characterization and numerical simulation of the water resources in the nisqually river watershed:...
DESCRIPTION
Presentation Given By: Mark Savoca, USGS HydrologistTRANSCRIPT
USGS Numerical Models -Drost and others, 1999 -Johnson and others, 2011
Aquifers and Aquitards
GW and SW Movement
Water Budget
Proposed Time Line
Agency FY2014 FY2015 FY2016 FY2017 FY2018
USGS $64,000 $80,000 $88,000 $88,000 $40,000
Project Partners $96,000 $120,000 $112,000 $112,000 $60,000
Total $160,000 $200,000 $220,000 $220,000 $100,000
The estimated project cost is $900,000 over five fiscal years (FY 2014-2018). All project costs would be shared by the USGS (40%) and the project partners (60%).
Drost, B.W., Ely, D.M., and Lum II, W.E., 1999, Conceptual model and numerical simulation of the ground-water-flow system in the unconsolidated sediments of Thurston County, Washington: U.S. Geological Survey Water-Resources Investigations Report 99-4165, 254 p.
Johnson, K.H., Savoca, M.E., and Clothier, Burt, 2011, Numerical simulation of the groundwater-flow system in the Chambers-Clover Creek Watershed and Vicinity, Pierce County, Washington: U.S. Geological Survey Scientific Investigations Report 2011–5086, 108 p.
Mark Savoca [email protected] http://wa.water.usgs.gov/
USGS Model Reports