![Page 1: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/1.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved
2020 IAEA General Conference, Side Event
Fukushima Daiichi Decontamination and Decommissioning
-From 3.11 toward the future-
September 21, 2020
Akira ONO Chief Decommissioning Officer
President of Fukushima Daiichi Decontamination and Decommissioning Engineering Company,
Tokyo Electric Power Company Holdings, Inc.
![Page 2: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/2.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved1
The New Norm at Fukushima Daiichi
No face-to-face sittingat Cafeteria
Thermographic measurementat entrance
All employees wearing masks
![Page 3: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/3.jpg)
T H E F U K U S H I M A F O R U M I V • M A R C H 1 5 - 1 8 , 2 0 1 6 • T O K Y O , J A P A N
1. Fuel Removal from Spent Fuel Pools
2. Toward Fuel Debris Retrieval
3. Striking a Balance betweenReconstruction & Decommissioning
Agenda
![Page 4: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/4.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved
Dismantlement of Exhaust Stack for Units 1&2
▼Ground Level+120m
Before Dismantlement (July 2019)
▼Ground Level+59m
After Dismantlement (May 2020)
3
![Page 5: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/5.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved
1. Fuel Removal from Spent Fuel Pools
![Page 6: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/6.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved 5
Removal of rubble & Decontamination etc.
Installation of fuel removal facility Fuel removal
Units 1 & 2 Unit 3 Unit 4
Storage & Transportation
Unit 1 Unit 2 Unit 3
Jun. 2011 Sep. 2011Sep. 2011
Feb. 2019Dec. 2019 Aug. 2019
Overview of tasks toward fuel removal
Frontchamber
Feb. 2019
Removal tostart in
FY2027 to 2028
Removal tostart in
FY2024 to 2026Removal started
in Apr. 2019
![Page 7: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/7.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved 6
Method of fuel removal at Units 1 & 2
Crane
As the return of local residents and reconstruction efforts make progress, we put premium on their safety and peace of mind by preventing radioactive dust from scattering.
As the return of local residents and reconstruction efforts make progress, we put premium on their safety and peace of mind by preventing radioactive dust from scattering.
<Unit 1>
Reactor Building
Front Chamber
Gantry
Fuel Handling Machine
<Unit 2>
Cover
![Page 8: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/8.jpg)
T H E F U K U S H I M A F O R U M I V • M A R C H 1 5 - 1 8 , 2 0 1 6 • T O K Y O , J A P A N
2. Toward Fuel Debris Retrieval
IRID has contributed to some work shown here
![Page 9: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/9.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved
Assumed distribution of fuel debris
8
Mar. 2017 Jul. 2017
Feb. 2017Jan. 2018
Unit 2 Unit 2Unit 1構台
Feb. 2019
Jan. 2018 Feb. 2019
PCV
RPV Core
Unit 3
Robotic explorationAnalysis of
accident progression
Muon Survey
Experimental retrieval to start at Unit 2 in 2021
![Page 10: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/10.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved 9
Step by step approach to be taken for fuel retrieval at Unit 2
Step by step approach will be implemented, first with experimental retrieval followed by its review, then with stepwise expansion of the retrieval scale.Step by step approach will be implemented, first with experimental retrieval followed by its review, then with stepwise expansion of the retrieval scale.
Experimental retrieval in 2021 Stepwise expansion of the scale
Metal brush Vacuum container
Robot arm Collection equipment
Gripper tool Drilling retrieval tool
②Enclosure
X-6 penetration hole
①Robot armPCV
③Connection pipe Whole Picture
Robot arm Collection equipment
![Page 11: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/11.jpg)
T H E F U K U S H I M A F O R U M I V • M A R C H 1 5 - 1 8 , 2 0 1 6 • T O K Y O , J A P A N
3. Striking a Balance betweenReconstruction & Decommissioning
![Page 12: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/12.jpg)
©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved
Mid-and-Long-Term Roadmap and TEPCO’s Action Plan
Phase 1 Phase 2 Phase 3Period until start of fuel removal (in 2 years)
Period until start of fuel debris retrieval (in 10 years)
Dec. 2011cold shutdownannouncement
Nov. 2013(start of Unit 4 spent fuel removal)Apr. 2019(start of Unit 3 spent fuel removal)
Dec. 2021 30~40 years aftercold shutdownannouncement
Period until completion of decommissioning (in 30 to 40 years)
Phase 3-(1)
End of 2031
Show Major work processes for each activity until 2031• Complete stagnant water treatment except for Unit 1 to 3 reactor bldgs. etc. in 2020• Complete fuel removal from pools at all Units (Units 1 to 6) by 2031 • Start fuel debris retrieval from Unit 2 in 2021. Expand the scale of retrieval in stages• Eliminate temporary waste storage in FY2028
“Mid-and-Long-Term Decommissioning Action Plan 2020”
https://www.tepco.co.jp/en/hd/decommission/information/dap/index-e.html
11
Proceed with tasks safely steadily, and efficiently, looking to the future
<The Locals><TEPCO>・Understand future work
in a concrete manner ・Join the decommissioning
work proactively
![Page 13: Chief Decommissioning Officer President of Fukushima ......Jun. 2011 Sep. 2011 Sep. 2011 Dec. 2019 Feb. 2019 Aug. 2019 Overview of tasks toward fuel removal Front chamber Removal to](https://reader033.vdocuments.mx/reader033/viewer/2022051808/60096000239e5f45a63d58eb/html5/thumbnails/13.jpg)
T H E F U K U S H I M A F O R U M I V • M A R C H 1 5 - 1 8 , 2 0 1 6 • T O K Y O , J A P A N©Tokyo Electric Power Company Holdings, Inc. All Rights Reserved
Thank you for your kind attentionThank you for your kind attention