TOWN OF BURLINGTON DEPARTMENT OF PUBLIC WORKS CHANNEL GRINDER Terrace Hall Pump Station Contract # 16S-411-0003 This is an unofficial Bid Spec. If this document is used to submit a bid then you must submit your contact information to Lisa Matarazzo at [email protected] in order to be added to the bidders list. Department of Public Works Engineering Division 25 Center Street Burlington MA 01803 (781) 270-1640 November 2015

Upload: trinhdien

Post on 16-Apr-2018

222 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

TOWN OF BURLINGTON

DEPARTMENT OF PUBLIC WORKS

CHANNEL GRINDER

Terrace Hall Pump Station Contract # 16S-411-0003

This is an unofficial Bid Spec. If this document is used to submit a bid

then you must submit your contact information to Lisa Matarazzo at

[email protected] in order to be added to the bidders list.

Department of Public Works

Engineering Division

25 Center Street

Burlington MA 01803

(781) 270-1640

November 2015

Page 2: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

2

TABLE OF CONTENTS

PROJECT DESCRIPTION 4 INSTRUCTIONS TO BIDDERS 5 FORM OF GENERAL BID 8 ADDENDA 9 BID FORM 10

TOTAL BID PRICE 11 CONTRACTOR CERTIFICATION 12 AGREEMENT 13 SPECIAL CONDITIONS 14 SPECIFICATIONS 15

Page 3: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

3

1. INVITATION FOR BID

SUPPLIES AND SERVICES

Sealed bids for Channel Grinder Terrace Hall Pump Station Contract #16S-411-0003

will be received by DPW/Engineering, Town Hall, 25Center Street, Burlington,

Massachusetts, 01803 until 9:30AM December 2, 2015 and will be publicly opened

and read aloud at such time.

Specifications and bid forms are available on the DPW website site at:

http://www.burlington.org ,under the Projects & Programs tab.

Specifications and bid forms may be obtained at the DPW/Engineering, 25 Center

Street, Burlington, Massachusetts, 01803 on November 18, 2015 between 8:30

AM and 4:00 PM.

This project is bid according to MGL 30B.

Page 4: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

4

PROJECT DESCRIPTION

The Contractor shall furnish, warrant, and deliver to the Terrace Hall Pump

Station a replacement Muffin Monster sewage grinder the Wipes Ready CDD-

XDS2.0 for shredding municipal wastewater solids.

Muffin Monster Model:CDD3216-XDS2.0-Exchange

1:1 Stack 11 Cam Alloy STL Cutters

Viton Elastomers

Less Electric Motor

With Adapter Spool

With 29:1 Reducer

1/2" Perforated Drums

Paint Epoxy Green

3 REDUCER ASSY, 29:1 W/GUARDS

Page 5: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

5

INSTRUCTIONS TO BIDDERS

Receipt and Opening of Bids

The Town of Burlington, Massachusetts, herein called the Owner, acting by and through

its Department of Public Works, will receive sealed bids as specified in the invitation for

Bids at which time bids will be publicly opened and read.

Any bid may be withdrawn prior to the above scheduled time for the opening of bids or

authorized postponement thereof. Any bid received after the time and date specified will

not be considered. The bidder agrees that this bid shall be good and may not be

withdrawn for a period of thirty (30) days, Saturdays, Sundays, and legal holidays

excluded, after opening the bids.

Preparation of Bid

Each bid must be submitted on the prescribed form. All blank spaces for bid prices must

be filled in, in ink or typewritten, in both words and figures.

Each bid must be submitted in a sealed envelope bearing on the outside the name of the

bidder, his address, and endorsed with the name of the project.

If forwarded by mail, the sealed envelope containing the bid must be enclosed in

another envelope addressed as specified in Receipt and Opening of Bids.

The following sections must be completed as part of the bid package:

Form of General Bid

Acknowledgement of Addenda, if any

Bid Form

Total Bid Price

Contractor Certification

Bid Opening Procedure

The following list of requirements shall apply to each filed bid. Bids not meeting all the

requirements for timeliness and security will be rejected without opening; bids not

meeting signature and addenda requirements will be rejected prior to checking of bid

amounts. The total dollar amount of each bid will be read, and the three apparent lowest

bids will be selected for further consideration. All those present at the bid opening may

arrange a time to examine all bids after the bid opening and after the reading of the three

apparent low bids.

Addenda and Interpretations

Page 6: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

6

No interpretation of the bid documents will be made orally. Every request for such

interpretation should be in writing addressed to the Engineering Division, Town Hall

Annex, 25 Center Street, Burlington, MA 01803 and to be given consideration must

be received at least seven (7) days prior to the date fixed for the opening of bids. Any and

all such interpretations and any supplemental instructions will be in the form of written

addenda to the Contract Documents. Failure of any bidder to receive any such addendum

or interpretation shall not relieve such bidder from any obligation under this bid as

submitted. All addenda so issued shall become part of the Contract Documents.

Right to Reject Bid

The Owner reserves the right to waive any informality or reject any and all bids and

alternate bids, should the Owner deem it to be in the public interest to do so.

Time for Completion

The bidder must agree to commence work and to fully complete the project within the

time limit stated in SPECIAL CONDITIONS.

Comparison of Bids

In the event that there is a discrepancy in FORM OF GENERAL BID between the lump

sum or unit prices written in words and figures, the prices written in words will govern.

Rule for Award of Contract

The Contract will be awarded to “the lowest responsible and responsive bidder” for the

Total Price Bid pursuant to General Laws Chapter 30B as amended. Such a bidder shall

possess the skill ability and integrity necessary for the faithful performance of the work,

shall be able to furnish labor that can work in harmony with all other elements of labor

employed, or to be employed, in the work, and shall otherwise comply with all applicable

provisions of law. Bidder shall execute formal agreement within ten (10) days of the

Notice of Award.

Page 7: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

7

Statutes Regulating Competitive Bidding

Any bid that does not comply with the provisions of Massachusetts General Laws

Chapter 30B, as amended, need not be accepted and the Owner may reject every such

bid.

Bid Items Not Guaranteed

The successful bidder is not guaranteed all items or the total bid price under this contract.

Page 8: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

8

FORM OF GENERAL BID

Bid of ____________________________________ (hereinafter called

“Bidder”)*

(____) a corporation, organized and existing under the laws of the state of ___________.

(____) a partnership

(____) a joint venture

(____) an individual doing business as ___________________________________

To the Town of Burlington, Massachusetts (hereinafter called “Owner”).

Gentlemen:

The bidder, in compliance with your invitation for bids, having examined the Contract

Documents and being familiar with all of the conditions surrounding the construction of

the proposed project including the availability of materials and labor, hereby propose to

furnish all labor, materials, and supplies, and to construct the project in accordance with

the Contract Documents within the time set forth in the agreement, and at the prices

stated below. These prices are to cover all expenses incurred in performing the work

required under the Contract Documents, or which this proposal is a part.

----------------------

*Insert corporation, partnership or individual as applicable.

Page 9: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

9

ADDENDA

Bidder acknowledges receipt of the following addenda:

No.______________________Dated:______________________

No.______________________Dated:_______________________

No.______________________Dated:______________________

No.______________________Dated:_______________________

No.______________________Dated:_______________________

Page 10: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

10

BID FORM

ITEMS QT.

UNIT PRICE

TOTAL

ITEM 1.

CHANNEL

MONSTER GRINDER

Series CDD-XDS2.0

1 EA $ EA $

Page 11: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

11

TOTAL BID PRICE

Total Price Bid: $

Bid Price in Words:

Name:

Signature:

Title:

Company:

Address:

Phone:

This is an unofficial Bid Spec. If this document is used to submit a bid

then you must submit your contact information to Lisa Matarazzo at

[email protected] in order to be added to the bidders list.

Page 12: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

12

CONTRACTOR CERTIFICATION

NON-COLLUSION

I certify under penalties of perjury that this bid or proposal has been made and submitted

under good faith and without collusion or fraud with any other person. As used in this

certification, the word “person” shall mean any natural person, business, partnership,

corporation, union, committee, club, or other organization, entity, or group of individuals.

TAX COMPLIANCE

Pursuant to Massachusetts General Law Chapter 62C, Section 49A, I certify under the

penalties of perjury that, to the best of my knowledge and belief, I am in compliance with

all laws of the Commonwealth relating to taxes, reporting of employees and contractors,

and withholding and remitting child support.

Signature: __________________________________________________________

(Person Signing Bid)

___________________________________________________________________

(Name of Business)

Page 13: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

13

AGREEMENT

THIS AGREEMENT, by and between the party of the first part, the Town of Burlington,

hereinafter called “OWNER”, acting herein through its Town Administrator, and the

party of the second part hereinafter called “CONTRACTOR”.

WITNESSETH: That for and in consideration of the payments and agreements

hereinafter mentioned, to be made and performed by the OWNER, the CONTRACTOR

hereby agrees with the OWNER to commence and complete the project described by

these bid documents hereinafter called the project, for the sum of the contract price and

all extra work in connection therewith, under the terms as stated in the Contract

Documents; and at his (its and their) own proper cost and expense to furnish all the

materials, supplies, machinery equipment, tools, superintendence, labor, insurance, and

other accessories and services necessary to complete the said project in accordance with

the conditions and prices stated in FORM OF GENERAL BID, GENERAL

CONDITIONS, Contract Documents as prepared by the Owner.

IN WITNESS WHEREOF, the parties to these presents have executed this contract.

$

Contract Price

AGREED:

Town of Burlington

Town Administrator Date

Contractor

Contractor Date

Company

Name:

Address:

In accordance with M.G.L. C. 44, Section 31C, this is to certify than an appropriation in

the amount of this contract is available therefore and that the Town Administrator has

been authorized to execute the contract and approve all requisitions and change orders.

Town Accountant Account#

Page 14: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

14

SPECIAL CONDITIONS

1. The Town of Burlington, acting through its Board of Selectmen, an awarding

authority, reserves the right to accept or reject any and/or all bids or portions

thereof, and to waive any informalities in bidding, and/or to make the award as

appears in the best interest of the Town of Burlington.

2. Payment will be made monthly, unless otherwise specified.

3. Normal Hours of work: Work hours shall be between the hours of 7:00 AM and

3:30 PM Monday through Friday, unless otherwise specified. The successful

Contractor shall not work on Saturdays, Sundays, Holidays or other hours,

without express authority from the Director of Public Works.

4. This Contract includes estimated quantities that may or may not be purchased

during Fiscal Year. Additionally, quantities are used for comparison of bids and

establishing the Bid Deposit.

5. This Contract may be terminated, with fifteen (15) days’ notice, for unsatisfactory

performance and/or availability of funds. The contractor will hold the Town

harmless from all damages as a result of funding restraints.

6. Channel Grinder must be delivered within 8 weeks of execution of agreement.

Page 15: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

15

SPECIFICATIONS

CHANNEL MONSTER GRINDER Series CDD-XDS2.0

2” hex/Dual drum/Wipes Ready/XPNV Immersible Single Drive/PC2200 Controller

PART 1 - GENERAL

1.1 SCOPE OF WORK

A. The Contractor shall furnish, warrant, and deliver to the Terrace Hall Pump

Station the Wipes Ready CDD-XDS2.0 for shredding municipal wastewater

solids.

B. All items detailed in this section shall be provided by the same manufacturer.

1.2 REFERENCE STANDARDS

A. Equipment shall, as applicable, meet the requirements of the following

industry standards:

1. American Society for Testing and Materials (ASTM) A36 Carbon Steel

Plate

2. American Society for Testing and Materials (ASTM) A536-84 Ductile

Iron Castings

3. American Iron and Steel Institute (AISI) 4130 Heat Treated Alloy Steel

4. American Iron and Steel Institute (AISI) 4140 Heat Treated Alloy Steel

5. American Iron and Steel Institute (AISI) 8620 Heat Treated Alloy Steel

6. American Iron and Steel Institute (AISI) 303 Stainless Steel

7. American Iron and Steel Institute (AISI) 304 Stainless Steel

8. American Iron and Steel Institute (AISI) 316 Stainless Steel

9. American Iron and Steel Institute (AISI) 17-4 PH Stainless Steel

10. Society of Automotive Engineers (SAE) 600 Bearing Bronze

A. Controllers shall, as applicable, meet the requirements of the following

Regulatory Agencies:

1. National Electrical Manufacturer’s Association (NEMA) Standards

2. National Electrical Code (NEC)

3. Underwriters Laboratory (UL and cUL)

4. International Electrotechnical Commission (IEC)

1.3 QUALITY ASSURANCE

A. Identification

1. Equipment shall be identified with a corrosion-resistant nameplate affixed

in a conspicuous location.

2. Nameplate information shall include manufacturer’s name and address,

equipment model number, and serial number.

Page 16: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

16

B. Manufacturer

1. Supplier shall be ISO9001 certified and have a minimum 40 years

experience as a manufacturer of municipal waste water equipment and a

minimum 2000 prior installations of similar equipment.

2. Supplier shall, at request, provide a list of reference sites of similar

equipment for verification by the Engineer or Owner’s representative.

3. Supplier shall conduct factory testing and verification of equipment prior

to shipment.

4. Supplier shall have factory-owned bi-coastal service centers in USA.

1.4 SUBMITTALS

A. Approval Documents

Supplier shall submit approval documents in .pdf format. Submittals shall

include equipment descriptions, functional descriptions, dimensional and

assembly drawings, catalog data, job specific drawings and manufacturer’s

instructions.

B. Operation and Maintenance Manuals

The supplier shall submit one (1) copy of a suitable operation & maintenance

manual. An electronic version shall be supplied to create additional copies.

The manuals shall include equipment descriptions, operating instructions,

drawings, troubleshooting techniques, a recommended maintenance schedule,

recommended lubricants and recommended spare parts.

C. Warranty Documentation

The supplier shall submit a warranty statement clearly identifying the scope

and term of the warranty.

1.5 DELIVERY, STORAGE, AND HANDLING A. Packaging and Shipment

1. Equipment shall be packaged in containers or on skids suitable for normal

shipping, handling, and storage.

2. Equipment shall be protected from rain, snow, impact and abrasion while

in the possession of the carrier.

B. Delivery and Acceptance Requirements

Contractor shall review the contents of the shipment at time of delivery and

promptly notify the carrier and supplier of any discrepancies.

1.6 WARRANTY Manufacturer’s standard 12-month limited warranty shall be provided with the

equipment.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Equipment shall be in accordance with these plans and specifications and shall

be supplied by:

Page 17: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

17

1. JWC Environmental, LLC, 290 Paularino Ave., Costa Mesa, CA 92626;

Tel: 800-331-2277

2.3 PERFORMANCE REQUIREMENTS

A. General

Grinder shall reduce or shred influent solids for protection of downstream

equipment.

B. Design Summary

1. Number of grinders 1

2. Number of motor controllers 1

3. Environment rating for grinders Hazardous, subject to

flooding

4. Environment rating for motor controllers Non-hazardous

5. Supply power characteristics 460 volt / 3 phase / 60 Hertz

6. Nominal stack height 32”

7. Nominal drum diameter, perforation size 16” , 1/2” dia. hole

8. Minimum liquid handling capacity per grinder 10.6 MGD

9. Maximum head drop across cutter stack 20” max capacity

10. Cutter type Serrated 17-tooth

11. Spacer type Knurled

12. Shaft seal type Mechanical, Tungsten

Carbide

13. Seal maximum pressure 90 psi (620 kPa)

14. Speed reducer type and ratio Cycloidal, 29:1

15. Installed horsepower 5 hp (3.7 kW)

16. Motor type XPNV, immersible

17. Motor service factor 1.15

18. Minimum motor efficiency (at full load) 91.5%

19. Minimum motor power factor (at full load) 74%

20. Minimum peak shaft torque 3,995 lb-in/hp (605 Nm/kW)

21. Minimum peak force at cutter tip 1,696 lbf /hp (10,119 N/kW)

2.4 FRAME AND SUPPORTS

A. General

1. Grinder shall be compatible with existing frame & supports.

2.5 GRINDER

A. General

Grinder shall be of two-shafted design consisting of individual cutters and

spacers driven by hexagonal shafts. The cutters shall actively grab and pull

material into the stack for shredding. Twin rotating perforated drums shall

maximize hydraulic capacity by screening the wastewater to capture solids

larger than the perforation diameter and transfer the solids to the cutter stack

Page 18: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

18

for shredding. Grinder shall have upper and lower end housings to retain shaft

support bearings and seals. Side rails shall provide structural rigidity while

optimizing throughput and capture. Grinder shall have a motor and speed

reducer to drive the cutter shafts and rotating drums. The equipment shall

operate at low speed with a maximum cutter shaft speed of 60 rpm and shall

be specifically designed for capturing and shredding wipes.

B. Components

1. Cutters and Spacers

a. Cutting stack shall be of nominal height listed in Performance

Requirements.

b. Cutters shall have 17 teeth and be 0.438” (11.13 mm) thick.

c. Spacers shall be 0.446” (11.33 mm) thick.

d. Cutters and spacers shall be individual disks constructed of heat

treated alloy steel

e. Cutter tooth height shall be not greater than ½-inch (13 mm) above the

root diameter of the cutter.

f. Cutter outside diameter shall not exceed a maximum 4.73" (120.14

mm).

g. Cutter thickness tolerance shall be +.000/-.001” (+.000/-.025 mm).

Spacer thickness tolerance shall be +.001/-.000” (+.025/-.000 mm).

h. Cutters shall be heat treated to 45-53 HRc.

i. Spacers shall be heat treated to 34-53 HRc.

j. Spacers shall have a knurled outside diameter.

k. Cutter to cutter clearance shall be a maximum of 0.010” (0.25 mm).

l. Clearance between any cutter tip and adjacent spacer shall be nominal

0.015” (0.38 mm).

2. Shafts

a. Shafts shall be hexagonal, 2” (50.8 mm) across flats.

b. Shafts shall be of heat treated 4140 alloy steel with a minimum tensile

strength of 149,000 psi (1,027 kPa).

c. Shaft hardness shall be 38-42 Rockwell C.

3. Intermediate Shaft Yokes with Vertical Support (as applicable)

a. Intermediate shaft yokes shall provide radial support to the shafts

during severe grinding demands.

b. Intermediate shaft yokes shall be constructed of 304 stainless steel,

660 bronze, and 17-4PH Stainless steel.

c. Intermediate shaft yokes shall be factory lubricated with high

temperature marine grade grease.

d. Grease fittings shall be provided on intermediate shaft yokes for

periodic maintenance.

e. Vertical support shall be constructed of 304 stainless steel.

f. Vertical support shall have brackets to locate and secure intermediate

shaft yokes within the cutter stack.

g. Vertical support shall have a shape that coincides with the radial

profile of the cutters to allow for a close interface.

Page 19: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

19

h. Vertical support shall have adjustable brackets for mounting to the top

and bottom end housings.

i. Intermediate shaft yokes and vertical support shall only be supplied on

cutter stacks of 32-inches (813mm) and taller.

4. Rotating Drum

a. Drums shall be of nominal diameter and perforation size listed in

Performance Requirements.

b. Drums shall be of 304 stainless steel.

c. Nominal clearance between the drums and adjacent cutters shall not

exceed 0.100” (2.54 mm).

5. Side Rails

a. Side rails shall be constructed of ASTM A536 ductile iron.

b. Side rails shall have an adjustable UHMWPE sealing strip creating an

interface between the drums and side rail to minimize clearance.

c. Each side rail shall have an integral guide slot for installing into

framework.

6. Shaft Bearings and Seals

a. Radial and axial loads shall be borne by sealed, oversized, deep-

groove ball bearings.

b. Shaft seal type shall be mechanical.

c. Each bearing and seal arrangement shall be incorporated into a

cartridge-style housing.

d. Cutter shafts shall be supported on both ends. Cantilever-style

arrangements shall not be permitted.

e. Dynamic and rotating seal faces shall be Tungsten Carbide with 6%

Nickel binder.

f. Seal cartridges shall be rated to a maximum pressure of 90 psi (620

kPa).

g. O-rings shall be of BUNA-N.

h. Seal cartridges shall not require flushing.

i. Seals shall be rated to operate wet or dry.

7. Housings and Covers

a. Housings and top cover shall be of ASTM A536 ductile iron. Bottom

housing cover shall be of A36 carbon steel.

b. End housings shall have integral bushing deflectors to guide solids

away from seal cartridges.

8. Transfer Gears

a. Transfer gears shall be of involute profile and fabricated from heat

treated alloy steel.

b. Transfer gear tooth design, thickness and hardness shall be suitable to

transfer torque between shafts up to the rated breakdown torque of the

motor.

c. The interface between transfer gears shall be factory lubricated with

grease to minimize wear.

9. Low Speed Coupling

a. Low speed coupling shall be of type and material as listed in

Performance Requirements.

Page 20: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

20

b. The interface between low speed coupling halves shall be factory

lubricated with grease to minimize wear.

10. Speed Reducer

a. Speed reducer shall be manufactured by Sumitomo Machinery

Corporation of America.

b. Speed reducer shall be a cycloidal type.

c. Gear motor speed reduction ratio shall be 29:1.

d. Speed reducer shall be grease lubricated.

11. High Speed Coupling

a. High speed coupling shall be a 3-jaw type with elastomer spider.

b. The 3-jaw halves shall be of sintered iron.

c. The spider shall be of BUNA-N.

12. Motor

a. Motor shall be manufactured by Baldor Electric Company.

b. Motor shall have characteristics as listed in Performance

Requirements

13. Hoist Rings

a. Grinder shall be fitted with four (4) hoist rings for lifting.

b. Hoist rings shall be designed to pick the grinder above the center of

gravity and ensure grinder remains suitably vertical in movement.

c. Hoist rings must be suitable to bear the side loads associated with

laying the grinder down in any direction.

2.6 MOTOR CONTROLLER

A. Description

Controller shall provide factory-programmed operation of the grinder system.

Controller shall have switches, indicator lights, and other control devices.

Controller shall be designed to suit the supply power and motor characteristics

listed in Performance Requirements.

B. Components

1. Enclosure

a. Enclosure shall be fiberglass reinforced plastic, NEMA 4X.

b. Enclosure shall house motor starter, PLC, and control devices.

2. Selector switches

a. Selector switches shall be 22 mm, rated equal to or better than the

enclosure.

b. Grinder selector switch shall be three-position and indicate On-

Off/Reset-Remote.

3. Pilot Lights

a. Lights shall be 22 mm, LED (pilot lamp), rated equal or better than the

enclosure.

b. Lights shall indicate POWER ON, grinder RUN, grinder JAMMED

and MOTOR FAULT.

4. Motor Starter

Page 21: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

21

a. Starter shall be IEC, full voltage, reversing.

b. Contactors shall have 120-volt operating coils.

c. Overload relays shall be adjustable and sized to full load amperes

(FLA) of the motor.

5. Control Power Transformer

a. Control power transformer shall produce 120-volt AC power from the

supply power. Transformer shall be sized and fused in accordance

with code to accommodate the control power requirements.

6. Programmable Logic Controller

a. PLC shall be a Panasonic FPX.

7. Current Transducer

a. Current transducer shall be a discrete output type.

b. Current transducer shall have adjustable set point from 1-135A with

200 ms or faster response time.

C. Operation

1. Grinder control shall be in accordance with the setting of the On-

Off/Reset-Remote selector switch.

a. In the OFF/RESET position the grinder shall not run. Motor controller

faults shall be cleared.

b. In the ON position, the grinder shall run forward.

c. In the REMOTE position, the grinder shall operate as controlled by a

remote start/stop dry contact.

2. When an obstruction jams the grinder, the controller shall stop the grinder

and reverse the rotation to clear the obstruction. If the obstruction is

cleared, the controller shall return the grinder to normal operation. If three

(3) reverses occur within a 30 second interval, the controller shall stop the

grinder motor and activate the grinder FAIL indicator and relay.

3. When a motor overload or motor over-temperature condition occurs, the

motor shall be de-energized, the MOTOR FAULT indicator lamp shall be

illuminated and the FAIL relay shall be energized.

4. When a power failure occurs while the system is operating, the system

shall return to normal operation when power is restored.

5. When a power failure occurs while the grinder is in a fail condition, the

system shall return to a fail state when power is restored. The fail state

shall not be cleared until reset.

6. Reset of the grinder shall be accomplished from the controller only.

2.7 FINISHES

A. Paint Coatings (Ferrous Materials)

Ferrous metal surfaces shall be prepared to SSPC-SP6 (Commercial Blast

Cleaning) and coated with minimum 6-8 mils TDFT (total dry film thickness)

paint of type and color listed in Performance Requirements.

B. Paint Coatings (Previously-Coated Components)

Page 22: CHANNEL GRINDER Terrace Hall Pump Station - … GRINDER Terrace Hall Pump Station ... If this document is used to submit a bid ... Channel Grinder must be delivered within 8 weeks

Town of Burlington 30B Supplies

Engineering Division

Channel Grinder 16S-411-0003

9:30 AM 12/2/15

22

Previously-coated components (motors, speed reducers, etc.) shall be prepared

to SSPC-SP1 (Solvent Cleaning) and SSPC-SP2 (Hand Tool Cleaning) and

coated with minimum 6-8 mils TDFT (total dry film thickness) paint of type

and color listed in Performance Requirements.