christian hofstadler - calculation of construction costs for building projects - application of the...
TRANSCRIPT
-
1ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
CASE STUDY
Hofstadler
Univ.-Doz.Dipl.-Ing.Dr.techn.
Christian HofstadlerAssociate Professor
Institute of Construction Management and Economics
Graz University of Technology, Austria
-
2ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
CASE STUDY
Hofstadler
Construction time is of crucial importance when it comes to utilizing the
production factors in an effective and efficient way.
Construction periods that are too short usually result in higher cost, poorer quality
and a larger number of disputes.
This presentation sets out to demonstrate the calculation of construction time and
cost whilst considering key construction management parameters.
Beyond a simple, deterministic method, other options for calculation
are shown that rely on probability calculus.
The approaches described to determine construction time and cost are illustrated
by a building project example.
-
3ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Production Factors
Production Factors
Work
Material
Equipment
Elementary
Production Factors
Dispositive
Production Factors
Organisation
Direction
Planning
Monitoring
Control Circuit
Construction
Time/Cost
-
4ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Productivity as a Function of Time
Pro
du
ctiv
ity [%
]
Construction time [d]
100 %
Adequate
Construction time
No go
Hofstadler
-
5ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Duration: From the Rough Planning to Detailed Planning
Hofstadler
Construction Time/
Costs
Rough Planning Detailed Planning
Entire constructionComponent
Assembly
Component
Assembly per Floor
Components/
Production units
-
6ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Duration: From the Rough Planning to Detailed Planning
Accuracy
Processing effort
Certainty
+
_
+
_
+
_
Hofstadler
Construction Time/
Costs
Rough Planning Detailed Planning
Entire constructionComponent
Assembly
Component
Assembly per Floor
Components/
Production units
-
7ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation of Construction Time and Costs
Calculation
Construction Time/Costs
Calculation Mode 1 Calculation Mode 2 Calculation Mode 3
Deterministic ApproachSimplified Stochastic
Approach
Application of Monte
Carlo Method
Hofstadler
-
8ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation of Construction Time and Costs
Calculation
Construction Time/Costs
Calculation Mode 1 Calculation Mode 2 Calculation Mode 3
Deterministic ApproachSimplified Stochastic
Approach
Application of Monte
Carlo Method
Hofstadler
-
9ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation of Construction Time: Deterministic Approach
Hofstadler
-
10ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation Equation: Rough planning
Calculation of Construction Time for Reinforced Concrete Works
Hofstadler
Maximum number of workers [wh/hr].....................MAXRCWW ,
Average number of workers [wh/hr].....................ARCWW ,
Total duration of reinforced concrete works [d].....................TOTD
Duration of the starting period of reinforced concrete works [d].....................SPD
Duration of the main construction time of reinforced concrete works [d].....................MCT
D
Duration of the final stage of reinforced concrete works [d].....................FSD
-
11ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
%1001
,
,
,
RCWT
RCWA
RCWRCW
CBURCW
BU
TRC
WTW
QD
Calculation Equation: Rough planning
Calculation of Construction Time for Reinforced Concrete Works
MAXRCWRCWMINRCW DDD ,,
Hofstadler
-
12ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
%1001
,
,,,,,
,
RCWT
CWABDARWABDAFWA
RCWRCW
CBURCW
BU
RCRRRCFRRC
WTW
QD
Calculation Equation: Rough planning
Calculation of Construction Time for Reinforced Concrete Works
Hofstadler
MAXRCWRCWMINRCW DDD ,,
-
13ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
FWARC ,
RWARC ,
CWARC ,
Average labor consumption rate for
. formwork-related activities [wh/m]
. Average formwork ratio for the entire building [m/m]
. Average labor consumption rate for reinforcement works [wh/t]
. Average reinforcement ratio for the entire building [t/m]
. Average labor consumption rate for concrete works [wh/m]
BDAFR ,
BDARR ,
. Average daily working time [hr/d]RCWWT
. Average number of workers [wh/hr]RCWW
. Concrete quantity [m]CQ
. Duration of the reinforced concrete works incl. Buffer [d]BURCWD ,
Calculation Equation: Calculation of Construction Time
Hofstadler
%1001
,
,,,,,
,
RCWT
CWABDARWABDAFWA
RCWRCW
CBURCW
BU
RCRRRCFRRC
WTW
QD
RCWTBU , . Buffer for construction time [%]
-
14ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation of Cost of Production: Deterministic Approach
Hofstadler
-
15ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation Equation: Rough planning
Calculation of Cost of Production for Reinforced Concrete Works
Hofstadler
RCWEMAc ,,
. Average average wage for reinforced concrete works [/wh]RCWAWA ,
. Concrete quantity [m]CQ
. Duration of the reinforced concrete works incl. Buffer [d]BURCWC ,
Hofstadler
%1001
%1001
,
,,,,,
RCWCOHDRCWEMARCWARCWACBURCW
BUMUcWATCRQCP
Average total labor consumption rate for
. reinforced concrete works [wh/m]RCWATCR ,
. Mark-up for overhead costs [%]OHDMU
. Buffer for costs [%]RCWCBU ,
Average equipment and materials costs for
. reinforced concrete works [/m]
-
16ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation Equation: Rough planning
Calculation of Cost of Production for Reinforced Concrete Works
HofstadlerHofstadler
%1001
%1001
,
,,,,,
RCWCOHDRCWEMARCWARCWACBURCW
BUMUcWATCRQCP
MAXRCWRCWMINRCW CPCPCP ,,
-
17ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Average total labor consumption rate for
. reinforced concrete works [wh/m]RCWATCR ,
FWARC ,
RWARC ,
CWARC ,
Average labor consumption rate for
. formwork-related activities [wh/m]
. Average formwork ratio for the entire building [m/m]
. Average labor consumption rate for reinforcement works [wh/t]
. Average reinforcement ratio for the entire building [t/m]
. Average labor consumption rate for concrete works [wh/m]
BDAFR ,
BDARR ,
Hofstadler
CWABDARWABDAFWARCWA RCRRRCFRRCTCR ,,,,,,
Calculation Equation: Rough planning
-
18ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
RCWEMAc ,,
FWEMAc ,,
RWEMAc ,,
CWEMAc ,,
. Average formwork ratio for the entire building [m/m]
. Average reinforcement ratio for the entire building [t/m]
BDAFR ,
BDARR ,
Hofstadler
CWEMABDARWEMABDAFWEMARCWEMA cRRcFRcc ,,,,,,,,,,
Calculation Equation: Rough planning
Average equipment and materials costs for
. reinforced concrete works [/m]
Average equipment and materials costs for
. formwork works [/m]
Average equipment and materials costs for
. reinforcement works [/t]
Average equipment and materials costs for
. concrete works [/m]
-
19ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource: Hofstadler
Calculation of Construction Time: Application of Monte Carlo Method
-
20ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Influences on Production Rate
Labor productivityProduction
Rate
General construction
site conditions
Number of workers
Availability
Construction
method
Number of
equipment
General operating
conditions
Specific structural
conditions
Influences of the
construction method
Daily working time
Working time
scheme
Construction
method
Type of
construction projectLocation of the
construction project
Familiarization
Specific structure
conditions
General operating
conditions
General construction
site conditions
Practice
Influences of the
construction method
Work space
Staff qualification
Composition of the
working group
Disruptive
influences
External
Internal
Working time
regulations
Hofstadler
-
*RCFW FRBD RCRW RRBD RCCW+ * +
Selection of distribution functions and input of individual values
TRCRCW
Calculation with @RISK Monte Carlo Method
Presenting the Results as Probability Distribution
-
22ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
0102030405060708090100110120130140
DRCW= 40 d
DRCW= 45 d
DRCW= 50 d
DRCW= 55 d
DRCW= 60 d
DRCW= 65 d
DRCW= 70 d
DRCW= 75 d
DRCW= 80 d
DRCW= 85 d
DRCW= 90 d
DRCW= 95 d
DRCW= 100 d
DRCW= 105 d
DRCW= 110 d
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
9,000
10,000
5.00 5.25 5.50 5.75 6.00 6.25 6.50 6.75 7.00 7.25 7.50 7.75 8.00 8.25 8.50
TWH= 10,000 wh TWH= 12,500 wh TWH= 15,000 wh TWH= 17,500 whTWH= 20,000 wh TWH= 22,500 wh TWH= 25,000 wh TWH= 27,500 whTWH= 30,000 wh TWH= 32,500 wh TWH= 35,000 wh TWH= 37,500 whTWH= 40,000 wh TWH= 42,500 wh TWH= 45,000 wh TWH= 47,500 whTWH= 50,000 wh TWH= 52,500 wh TWH= 55,000 wh TWH= 57,500 wh
0.0000.5001.0001.5002.0002.5003.0003.5004.0004.5005.0005.5006.0006.5007.0007.5008.0008.5009.0009.50010.00010.50011.00011.50012.000
0102030405060708090100110120130140
DWT = 8 hr/d
DWT = 9 hr/d
DWT = 10 hr/d
DWT = 11 hr/d
DWT = 12 hr/d
DWT = 13 hr/d
DWT = 14 hr/d
DWT = 15 hr/d
DWT = 16 hr/d
0.0000.5001.0001.5002.0002.5003.0003.5004.0004.5005.0005.5006.0006.5007.0007.5008.0008.5009.0009.500
10.00010.50011.00011.50012.000
5.00 5.25 5.50 5.75 6.00 6.25 6.50 6.75 7.00 7.25 7.50 7.75 8.00 8.25 8.50
W = 10 wh/hr W = 15 wh/hr W = 20 wh/hr
W = 25 wh/hr W = 30 wh/hr W = 35 wh/hr
W = 40 wh/hr W = 45 wh/hr W = 50 wh/hr
W = 55 wh/hr W = 60 wh/hr W = 65 wh/hr
W = 70 wh/hr W = 75 wh/hr W = 80 wh/hr
Total labor productivity [wh/m]Daily output [m/d]
Ho
url
y o
utp
ut [m
/h
r]C
on
cre
te q
ua
nti
ty [m
]
ChristianHOFSTADLER
III
III IV
Interaction diagram for reinforced concrete works
Use within Interaction Diagrams
107 d
91 d
38,500 Std33,000 Std
Hofstadler
Total consumption rate [wh/m]
-
*RCFW FRBD RCRW RRBD RCCWWRCW WTRCW
DRCW, BU
+ * +
Selection of distribution functions and input of individual values
QC BUT,RCW
TRCRCW
PRRCW,ML
DRCW
Calculation with @RISK Monte Carlo Method
Presenting the Results as Probability Distribution
-
24ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource: Hofstadler
Calculation of Cost of Production: Application of Monte Carlo Method
-
*RCFW FRBD RCRW RRBD RCCW+ * +
Selection of distribution functions and input of individual values
*cEM,FW FRBD cEM,RW RRBD cEM,CW+ * +
cEM,RCW*TRCRCW * QCWARCW * QC
DCLC,RCW + DCEM,RCW
CPRCW,BU
DCRCW MUOHD+
CPRCW BURCW+
-
26ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Application
Hofstadler
-
27ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
High-Rise Building Project - Key Details
Hofstadler
Sectional view
-
28ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
High-Rise Building Project - Key Details
Hofstadler
Floor plan
-
29ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
[m] [%] [t] [%] [m] [%]1 2 3 4 5 6 7
Ground plate 225 0.46 431 23.28 3,080 24.39
Walls 5,553 11.26 103 5.56 739 5.85
Columns 3,598 7.30 89 4.81 270 2.14
Shafts 15,554 31.54 266 14.37 1,902 15.06
Slabs 24,386 49.45 962 51.97 6,638 52.56
49,316 100 1,851 100 12,629 100
ComponentsForming area
Reinforcement
quantityConcrete quantity
High-Rise Building Project - Key Details
Hofstadler
Office building: quantity determination
-
30ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Average labor consumption rate - formwork works 0.60 wh/m 0.65 wh/m 0.90 wh/m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Average labor consumption rate - reinforcement works 7.00 wh/t 8.00 wh/t 10.00 wh/t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Average labor consumption rate - concrete works 0.42 wh/m 0.45 wh/m 0.60 wh/m
Maximum number of workers 36.00 wh/hr 37.00 wh/hr 40.00 wh/hr
Proportion of the average number of workers 75.00 % 80.00 % 88.00 %
Daily working time 7.00 hr/d 8.50 hr/d 10.00 hr/d
Concrete Quanity 12,000 m 12,629 m 13,000 m
Buffer 7.50 % 10.00 % 13.00 %
MIN EXP MAX
High-Rise Building Project - Key Details
Input values to calculate the construction time
Hofstadler
Labor productivityProduction
Rate
General construction
site conditions
Number of workers
Availability
Construction
method
Number of
equipment
General operating
conditions
Specific structural
conditions
Influences of the
construction method
Daily working time
Working time
scheme
Construction
method
Type of
construction projectLocation of the
construction project
Familiarization
Specific structure
conditions
General operating
conditions
General construction
site conditions
Practice
Influences of the
construction method
Work space
Staff qualification
Composition of the
working group
Disruptive
influences
External
Internal
Working time
regulations
-
31ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
d
mwhmttwhmmmwh
dhrhrwh
mD BURCW 231
%100
%101
/45.0/15.0/8/9.3/65.0
/5.88.0/37
629,12,
Hofstadler
Calculation of Construction Time: Calculation Mode 1
%1001
,
,,,,,
,
RCWT
CWABDARWABDAFWA
RCWRCW
CBURCW
BU
RCRRRCFRRC
WTW
QD
Average labor consumption rate - formwork works 0.60 wh/m 0.65 wh/m 0.90 wh/m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Average labor consumption rate - reinforcement works 7.00 wh/t 8.00 wh/t 10.00 wh/t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Average labor consumption rate - concrete works 0.42 wh/m 0.45 wh/m 0.60 wh/m
Maximum number of workers 36.00 wh/hr 37.00 wh/hr 40.00 wh/hr
Proportion of the average number of workers 75.00 % 80.00 % 88.00 %
Daily working time 7.00 hr/d 8.50 hr/d 10.00 hr/d
Concrete Quanity 12,000 m 12,629 m 13,000 m
Buffer 7.50 % 10.00 % 13.00 %
MIN EXP MAX
-
32ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Pro
duct
ivit
y [
%]
Construction time [d]
100 %
Adequate
Construction time
No go
Calculation of Construction Time: Calculation Mode 1
Hofstadler
231d
%1001
,
,,,,,
,
RCWT
CWABDARWABDAFWA
RCWRCW
CBURCW
BU
RCRRRCFRRC
WTW
QD
-
33ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
The values from this table are used for the input variables to calculate total labour
consumption rate, daily production rate and duration (weighted triangular
distribution).
Calculation of Construction Time: Calculation Mode 3
Hofstadler
Average labor consumption rate - formwork works 0.60 wh/m 0.65 wh/m 0.90 wh/m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Average labor consumption rate - reinforcement works 7.00 wh/t 8.00 wh/t 10.00 wh/t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Average labor consumption rate - concrete works 0.42 wh/m 0.45 wh/m 0.60 wh/m
Maximum number of workers 36.00 wh/hr 37.00 wh/hr 40.00 wh/hr
Proportion of the average number of workers 75.00 % 80.00 % 88.00 %
Daily working time 7.00 hr/d 8.50 hr/d 10.00 hr/d
Concrete Quanity 12,000 m 12,629 m 13,000 m
Buffer 7.50 % 10.00 % 13.00 %
MIN EXP MAX
-
34ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
CT
1 =
20
2 d
5 %
CT
2 =
28
6 d
95 %
@RISK, Hofstadler
Calculation of Construction Time: Calculation Mode 3
Monte-Carlo Simulation Results: Duration (incl. Buffer)
-
35ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Change of Distribution Functions
?
Consequences
Isosceles
Triangular Distribution
Weighted
Triangular Distribution
Uniform Distribution Beta Distribution
Hofstadler
-
36ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Change of Distribution Functions
Hofstadler
0.000
0.002
0.004
0.006
0.008
0.010
0.012
0.014
0.016
0.018
150 200 250 300 350 400
Construction Time incl. Buffer [d]
Simulation 1 IsoscelesTriangular Distribution
Simulation 2 Weighted Triangular Distribution
Simulation 3 Uniform Distribution
Simulation 4 Beta Distribution
-
37ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Pro
duct
ivit
y [
%]
Construction time [d]
100 %
Adequate
Construction time
No go
Productivity and Construction Time
Hofstadler
-
38ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Equipment and materials costs - formwork 5.00 /m 6.00 /m 8.00 /m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Equipment and materials costs - reinforcement 400.00 /t 500.00 /t 600.00 /t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Equipment and materials costs - concrete 80.00 /m 90.00 /m 95.00 /m
Average wage 27.00 /wh 30.00 /wh 31.00 /wh
Mark-up for overheads 10.00 % 14.00 % 17.00 %
Buffer 5.00 % 10.00 % 15.00 %
MIN EXP MAX
High-Rise Building Project - Key Details
Input values to calculate the construction time
Hofstadler
Labor productivityProduction
Rate
General construction
site conditions
Number of workers
Availability
Construction
method
Number of
equipment
General operating
conditions
Specific structural
conditions
Influences of the
construction method
Daily working time
Working time
scheme
Construction
method
Type of
construction projectLocation of the
construction project
Familiarization
Specific structure
conditions
General operating
conditions
General construction
site conditions
Practice
Influences of the
construction method
Work space
Staff qualification
Composition of the
working group
Disruptive
influences
External
Internal
Working time
regulations
-
39ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource: Hofstadler
Calculation of the Cost of Production: Calculation Mode 1
Equipment and materials costs - formwork 5.00 /m 6.00 /m 8.00 /m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Equipment and materials costs - reinforcement 400.00 /t 500.00 /t 600.00 /t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Equipment and materials costs - concrete 80.00 /m 90.00 /m 95.00 /m
Average wage 27.00 /wh 30.00 /wh 31.00 /wh
Mark-up for overheads 10.00 % 14.00 % 17.00 %
Buffer 5.00 % 10.00 % 15.00 %
MIN EXP MAX
%1001
%1001
,
,,,,,
RCWCOHDRCWEMARCWARCWACBURCW
BUMUcWATCRQCP
%1001
%1001
,
,,,,,
RCWCOHDRCWEMARCWARCWACBURCW
BUMUcWATCRQCP
-
40ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource: Hofstadler
Calculation of the Cost of Production: Calculation Mode 1
Equipment and materials costs - formwork 5.00 /m 6.00 /m 8.00 /m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Equipment and materials costs - reinforcement 400.00 /t 500.00 /t 600.00 /t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Equipment and materials costs - concrete 80.00 /m 90.00 /m 95.00 /m
Average wage 27.00 /wh 30.00 /wh 31.00 /wh
Mark-up for overheads 10.00 % 14.00 % 17.00 %
Buffer 5.00 % 10.00 % 15.00 %
MIN EXP MAX
CWABDARWABDAFWARCWA RCRRRCFRRCTCR ,,,,,,
Average labor consumption rate - formwork works 0.60 wh/m 0.65 wh/m 0.90 wh/m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Average labor consumption rate - reinforcement works 7.00 wh/t 8.00 wh/t 10.00 wh/t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Average labor consumption rate - concrete works 0.42 wh/m 0.45 wh/m 0.60 wh/m
Maximum number of workers 36.00 wh/hr 37.00 wh/hr 40.00 wh/hr
Proportion of the average number of workers 75.00 % 80.00 % 88.00 %
Daily working time 7.00 hr/d 8.50 hr/d 10.00 hr/d
Concrete Quanity 12,000 m 12,629 m 13,000 m
Buffer 7.50 % 10.00 % 13.00 %
MIN EXP MAX
/19.4/45.0/15.0/00.8/90.3/65.0, mwhmwhmttwhmmmwhTCR RCWA
Equipment and materials costs - formwork 5.00 /m 6.00 /m 8.00 /m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Equipment and materials costs - reinforcement 400.00 /t 500.00 /t 600.00 /t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Equipment and materials costs - concrete 80.00 /m 90.00 /m 95.00 /m
Average wage 27.00 /wh 30.00 /wh 31.00 /wh
Mark-up for overheads 10.00 % 14.00 % 17.00 %
Buffer 5.00 % 10.00 % 15.00 %
MIN EXP MAX
CWEMABDARWEMABDAFWEMARCWEMA cRRcFRcc ,,,,,,,,,,
/40.188/00.90/15.0/00.500/90.3/00.6,, mmmttmmmc RCWEMA
%1001
%1001
,
,,,,,
RCWCOHDRCWEMARCWARCWACBURCW
BUMUcWATCRQCP
-
41ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource: Hofstadler
Calculation of the Cost of Production: Calculation Mode 1
Equipment and materials costs - formwork 5.00 /m 6.00 /m 8.00 /m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Equipment and materials costs - reinforcement 400.00 /t 500.00 /t 600.00 /t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Equipment and materials costs - concrete 80.00 /m 90.00 /m 95.00 /m
Average wage 27.00 /wh 30.00 /wh 31.00 /wh
Mark-up for overheads 10.00 % 14.00 % 17.00 %
Buffer 5.00 % 10.00 % 15.00 %
MIN EXP MAX
%1001
%1001
,
,,,,,
RCWCOHDRCWEMARCWARCWACBURCW
BUMUcWATCRQCP
328,974,4%100
%101
%100
%141/40.188/30/19.4629,12, mwhmwhmCP BURCW
-
42ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
The values from this table are used for the input variables to calculate cost of
production (weighted triangular distribution).
Calculation of the Cost of Production: Calculation Mode 3
Hofstadler
Equipment and materials costs - formwork 5.00 /m 6.00 /m 8.00 /m
Average formwork ratio for the entire building 3.60 m/m 3.90 m/m 4.00 m/m
Equipment and materials costs - reinforcement 400.00 /t 500.00 /t 600.00 /t
Average reinforcement ratio for the entire building 140.00 kg/m 150.00 kg/m 160.00 kg/m
Equipment and materials costs - concrete 80.00 /m 90.00 /m 95.00 /m
Average wage 27.00 /wh 30.00 /wh 31.00 /wh
Mark-up for overheads 10.00 % 14.00 % 17.00 %
Buffer 5.00 % 10.00 % 15.00 %
MIN EXP MAX
-
43ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Calculation of the Cost of Production: Calculation Mode 3
Monte-Carlo Simulation Results: Costs (incl. Buffer)
@RISK, Hofstadler
CP
1 =
4,6
4
5 %
CP
2 =
5,4
0
95 %
-
44ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Change of Distribution Functions
?
Consequences
Isosceles
Triangular Distribution
Weighted
Triangular Distribution
Uniform Distribution Beta Distribution
Hofstadler
-
45ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Change of Distribution Functions
Hofstadler
0.0000000
0.0000002
0.0000004
0.0000006
0.0000008
0.0000010
0.0000012
0.0000014
0.0000016
0.0000018
0.0000020
4,000,000 4,500,000 5,000,000 5,500,000 6,000,000 6,500,000
Cost of Production incl. Buffer []
Simulation 1 IsoscelesTriangular Distribution
Simulation 2 Weighted Triangular Distribution
Simulation 3 Uniform Distribution
Simulation 4 Beta Distribution
-
46ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Construction Time and Construction Costs
The specification of a reasonable construction time makes a substantial
contribution towards the economical use of elementary and discretionary
production factors, or at least creates the preconditions to do so. Workers,
equipment and materials can be used cost-efficiently.
A realistic construction time can be calculated once construction management
boundary conditions have been considered.
Hofstadler
Pro
duct
ivit
y [
%]
Construction time [d]
100 %
Adequate
Construction time
No go
-
47ChristianHOFSTADLER2010 Construction Management
Analysis of Situation
Objective
Calculation Mode 1:
Deterministic
Approach
Calculation Mode 3:
Monte Carlo Method
Application:
High-Rise Building
Conclusion
Palisade Risk Conference in LondonSource:
Many Thanks!
Hofstadler