538 AED0
All Zones 32 26-Mar-16 01-May-16 26-Mar-16 01-May-16 0% AED79,538 AED0
Civil clearance for Shaft Works 0 26-Mar-16 26-Mar-16 0% AED0 AED0
Mechanical Shafts 32 26-Mar-16 01-May-16 26-Mar-16 01-May-16 0% AED45,451 AED0
SECOND FIX 22 26-Mar-16 19-Apr-16 26-Mar-16 19-Apr-16 0% AED34,089 AED0
2015 2016 2017
Maintenance Building-INSTALLATION
Maintenance Building-INSTALLATION
Maintenance Building-TERMINATION
Maintenance Building-INSTALLATION
Maintenance Building-INSTALLATION
Maintenance Building-INSTALLATION
Maintenance Building-INSTALLATION
Maintenance Building-THERMOSTAT FIXING
Maintenance Building-MEP Final Fix Clearance
Maintenance Building- Installation of S
16-May-16, Roof Floor
16-May-16, All Zones
Civil clearance for Roof - Mechanical Works
Civil clearance for Roof - Electrical Works
16-May-16, Mechanical
09-May-16, SECOND FIX
Maintenance Building-PRESSURE T
Maintenance Building-SUPPORTS FOR
Maintenance Building-SUPPORTS FOR
Maintenance Building-DUCTING WO
Maintenance Building-PIPING WORK
Maintenance Building-INSTALLATION
Maintenance Building-INSTALLATION
16-May-16, FINAL FIX
Maintenance Building-CLADDING W
04-May-16, Electrical
24-Mar-16, FIRST FIX
Maintenance Building-SLEEVES,CONDUT
17-Apr-16, SECOND FIX
Maintenance Building-WIRING FOR LIG
Maintenance Building-CABLE TRAY / TRUNKING
Maintenance Building-CABLING INCLU
04-May-16, FINAL FIX
Maintenance Building-INSTILLATION O
Maintenance Building-TERMINATION
Maintenance Building-INSTALLATION
Maintenance Building-INSTALLATION
Maintenance Building-INSTALL OF LIG
11-Apr-16, Plumbing
11-Apr-16, SECOND FIX
Maintenance Building-WATER SUPPLY &
Maintenance Building-PRESSURE TESTING
Maintenance Building-BIB Taps / PIPE IN
01-May-16, All Floors
01-May-16, All Zones
Civil clearance for Shaft Works
01-May-16, Mechanical Shafts
19-Apr-16, SECOND FIX
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 29 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Maintenance Building-DUCT RISERS IN SHAFTS 15 26-Mar-16 11-Apr-16 26-Mar-16 11-Apr-16 0% AED17,044 AED0
Maintenance Building-PIPING IN SHAFTS 15 03-Apr-16 19-Apr-16 03-Apr-16 19-Apr-16 0% AED17,044 AED0
FINAL FIX 10 20-Apr-16 01-May-16 20-Apr-16 01-May-16 0% AED11,362 AED0
Maintenance Building-CLADDING WORK FOR DUCTS&PIPING 10 20-Apr-16 01-May-16 20-Apr-16 01-May-16 0% AED11,362 AED0
Electrical Shafts 20 26-Mar-16 17-Apr-16 26-Mar-16 17-Apr-16 0% AED22,725 AED0
SECOND FIX 20 26-Mar-16 17-Apr-16 26-Mar-16 17-Apr-16 0% AED22,725 AED0
Maintenance Building-CABLE TRAY 10 26-Mar-16 05-Apr-16 26-Mar-16 05-Apr-16 0% AED11,362 AED0
Maintenance Building-CABLE PULLING 10 06-Apr-16 17-Apr-16 06-Apr-16 17-Apr-16 0% AED11,362 AED0
Plumbing Shafts 10 26-Mar-16 05-Apr-16 26-Mar-16 05-Apr-16 0% AED11,362 AED0
SECOND FIX 10 26-Mar-16 05-Apr-16 26-Mar-16 05-Apr-16 0% AED11,362 AED0
Maintenance Building-SHAFTS DRAINAGE & PLUMBING PIPES 10 26-Mar-16 05-Apr-16 26-Mar-16 05-Apr-16 0% AED11,362 AED0
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 12 15-May-16 28-May-16 15-May-16 28-May-16 0% AED11,284 AED0
All Floors 12 15-May-16 28-May-16 15-May-16 28-May-16 0% AED11,284 AED0
All Zones 12 15-May-16 28-May-16 15-May-16 28-May-16 0% AED11,284 AED0
Maintenance Building-Electrical System Preliminary Testing & Commissioning 10 15-May-16 25-May-16 15-May-16 25-May-16 0% AED3,761 AED0
Maintenance Building-HVAC System Preliminary Testing & Commissioning 10 17-May-16 28-May-16 17-May-16 28-May-16 0% AED3,761 AED0
Maintenance Building-Plumbing System Preliminary Testing & Commissioning 10 15-May-16 25-May-16 15-May-16 25-May-16 0% AED3,761 AED0
House ConnectionsHouse Connections 43 31-Mar-16 21-May-16 31-Mar-16 21-May-16 0% AED18,806 AED0
All Floors 43 31-Mar-16 21-May-16 31-Mar-16 21-May-16 0% AED18,806 AED0
All Zones 43 31-Mar-16 21-May-16 31-Mar-16 21-May-16 0% AED18,806 AED0
Maintenance Building-Drainage House Connection 10 10-May-16 21-May-16 10-May-16 21-May-16 0% AED3,761 AED0
Maintenance Building-Water Supply House Connection 10 25-Apr-16 07-May-16 25-Apr-16 07-May-16 0% AED3,761 AED0
Maintenance Building-Chilled Water House Connection 10 25-Apr-16 07-May-16 25-Apr-16 07-May-16 0% AED3,761 AED0
Maintenance Building-Low Current House Connection 10 02-Apr-16 12-Apr-16 02-Apr-16 12-Apr-16 0% AED3,761 AED0
Maintenance Building-Electrical House Connection 10 31-Mar-16 11-Apr-16 31-Mar-16 11-Apr-16 0% AED3,761 AED0
Amunition & Light Weapon StorageAmunition & Light Weapon Storage 220 26-Sep-15 01-Jun-16 26-Sep-15 A 01-Jun-16 2.53% AED570,463 AED14,410
SkeletonSkeleton 100 26-Sep-15 14-Jan-16 26-Sep-15 A 14-Jan-16 A 100% AED14,410 AED14,410
Sub Structure 35 26-Sep-15 16-Nov-15 26-Sep-15 A 16-Nov-15 A 100% AED11,629 AED11,629
All Zones 35 26-Sep-15 16-Nov-15 26-Sep-15 A 16-Nov-15 A 100% AED11,629 AED11,629
Concrete Works 35 26-Sep-15 16-Nov-15 26-Sep-15 A 16-Nov-15 A 100% AED11,629 AED11,629
Ammunition Building-MEP Under Ground Services 2 26-Sep-15 16-Nov-15 26-Sep-15 A 16-Nov-15 A 100% AED3,650 AED3,650
Clearance for MEP Works - Ammunition Building 0 26-Sep-15 26-Sep-15 A 100% AED0 AED0
Ammunition Building-Grade Slab Rebar & MEP Services 3 24-Oct-15 31-Oct-15 24-Oct-15 A 31-Oct-15 A 100% AED7,979 AED7,979
Super Structure 1 12-Jan-16 14-Jan-16 12-Jan-16 A 14-Jan-16 A 100% AED2,781 AED2,781
All Zones 1 12-Jan-16 14-Jan-16 12-Jan-16 A 14-Jan-16 A 100% AED2,781 AED2,781
First Floor 1 12-Jan-16 14-Jan-16 12-Jan-16 A 14-Jan-16 A 100% AED2,781 AED2,781
Ammunition Building-MEP Conduits & Sleeves Inside The Slab 3 12-Jan-16 14-Jan-16 12-Jan-16 A 14-Jan-16 A 100% AED2,781 AED2,781
MEPMEP 72 24-Feb-16 18-May-16 24-Feb-16 18-May-16 0% AED531,496 AED0
Ground Floor 72 24-Feb-16 18-May-16 24-Feb-16 18-May-16 0% AED271,399 AED0
All Zones 72 24-Feb-16 18-May-16 24-Feb-16 18-May-16 0% AED271,399 AED0
MEP 1st Fix 5 24-Feb-16 29-Feb-16 24-Feb-16 29-Feb-16 0% AED27,868 AED0
Ammunition Building-Civil clearance to Start 1st Fix 0 24-Feb-16 24-Feb-16 0% AED0 AED0
Ammunition Building-DRAINAGE PIPES ( IN WALLS) 5 24-Feb-16 29-Feb-16 24-Feb-16 29-Feb-16 0% AED9,289 AED0
Ammunition Building-WATER SUPPLY PIPES ( IN WALLS) 5 24-Feb-16 29-Feb-16 24-Feb-16 29-Feb-16 0% AED9,289 AED0
Ammunition Building-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 5 24-Feb-16 29-Feb-16 24-Feb-16 29-Feb-16 0% AED9,289 AED0
Ammunition Building-MEP clearance to Start Plaster 0 29-Feb-16 29-Feb-16 0% AED0 AED0
MEP 2nd Fix 50 03-Mar-16 01-May-16 03-Mar-16 01-May-16 0% AED183,926 AED0
Ammunition Building-DRAINAGE PIPES (HIGH L) 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-WATER SUPPLY PIPES \ WATER HEATERS (HIGH L) 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
2015 2016 2017
Maintenance Building-DUCT RISERS IN SHAFTS
Maintenance Building-PIPING IN SHAFTS
01-May-16, FINAL FIX
Maintenance Building-CLADDING WO
17-Apr-16, Electrical Shafts
17-Apr-16, SECOND FIX
Maintenance Building-CABLE TRAY
Maintenance Building-CABLE PULLING
05-Apr-16, Plumbing Shafts
05-Apr-16, SECOND FIX
Maintenance Building-SHAFTS DRAINA
28-May-16, Preliminary Testing & P
28-May-16, All Floors
28-May-16, All Zones
Maintenance Building-Electrical Sys
Maintenance Building-HVAC Syste
Maintenance Building-Plumbing Sy
21-May-16, House Connections
21-May-16, All Floors
21-May-16, All Zones
Maintenance Building-Drainage Hou
Maintenance Building-Water Supply H
Maintenance Building-Chilled Water H
Maintenance Building-Low Current Hou
Maintenance Building-Electrical House Connection
01-Jun-16, Amunition & Light Wea
14-Jan-16 A, Skeleton
16-Nov-15 A, Sub Structure
16-Nov-15 A, All Zones
16-Nov-15 A, Concrete Works
Ammunition Building-MEP Under Ground Services
Clearance for MEP Works - Ammunition Building
Ammunition Building-Grade Slab Rebar & MEP Services
14-Jan-16 A, Super Structure
14-Jan-16 A, All Zones
14-Jan-16 A, First Floor
Ammunition Building-MEP Conduits & Sleeves Insid
18-May-16, MEP
18-May-16, Ground Floor
18-May-16, All Zones
29-Feb-16, MEP 1st Fix
Ammunition Building-Civil clearance to Start 1st Fix
Ammunition Building-DRAINAGE PIPES ( IN WALLS)
Ammunition Building-WATER SUPPLY PIPE
Ammunition Building-SLEEVES,CONDUITS,G
Ammunition Building-MEP clearance to Start Plaster
01-May-16, MEP 2nd Fix
Ammunition Building-DRAINAGE PIPES (HIGH L)
Ammunition Building-WATER SUPPLY PIPE
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 30 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Ammunition Building-GRAVITY TEST 3 14-Mar-16 16-Mar-16 14-Mar-16 16-Mar-16 0% AED5,573 AED0
Ammunition Building-FIRE FIGHTING PIPES 7 07-Mar-16 14-Mar-16 07-Mar-16 14-Mar-16 0% AED13,005 AED0
Ammunition Building-PRESSURE TESTING 3 14-Mar-16 16-Mar-16 14-Mar-16 16-Mar-16 0% AED5,573 AED0
Ammunition Building-ACOUSTIC DRAINAGE PIPE INSULATION 3 16-Mar-16 19-Mar-16 16-Mar-16 19-Mar-16 0% AED5,573 AED0
Ammunition Building-FIRE FIGHTING TESTING 3 14-Mar-16 16-Mar-16 14-Mar-16 16-Mar-16 0% AED5,573 AED0
Ammunition Building-WIRING FOR LIGHTING WORKS 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-WIRING FOR POWER 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-CABLE TRAY / TRUNKING 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-STRUC&ELEC CABLING INCLUDING DRESSING 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-DUCTING WORK INCLUDING INSULATION 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-INSTALLATION OF FANS 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-FINAL DUCT CONNECTION TO FANS 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
Ammunition Building-PRESSURE TEST&INSULATION 3 10-Mar-16 13-Mar-16 10-Mar-16 13-Mar-16 0% AED5,573 AED0
Ammunition Building-MEP clearance to close Control & Guard Rooms ceilings 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Ammunition Building-Civil clearance to Start 2nd Fix 0 03-Mar-16 03-Mar-16 0% AED0 AED0
Ammunition Building-MEP clearance to close corridors ceilings 0 01-May-16 01-May-16 0% AED0 AED0
Ammunition Building-CHILD WATER PIPES (HIGH L) 7 06-Mar-16 13-Mar-16 06-Mar-16 13-Mar-16 0% AED13,005 AED0
MEP Final Fix 14 01-May-16 18-May-16 01-May-16 18-May-16 0% AED59,605 AED0
Ammunition Building-Civil Clearance to Start Final Fix 0 01-May-16 01-May-16 0% AED0 AED0
Ammunition Building-SPRINKLERS, HOSE REEL&FIRE EXTINGUISHERS 3 02-May-16 05-May-16 02-May-16 05-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF DBS 3 02-May-16 05-May-16 02-May-16 05-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF PANELS / SMDBS 3 02-May-16 05-May-16 02-May-16 05-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF TELEPHONE SYSTEM 3 07-May-16 09-May-16 07-May-16 09-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF CCTV SYSTEM 3 07-May-16 09-May-16 07-May-16 09-May-16 0% AED5,573 AED0
Ammunition Building-TERMINATION & DRESSING OF DBS 3 07-May-16 09-May-16 07-May-16 09-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 3 02-May-16 05-May-16 02-May-16 05-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF LIGHT FITTING & E.M LIGHT 3 07-May-16 09-May-16 07-May-16 09-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF WIRING ACCESSORIES 3 07-May-16 09-May-16 07-May-16 09-May-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF GRILLS&DIFFUSERS 3 02-May-16 05-May-16 02-May-16 05-May-16 0% AED5,573 AED0
Ammunition Building-THERMOSTAT FIXING 2 07-May-16 08-May-16 07-May-16 08-May-16 0% AED3,715 AED0
Ammunition Building-MEP Final Fix Clearance 0 18-May-16 18-May-16 0% AED0 AED0
Amunition Building- Installation of Sanitary Wares 6 02-May-16 09-May-16 02-May-16 09-May-16 0% AED155 AED0
Roof Floor 42 08-Mar-16 25-Apr-16 08-Mar-16 25-Apr-16 0% AED196,929 AED0
All Zones 42 08-Mar-16 25-Apr-16 08-Mar-16 25-Apr-16 0% AED196,929 AED0
Civil clearance - Mechanical Works 0 08-Mar-16 08-Mar-16 0% AED0 AED0
Civil clearance - Electrical Works 0 08-Mar-16 08-Mar-16 0% AED0 AED0
Mechanical 31 08-Mar-16 12-Apr-16 08-Mar-16 12-Apr-16 0% AED105,896 AED0
SECOND FIX 25 08-Mar-16 05-Apr-16 08-Mar-16 05-Apr-16 0% AED98,464 AED0
Ammunition Building-PRESSURE TEST&INSULATION 3 03-Apr-16 05-Apr-16 03-Apr-16 05-Apr-16 0% AED5,573 AED0
Ammunition Building-SUPPORTS FOR DUCTING WORK 7 08-Mar-16 15-Mar-16 08-Mar-16 15-Mar-16 0% AED13,005 AED0
Ammunition Building-SUPPORTS FOR PIPING WORKS 7 14-Mar-16 21-Mar-16 14-Mar-16 21-Mar-16 0% AED13,005 AED0
Ammunition Building-DUCTING WORK ON ROOF 9 22-Mar-16 31-Mar-16 22-Mar-16 31-Mar-16 0% AED16,720 AED0
Ammunition Building-PIPING WORK ON ROOF 9 22-Mar-16 31-Mar-16 22-Mar-16 31-Mar-16 0% AED16,720 AED0
Ammunition Building-INSTALLATION OF FANS AND CONNECTION 9 16-Mar-16 26-Mar-16 16-Mar-16 26-Mar-16 0% AED16,720 AED0
Ammunition Building-INSTALLATION OF CU AND PACKAGE UNITS 9 12-Mar-16 21-Mar-16 12-Mar-16 21-Mar-16 0% AED16,720 AED0
FINAL FIX 4 09-Apr-16 12-Apr-16 09-Apr-16 12-Apr-16 0% AED7,431 AED0
2015 2016 2017
Ammunition Building-GRAVITY TEST
Ammunition Building-FIRE FIGHTING PIPES
Ammunition Building-PRESSURE TESTING
Ammunition Building-ACOUSTIC DRAINAG
Ammunition Building-FIRE FIGHTING TESTING
Ammunition Building-WIRING FOR LIGHTI
Ammunition Building-WIRING FOR POWER
Ammunition Building-WIRING FOR FIRE AL
Ammunition Building-CABLE TRAY / TRUNKING
Ammunition Building-STRUC&ELEC CABLI
Ammunition Building-DUCTING WORK INC
Ammunition Building-INSTALLATION OF FANS
Ammunition Building-FINAL DUCT CONNE
Ammunition Building-PRESSURE TEST&IN
Ammunition Building-MEP clearance to
Ammunition Building-Civil clearance to Start 2nd Fix
Ammunition Building-MEP clearance t
Ammunition Building-CHILD WATER PIPES
18-May-16, MEP Final Fix
Ammunition Building-Civil Clearance to
Ammunition Building-SPRINKLERS, H
Ammunition Building-INSTALLATION OF DBS
Ammunition Building-INSTALLATION
Ammunition Building-INSTALLATION
Ammunition Building-INSTALLATION
Ammunition Building-TERMINATION
Ammunition Building-INSTALLATION
Ammunition Building-INSTALLATION
Ammunition Building-INSTALLATION
Ammunition Building-INSTALLATION
Ammunition Building-THERMOSTAT FIXING
Ammunition Building-MEP Final Fix Clearance
Amunition Building- Installation of San
25-Apr-16, Roof Floor
25-Apr-16, All Zones
Civil clearance - Mechanical Works
Civil clearance - Electrical Works
12-Apr-16, Mechanical
05-Apr-16, SECOND FIX
Ammunition Building-PRESSURE TEST&
Ammunition Building-SUPPORTS FOR DU
Ammunition Building-SUPPORTS FOR PIP
Ammunition Building-DUCTING WORK ON ROOF
Ammunition Building-PIPING WORK ON ROOF
Ammunition Building-INSTALLATION OF F
Ammunition Building-INSTALLATION OF C
12-Apr-16, FINAL FIX
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 31 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Ammunition Building-CLADDING WORKS FOR DUCTS&PIPING 4 09-Apr-16 12-Apr-16 09-Apr-16 12-Apr-16 0% AED7,431 AED0
Electrical 42 08-Mar-16 25-Apr-16 08-Mar-16 25-Apr-16 0% AED76,171 AED0
FIRST FIX 4 08-Mar-16 12-Mar-16 08-Mar-16 12-Mar-16 0% AED7,431 AED0
Ammunition Building-SLEEVES,CONDUTES,GI BOX,DB BOX IN WALL 4 08-Mar-16 12-Mar-16 08-Mar-16 12-Mar-16 0% AED7,431 AED0
SECOND FIX 18 29-Mar-16 18-Apr-16 29-Mar-16 18-Apr-16 0% AED35,299 AED0
Ammunition Building-WIRING FOR LIGHTING & POWER 6 29-Mar-16 04-Apr-16 29-Mar-16 04-Apr-16 0% AED11,147 AED0
Ammunition Building-CABLE TRAY / TRUNKING 6 05-Apr-16 11-Apr-16 05-Apr-16 11-Apr-16 0% AED13,005 AED0
Ammunition Building-CABLING INCLUDING DRESSING OF CABLES 6 12-Apr-16 18-Apr-16 12-Apr-16 18-Apr-16 0% AED11,147 AED0
FINAL FIX 6 19-Apr-16 25-Apr-16 19-Apr-16 25-Apr-16 0% AED33,441 AED0
Ammunition Building-INSTILLATION OF PANELS / SMDBS /MCC 4 19-Apr-16 23-Apr-16 19-Apr-16 23-Apr-16 0% AED7,431 AED0
Ammunition Building-TERMINATION & DRESSING OF DBS 4 21-Apr-16 25-Apr-16 21-Apr-16 25-Apr-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF WIRING ACCESSORIES 4 19-Apr-16 23-Apr-16 19-Apr-16 23-Apr-16 0% AED5,573 AED0
Ammunition Building-INSTALLATION OF LIGHTING CONTROL SYSTEM 4 19-Apr-16 23-Apr-16 19-Apr-16 23-Apr-16 0% AED7,431 AED0
Ammunition Building-INSTALL OF LIGHT FITTING & E.M LIGHT 4 19-Apr-16 23-Apr-16 19-Apr-16 23-Apr-16 0% AED7,431 AED0
Plumbing 8 14-Mar-16 22-Mar-16 14-Mar-16 22-Mar-16 0% AED14,862 AED0
SECOND FIX 8 14-Mar-16 22-Mar-16 14-Mar-16 22-Mar-16 0% AED14,862 AED0
Ammunition Building-WATER SUPPLY & DRAINAGE PIPES ON ROOF 3 14-Mar-16 16-Mar-16 14-Mar-16 16-Mar-16 0% AED5,573 AED0
Ammunition Building-PRESSURE TESTING 3 17-Mar-16 20-Mar-16 17-Mar-16 20-Mar-16 0% AED5,573 AED0
Ammunition Building-BIB Taps / PIPE INSULATION 2 21-Mar-16 22-Mar-16 21-Mar-16 22-Mar-16 0% AED3,715 AED0
All Floors 19 12-Mar-16 02-Apr-16 12-Mar-16 02-Apr-16 0% AED63,168 AED0
All Zones 19 12-Mar-16 02-Apr-16 12-Mar-16 02-Apr-16 0% AED63,168 AED0
Civil clearance for Shaft Works 0 12-Mar-16 12-Mar-16 0% AED0 AED0
Mechanical Shafts 19 12-Mar-16 02-Apr-16 12-Mar-16 02-Apr-16 0% AED35,299 AED0
SECOND FIX 14 12-Mar-16 27-Mar-16 12-Mar-16 27-Mar-16 0% AED26,010 AED0
Ammunition Building-DUCT RISERS IN SHAFTS 7 12-Mar-16 19-Mar-16 12-Mar-16 19-Mar-16 0% AED13,005 AED0
Ammunition Building-PIPING IN SHAFTS 7 20-Mar-16 27-Mar-16 20-Mar-16 27-Mar-16 0% AED13,005 AED0
FINAL FIX 5 28-Mar-16 02-Apr-16 28-Mar-16 02-Apr-16 0% AED9,289 AED0
Ammunition Building-CLADDING WORK FOR DUCTS&PIPING 5 28-Mar-16 02-Apr-16 28-Mar-16 02-Apr-16 0% AED9,289 AED0
Electrical Shafts 15 12-Mar-16 28-Mar-16 12-Mar-16 28-Mar-16 0% AED18,579 AED0
SECOND FIX 15 12-Mar-16 28-Mar-16 12-Mar-16 28-Mar-16 0% AED18,579 AED0
Ammunition Building-CABLE TRAY 5 12-Mar-16 16-Mar-16 12-Mar-16 16-Mar-16 0% AED9,289 AED0
Ammunition Building-CABLE PULLING 5 23-Mar-16 28-Mar-16 23-Mar-16 28-Mar-16 0% AED9,289 AED0
Plumbing Shafts 5 12-Mar-16 16-Mar-16 12-Mar-16 16-Mar-16 0% AED9,289 AED0
SECOND FIX 5 12-Mar-16 16-Mar-16 12-Mar-16 16-Mar-16 0% AED9,289 AED0
Ammunition Building-SHAFTS DRAINAGE & PLUMBING PIPES 5 12-Mar-16 16-Mar-16 12-Mar-16 16-Mar-16 0% AED9,289 AED0
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED10,524 AED0
All Floors 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED10,524 AED0
All Zones 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED10,524 AED0
Ammunition Building-Electrical System Preliminary Testing & Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED3,508 AED0
Ammunition Building-HVAC System Preliminary Testing & Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED3,508 AED0
Ammunition Building-Plumbing System Preliminary Testing & Commissioning 12 19-May-16 01-Jun-16 19-May-16 01-Jun-16 0% AED3,508 AED0
House ConnectionsHouse Connections 26 14-Apr-16 15-May-16 14-Apr-16 15-May-16 0% AED14,033 AED0
All Floors 26 14-Apr-16 15-May-16 14-Apr-16 15-May-16 0% AED14,033 AED0
All Zones 26 14-Apr-16 15-May-16 14-Apr-16 15-May-16 0% AED14,033 AED0
Ammunition Building-Drainage House Connection 5 10-May-16 15-May-16 10-May-16 15-May-16 0% AED3,508 AED0
Ammunition Building-Water Supply House Connection 5 25-Apr-16 30-Apr-16 25-Apr-16 30-Apr-16 0% AED3,508 AED0
Ammunition Building-Low Current House Connection 5 14-Apr-16 19-Apr-16 14-Apr-16 19-Apr-16 0% AED3,508 AED0
Ammunition Building-Electrical House Connection 5 28-Apr-16 04-May-16 28-Apr-16 04-May-16 0% AED3,508 AED0
Gatehouse BuildingGatehouse Building 114 23-Jan-16 04-Jun-16 23-Jan-16 A 04-Jun-16 2.4% AED685,962 AED15,791
2015 2016 2017
Ammunition Building-CLADDING WORK
25-Apr-16, Electrical
12-Mar-16, FIRST FIX
Ammunition Building-SLEEVES,CONDUTES
18-Apr-16, SECOND FIX
Ammunition Building-WIRING FOR LIGH
Ammunition Building-CABLE TRAY / TRUNKING
Ammunition Building-CABLING INCLUD
25-Apr-16, FINAL FIX
Ammunition Building-INSTILLATION O
Ammunition Building-TERMINATION &
Ammunition Building-INSTALLATION O
Ammunition Building-INSTALLATION O
Ammunition Building-INSTALL OF LIGH
22-Mar-16, Plumbing
22-Mar-16, SECOND FIX
Ammunition Building-WATER SUPPLY & D
Ammunition Building-PRESSURE TESTING
Ammunition Building-BIB Taps / PIPE INSULATION
02-Apr-16, All Floors
02-Apr-16, All Zones
Civil clearance for Shaft Works
02-Apr-16, Mechanical Shafts
27-Mar-16, SECOND FIX
Ammunition Building-DUCT RISERS IN SHAFTS
Ammunition Building-PIPING IN SHAFTS
02-Apr-16, FINAL FIX
Ammunition Building-CLADDING WORK
28-Mar-16, Electrical Shafts
28-Mar-16, SECOND FIX
Ammunition Building-CABLE TRAY
Ammunition Building-CABLE PULLING
16-Mar-16, Plumbing Shafts
16-Mar-16, SECOND FIX
Ammunition Building-SHAFTS DRAINAGE
01-Jun-16, Preliminary Testing & P
01-Jun-16, All Floors
01-Jun-16, All Zones
Ammunition Building-Electrical Sys
Ammunition Building-HVAC System
Ammunition Building-Plumbing Sys
15-May-16, House Connections
15-May-16, All Floors
15-May-16, All Zones
Ammunition Building-Drainage Hous
Ammunition Building-Water Supply Ho
Ammunition Building-Low Current Hous
Ammunition Building-Electrical House
04-Jun-16, Gatehouse Building
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 32 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
SkeletonSkeleton 31 23-Jan-16 08-Feb-16 23-Jan-16 A 08-Feb-16 72.48% AED22,745 AED15,791
Sub Structure 12 23-Jan-16 06-Feb-16 23-Jan-16 A 06-Feb-16 100% AED15,791 AED15,791
All Zones 12 23-Jan-16 06-Feb-16 23-Jan-16 A 06-Feb-16 100% AED15,791 AED15,791
Concrete Works 12 23-Jan-16 06-Feb-16 23-Jan-16 A 06-Feb-16 100% AED15,791 AED15,791
Clearance for Gate House 0 06-Feb-16 06-Feb-16 0% AED0 AED0
Gate House-MEP Under Ground Services 3 23-Jan-16 25-Jan-16 23-Jan-16 A 25-Jan-16 A 100% AED6,954 AED6,954
Gate House-Grade Slab Rebar & MEP Services 3 27-Jan-16 30-Jan-16 27-Jan-16 A 30-Jan-16 A 100% AED8,838 AED8,838
Super Structure 3 06-Feb-16 08-Feb-16 06-Feb-16 A 08-Feb-16 10% AED6,954 AED0
All Zones 3 06-Feb-16 08-Feb-16 06-Feb-16 A 08-Feb-16 10% AED6,954 AED0
First Floor 3 06-Feb-16 08-Feb-16 06-Feb-16 A 08-Feb-16 10% AED6,954 AED0
Gate House-MEP Conduits & Sleeves Inside The Slab 3 06-Feb-16 08-Feb-16 06-Feb-16 A 08-Feb-16 10% AED6,954 AED0
MEPMEP 75 21-Feb-16 18-May-16 21-Feb-16 18-May-16 0% AED626,676 AED0
Ground Floor 70 21-Feb-16 12-May-16 21-Feb-16 12-May-16 0% AED335,945 AED0
All Zones 70 21-Feb-16 12-May-16 21-Feb-16 12-May-16 0% AED335,945 AED0
MEP 1st Fix 5 21-Feb-16 25-Feb-16 21-Feb-16 25-Feb-16 0% AED35,852 AED0
Gate House-Civil clearance to Start 1st Fix 0 21-Feb-16 21-Feb-16 0% AED0 AED0
Gate House-DRAINAGE PIPES ( IN WALLS) 5 21-Feb-16 25-Feb-16 21-Feb-16 25-Feb-16 0% AED11,951 AED0
Gate House-WATER SUPPLY PIPES ( IN WALLS) 5 21-Feb-16 25-Feb-16 21-Feb-16 25-Feb-16 0% AED11,951 AED0
Gate House-SLEEVES,CONDUITS,GI BOX,DB BOX IN WALL 5 21-Feb-16 25-Feb-16 21-Feb-16 25-Feb-16 0% AED11,951 AED0
Gate House-MEP clearance to Start Plaster 0 25-Feb-16 25-Feb-16 0% AED0 AED0
MEP 2nd Fix 34 15-Mar-16 24-Apr-16 15-Mar-16 24-Apr-16 0% AED194,523 AED0
Gate House-DRAINAGE PIPES (HIGH L) 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-WATER SUPPLY PIPES \ WATER HEATERS (HIGH L) 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-GRAVITY TEST 4 27-Mar-16 30-Mar-16 27-Mar-16 30-Mar-16 0% AED9,561 AED0
Gate House-FIRE FIGHTING PIPES 8 19-Mar-16 27-Mar-16 19-Mar-16 27-Mar-16 0% AED12,252 AED0
Gate House-PRESSURE TESTING 4 27-Mar-16 30-Mar-16 27-Mar-16 30-Mar-16 0% AED4,780 AED0
Gate House-ACOUSTIC DRAINAGE PIPE INSULATION 4 29-Mar-16 02-Apr-16 29-Mar-16 02-Apr-16 0% AED9,561 AED0
Gate House-FIRE FIGHTING TESTING 4 27-Mar-16 30-Mar-16 27-Mar-16 30-Mar-16 0% AED9,561 AED0
Gate House-WIRING FOR LIGHTING WORKS 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-WIRING FOR POWER 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-WIRING FOR FIRE ALARM&LOW CURRENT SYSTEM 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-CABLE TRAY / TRUNKING 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED16,731 AED0
Gate House-STRUC&ELEC CABLING INCLUDING DRESSING 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-DUCTING WORK INCLUDING INSULATION 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-INSTALLATION OF FANS 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-FINAL DUCT CONNECTION TO FANS 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
Gate House-PRESSURE TEST&INSULATION 4 22-Mar-16 26-Mar-16 22-Mar-16 26-Mar-16 0% AED9,561 AED0
Gate House-MEP clearance to close Control & Guard Rooms ceilings 0 02-Apr-16 02-Apr-16 0% AED0 AED0
Gate House-Civil clearance to Start 2nd Fix 0 15-Mar-16 15-Mar-16 0% AED0 AED0
Gate House-MEP clearance to close corridors ceilings 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Gate House-CHILD WATER PIPES (HIGH L) 8 17-Mar-16 26-Mar-16 17-Mar-16 26-Mar-16 0% AED12,252 AED0
MEP Final Fix 15 24-Apr-16 12-May-16 24-Apr-16 12-May-16 0% AED105,570 AED0
Gate House-Civil Clearance to Start Final Fix 0 24-Apr-16 24-Apr-16 0% AED0 AED0
Gate House-SPRINKLERS, HOSE REEL&FIRE EXTINGUISHERS 4 25-Apr-16 28-Apr-16 25-Apr-16 28-Apr-16 0% AED9,561 AED0
Gate House-INSTALLATION OF DBS 4 25-Apr-16 28-Apr-16 25-Apr-16 28-Apr-16 0% AED9,561 AED0
Gate House-INSTALLATION OF PANELS / SMDBS 4 25-Apr-16 28-Apr-16 25-Apr-16 28-Apr-16 0% AED9,561 AED0
Gate House-INSTALLATION OF TELEPHONE SYSTEM 4 30-Apr-16 04-May-16 30-Apr-16 04-May-16 0% AED9,561 AED0
Gate House-INSTALLATION OF CCTV SYSTEM 4 30-Apr-16 04-May-16 30-Apr-16 04-May-16 0% AED9,561 AED0
2015 2016 2017
08-Feb-16, Skeleton
06-Feb-16, Sub Structure
06-Feb-16, All Zones
06-Feb-16, Concrete Works
Clearance for Gate House
Gate House-MEP Under Ground Services
Gate House-Grade Slab Rebar & MEP Services
08-Feb-16, Super Structure
08-Feb-16, All Zones
08-Feb-16, First Floor
Gate House-MEP Conduits & Sleeves Inside The Slab
18-May-16, MEP
12-May-16, Ground Floor
12-May-16, All Zones
25-Feb-16, MEP 1st Fix
Gate House-Civil clearance to Start 1st Fix
Gate House-DRAINAGE PIPES ( IN WALLS)
Gate House-WATER SUPPLY PIPES ( IN WALLS)
Gate House-SLEEVES,CONDUITS,GI BOX,D
Gate House-MEP clearance to Start Plaster
24-Apr-16, MEP 2nd Fix
Gate House-DRAINAGE PIPES (HIGH L)
Gate House-WATER SUPPLY PIPES \ WA
Gate House-GRAVITY TEST
Gate House-FIRE FIGHTING PIPES
Gate House-PRESSURE TESTING
Gate House-ACOUSTIC DRAINAGE PIP
Gate House-FIRE FIGHTING TESTING
Gate House-WIRING FOR LIGHTING WORKS
Gate House-WIRING FOR POWER
Gate House-WIRING FOR FIRE ALARM&
Gate House-CABLE TRAY / TRUNKING
Gate House-STRUC&ELEC CABLING IN
Gate House-DUCTING WORK INCLUDIN
Gate House-INSTALLATION OF FANS
Gate House-FINAL DUCT CONNECTION TO FANS
Gate House-PRESSURE TEST&INSULATION
Gate House-MEP clearance to close Con
Gate House-Civil clearance to Start 2nd Fix
Gate House-MEP clearance to close co
Gate House-CHILD WATER PIPES (HIGH L)
12-May-16, MEP Final Fix
Gate House-Civil Clearance to Start Final Fix
Gate House-SPRINKLERS, HOSE RE
Gate House-INSTALLATION OF DBS
Gate House-INSTALLATION OF PAN
Gate House-INSTALLATION OF TEL
Gate House-INSTALLATION OF CCT
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 33 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Gate House-TERMINATION & DRESSING OF DBS 4 30-Apr-16 04-May-16 30-Apr-16 04-May-16 0% AED9,561 AED0
Gate House-INSTALLATION OF FIRE ALARM PANEL & VOICE ALARM S 4 25-Apr-16 28-Apr-16 25-Apr-16 28-Apr-16 0% AED9,561 AED0
Gate House-INSTALLATION OF LIGHT FITTING & E.M LIGHT 4 30-Apr-16 04-May-16 30-Apr-16 04-May-16 0% AED9,561 AED0
Gate House-INSTALLATION OF WIRING ACCESSORIES 4 30-Apr-16 04-May-16 30-Apr-16 04-May-16 0% AED9,561 AED0
Gate House-INSTALLATION OF GRILLS&DIFFUSERS 4 25-Apr-16 28-Apr-16 25-Apr-16 28-Apr-16 0% AED9,561 AED0
Gate House-THERMOSTAT FIXING 2 30-Apr-16 01-May-16 30-Apr-16 01-May-16 0% AED4,780 AED0
Gate House-MEP Final Fix Clearance 0 10-May-16 10-May-16 0% AED0 AED0
Gate House-INSTALLATION OF GATE BARRIER SYSTEM 15 25-Apr-16 12-May-16 25-Apr-16 12-May-16 0% AED1,022 AED0
Gate House- Installation of Sanitary Wares 7 25-Apr-16 02-May-16 25-Apr-16 02-May-16 0% AED4,161 AED0
Roof Floor 46 26-Mar-16 18-May-16 26-Mar-16 18-May-16 0% AED210,953 AED0
All Zones 46 26-Mar-16 18-May-16 26-Mar-16 18-May-16 0% AED210,953 AED0
Civil clearance- Mechanical Works 0 02-Apr-16 02-Apr-16 0% AED0 AED0
Civil Clearance- Electrical Works 0 26-Mar-16 26-Mar-16 0% AED0 AED0
Mechanical 40 02-Apr-16 18-May-16 02-Apr-16 18-May-16 0% AED86,667 AED0
SECOND FIX 27 02-Apr-16 02-May-16 02-Apr-16 02-May-16 0% AED74,716 AED0
Gate House-PRESSURE TEST&INSULATION 4 28-Apr-16 02-May-16 28-Apr-16 02-May-16 0% AED9,561 AED0
Gate House-SUPPORTS FOR DUCTING WORK 8 02-Apr-16 10-Apr-16 02-Apr-16 10-Apr-16 0% AED12,252 AED0
Gate House-SUPPORTS FOR PIPING WORKS 8 07-Apr-16 16-Apr-16 07-Apr-16 16-Apr-16 0% AED12,252 AED0
Gate House-DUCTING WORK ON ROOF 10 17-Apr-16 27-Apr-16 17-Apr-16 27-Apr-16 0% AED10,163 AED0
Gate House-PIPING WORK ON ROOF 10 17-Apr-16 27-Apr-16 17-Apr-16 27-Apr-16 0% AED10,163 AED0
Gate House-INSTALLATION OF FANS AND CONNECTION 10 10-Apr-16 20-Apr-16 10-Apr-16 20-Apr-16 0% AED10,163 AED0
Gate House-INSTALLATION OF CU AND PACKAGE UNITS 10 05-Apr-16 16-Apr-16 05-Apr-16 16-Apr-16 0% AED10,163 AED0
FINAL FIX 5 14-May-16 18-May-16 14-May-16 18-May-16 0% AED11,951 AED0
Gate House-CLADDING WORKS FOR DUCTS&PIPING 5 14-May-16 18-May-16 14-May-16 18-May-16 0% AED11,951 AED0
Electrical 46 26-Mar-16 18-May-16 26-Mar-16 18-May-16 0% AED105,166 AED0
FIRST FIX 3 26-Mar-16 28-Mar-16 26-Mar-16 28-Mar-16 0% AED7,170 AED0
Gate House-SLEEVES,CONDUTES,GI BOX,DB BOX IN WALL 3 26-Mar-16 28-Mar-16 26-Mar-16 28-Mar-16 0% AED7,170 AED0
SECOND FIX 19 19-Apr-16 11-May-16 19-Apr-16 11-May-16 0% AED50,192 AED0
Gate House-WIRING FOR LIGHTING & POWER 7 19-Apr-16 26-Apr-16 19-Apr-16 26-Apr-16 0% AED16,731 AED0
Gate House-CABLE TRAY / TRUNKING 7 26-Apr-16 04-May-16 26-Apr-16 04-May-16 0% AED16,731 AED0
Gate House-CABLING INCLUDING DRESSING OF CABLES 7 04-May-16 11-May-16 04-May-16 11-May-16 0% AED16,731 AED0
FINAL FIX 6 12-May-16 18-May-16 12-May-16 18-May-16 0% AED47,803 AED0
Gate House-INSTILLATION OF PANELS / SMDBS /MCC 4 12-May-16 16-May-16 12-May-16 16-May-16 0% AED9,561 AED0
Gate House-TERMINATION & DRESSING OF DBS 4 15-May-16 18-May-16 15-May-16 18-May-16 0% AED9,561 AED0
Gate House-INSTALLATION OF WIRING ACCESSORIES 4 12-May-16 16-May-16 12-May-16 16-May-16 0% AED9,561 AED0
Gate House-INSTALLATION OF LIGHTING CONTROL SYSTEM 4 12-May-16 16-May-16 12-May-16 16-May-16 0% AED9,561 AED0
Gate House-INSTALL OF LIGHT FITTING & E.M LIGHT 4 12-May-16 16-May-16 12-May-16 16-May-16 0% AED9,561 AED0
Plumbing 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED19,121 AED0
SECOND FIX 8 16-Apr-16 24-Apr-16 16-Apr-16 24-Apr-16 0% AED19,121 AED0
Gate House-WATER SUPPLY & DRAINAGE PIPES ON ROOF 4 16-Apr-16 19-Apr-16 16-Apr-16 19-Apr-16 0% AED9,561 AED0
Gate House-PRESSURE TESTING 2 20-Apr-16 21-Apr-16 20-Apr-16 21-Apr-16 0% AED4,780 AED0
Gate House-BIB Taps / PIPE INSULATION 2 23-Apr-16 24-Apr-16 23-Apr-16 24-Apr-16 0% AED4,780 AED0
All Floors 24 31-Mar-16 27-Apr-16 31-Mar-16 27-Apr-16 0% AED79,777 AED0
All Zones 24 31-Mar-16 27-Apr-16 31-Mar-16 27-Apr-16 0% AED79,777 AED0
Civil clearance for Shaft Works 0 31-Mar-16 31-Mar-16 0% AED0 AED0
Mechanical Shafts 24 31-Mar-16 27-Apr-16 31-Mar-16 27-Apr-16 0% AED43,925 AED0
SECOND FIX 17 31-Mar-16 19-Apr-16 31-Mar-16 19-Apr-16 0% AED27,195 AED0
Gate House-DUCT RISERS IN SHAFTS 10 31-Mar-16 11-Apr-16 31-Mar-16 11-Apr-16 0% AED17,032 AED0
2015 2016 2017
Gate House-TERMINATION & DRES
Gate House-INSTALLATION OF FIRE
Gate House-INSTALLATION OF LIGH
Gate House-INSTALLATION OF WIR
Gate House-INSTALLATION OF GRIL
Gate House-THERMOSTAT FIXING
Gate House-MEP Final Fix Clearance
Gate House-INSTALLATION OF GA
Gate House- Installation of Sanitary Wares
18-May-16, Roof Floor
18-May-16, All Zones
Civil clearance- Mechanical Works
Civil Clearance- Electrical Works
18-May-16, Mechanical
02-May-16, SECOND FIX
Gate House-PRESSURE TEST&INSULATION
Gate House-SUPPORTS FOR DUCTING WORK
Gate House-SUPPORTS FOR PIPING WORKS
Gate House-DUCTING WORK ON ROOF
Gate House-PIPING WORK ON ROOF
Gate House-INSTALLATION OF FANS
Gate House-INSTALLATION OF CU A
18-May-16, FINAL FIX
Gate House-CLADDING WORKS F
18-May-16, Electrical
28-Mar-16, FIRST FIX
Gate House-SLEEVES,CONDUTES,GI B
11-May-16, SECOND FIX
Gate House-WIRING FOR LIGHTING
Gate House-CABLE TRAY / TRUNKING
Gate House-CABLING INCLUDING
18-May-16, FINAL FIX
Gate House-INSTILLATION OF PAN
Gate House-TERMINATION & DRE
Gate House-INSTALLATION OF WI
Gate House-INSTALLATION OF LI
Gate House-INSTALL OF LIGHT FI
24-Apr-16, Plumbing
24-Apr-16, SECOND FIX
Gate House-WATER SUPPLY & DRAIN
Gate House-PRESSURE TESTING
Gate House-BIB Taps / PIPE INSULATION
27-Apr-16, All Floors
27-Apr-16, All Zones
Civil clearance for Shaft Works
27-Apr-16, Mechanical Shafts
19-Apr-16, SECOND FIX
Gate House-DUCT RISERS IN SHAFTS
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 34 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Gate House-PIPING IN SHAFTS 10 09-Apr-16 19-Apr-16 09-Apr-16 19-Apr-16 0% AED10,163 AED0
FINAL FIX 7 20-Apr-16 27-Apr-16 20-Apr-16 27-Apr-16 0% AED16,731 AED0
Gate House-CLADDING WORK FOR DUCTS&PIPING 7 20-Apr-16 27-Apr-16 20-Apr-16 27-Apr-16 0% AED16,731 AED0
Electrical Shafts 15 31-Mar-16 17-Apr-16 31-Mar-16 17-Apr-16 0% AED23,901 AED0
SECOND FIX 15 31-Mar-16 17-Apr-16 31-Mar-16 17-Apr-16 0% AED23,901 AED0
Gate House-CABLE TRAY 5 31-Mar-16 05-Apr-16 31-Mar-16 05-Apr-16 0% AED11,951 AED0
Gate House-CABLE PULLING 5 12-Apr-16 17-Apr-16 12-Apr-16 17-Apr-16 0% AED11,951 AED0
Plumbing Shafts 5 31-Mar-16 05-Apr-16 31-Mar-16 05-Apr-16 0% AED11,951 AED0
SECOND FIX 5 31-Mar-16 05-Apr-16 31-Mar-16 05-Apr-16 0% AED11,951 AED0
Gate House-SHAFTS DRAINAGE & PLUMBING PIPES 5 31-Mar-16 05-Apr-16 31-Mar-16 05-Apr-16 0% AED11,951 AED0
Preliminary Testing & Pre-CommissioningPreliminary Testing & Pre-Commissioning 14 19-May-16 04-Jun-16 19-May-16 04-Jun-16 0% AED15,661 AED0
All Floors 14 19-May-16 04-Jun-16 19-May-16 04-Jun-16 0% AED15,661 AED0
All Zones 14 19-May-16 04-Jun-16 19-May-16 04-Jun-16 0% AED15,661 AED0
Gate House-Electrical System Preliminary Testing & Commissioning 14 19-May-16 04-Jun-16 19-May-16 04-Jun-16 0% AED5,220 AED0
Gate House-HVAC System Preliminary Testing & Commissioning 14 19-May-16 04-Jun-16 19-May-16 04-Jun-16 0% AED5,220 AED0
Gate House-Plumbing System Preliminary Testing & Commissioning 14 19-May-16 04-Jun-16 19-May-16 04-Jun-16 0% AED5,220 AED0
House ConnectionsHouse Connections 53 17-Mar-16 18-May-16 17-Mar-16 18-May-16 0% AED20,881 AED0
All Floors 53 17-Mar-16 18-May-16 17-Mar-16 18-May-16 0% AED20,881 AED0
All Zones 53 17-Mar-16 18-May-16 17-Mar-16 18-May-16 0% AED20,881 AED0
Gate House-Drainage House Connection 6 17-Mar-16 23-Mar-16 17-Mar-16 23-Mar-16 0% AED5,220 AED0
Gate House-Water Supply House Connection 7 25-Apr-16 02-May-16 25-Apr-16 02-May-16 0% AED5,220 AED0
Gate House-Low Current House Connection 7 26-Apr-16 04-May-16 26-Apr-16 04-May-16 0% AED5,220 AED0
Gate House-Electrical House Connection 7 11-May-16 18-May-16 11-May-16 18-May-16 0% AED5,220 AED0
External Works UnitExternal Works Unit 161 28-Sep-15 05-Apr-16 28-Sep-15 A 05-Apr-16 66.54% AED9,601,263 AED5,928,292
HelipadHelipad 27 05-Mar-16 05-Apr-16 05-Mar-16 05-Apr-16 0% AED20,861 AED0
MEP Works 27 05-Mar-16 05-Apr-16 05-Mar-16 05-Apr-16 0% AED20,861 AED0
Helipad-MEP Conduits & Sleeves 3 05-Mar-16 08-Mar-16 05-Mar-16 08-Mar-16 0% AED3,477 AED0
Clearance MEP Works - Helipad 0 05-Mar-16 05-Mar-16 0% AED0 AED0
All Zones 21 12-Mar-16 05-Apr-16 12-Mar-16 05-Apr-16 0% AED17,384 AED0
MEP 2nd Fix 9 12-Mar-16 22-Mar-16 12-Mar-16 22-Mar-16 0% AED3,477 AED0
Helipad-WIRING & CABLING WORKS 8 13-Mar-16 22-Mar-16 13-Mar-16 22-Mar-16 0% AED3,477 AED0
Helipad-Civil clearance to Start 2nd Fix 0 12-Mar-16 12-Mar-16 0% AED0 AED0
Helipad-MEP 2nd Fix Clearance 0 22-Mar-16 22-Mar-16 0% AED0 AED0
MEP Final Fix 12 22-Mar-16 05-Apr-16 22-Mar-16 05-Apr-16 0% AED13,907 AED0
Helipad-Clearance to Start Final Fix 0 22-Mar-16 22-Mar-16 0% AED0 AED0
Helipad-INSTALLATION OF PANELS / DBS 4 22-Mar-16 27-Mar-16 22-Mar-16 27-Mar-16 0% AED2,086 AED0
Helipad-TERMINATION & DRESSING OF DBS / Panels 4 27-Mar-16 31-Mar-16 27-Mar-16 31-Mar-16 0% AED8,344 AED0
Helipad-INSTALLATION OF LIGHT FITTING & LIGHTING CONTROL SYSTEM 4 31-Mar-16 05-Apr-16 31-Mar-16 05-Apr-16 0% AED3,477 AED0
Helipad-MEP Final Fix Clearance 0 05-Apr-16 05-Apr-16 0% AED0 AED0
External MEP WorksExternal MEP Works 105 28-Sep-15 31-Mar-16 28-Sep-15 A 31-Mar-16 66.69% AED9,580,402 AED5,928,292
EARTH WORK/ CIVIL CLEARANCE FOR EXTERNAL WORKS 30 28-Sep-15 28-Feb-16 28-Sep-15 A 28-Feb-16 90% AED1,172,969 AED991,113
EXTERNAL POWER "INCLUDING HV CONNECTION", STREET LIGHTENING NETWORK30 28-Dec-15 28-Mar-16 28-Dec-15 A 28-Mar-16 35% AED1,633,811 AED703,159
EXTERNAL STORM WATER \ SEWAGE NETWORK 30 25-Oct-15 16-Mar-16 25-Oct-15 A 16-Mar-16 82% AED1,833,194 AED1,307,278
EXTERNAL FIRE FIGHTING NETWORK 30 01-Nov-15 28-Mar-16 01-Nov-15 A 28-Mar-16 82% AED1,485,507 AED954,969
EXTERNAL LOW CURRENT NETWORK 30 28-Dec-15 31-Mar-16 28-Dec-15 A 31-Mar-16 40% AED1,887,598 AED812,384
EXTERNAL WATER SUPPLY / CHILLED WATER / IRRIGATION NETWORK 30 29-Sep-15 20-Mar-16 29-Sep-15 A 20-Mar-16 82% AED1,567,322 AED1,159,389
Commissioning & Close OutCommissioning & Close Out 72 02-Apr-16 02-Jul-16 02-Apr-16 02-Jul-16 0% AED3,453,003 AED0
AuthoritiesAuthorities 24 15-May-16 13-Jun-16 15-May-16 13-Jun-16 0% AED116,774 AED0
Telecommunications (Etisalat) 24 15-May-16 13-Jun-16 15-May-16 13-Jun-16 0% AED116,774 AED0
2015 2016 2017
Gate House-PIPING IN SHAFTS
27-Apr-16, FINAL FIX
Gate House-CLADDING WORK FOR
17-Apr-16, Electrical Shafts
17-Apr-16, SECOND FIX
Gate House-CABLE TRAY
Gate House-CABLE PULLING
05-Apr-16, Plumbing Shafts
05-Apr-16, SECOND FIX
Gate House-SHAFTS DRAINAGE & PLU
04-Jun-16, Preliminary Testing & P
04-Jun-16, All Floors
04-Jun-16, All Zones
Gate House-Electrical System Pre
Gate House-HVAC System Prelim
Gate House-Plumbing System Pre
18-May-16, House Connections
18-May-16, All Floors
18-May-16, All Zones
Gate House-Drainage House Connection
Gate House-Water Supply House Connection
Gate House-Low Current House Connection
Gate House-Electrical House Connection
05-Apr-16, External Works Unit
05-Apr-16, Helipad
05-Apr-16, MEP Works
Helipad-MEP Conduits & Sleeves
Clearance MEP Works - Helipad
05-Apr-16, All Zones
22-Mar-16, MEP 2nd Fix
Helipad-WIRING & CABLING WORKS
Helipad-Civil clearance to Start 2nd Fix
Helipad-MEP 2nd Fix Clearance
05-Apr-16, MEP Final Fix
Helipad-Clearance to Start Final Fix
Helipad-INSTALLATION OF PANELS / DBS
Helipad-TERMINATION & DRESSING OF
Helipad-INSTALLATION OF LIGHT FITT
Helipad-MEP Final Fix Clearance
31-Mar-16, External MEP Works
EARTH WORK/ CIVIL CLEARANCE FOR EX
EXTERNAL POWER "INCLUDING HV C
EXTERNAL STORM WATER \ SEWAGE NETWORK
EXTERNAL FIRE FIGHTING NETWORK
EXTERNAL LOW CURRENT NETWORK
EXTERNAL WATER SUPPLY / CHILLED W
02-Jul-16, Commissioning & Close Out
13-Jun-16, Authorities
13-Jun-16, Telecommunications (Etisalat)
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 35 of 36 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name OriginalDuration
BL Project Start
BL Project Finish
Start Finish Performance %Complete
Budgeted Total Cost Actual Cost
Apply For Reinstallation Inspection 6 15-May-16 21-May-16 15-May-16 21-May-16 0% AED24,042 AED0
Reinstallation Inspection & Comments 6 22-May-16 28-May-16 22-May-16 28-May-16 0% AED30,911 AED0
Attain Reinstallation Comments 6 29-May-16 04-Jun-16 29-May-16 04-Jun-16 0% AED30,911 AED0
Reinstallation Reinspection & Approval 6 05-Jun-16 13-Jun-16 05-Jun-16 13-Jun-16 0% AED30,911 AED0
Final Testing & Pre-CommissioningFinal Testing & Pre-Commissioning 54 23-Apr-16 02-Jul-16 23-Apr-16 02-Jul-16 0% AED3,061,467 AED0
Over All Testing & Commissioning 54 23-Apr-16 02-Jul-16 23-Apr-16 02-Jul-16 0% AED2,979,039 AED0
Over All Final Testing, Commissioning & Synchronization 4 26-Jun-16 02-Jul-16 26-Jun-16 02-Jul-16 0% AED691,258 AED0
Accommodation-Over All Final Testing & Commissioning 10 06-Jun-16 20-Jun-16 06-Jun-16 20-Jun-16 0% AED486,123 AED0
Administration-Over All Final Testing & Commissioning 10 06-Jun-16 20-Jun-16 06-Jun-16 20-Jun-16 0% AED596,252 AED0
Substation-Over All Final Testing & Commissioning 10 06-Jun-16 20-Jun-16 06-Jun-16 20-Jun-16 0% AED382,722 AED0
Service Yard-Over All Final Testing & Commissioning 10 09-Jun-16 25-Jun-16 09-Jun-16 25-Jun-16 0% AED168,204 AED0
Vehicle Washing Shed-Over All Final Testing & Commissioning 10 06-Jun-16 20-Jun-16 06-Jun-16 20-Jun-16 0% AED84,228 AED0
Maintenance Building-Over All Final Testing & Commissioning 10 06-Jun-16 20-Jun-16 06-Jun-16 20-Jun-16 0% AED209,831 AED0
Gate House-Over All Final Testing & Commissioning 10 06-Jun-16 20-Jun-16 06-Jun-16 20-Jun-16 0% AED142,600 AED0
Ammunition Building-Over All Final Testing & Commissioning 6 06-Jun-16 14-Jun-16 06-Jun-16 14-Jun-16 0% AED106,542 AED0
Helipad-Testing & Commissioning 10 23-Apr-16 05-May-16 23-Apr-16 05-May-16 0% AED111,278 AED0
Snagging & Desnagging 12 09-Jun-16 28-Jun-16 09-Jun-16 28-Jun-16 0% AED82,428 AED0
Snagging & De-Snagging 12 09-Jun-16 28-Jun-16 09-Jun-16 28-Jun-16 0% AED82,428 AED0
Handing Over DocumentationHanding Over Documentation 70 02-Apr-16 28-Jun-16 02-Apr-16 28-Jun-16 0% AED274,762 AED0
Project Close Out Documents 70 02-Apr-16 28-Jun-16 02-Apr-16 28-Jun-16 0% AED274,762 AED0
As Built Drawings 60 02-Apr-16 13-Jun-16 02-Apr-16 13-Jun-16 0% AED68,690 AED0
Operation & Maintaince Manulas 60 02-Apr-16 13-Jun-16 02-Apr-16 13-Jun-16 0% AED68,690 AED0
Warranties & Gurantees 60 02-Apr-16 13-Jun-16 02-Apr-16 13-Jun-16 0% AED68,690 AED0
Training & Key Handing Over 10 13-Jun-16 28-Jun-16 13-Jun-16 28-Jun-16 0% AED68,690 AED0
2015 2016 2017
Apply For Reinstallation Inspection
Reinstallation Inspection & Comments
Attain Reinstallation Comments
Reinstallation Reinspection & Approval
02-Jul-16, Final Testing & Pre-
02-Jul-16, Over All Testing & C
Over All Final Testing, Commis
Accommodation-Over All Final T
Administration-Over All Final Tes
Substation-Over All Final Testing
Service Yard-Over All Final Test
Vehicle Washing Shed-Over All F
Maintenance Building-Over All F
Gate House-Over All Final Testin
Ammunition Building-Over All Fin
Helipad-Testing & Commissioning
28-Jun-16, Snagging & Desnagging
Snagging & De-Snagging
28-Jun-16, Handing Over Documentation
28-Jun-16, Project Close Out Documents
As Built Drawings
Operation & Maintaince Manulas
Warranties & Gurantees
Training & Key Handing Over
Consrtruction of CICPA CAMPS -QUSHAWIRA MEP Works Client : Al Hons
Consultant : ECG
Main Contractor : ASGC
MEP Contractor : SEMCO
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 36 of 36 TASK filter: All Activities
© Oracle Corporation