chp in hospitals, nhs and facilities management conference, london 2013

19

Upload: toni-pedder

Post on 26-Jun-2015

575 views

Category:

Business


2 download

DESCRIPTION

A presentation on the utilisation of gas engines for combined heat and power (CHP) on hospitals. This presentation provides an outline of the technology, along with diagrams of cost and carbon emission benefits.

TRANSCRIPT

Page 1: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 2: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 3: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Generation in Clarke Territories – 2.8GWe

Page 4: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 5: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 6: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 7: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Savings in primary energy usage

Reduced transportation and distribution losses across the network

Attractive life-cycle savings

Resilience of operation

Quick return on investment

Significant reduction in CO2 emissions

Overall efficiencies can exceed 90%

Flexible solutions to meet various applications

Finance packages available

Tax relief from ECA’s and CCL

Page 8: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Greater Savings

Greater Running Time

Sensitive Analysis

Safe Option

Oversized?

Jan Dec

Page 9: CHP in hospitals, NHS and Facilities Management Conference, London 2013

1.80 kWh loss4.05 kWh

1.00 kWh electricity

1.25 kWh heat

Grid Generation

Boiler

1.47 kWh

2.58 kWh

2.5 kWh

Primary Energy Supply 1.00 kWh electricity

0.25 kWh losses

1.25 kWh heat

CHP engine

0.520kg CO2

0.270 kg CO2

0.790 kg CO2

0.460 kg CO2

42% CO2 reduction

38% Primary Energy Savings

Page 10: CHP in hospitals, NHS and Facilities Management Conference, London 2013

2.08 kWh loss4.33 kWh

1.00 kWh electricity @ 8.42p/kWh

1.25 kWh heat

Grid Generation

Boiler1.47 kWh gas @ 2.40p/kWh

2.86 kWh

2.5 kWh @ 2.31p/kWh

Primary Energy Supply 1.00 kWh electricity

0.25 kWh losses

1.25 kWh heat

CHP engine

8.42p

3.53p

11.95p

5.78p

45% cost reduction

Maintenance @ 0.84p/kWh

6.62p

Page 11: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 12: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Site Commission date Config. Engine No. of units

Total MWe

InstalledPower type

Freemans Hospital Nov-97 JMS 612 2 3.0 Cogen. / CHP (Hot water)North Tyne Hospital Mar-99 JMS 612 1 1.0 Cogen. / CHP (Hot water)

Western General Hospital Sep-99 JMS 320 1 1.0 Cogen. / CHP (Hot water)Royal Victoria Hosptial Nov-01 JMS 616 2 4.0 Cogen. / CHP (Hot water)

Hartlepool Hospital Oct-03 JMS 420 1 1.4 Cogen. / CHP (Hot water)Lincoln Hospital Dec-03 JMS 420 1 1.4 Cogen. / CHP (Steam)Christie Hospital Nov-04 JMS 420 1 1.4 Cogen. / CHP (Hot water)

Broadgreen Hospital May-05 JMS 616 1 2.2 Cogen. / CHP (Hot water & Steam)

Ormskirk Hospital Jan-06 JMS 320 1 1.1 Cogen. / CHP (Hot water)Kingston Hospital Nov-07 JMS 420 1 1.4 Cogen. / CHP (Hot water)

Portsmouth Hospital Feb-08 JMS 612 2 3.3 Cogen. / CHP (Hot water)Freemans Hospital Jul-08 JMS 420 1 1.4 Cogen. / CHP (Hot water)

University Hospital Wales Jan-09 JMS 616 2 4.4 Cogen. / CHP (Hot water & Steam)

Pilgrim Hospital May-09 JMC 312 1 0.6 Cogen. / CHP (Hot water)Guys Hospital Jun-09 JMS 620 1 3.0 Cogen. / CHP (Hot water)

St Thomas Hospital Jul-09 JMS 620 1 3.0 Cogen. / CHP (Hot water & Steam)

Royal Preston Hospital Dec-09 JMS 612 1 1.8 Cogen. / CHP (Hot water)Queen's Hospital Jan-10 JMS 312 1 0.5 Cogen. / CHP (Hot water)

Kings Cross College Hospital Jan-10 JMS 616 1 2.4 Cogen. / CHP (Hot water)Kings Cross College Hospital Jan-10 JMS 612 1 1.8 Cogen. / CHP (Hot water)Great Ormond Street Hospital Aug-11 JGMC 420 2 1.4 Cogen. / CHP (Hot water)

Musgrove Hospital Nov-12 JMS 208 1 0.3 Cogen. / CHP (Hot water)Freemans Hospital On Order JMS 420 2 3.0 Cogen. / CHP (Hot water)

Barnsley Hospital Pre-Commissioning JMS 416 1 1.1 Cogen. / CHP (Steam)

Page 13: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Client: Guys’ & Saint Thomas’ NHS Hospital TrustsCommissioning: May 2009

2 x J6206MWe & 5.5MWth

<3 Year Payback!>£1.5m energy cost saving!

Page 14: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Client: NG BaileyCommissioning: Aug 2011

1 x J4201.4MWe & 1.4MWth

A particularly difficult install!Container on the roof!

Page 15: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Client: DalkiaCommissioning: May 2005

1 x J6162.2MWe & 2.3MWth

£70m redevelopment to improve services including CHP!

Page 16: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Client: DalkiaCommissioning: Nov 1997 & Jul 2008

2 x J612 & 1 x J420 4.4MWe & 4MWth

2 replacement sets on order!

Page 17: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Client: CarillionCommissioning: Feb 2008

2 x J6123.3MWe & 2.7MWth

1.2MWth as hot water!

1.5MWth as steam!

Page 18: CHP in hospitals, NHS and Facilities Management Conference, London 2013
Page 19: CHP in hospitals, NHS and Facilities Management Conference, London 2013

Haydn Rees+44 151 546 [email protected]