China's Regulatory Practice On New Reactors Transition To Operation
National Nuclear Safety Administration, P.R.China
Mar. 14, 2019
2
1
Regulatory Approach on New Reactor Commissioning2
3
NPPs in the Mainland of China
Contents
2
Regulatory Approach on Transition to Operation
3
1.1 Overview of NPPs in the Mainland of China
吉林
黑龙江
Hongyanhe
Haiyang
Shidaowan
Tianwan
Qinshan
Qinshan Phase IIQinshan Phase IIISanmenNingde
Fuqing
Dayabay
Lingao
Taishan
Yangjiang
In Commercial Operation(45)
Under Construction (11)
陕西陕西
吉林
黑龙江
新疆
西藏
青海
甘肃 内蒙古
四川
云南
贵州
山西
重庆湖北
湖南
广西 广东
江西
安徽
河南
山东
河北
北京
辽宁
江苏
浙江
福建
台湾
海南
上海
天津
宁夏
Fang Cheng GangChang Jiang 3
4
1.1 Overview of NPPs in Mainland of China
4
Commercial Operation
45 units,45898 Gross Electrical Capacity (MW)
• 1 CNP300 unit• 6 CNP600 units• 4 VVER units• 2 CANDU units• 27 M310/M310+ units• 4 AP1000 units• 1 ERP unit
Construction Commissioning
11 units, 12181 Gross Electrical Capacity (MW)
• 5 M310+ units• 1 EPR units• 4 HPR-1000 units• 1 HTGR unit
5
1.2 NPP License issuance in 2018
5
• Operation License
Units Reactor type Date of issuance
Hongyanhe 1&2 M310+ Feb 5,2018
Yangjiang 1&2 M310+ Feb 22,2018
Fangjiashan 1&2 M310+ Feb 22,2018
6
1.2 NPP License issuance in 2018
6
• First fuel loading approval
Units Reactor type Date of issuance Status
Taishan 1 EPR Apr 9,2018 Commercial operation
Yangjiang 5 M310+ Apr 17,2018 Commercial operation
Sanmen 1&2 AP1000Apr 27,2018Jul 4,2018
Commercial operation
Haiyang 1&2 AP1000Jun 21,2018Aug 7, 2018
Commercial operationCommercial operation in Jan. 2019
Tianwan 4 VVER Aug 23, 2018 Commercial operation
7
7
Year20092010
2016 20182017
2017-12-19Start of Unit 2 CI cold
flushing
Unit 1
2009-10-26FCD
2016-1-27CFT completed
2010-4-15FCD
2017-08-5HFT completed
1.3 New Reactor Status―Taishan Projects (EPR Type)
Unit 2
2018-4-10First Fuel Load
(FFL)
2018-6-6Initial Criticality
2018-12-13End of Performance
Test
2018-7-15CFT finish
2019-1-25HFT finish
2019-3-31End of
Performance Test
8
8
Year2009
2010
2016 20182017
2017-9-17CFT
completed
2018-1-31HFT completed
Unit 1
2009-4-19FCD
2016-5-26CFT completed
2017-6-30HFT completed
2018-4-29FFL completed
2009-12-15FCD
2018-6-20Initial Criticality
1.4 New Reactor Status―Sanmen Projects (AP1000 Type)
Unit 22018-7-8
FFL completed
2018-9-21End of Performance
Test
2018-8-17Initial Criticality
2018-11-5End of Performance
Test
9
9
Year2009
2010
2016
2018
2017-12-27CFT completed
2018-5-26HFT completed
Unit 1
2009-9-24FCD
2016-7-2CFT completed
2017-7-12HFT completed
2018-6-25FFL completed
2010-6-20FCD
2018-8-8Initial Criticality
1.5 New Reactor Status―Haiyang Projects (AP1000 Type)
Unit 2
2018-11-10End of Performance
Test
2018-9-29Initial Criticality
2018-8-11FFL completed
2019-1-20End of Performance
Test
2019
2017
10
1
Regulatory Approach on New Reactor Commissioning2
3
NPPs in the Mainland of China
Contents
10
Regulatory Approach on Transition to Operation
11
2.1 Nuclear Safety Laws and Regulations System
11
2 Laws
7 Decrees
30 DepartmentRules
93 Regulatory Guides
• 《 Nuclear Safety Act 》came into force on 1st
January 2018.
12
2.2 Licensing review before first fuel loading
13 documents including:• FSAR/Final Safety Analysis Report,• Environmental Impact Report,• Commissioning Program, • In-service Inspection Program,• Maintenance Program,• Quality Assurance Program (commissioning stage) ,• Commissioning Report before Fuel Loading,• and so on…
12
13
13
-National Nuclear Safety Administration (NNSA HQ)- 6 Regional Offices-Technical Support (TSO)-Expert Committee---------technical support
inspecting
2.3 Regulation
NNSA(HQ)
Regional Office
NPP
TSOExpert Committee
2.3.1 Organization
14
14
Previous (Reactor Status)
• General Division
• Division I (Operation)
• Division II (Under Construction)
• Division III(New Reactors)
• Reactor Division
Now (Regional)
• General Division
• Division I (Southern)
• Division II (South‐East)
• Division III (North‐East)
• Reactor Division
• Experience Feedback Division
Organization of Nuclear Power Department
15
2.3.2 Inspection of EPR/AP1000 Commissioning (1)NNSA approved the Commissioning Program of Taishan(EPR) ,Sanmen and Haiyang (AP1000) Unit 1&2, and the subsequent revisions.
(2)NNSA issued Commissioning Inspection Program of Taishan, Sanmenand Haiyang Unit 1&2 in 2016.
15
16
2.3.2 Inspection of EPR/AP1000 Commissioning (3)Joint team consists of inspectors and technical staff were set up to inspect selected significant tests, including First Of A Kind Tests.
(4)NNSA and Regional Offices (SRO and ERO) developed commissioning test inspection procedures for all selected tests.
16
17
2.3.2 Inspection of EPR/AP1000 Commissioning (5)International regulators were invited to observe commissioning inspection and share regulatory experience.
(6)Extensive international cooperation facilitated common position on key issues and regulation consistency.
17
18
2.4 Commissioning Inspection Activities Before the FFL NNSA finished 2 control points , including:
• Cold hydrostatic test for Reactor Coolant System• First fuel loading NNSA witnessed 56 commissioning tests for EPR, 47 tests for AP1000.
18
19
2.5 Key steps before issuing the first fuel loading permit
All remaining questions found during the review must be closed before licensing, if not, a viable action plan must be provided.
All commissioning items in the Commissioning Program (approved by regulatory authority) must be completed, acceptance criteria must be met.
Non-conformance or unexpected results during commissioning must be closed.
After the above requirements are met, the results of the review will be submitted to expert committee for consultation, after which the licensee shall obtain the permit for the first fuel loading.
19
20
2.6 Inspection Activities After the FFL
20
4 control point inspections, including:• Initial criticality• Before leaving 5% rated power or Before
connection to the grid(AP1000 or EPR)• Before leaving 50% or 60% rated power
(AP1000 or EPR)• Before leaving 90% rated power Dozens of commissioning tests to witness
or review test reports.
21
1
Regulatory Approach on New Reactor Commissioning2
3
NPPs in the Mainland of China
Contents
21
Regulatory Approach on Transition to Operation
22
3.1 Licensing review for operation permit after one year
• Revised FSAR • Commissioning Report after Fuel Loading• Quality Assurance Program (operation stage)
22
If the documents are acceptable after reviewing, NNSA will issue Operation License.
23
3.2 Changes After Nuclear Safety Act Came Into Force
To improve NNSA’s efficiency and optimize regulatory resource allocation , and streamline the licensing process
NNSA combined the First Fuel Loading Permit and the Operation Permit into the Operation License.
Operation Licensee shall be obtained Operation License before the first fuel loading.
23
24
Optimization of the division of responsibilities between the NNSA headquarters and regional offices:
• Regional offices: onsite inspection; hold points review and release such as refueling.
• Headquarters: licensing modifications, nuclear and radiological events, major and common issues.
Development of regulatory tools, optimization of the Inspection Program and procedures such as the revision of the Commissioning Inspection Program.
24
25
3.3 Develop Generic Inspection ProgramsNNSA have integrated all project Inspection Programs and develop 3 Generic Inspection Programs (including construction, commissioning and operation).
25
26