chavdar ivanov, entso-e secretariat | 18 june 2010 entso-e roadmap on cim cim user group meeting, 18...

17
Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Upload: annabelle-booth

Post on 24-Dec-2015

221 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010

ENTSO-E Roadmap on CIM

CIM User Group meeting, 18 June 2010, Milan, Italy

Page 2: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 2 of 17

ENTSO-E fully operational since 1 July 2009

Represents 42 TSOs from 34 countries

• 525 million citizens served

• 828 GW generation

• 305,000 km of transmission lines managed by the TSOs

• 3,400 TWh/year demand:

• 400 TWh/year exchanges:

Replaces former TSO organisations: ATSOI, BALTSO, ETSO, NORDEL, UCTE, UKTSOA

Web site: www.entsoe.eu

Page 3: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Development and Implementation of CIM in ENTSO-E

November 2007: UCTE agreed to launch an initiative for development of new UCTE XML based data exchange format that will considered as a standard for exchange of load flow and dynamic data and allows performing of all kind of analyses as follows: steady state, unbalanced short circuit and dynamic analyses.

AhG UCTE format was established.

May 2008: UCTE Steering Committee approved

Cooperation of AhG “UCTE format” with international organizations aiming at inclusion of UCTE needs into international standard

UCTE participation in EPRI project (CIM for Dynamics)

Summer 2008: UCTE joins the EPRI Project and creates a liaison with IEC TC57. UCTE CIM TF is established during CIM user Group meeting in Vasteras (June 2008)

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 3 of 17

Page 4: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Development and Implementation of CIM in ENTSO-E

January 2009: UCTE Steering Committee approved Migration Policy. Priority of migration of “planning” models is given.

March 2009: UCTE IOP. Successful interoperability among IOP participants

May 2009: UCTE Profile finalized and submitted to IEC

July 2009: ENTSO-E is fully operational: new work organization related to CIM is implemented

All contracts and agreements have been transferred from UCTE to ENTSO-E. ENTSO-E has liaisons with IEC TC57 (WG13 and WG16) and it is a member of EPRI project “CIM for Dynamics”, etc.

July 2009: CIMdesk and Migration Converter provided to ENTSO-E members

Nov 2009: First IOP CIM for Dynamics. The concept is proved

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 4 of 17

Page 5: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Important ENTSO-E decisions

1 Oct 2009: System Development Committee (SDC) agreed that CIM/XML will be used in ENTSO-E data exchanges related to SDC activities (system studies, planning data exchanges)

2 Sep 2009: System Operations Committee (SOC) recommends:

Regional Group Continental Europe: The change from the UCTE format to CIM was decided by the UCTE Steering Committee. The goal is to switch to the new format before the end of 2010 at the latest (DACF exchanges)

Other Regional Groups to consider implementation of the standard with an aim of the pan-European harmonization

2 Dec 2009: SDC and SOC: Approved the roadmap for future development and implementation of updates of the CIM/XML format

11 Dec 2009: SDC, SOC and Market Committee: Approved ENTSO-E CIM Interoperability tests

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 5 of 17

Page 6: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E Secretariat serves as a central function of coordination, maintenance and support of Common Information Model (CIM) related issues and therefore, it

is the interface to international organizations

6

- Maintenance ENTSO-E CIM tools;- contacts with providers

Requests that concern CIM must be submitted to Secretariat

ENTSO-E Data Expert Group

System Development Committee

Operations Committee

Market Committee

WGs defining needs

International organizations: IEC, EPRI, CIMug, …

- Liaisons, - Submitting ENTSO-E needs, - - Participation in the discussion, - etc

- Discussion on Committees/WGs requests; - Information on IEC opinion; - Possible solutions - etc.

CIM toolsSecretariat

WGs defining needs

WGs defining needs

WG

NM&D WG EDI

SG NMFT in RG CE

CIMdesk; Migration Converter

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 6 of 17

Page 7: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Current ENTSO-E CIM/XML Profile

Current ENTSO-E Profile is the “UCTE CIM Profile” tested in UCTE IOP in March 2009 in Paris. THIS IS THE PROFILE THAT IS BEING IMPLEMENTED BY ENTSO-E MEMBERS.

Updates of this profile should follow the approved Roadmap Proposals for changes are welcome and will be discussed within ENTSO-E,

IEC and will be tested in the ENTSO-E IOP once agreed among IOP participants.

Current ENTSO-E CIM/XML profile is published on ENTSO-E web site (CIM part: http://www.entsoe.eu/index.php?id=237)

A draft version of the second edition of the ENTSO-E CIM/XML profile is developed for the ENTSO-E interoperability test in July 2010

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 7 of 17

Page 8: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Roadmap for future implementation of CIM

The aim: to structure the implementation effort. No yearly implementation. An exception could be only if a change is introduced which is critical for ENTSO-E processes

The implementation process is foreseen to last one year.

On regular basis the implementation effort is foreseen every three years, if necessary.

Next versions of the ENTSO-E Profile have to be approved by SDC. In case of changes that affect operational data, SOC decision is also required.

SDC or SDC&SOC decision ensures one year implementation period. Coming into force date is fixed and mandatory for TSOs

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 8 of 17

Page 9: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E CIM Interoperability Tests

1st ENTSO-E Test “CIM for System Development and Operations” was announced on 29 Jan 2010.

Registration for vendors was closed on 26 Feb at 17:00h CET The test will be held in Brussels in the week of 12 July

Test name / Schedule 2010 2011 on

1. ENTSO-E IOP “CIM for System Development and Operations” May-June March-April

2. ENTSO-E IOP “CIM for Energy Market” October-November

May-June

Postponed for 2011

Week of 12 July 2010

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 9 of 17

Page 10: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E CIM Interoperability Tests Registered vendors

BCP Busarello + Cott + Partner AG (NEPLAN) Siemens Power Technologies International (PSS/ODMS; PSS/E) CESI (SPIRA; CRESO; SICRE) Tractebel and RTE (EUROSTAG) ABB Power Technologies (ABB Network Manager) Open Grid Systems (Cimphony) FGH (INTEGRAL7) SISCO (UIB Adapter for PI-AF) ABB (BMS CIM Explorer) Intercompro AG (ISPEN) EMS (Power System Analyzer, PSA) AREVA T&D (e-terrasource; e-terraplatform) EDF R&D (GEDEON Database; CIMclipse; CIM-ENTSO-E Converters) DIgSILENT GmbH (PowerFactory 14.1) TIBCO (TIBCO ActiveMatrix platform) GE Energy (Enterprise Gateway)

In addition to these vendors, GE Energy (PSLF) is interested to participate in the preparation leading up to the Interoperability test, but will not participate in the actual test.

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 10 of 17

Page 11: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E CIM Interoperability Tests Registered test witnesses

Svein Olsen (Statnett, Norway) Vladimir Milic (EMS, Serbia) Marcel Forlong (Amprion, Germany) Reinier van Offeren (TenneT, Netherlands) Oana - Raluca STANESCU (Transelectrica, Romania) Adriano Gubernali (TERNA, Italy) Domenico Iorio (TERNA, Italy) – but as substitute – not sure if he attends Pietro Capurso (TERNA, Italy) Tomasz Rogowski (PSE-Operator, Poland) Pierluigi Portoghese (TERNA, Italy) – but as substitute – not sure if he attends Marc Emery (swissgrid, Switzerland) Michael Rotzinger (swissgrid, Switzerland) Oana Udrea (Transelectrica, Romania) Gorazd Berginc (ELES, Slovenia)

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 11 of 17

Page 12: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

IOP Plans

5 days IOP (12-16 July 2010)

Final report of the IOP available shortly after the test on ENTSO-E and CIMug web sites

Profile and test files also publicly available

Identified CIM issues listed in the final report and submitted to IEC WG13 for further discussion

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 12 of 17

Page 13: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E and CIM Tools

CIMdesk Visualization and editing tool developed by PowerInfo LLC, US

Provides users with possibilities for direct editing of CIM data exchange format and graphical visualizationIt is not related to the migration. It will be used and maintained as long as CIM /XML format is usedMaintenance contact ends in July 2010. A new maintenance contract which includes re-licensing conditions is now negotiated

Migration converter Developed by EDF R&D, FR

Converts from UCTE CIM to UCTE DEF (current version: version 02) and vice versaTo be used during the migration stage; useful for RG Continental EuropeMaintenance contract ends in the end of 2010

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 13 of 17

Page 14: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E exchanges in CIM

System development – planning exchanges • Still in migration period. Implementation efforts are necessary from both

sides users and vendors. • Some TSOs already provide models in CIM

•Lessons learned: Testing with real data is necessary. IOP test cases cannot fully represent all

modelling approaches More complex test models are needed. The role of CIMug and IEC in test

models preparation is to be discussed Some vendors introduced post IOP changes which made real

interoperability not possible. Off-line IOPs may need to be performed.

DACF process • The goal is to complete migration stage by the end of 2010

•Test exchanges started on 8 June 2010

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 14 of 17

Page 15: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

CIM and ENTSO-E web site (www.entsoe.eu)

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 15 of 17

Page 16: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

ENTSO-E CIM in the CIMug web site

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 16 of 17

Page 17: Chavdar Ivanov, ENTSO-E Secretariat | 18 June 2010 ENTSO-E Roadmap on CIM CIM User Group meeting, 18 June 2010, Milan, Italy

Summary

ENTSO-E TSOs are implementing CIM in order to improve and harmonize data exchange processes improve the quality of network analyses

Therefore, to ensure fulfillment of ENTSO-E tasks defined by the 3rd Energy Package the EU

ENTSO-E set up an internal process in order to deals with CIM issues ENTSO-E would like to base its profiles on the IEC CIM Standards. This

will be possible only if CIM is developed following clear roadmap that avoids major changes of already implemented classes.

ENTSO-E will not be able to follow yearly updates on regular basis. Therefore changes in ENTSO-E Profile and IEC Standards will be carefully analyzed and applied in accordance with ENTSO-E needs.

ENTSO-E will actively participate in the CIM development process by providing technical expertise and a platform to demonstrate interoperability (IOPs covering WG13 and WG16 topics)

ENTSO-E Roadmap on CIM | Chavdar Ivanov | 18 June 2010 | Page 17 of 17