Christelle Roy - Subatech 1
EMCal – FranceEMCal – France
StatusStatusCERN-020707CERN-020707
Since the Scientific Since the Scientific CouncilCouncil
![Page 2: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/2.jpg)
EMCal designdesign participation
Mechanics :Mechanics : Mechanical architecture of StripModules and SuperModules : completedcompleted SuperModules Crates : completedcompleted (pict.) StrongBacks : in progressin progress Interfaces SuperModules – CalFrame (rails + crates) : completedcompleted Insertion Tooling : completedcompleted StripModules handling and tooling : completedcompleted Electronics/mechanics interfaces : completedcompleted
Electronics :Electronics : T-cards + IPCB + GTL bus : in progressin progress
Request from Electronics/Daq pool of Subatech
![Page 3: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/3.jpg)
SuperModule Crate
As designed
As machined
![Page 4: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/4.jpg)
EMCal realizationrealization participation
Mechanics :Mechanics : SuperModules – CalFrame interfaces (rails and crates) : completedcompleted StrongBacks manufacturer consulting : in progressin progress Insertion tooling : order ready to be sentorder ready to be sent
Installation of the rails on the CalFrame : completed completed …last week Load test
Writing of EMCal 3D-Model : completedcompleted + constant upgrade
…coming soon… Tests at CERN in October : 4/5 persons available Module assembly (288) StripModules assembly (24)
![Page 5: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/5.jpg)
Calframe : Preparation of load test
Load test finished week 22, deflections conform to FEA calculations
![Page 6: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/6.jpg)
![Page 7: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/7.jpg)
CalFrame
Installation of cables trays in SXL2 (on the way)
![Page 8: Christelle Roy - Subatech 1 EMCal – France StatusCERN-020707 Since the Scientific Council](https://reader036.vdocuments.mx/reader036/viewer/2022062410/56649d7a5503460f94a5e0f4/html5/thumbnails/8.jpg)
LPSC activities
1/ Supermodule assembly (see J.F. Muraz's talk) - Hall removal - Assembly tools
2/ EMCal Global trigger (see O. Bourrion's talk) - STU design - Test TRU/STU link
3/ Simulation for cosmics calibration (see C. Furget's talk)