ch 4 - forecasting cost · pdf filech 4 - forecasting cost overruns ... 4.1 - identifying and...
TRANSCRIPT
Ch 4 - Forecasting Cost Overruns
bull 40 - Chapter Introduction bull 41 - Identifying And Analyzing Cost And Schedule Variances bull 42 - Estimating Cost To Complete bull 43 - Resolving Potential Cost Overruns bull App 4A - Earned Value Management System Guidelines
40 Chapter Introduction
This chapter will examine methods that you can use to identify analyze and resolve contract cost and schedule variances
Contract Surveillance (FAR 421103 421104 and 421105) While the contractor is responsible for timely cost-effective contract performance the Government is responsible for maintaining contract surveillance to the extent necessary to protect the Governments interests Appropriate procedures for identification and analysis of cost and schedule variances should be a part of every contract surveillance plan
If you are a contracting officer preparing a new contract consider the information required for effective surveillance of contract performance as you define contract-reporting requirements If you are the contracting officer responsible for contract administration determine the contract surveillance requirements based on the criticality of the contract requirement to the Government and the circumstances affecting contract performance
bull Criticality to the Government The contracting officer must assign a criticality designator to each contract following the guidelines in the table below In general the more critical the requirement is to the Government the more attention you should give to contract surveillance including cost and schedule variance identification and analysis
Contract Criticality To Government Operations
Criticality Designator
Relative Criticality
Criterion
A Most Critical contracts
critical (including DX-rated contracts) contracts involving unusual and compelling urgency and contracts for major systems
B Moderately critical
Contracts (other than those designated A) for items needed to maintain a Government or contractor production or repair line to preclude out-of-stock conditions or to meet user needs for non-stock items
C Least critical
All other contracts
bull Circumstances of the Contract In general the more complex or difficult the contract the more consideration you should give to contract surveillance When analyzing contract complexity consider
o Contract requirements for reporting production progress and performance Cost-reimbursement time-and-materials and labor-hour contracts typically have stricter requirements for reporting progress and
ontracts performance than fixed-price co Contract performance schedule Contracts with longer
schedules will normally merit closer surveillance because there is a longer period before late deliveries and other routine indicators will indicate a problem A contract with an ambitious completion schedule also will normally merit closer surveillance
o Contractors history of contract performance A contractor with a history of overruns or late deliveries will normally merit closer surveillance
o Contractors experience with the contract supplies or services A contractor with limited experience will normally merit closer surveillance
o Contractors financial capability A contractor with marginal financial capability will normally merit closer surveillance
o Any supplementary written instructions from the contracting office
41 Identifying And Analyzing Cost And Schedule Variances
Uses for Information on Variances (FAR 52232-7(c) 52232-20(a) 52232-22(a) 52243-1(b) 52243-2(b) 52243-3(b) and 52243-4(d))
Information on variances from cost and schedule projections can provide vital input to many contract administration decisions
bull Information on the contractors progress toward timely contract completion is important for the administration of any contract However it is most important for cost-reimbursement time-and-material and labor-hour contracts For these contracts the contractor only agrees to put forth its best effort to complete the contract effort within funding cost or price limitations
bull Information on contractor cost and schedule performance is essential to negotiating an equitable adjustment that leaves the contractor in the same profit position as it was before the modification
bull Information on cost of the current contract can be a key element in projecting the cost of follow-on contracts awarded before the current contract is complete
Consider Both Cost and Schedule Variances To analyze variances you need to be able to consider contractor cost and schedule variances from initial cost estimates For example a contractor in Month 4 of a 12-month contract is tracking perfectly with estimated costs through Month 4 However the contractor is two months behind schedule In other words two months of actual performance have cost as much as four months were projected to cost If we consider only cost there does not appear to be a problem However if we consider both cost and schedule there appears to be significant potential for a cost andor schedule overrun
Information Sources You can use information from a variety of sources to monitor cost and schedule performance variance such as
bull Contractually required costschedule analysis and reporting including
o Cost Performance Reports under Earned Value Management System (EVMS) Guidelines and
o CostSchedule Status Reports bull Contractually required cost information including
o Contract Funds Status Reports o Progress payment requests o Cost-reimbursement vouchers o Contract progress reports or o Limitation of costfunds notices
bull Contractor production management reports and analyses Including
o Phase Planning or Gantt Charts o Production Flow Charts o Program Evaluation and Review Technique (PERT) network
analyses bull Progress review meetings bull Observation by Government personnel
Points to Consider in Information Source Selection The method that you select must be appropriate for the contract When you have a complex or difficult contract for a requirement with a Criticality A Designator you should consider contractually mandated analysis and reporting system (eg compliance with EVMS Guidelines for a major acquisition) The risk involved will likely merit the additional cost of the required system
It is unlikely that a requirement with a Criticality C Designator would merit the added cost of any contractually mandated costschedule reporting For low-value low-risk items you would probably rely on routine observation by Government personnel
To be effective the method that you select must provide or permit you to develop
bull A cost baseline upon which the original contract cost was derived (usually the contractors budget or proposal)
bull Actual costs incurred for completed work bull An estimate to complete
Earned Value Management Systems (DODD 50002R para 3353 MIL-STD-881 and DFARS 252234-7001)
Appendix 4A presents the 32 Industry Standard Guidelines for development and operation of Earned Value Management Systems (EVMSs) Under these guidelines contract work is planned budgeted and scheduled in time-phased planned value increments to establish a cost and schedule measurement baseline Actual cost and schedule performance is then compared to the established baseline
bull Requiring Compliance Requiring contractors to comply with EVMS Guidelines encourages them to use effective internal cost and schedule management control systems and permits the Government to rely on timely data produced by those systems for determining product-oriented contract status However compliance should only be required when contract cost and complexity merit the cost of compliance with EVMS Guidelines
o Unless the requirement is waived by the acquisition Milestone Decision Authority (MDA) the DoD requires EVMS Guideline compliance from any firm with a flexibly-priced
o System research development test or evaluation contract or subcontract with a value of $70 million or more in (FY 1996 constant dollars) or
o System procurement contract with a value of $300 million or more in (FY 1996 constant dollars)
o If you are assigned to another agency consult agency guidance for contracting situations that require contractor compliance with EVMS Guidelines
bull Stipulating a Work Breakdown Structure The framework for EVMS is the Work Breakdown Structure (WBS) and the contractors baseline plan developed using that structure
o The WBS is a product-oriented family tree division of hardware software services and other work tasks which organizes defines and graphically displays the product to be produced as well as the work to be accomplished to achieve the specified product
o When you expect that the contract will require the contractor to comply with EVMS guidelines the request for proposal should require the offeror to provide cost information based on a WBS identified in the solicitation The offeror can provide more levels of information than required by the solicitation but the firm cannot provide fewer
o The multiple levels of the WBS explode the work required down to identifiable work packages that relate costs to specific contract effort In a common WBS
Level 1 is the entire system Level 2 identifies the major elements of Level 1 Level 3 identifies the major elements of Level 2 and
Each lower level provides increasingly detailed information
The following table provides an example of a 3-level WBS structure The example is for a missile system but the concept can be applied to any large system Missile System Work Breakdown Structure Levels 1-
3 Level 1 Level 2 Level 3
Air Vehicle Vehicle Integration and Assembly
Propulsion
Vehicle Stages (each stage included in system design)
Guidance and Control Equipment
Airborne Test Equipment
Auxiliary Equipment
Missile System
Command and Launch Equipment
Integration and Assembly
Surveillance Identification and Tracking Sensors
Launch and Guidance Control
Communications
Data Processing
Launcher Equipment
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
critical (including DX-rated contracts) contracts involving unusual and compelling urgency and contracts for major systems
B Moderately critical
Contracts (other than those designated A) for items needed to maintain a Government or contractor production or repair line to preclude out-of-stock conditions or to meet user needs for non-stock items
C Least critical
All other contracts
bull Circumstances of the Contract In general the more complex or difficult the contract the more consideration you should give to contract surveillance When analyzing contract complexity consider
o Contract requirements for reporting production progress and performance Cost-reimbursement time-and-materials and labor-hour contracts typically have stricter requirements for reporting progress and
ontracts performance than fixed-price co Contract performance schedule Contracts with longer
schedules will normally merit closer surveillance because there is a longer period before late deliveries and other routine indicators will indicate a problem A contract with an ambitious completion schedule also will normally merit closer surveillance
o Contractors history of contract performance A contractor with a history of overruns or late deliveries will normally merit closer surveillance
o Contractors experience with the contract supplies or services A contractor with limited experience will normally merit closer surveillance
o Contractors financial capability A contractor with marginal financial capability will normally merit closer surveillance
o Any supplementary written instructions from the contracting office
41 Identifying And Analyzing Cost And Schedule Variances
Uses for Information on Variances (FAR 52232-7(c) 52232-20(a) 52232-22(a) 52243-1(b) 52243-2(b) 52243-3(b) and 52243-4(d))
Information on variances from cost and schedule projections can provide vital input to many contract administration decisions
bull Information on the contractors progress toward timely contract completion is important for the administration of any contract However it is most important for cost-reimbursement time-and-material and labor-hour contracts For these contracts the contractor only agrees to put forth its best effort to complete the contract effort within funding cost or price limitations
bull Information on contractor cost and schedule performance is essential to negotiating an equitable adjustment that leaves the contractor in the same profit position as it was before the modification
bull Information on cost of the current contract can be a key element in projecting the cost of follow-on contracts awarded before the current contract is complete
Consider Both Cost and Schedule Variances To analyze variances you need to be able to consider contractor cost and schedule variances from initial cost estimates For example a contractor in Month 4 of a 12-month contract is tracking perfectly with estimated costs through Month 4 However the contractor is two months behind schedule In other words two months of actual performance have cost as much as four months were projected to cost If we consider only cost there does not appear to be a problem However if we consider both cost and schedule there appears to be significant potential for a cost andor schedule overrun
Information Sources You can use information from a variety of sources to monitor cost and schedule performance variance such as
bull Contractually required costschedule analysis and reporting including
o Cost Performance Reports under Earned Value Management System (EVMS) Guidelines and
o CostSchedule Status Reports bull Contractually required cost information including
o Contract Funds Status Reports o Progress payment requests o Cost-reimbursement vouchers o Contract progress reports or o Limitation of costfunds notices
bull Contractor production management reports and analyses Including
o Phase Planning or Gantt Charts o Production Flow Charts o Program Evaluation and Review Technique (PERT) network
analyses bull Progress review meetings bull Observation by Government personnel
Points to Consider in Information Source Selection The method that you select must be appropriate for the contract When you have a complex or difficult contract for a requirement with a Criticality A Designator you should consider contractually mandated analysis and reporting system (eg compliance with EVMS Guidelines for a major acquisition) The risk involved will likely merit the additional cost of the required system
It is unlikely that a requirement with a Criticality C Designator would merit the added cost of any contractually mandated costschedule reporting For low-value low-risk items you would probably rely on routine observation by Government personnel
To be effective the method that you select must provide or permit you to develop
bull A cost baseline upon which the original contract cost was derived (usually the contractors budget or proposal)
bull Actual costs incurred for completed work bull An estimate to complete
Earned Value Management Systems (DODD 50002R para 3353 MIL-STD-881 and DFARS 252234-7001)
Appendix 4A presents the 32 Industry Standard Guidelines for development and operation of Earned Value Management Systems (EVMSs) Under these guidelines contract work is planned budgeted and scheduled in time-phased planned value increments to establish a cost and schedule measurement baseline Actual cost and schedule performance is then compared to the established baseline
bull Requiring Compliance Requiring contractors to comply with EVMS Guidelines encourages them to use effective internal cost and schedule management control systems and permits the Government to rely on timely data produced by those systems for determining product-oriented contract status However compliance should only be required when contract cost and complexity merit the cost of compliance with EVMS Guidelines
o Unless the requirement is waived by the acquisition Milestone Decision Authority (MDA) the DoD requires EVMS Guideline compliance from any firm with a flexibly-priced
o System research development test or evaluation contract or subcontract with a value of $70 million or more in (FY 1996 constant dollars) or
o System procurement contract with a value of $300 million or more in (FY 1996 constant dollars)
o If you are assigned to another agency consult agency guidance for contracting situations that require contractor compliance with EVMS Guidelines
bull Stipulating a Work Breakdown Structure The framework for EVMS is the Work Breakdown Structure (WBS) and the contractors baseline plan developed using that structure
o The WBS is a product-oriented family tree division of hardware software services and other work tasks which organizes defines and graphically displays the product to be produced as well as the work to be accomplished to achieve the specified product
o When you expect that the contract will require the contractor to comply with EVMS guidelines the request for proposal should require the offeror to provide cost information based on a WBS identified in the solicitation The offeror can provide more levels of information than required by the solicitation but the firm cannot provide fewer
o The multiple levels of the WBS explode the work required down to identifiable work packages that relate costs to specific contract effort In a common WBS
Level 1 is the entire system Level 2 identifies the major elements of Level 1 Level 3 identifies the major elements of Level 2 and
Each lower level provides increasingly detailed information
The following table provides an example of a 3-level WBS structure The example is for a missile system but the concept can be applied to any large system Missile System Work Breakdown Structure Levels 1-
3 Level 1 Level 2 Level 3
Air Vehicle Vehicle Integration and Assembly
Propulsion
Vehicle Stages (each stage included in system design)
Guidance and Control Equipment
Airborne Test Equipment
Auxiliary Equipment
Missile System
Command and Launch Equipment
Integration and Assembly
Surveillance Identification and Tracking Sensors
Launch and Guidance Control
Communications
Data Processing
Launcher Equipment
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
o Contractors financial capability A contractor with marginal financial capability will normally merit closer surveillance
o Any supplementary written instructions from the contracting office
41 Identifying And Analyzing Cost And Schedule Variances
Uses for Information on Variances (FAR 52232-7(c) 52232-20(a) 52232-22(a) 52243-1(b) 52243-2(b) 52243-3(b) and 52243-4(d))
Information on variances from cost and schedule projections can provide vital input to many contract administration decisions
bull Information on the contractors progress toward timely contract completion is important for the administration of any contract However it is most important for cost-reimbursement time-and-material and labor-hour contracts For these contracts the contractor only agrees to put forth its best effort to complete the contract effort within funding cost or price limitations
bull Information on contractor cost and schedule performance is essential to negotiating an equitable adjustment that leaves the contractor in the same profit position as it was before the modification
bull Information on cost of the current contract can be a key element in projecting the cost of follow-on contracts awarded before the current contract is complete
Consider Both Cost and Schedule Variances To analyze variances you need to be able to consider contractor cost and schedule variances from initial cost estimates For example a contractor in Month 4 of a 12-month contract is tracking perfectly with estimated costs through Month 4 However the contractor is two months behind schedule In other words two months of actual performance have cost as much as four months were projected to cost If we consider only cost there does not appear to be a problem However if we consider both cost and schedule there appears to be significant potential for a cost andor schedule overrun
Information Sources You can use information from a variety of sources to monitor cost and schedule performance variance such as
bull Contractually required costschedule analysis and reporting including
o Cost Performance Reports under Earned Value Management System (EVMS) Guidelines and
o CostSchedule Status Reports bull Contractually required cost information including
o Contract Funds Status Reports o Progress payment requests o Cost-reimbursement vouchers o Contract progress reports or o Limitation of costfunds notices
bull Contractor production management reports and analyses Including
o Phase Planning or Gantt Charts o Production Flow Charts o Program Evaluation and Review Technique (PERT) network
analyses bull Progress review meetings bull Observation by Government personnel
Points to Consider in Information Source Selection The method that you select must be appropriate for the contract When you have a complex or difficult contract for a requirement with a Criticality A Designator you should consider contractually mandated analysis and reporting system (eg compliance with EVMS Guidelines for a major acquisition) The risk involved will likely merit the additional cost of the required system
It is unlikely that a requirement with a Criticality C Designator would merit the added cost of any contractually mandated costschedule reporting For low-value low-risk items you would probably rely on routine observation by Government personnel
To be effective the method that you select must provide or permit you to develop
bull A cost baseline upon which the original contract cost was derived (usually the contractors budget or proposal)
bull Actual costs incurred for completed work bull An estimate to complete
Earned Value Management Systems (DODD 50002R para 3353 MIL-STD-881 and DFARS 252234-7001)
Appendix 4A presents the 32 Industry Standard Guidelines for development and operation of Earned Value Management Systems (EVMSs) Under these guidelines contract work is planned budgeted and scheduled in time-phased planned value increments to establish a cost and schedule measurement baseline Actual cost and schedule performance is then compared to the established baseline
bull Requiring Compliance Requiring contractors to comply with EVMS Guidelines encourages them to use effective internal cost and schedule management control systems and permits the Government to rely on timely data produced by those systems for determining product-oriented contract status However compliance should only be required when contract cost and complexity merit the cost of compliance with EVMS Guidelines
o Unless the requirement is waived by the acquisition Milestone Decision Authority (MDA) the DoD requires EVMS Guideline compliance from any firm with a flexibly-priced
o System research development test or evaluation contract or subcontract with a value of $70 million or more in (FY 1996 constant dollars) or
o System procurement contract with a value of $300 million or more in (FY 1996 constant dollars)
o If you are assigned to another agency consult agency guidance for contracting situations that require contractor compliance with EVMS Guidelines
bull Stipulating a Work Breakdown Structure The framework for EVMS is the Work Breakdown Structure (WBS) and the contractors baseline plan developed using that structure
o The WBS is a product-oriented family tree division of hardware software services and other work tasks which organizes defines and graphically displays the product to be produced as well as the work to be accomplished to achieve the specified product
o When you expect that the contract will require the contractor to comply with EVMS guidelines the request for proposal should require the offeror to provide cost information based on a WBS identified in the solicitation The offeror can provide more levels of information than required by the solicitation but the firm cannot provide fewer
o The multiple levels of the WBS explode the work required down to identifiable work packages that relate costs to specific contract effort In a common WBS
Level 1 is the entire system Level 2 identifies the major elements of Level 1 Level 3 identifies the major elements of Level 2 and
Each lower level provides increasingly detailed information
The following table provides an example of a 3-level WBS structure The example is for a missile system but the concept can be applied to any large system Missile System Work Breakdown Structure Levels 1-
3 Level 1 Level 2 Level 3
Air Vehicle Vehicle Integration and Assembly
Propulsion
Vehicle Stages (each stage included in system design)
Guidance and Control Equipment
Airborne Test Equipment
Auxiliary Equipment
Missile System
Command and Launch Equipment
Integration and Assembly
Surveillance Identification and Tracking Sensors
Launch and Guidance Control
Communications
Data Processing
Launcher Equipment
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Information Sources You can use information from a variety of sources to monitor cost and schedule performance variance such as
bull Contractually required costschedule analysis and reporting including
o Cost Performance Reports under Earned Value Management System (EVMS) Guidelines and
o CostSchedule Status Reports bull Contractually required cost information including
o Contract Funds Status Reports o Progress payment requests o Cost-reimbursement vouchers o Contract progress reports or o Limitation of costfunds notices
bull Contractor production management reports and analyses Including
o Phase Planning or Gantt Charts o Production Flow Charts o Program Evaluation and Review Technique (PERT) network
analyses bull Progress review meetings bull Observation by Government personnel
Points to Consider in Information Source Selection The method that you select must be appropriate for the contract When you have a complex or difficult contract for a requirement with a Criticality A Designator you should consider contractually mandated analysis and reporting system (eg compliance with EVMS Guidelines for a major acquisition) The risk involved will likely merit the additional cost of the required system
It is unlikely that a requirement with a Criticality C Designator would merit the added cost of any contractually mandated costschedule reporting For low-value low-risk items you would probably rely on routine observation by Government personnel
To be effective the method that you select must provide or permit you to develop
bull A cost baseline upon which the original contract cost was derived (usually the contractors budget or proposal)
bull Actual costs incurred for completed work bull An estimate to complete
Earned Value Management Systems (DODD 50002R para 3353 MIL-STD-881 and DFARS 252234-7001)
Appendix 4A presents the 32 Industry Standard Guidelines for development and operation of Earned Value Management Systems (EVMSs) Under these guidelines contract work is planned budgeted and scheduled in time-phased planned value increments to establish a cost and schedule measurement baseline Actual cost and schedule performance is then compared to the established baseline
bull Requiring Compliance Requiring contractors to comply with EVMS Guidelines encourages them to use effective internal cost and schedule management control systems and permits the Government to rely on timely data produced by those systems for determining product-oriented contract status However compliance should only be required when contract cost and complexity merit the cost of compliance with EVMS Guidelines
o Unless the requirement is waived by the acquisition Milestone Decision Authority (MDA) the DoD requires EVMS Guideline compliance from any firm with a flexibly-priced
o System research development test or evaluation contract or subcontract with a value of $70 million or more in (FY 1996 constant dollars) or
o System procurement contract with a value of $300 million or more in (FY 1996 constant dollars)
o If you are assigned to another agency consult agency guidance for contracting situations that require contractor compliance with EVMS Guidelines
bull Stipulating a Work Breakdown Structure The framework for EVMS is the Work Breakdown Structure (WBS) and the contractors baseline plan developed using that structure
o The WBS is a product-oriented family tree division of hardware software services and other work tasks which organizes defines and graphically displays the product to be produced as well as the work to be accomplished to achieve the specified product
o When you expect that the contract will require the contractor to comply with EVMS guidelines the request for proposal should require the offeror to provide cost information based on a WBS identified in the solicitation The offeror can provide more levels of information than required by the solicitation but the firm cannot provide fewer
o The multiple levels of the WBS explode the work required down to identifiable work packages that relate costs to specific contract effort In a common WBS
Level 1 is the entire system Level 2 identifies the major elements of Level 1 Level 3 identifies the major elements of Level 2 and
Each lower level provides increasingly detailed information
The following table provides an example of a 3-level WBS structure The example is for a missile system but the concept can be applied to any large system Missile System Work Breakdown Structure Levels 1-
3 Level 1 Level 2 Level 3
Air Vehicle Vehicle Integration and Assembly
Propulsion
Vehicle Stages (each stage included in system design)
Guidance and Control Equipment
Airborne Test Equipment
Auxiliary Equipment
Missile System
Command and Launch Equipment
Integration and Assembly
Surveillance Identification and Tracking Sensors
Launch and Guidance Control
Communications
Data Processing
Launcher Equipment
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Earned Value Management Systems (DODD 50002R para 3353 MIL-STD-881 and DFARS 252234-7001)
Appendix 4A presents the 32 Industry Standard Guidelines for development and operation of Earned Value Management Systems (EVMSs) Under these guidelines contract work is planned budgeted and scheduled in time-phased planned value increments to establish a cost and schedule measurement baseline Actual cost and schedule performance is then compared to the established baseline
bull Requiring Compliance Requiring contractors to comply with EVMS Guidelines encourages them to use effective internal cost and schedule management control systems and permits the Government to rely on timely data produced by those systems for determining product-oriented contract status However compliance should only be required when contract cost and complexity merit the cost of compliance with EVMS Guidelines
o Unless the requirement is waived by the acquisition Milestone Decision Authority (MDA) the DoD requires EVMS Guideline compliance from any firm with a flexibly-priced
o System research development test or evaluation contract or subcontract with a value of $70 million or more in (FY 1996 constant dollars) or
o System procurement contract with a value of $300 million or more in (FY 1996 constant dollars)
o If you are assigned to another agency consult agency guidance for contracting situations that require contractor compliance with EVMS Guidelines
bull Stipulating a Work Breakdown Structure The framework for EVMS is the Work Breakdown Structure (WBS) and the contractors baseline plan developed using that structure
o The WBS is a product-oriented family tree division of hardware software services and other work tasks which organizes defines and graphically displays the product to be produced as well as the work to be accomplished to achieve the specified product
o When you expect that the contract will require the contractor to comply with EVMS guidelines the request for proposal should require the offeror to provide cost information based on a WBS identified in the solicitation The offeror can provide more levels of information than required by the solicitation but the firm cannot provide fewer
o The multiple levels of the WBS explode the work required down to identifiable work packages that relate costs to specific contract effort In a common WBS
Level 1 is the entire system Level 2 identifies the major elements of Level 1 Level 3 identifies the major elements of Level 2 and
Each lower level provides increasingly detailed information
The following table provides an example of a 3-level WBS structure The example is for a missile system but the concept can be applied to any large system Missile System Work Breakdown Structure Levels 1-
3 Level 1 Level 2 Level 3
Air Vehicle Vehicle Integration and Assembly
Propulsion
Vehicle Stages (each stage included in system design)
Guidance and Control Equipment
Airborne Test Equipment
Auxiliary Equipment
Missile System
Command and Launch Equipment
Integration and Assembly
Surveillance Identification and Tracking Sensors
Launch and Guidance Control
Communications
Data Processing
Launcher Equipment
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
o The multiple levels of the WBS explode the work required down to identifiable work packages that relate costs to specific contract effort In a common WBS
Level 1 is the entire system Level 2 identifies the major elements of Level 1 Level 3 identifies the major elements of Level 2 and
Each lower level provides increasingly detailed information
The following table provides an example of a 3-level WBS structure The example is for a missile system but the concept can be applied to any large system Missile System Work Breakdown Structure Levels 1-
3 Level 1 Level 2 Level 3
Air Vehicle Vehicle Integration and Assembly
Propulsion
Vehicle Stages (each stage included in system design)
Guidance and Control Equipment
Airborne Test Equipment
Auxiliary Equipment
Missile System
Command and Launch Equipment
Integration and Assembly
Surveillance Identification and Tracking Sensors
Launch and Guidance Control
Communications
Data Processing
Launcher Equipment
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Auxiliary Equipment Training Equipment
Services
Facilities Peculiar Support Equipment
Organizational Level
Intermediate Level
Depot Level System Test and Evaluation
Development of Test and Evaluation
Operational Test and Evaluation
Mock-ups
Test and Evaluation Support
Test Facilities SystemsProject Management
Systems Engineering
Project Management Data Technical Publications
Engineering Data
Management Data
Support Data
Data Depository OperationalSite Activation
Contractor Technical Support
Site Construction
SiteShipVehicle Conversion
On-site System Assembly Installation and Checkout
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Common Support Equipment
Organizational Level
Intermediate Level
Depot Level Industrial Facilities
Construction
ConversionExpansion Initial Spares and Repair Parts
Identified Spares Allowance List ( by system grouping or element)
41 Identifying And Analyzing Cost And Schedule Variances (cont)
bull Establishing A Contract CostSchedule Baseline When the contract requires EVMS compliance a multifunctional Integrated Baseline Review (IBR) should be conducted after contract award Government participants in the review will normally include engineers other technical personnel EVMS support personnel and program management personnel Together with contractor representatives this team will review the contractors baseline plan for contract performance This will normally include work authorizations schedules work package budgets and progress measurement methods
bull Comparing Actual CostSchedule With The Baseline Each month during contract performance the contractor will submit a Cost Performance Report (CPR) that compares actual performance with budgeted performance and establishes a common reference point for identifying variances
o CPRs provide key information on o Budgeted Cost of Work Scheduled (BCWS) BCWS is the
amount budgeted for work scheduled to be accomplished It is a time-phased expenditure plan measurable for the current cumulative-to-date and contract completion time periods
o Budgeted Cost of Work Performed (BCWP) BCWP is the amount budgeted for that portion of the scheduled work that was actually performed (ie what the contractor planned to spend for the work actually accomplished)
o Actual Cost of Work Performed (ACWP) ACWP is the amount actually spent in the accomplishment of work performed The amount actually spent includes direct costs (eg labor and material) and indirect costs (eg overhead and GampA expense)
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
o The following example demonstrates how BCWS BCWP and ACWP can be used to identify contract costschedule variances
In this example the contractor is ahead of schedule BCWP is $11000 greater than BCWS That is almost 29 percent more work completed than was scheduled However for the work performed the contractor is over budget The ACWP is $8000 more than the BCWP That is approximately 16 percent over budget
bull Analyzing Reported Variances Note that the calculations above identify an area where actual contract costs exceed budgeted costs but do not explain how the variances will affect the total contract
o To permit more detailed analysis the CPR must present
o An analysis of performance by work breakdown structure (WBS) element
o An analysis of performance by organizational category o A time-phased contract budgeted cost baseline for
contract completion o A time-phase manpower loading estimate for future
contract completion and o An explanation and analysis of significant variances o Normally you will need support from Government
technical personnel to review the contractors analysis and determine the reason for and the significance of any cost variance
bull Example Of Performance Analysis By WBS Element The table below presents key CPR information for several elements of the contract WBS
Cost Performance Report Work Breakdown Structure Budget Baseline
Cumulative Cost To Date (in $000) Cost At Completion (in $000)
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
$15 mil Budgeted Cost Variance WBS
Element Work
Scheduled Work
Performed
Schedule
Cost
Budgeted
Estimated
Variance11 250 250 260 0 (10) 250 260 (10)12 90 85 84 (5) 1 100 100 013 130 150 155 20 (5) 330 340 (10)14 200 200 185 0 15 250 235 1515 300 310 320 10 (10) 400 415 (15)16 120 120 140 0 (20) 120 140 (20)
Subtotal 1090 1115 1144 1450 1490 (40)Mgt Reserve
50 50
Total 1090 1115 1144 1500 1490 10
Based on the above report you could make the following observations
bull WBS Element 11 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all are equal and the work under WBS Element A is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $10000 cost overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $10000 cost overrun
bull WBS Element 12 o Comparison of BCWS with BCWP reveals that the work is
behind schedule o Comparison of BCWP with ACWP shows that the contractor
is slightly underrunning budgeted cost o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the work is expected to be on budget at completion
bull WBS Element 13 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing a slight overrun of $5000 over budgeted cost
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the overrun is expected to grow to $10000 at completion
bull WBS Element 14 o Comparison of BCWS with BCWP reveals that the work is
on schedule
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
o Comparison of BCWP with ACWP shows that the contractor is experiencing an underrun of $15000
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns indicates that the underrun is expected to remain at $15000 through completion
bull WBS Element 15 o Comparison of BCWS with BCWP reveals that the work is
ahead of schedule o Comparison of BCWP with ACWP shows that the contractor
is experiencing an overrun of $10000 o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance columns indicates that the overrun is expected to grow to $15000 at completion
bull WBS Element 16 o Comparison of BCWS BCWP and the Cost-at-Completion
Budgeted reveals that all equal and the work under Element F is complete
o Comparison of BCWP and ACWP reveals that the element experienced a $20000 overrun at completion
o Comparison of the Cost-at-Completion Budgeted Estimated and Variance columns also reflect the $20000 overrun
bull Subtotal o Comparison of the Cost-at-Completion Budgeted
Estimated and Variance Subtotals reveals a projected net overrun of $40000 Since the contractor had set aside a management reserve of $50000 the contract is still within the original Budgeted Cost baseline with $10000 of management reserve remaining There appears to be little need for in-depth technical analysis at this time because the contractor is still within the original Budget Cost baseline and the contract is 76 percent complete
CostSchedule Status Reports (DFARS 252242-7005) For flexibly-priced contracts that require close costschedule monitoring but do not merit a requirement for full compliance with EVMS guidelines consider requiring costschedule status reporting without requiring EVMS compliance One example of this type of reporting is the DoD CostSchedule Status Report (CSSR)
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
o Must assure that the contract requires the contractor to comply with CostSchedule Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 12 months o Does not meet the criteria for requiring compliance
with EVMS Guidelines and submission of CPRs and o Dollar value merits the CSSR requirement Application
to contracts of less than $6 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May insert a CostSchedule Status Reporting requirement in a contract that does not support major system acquisition if the need for costschedule
the requirement tracking justifies bull Planning And Reporting Under CostSchedule Status
Reporting the contractor is required to o Describe its plan for costschedule management and
reporting o Support an IBR of the contractors costschedule
baseline if required by the Government and o Provide monthly CSSRs analyzing contract performance
by WBS element in a format similar to the CPR performance analysis by WBS element The CSSR format is similar to the CPR format for analysis of contract performance by WBS
bull Analyzing Reports CSSR analysis can be performed using the same calculations described above for CPR WBS performance analysis The reliance that you can place on this analysis will depend on the contractors plan for CSSR reporting and the system for gathering the data provided
Contract Funds Status Report (DODD 50002-R para 644) For flexibly-priced contracts you may also consider requiring a continuing detailed report on the status of contract funding You may require this report in addition to or instead of the type of costschedule reporting described above One example of this type of reporting is the DoD Contract Funds Status Report (CFSR)
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
CONTRACT FUNDS STATUS REPORT (Dollars in ) Form approved OMB No 0704-0188
The public reporting burden for this collection of information is estimated to average 8 hours per response including the time for reviewing instructions searching existing data sources gathering and maintaining the data needed and completing and reviewing the collection of information Send comments regarding this burden estimate or any other aspect of this collection including suggestions for reducing the burden to Department of Defense Washington Headquarters Services Directorate for information Operations and Reports (0704-0188) 1215 Jefferson Davis Highway Suite 1204 Arlington VA 22202-4302 Respondents should be aware that notwithstanding any other provision of law no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number PLEASE DO NOT RETURN YOUR COMPLETED FORM TO THE ABOVE ADDRESS 1 Contract Number
3 Contract Funding For
5 Previous Report Date
7 Contractor (Name address and zip code)
9 Initial Contract Price
a Target b Ceiling 2 Contract Type
4 Appropriation 6 Current Report Date
8 Program 10 Adjusted Contract Price
a Target b Ceiling 11 FUNDING INFORMATION Accrued Contract Work
Authorized Forecast
Line ItemsWbs
Elemen
Appro-
Priation
Ident
Funding Authorized To Date
Expenditures Open
Commitments
Defintized
Not Definiti
Subtotal
Not Yet Authori
All Other
Subtotal
Total Require-
ments
Funds
Carry-
Net Funds Required
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
t
a
i-fication
b
c Total
d
e zed
f
g zed
h
Work
i
j k over
l
m
12 CONTRACT WORK AUTHORIZED (With FeeProfit) - ACTUAL OR PROJECTED Actual
to Date At
Completion
a Open Commitments
b Accrued Expenditures
c Total (12a + 12b)
13 Forecast of billings to the
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Government 14 Estimated Termination Costs
15 Remarks
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Requiring Compliance When preparing a flexibly-priced contract DoD contracting officers
o Must assure that the contract requires the contractor to comply with Contract Funds Status Reporting requirements when the contract
o Supports a major system acquisition o Period exceeds 6 months and o Dollar value merits the CFSR requirement Application
to contracts of less than $12 million (FY 1996 constant dollars) must be evaluated carefully to ensure that only the minimum information required for effective contract management is required
o May consider inserting a Contract Funds Status Reporting requirement in a contract that does not support major system acquisition if the need for cost
ng justifies the requirement trackibull Reporting The requirement for Contract Funds Status
Reporting should be tailored to the specific contract involved The CFSR normally required quarterly and must provide enough information for Government personnel to compare the estimate of total funds required to complete authorized contract work with existing contract funding
bull Analyzing Report Information These reports can be combined with cost information from contractor requests for progress payment or cost-reimbursement vouchers to obtain a general picture of contract progress compared to costs expended If you identify an apparent problem you should request a technical review of the contractors physical progress toward contract completion
Progress Payment Requests (FAR 32503-4 and -5) A contractor making a request for progress payments must complete a Standard Form (SF) 1443 Contractors Request for Progress Payment As part of the request the contractor must identify total costs to date and estimated additional cost to complete the contract The estimated additional cost to complete the contract may be the last estimate made adjusted for costs incurred since the last estimate However the contractor must update the estimate at least semi-annually
bull Before making progress payments you must establish the reliability of the contractors accounting system and controls Once you have done that you may rely on the accounting system and the certification on the SF 1443 when making a progress payment
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Normally you should not request an audit of individual progress payment requests However you should consider requesting an audit if you have reason to
o Question the reliability or accuracy of the contractors certification on the SF 1443 or
o Believe that the contract will involve a loss bull While you may rely on the contractors accounting system
and certification without prepayment review you must make periodic reviews to determine the validity of progress payments already made or expected to be made These post-payment reviews must include a number of elements including a determination that the contract price will be adequate to cover the anticipated cost of contract completion or that the contractor has adequate resources to complete the contract A review of the contractors actual physical progress should be a part of these post-payment reviews
Cost-Reimbursement Vouchers (FAR 52216-7(b)) Under cost-reimbursement contracts the contractor can submit vouchers or invoices for payment of costs Unlike the Contractors Request for Progress Payment the contractor is not required to submit an estimate of the cost to complete the contract with the cost-reimbursement voucher However the vouchers do provide an excellent record of the contractors costs that can be coupled with other information such as production surveillance and reporting documents to identify potential cost overruns The record includes
bull Those recorded costs that at the time of the request for reimbursement the contractor has paid by cash check or other form of actual payment for items or services purchased directly for the contract
bull Costs incurred but not necessarily paid for including o Materials issued from the contractors inventory and
placed in the production process for use on the contract
o Direct labor o Direct material o Other direct in-house costs and o Properly allocable and allowable indirect costs
bull The amount of progress payments that have been paid to the contractors subcontractors
bull Contractor contributions to any pension or other post-retirement benefit profit sharing or stock ownership plan paid in accordance with contract requirements
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Limitation of CostFunds NoticeI All cost-reimbursement contracts must include a contract clause limiting the Governments obligation to reimburse contractor costs As shown in the table below each of the clauses used to limit the Governments obligation also requires contractor notification that total costs are approaching that limit
Contractor Notification Requirements If the contract is
Then the contract must include the
Which requires the contractor to notify the Government
A fully-funded cost-reimbursement contract for other than consolidated facilities facilities acquisition or facilities use
Limitation of Cost clause
(FAR 52232-20)
Whenever the Government share of contract costs is expected to
middot Exceed a stated percentage (normally 75 percent) of estimated contract cost within a stated period (normally 60 days) or
middot Be either greater or substantially less than previously estimated
A cost-reimbursement contract for consolidated facilities facilities acquisition or facilities use
Limitation of Cost (Facilities) clause (FAR 52232-21)
Whenever the Government share of contract costs is expected to
middot Exceed 85 percent of estimated contract cost within the next 30 days or
middot Be either greater or substantively less than previously estimated
An incrementally-funded cost-reimbursement contract
Limitation of Funds clause
(FAR 52232-22)
Whenever the Government share of contract costs is expected to exceed a stated percentage (normally 75 percent) of the amount so far allocated to the contract cost within a stated
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
period (normally 60 days)
Sixty days before the end of the period specified in the contract schedule of the estimated amount of funds (if any) required to continue timely performance
A time-and-material or labor-hour contract
Payments Under Time-and-Materials and Labor-Hour Contracts clause
(FAR 52232-7)
Hourly rate payments and material costs are expected to
middot Exceed 85 percent of the ceiling price within the next 30 days or
middot Be substantially greater or less than the stated ceiling price
DO NOT expect contractor notification requirements to replace effective contract surveillance You should be questioning significant variations long before contractor notification By the time you receive contractor notification it may be too late for the contractor to take corrective action In fact the contractor may fail to provide timely notice despite the contract requirement There have been many contracts where the contractor did not provide notice until after all contract funds were expended
Gantt or Phase- Planning Charts One of the most common techniques for managing schedules for both supply and service contracts is the Gantt Chart (also known as the Phase-Planning Chart) The Gantt Chart provides a graphical representation of the start date end date and process time for each phase in the production process
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
The Gantt chart above depicts the critical tasks required to develop a Management Information System (MIS) Plan For each task
bull The estimated days required to complete the task are identified along with a graphic representation of the length of time required
bull In the graphic presentation bars representing contract effort and a grid scaled to the indicated time (eg weeks in the example above) are used to indicate the estimated length of time required to complete each task
bull As the work is performed the bars may be shaded to indicate the time worked
bull If more time than estimated is required to complete a task the related bar is extended
bull When the task is completed the actual days required are also annotated
With some understanding of the effort required you can use this Gantt chart to identify schedule problems that will effect the cost to complete the project For example the chart above shows that the performance specifications should be completed
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
before work begins on the general system concept If development of the performance specifications took 10 days instead of three that delay could effect the entire project The contractor would need to examine ways of shortening other tasks or performing tasks concurrently to meet the required schedule
If the problems extend the time required to complete an activity on the critical path the contractor must take action to identify cost effective ways to meet the original schedule When there is a threat to the contract schedule or cost estimates you should call upon Government technical personnel to examine the contractors estimates
Production Flow Charts Production flow charts can be developed to more clearly define contract schedules The production flow chart is developed using the major schedule milestones production sequence and projected manpower The example below depicts the first unit flow chart for production of a new product
The flow time for each of the assemblies is determined by utilizing the estimated labor-hours crew sizes and the operations shifts projected for contract performance
With the overall sequence of the major activity defined activities can be scheduled for completion to meet subsequent events which are dependent upon them Start times for each activity will be determined by estimating when the activity must be completed and the estimated time required to complete the activity
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
TampPP - Tools and Production Planning PCR - Production Control Records FTBO - Flow Time Between Orders UBO - Unit Buy Off PKG - Package Tran - Transportation
All Flow Times are Shown in Days
Using this procedure the entire schedule can be displayed on a single chart All organizations can determine at a glance when their responsibilities start the estimated time required and the required completion time The effect of any delay on the overall schedule becomes obvious
In the chart above if circuit card assembly and test required 22 days instead of 20 the overall project would not be delayed because of the 5-day flow time between orders However if circuit card assembly and test required 40 days because of production problems contractor corrective action would be necessary to meet the original schedule
With knowledge of the interrelated activities required for production Government personnel could raise questions regarding contractor corrective actions Contractor projected actions could be evaluated for effectiveness and potential effect on cost
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Program Evaluation and Review Technique The Program Evaluation and Review Technique (PERT) takes the analysis of production flow one step further PERT permits the contractor to analyze the relationships of all elements needed to complete a project and identify the critical path -- the path that defines the estimated time required to complete the project
If an element requires more time than estimated PERT permits analysis of the effect on timely project completion (the critical path) If the increased time required to complete the element does not affect the critical path no management action may be required If the completion schedule is affected PERT permits analysis of alternative corrective actions and the cost associated with each action
bull PERT Network Structure To understand PERT analysis you must first understand PERT network structure The PERT network is composed of events and activities
o An event is a specific milestone that must be reached before a new activity can begin For example a foundation must be completed before a contractor can start erecting a building frame On a PERT chart events are typically shown as circles or nodes
o An activity is the work effort over a period of time required to achieve a specific event On a PERT chart activities are shown as the lines that connect the event circles and in effect define the relationships of the activities and events required to complete a project
o The figure below depicts a PERT network Network events are labeled with letters (eg A B C etc) The activity that begins at A and ends at B is referred to as AB Note that activities AB BE AC CD and DE all must be completed before Event E can be achieved
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Activity Times The next thing needed to develop the PERT network is information on the length of time to accomplish each activity PERT uses three estimates of the time required to complete each activity
Where
a = Optimistic time -- the completion time if everything goes as well as can be expected
m = Most likely time -- the completion time if everything goes as expected
b = Pessimistic time -- the completion time if the things that may go wrong do go wrong
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
To facilitate analysis and discussion times for the activities in the network above are delineated in the following table
Activities and Times Required for Project Completion Activity Length
(Months) Activity Length
(Months) AB 3 EF 3 AC 1 EG 4 BE 2 FH 4 CD 1 GH 5 DE 1 HI 2
bull Early Start Times If you assume that Event A is project start you can work across the PERT network and determine how long it will take to complete the project The times developed by working from the beginning to end are known as the Early Start Times or Te When reading through the network below note that
o The Te entries are above the activity lines o The format of the Te entries is Length of Time
Required to Complete the Activity (Activity Start Time Start Time Plus Length of Time Required to Complete the Activity) For example
o Activity AB reads 3(03) which means the it will take three months to complete the activity the activity can begin at project start (Month 0) and it will end at the end of Month 3
o Activity BE reads 2(35) which means that it will take two months to complete the activity the activity can begin at the end of Month 3 and it will end at the end of Month 5
o When more than one activity ends at an event the earliest start time for the next activity is the latest time coming into the event For example DE is projected to be complete at the end of Month 3 but since BE is not projected to be complete until the end of Month 5 any activities beginning at E cannot start until the end of Month 5
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Late Start Times Based on the PERT network developed so far the project should take sixteen months to complete The next step is to determine Tl or Late Start Times -- the latest time that an event can start and still complete the project on time The Tl is calculated the same way as Te except the calculation is done from the end of the project back to the beginning When reading through the network below note that
o The Tl entries are below the activity lines o The format for Tl is similar to the format for Te For
example o Activity HI reads 2(1416) which means that it will
take two months to complete the activity If the activity is to end at Month 16 it must start no later than Month 14
o Activity FH reads 4(1014) which means that it will take four months to complete the activity and if the activity is to end at Month 14 it must start no later than Month 10
o When more than one activity begins at an event the earliest Tl is used to calculate the Tl for activities prior to the event For example EF has a Tl of Month 7 while EG has a Tl of Month 5 The end time used to calculate BE and DE would be the earliest available Tl or Month 5
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Critical Path Given the information now available you can identify the Critical Path The longest of these paths (a-b-e-g-h-I) is sixteen days which is the shortest time in which the entire network can be completed This is called the critical path of the network -- the path where the difference between Te and Tl (slack time) equals zero The following table and network show the critical path - AB BE EG GH and HI
Activity AB AC BE CD DE EF EG FH GH HI
Te 0 0 3 1 2 5 5 8 9 14 Tl 0 2 3 3 4 7 5 10 9 14
Slack Time
0 2 0 2 2 2 0 2 0 0
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull CostSchedule Impact With the critical path established you can consider the impact of any activity time change
o Any increase or decrease in the time required to complete any activity on the critical path will increase or decrease the time to complete the entire project
o If the time required to complete Activity HI grew from two months to three months then the entire project time would be increased by one month
o If there is a need to accelerate the project schedule then management knows which activities must be shortened to shorten the project (critical path activities) and can evaluate the costschedule trade-offs
o For activities not on the critical path changes do not impact the entire project time
o If the time required to complete Activity FH grew from four to five months there would be no increase in total project time because no activities beyond Event H can begin until all activities leading up to Event H have been completed Activity FH would still be completed a full month ahead of Activity GH
o If the time to complete Activity FH were accelerated to three months again there would be no effect on the time required to complete the project Activity GI could still not begin until Activity FH is completed
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Problem Analysis If the problems extend the time required to complete a task the contractor must determine the effect on the remaining schedule If timely performance is affected the contractor must take action to identify cost effective ways to shorten the critical path to meet the original schedule When there is a schedule or cost risk to the Government you should request Government technical personnel to examine the contractors analysis and projected action to correct the problem
Progress Review Meetings Regularly scheduled progress review meetings provide an excellent forum for the identification and resolution of contract problems that may affect contract cost and performance Many contracts include a requirement for periodic review meetings When there is no contract requirement and you feel that such meetings would be beneficial consider suggesting an informal review program to the contractor as a forum for sharing concerns before they become problems
bull Management Review Meetings Management review meetings typically include key members of the contractor and Government contract teams (eg program management contracting technical quality assurance and others)
o Together you can evaluate overall contract status including the identification and resolution of problems that may be affecting contract cost or schedule
o The contractor may be required to submit a contract status report prior to each review Those status reports then become the basis for conference analysis and discussion
o You should encourage open discussion to identify problems that may affect contract schedule or cost as early as possible so that action can be taken to resolve them and minimize their effect
bull Technical Team Meetings Periodic meetings between Government and contractor technical personnel provide a forum to discuss technical questions that may affect contract cost and schedule These technical meetings can be used to supplement or replace the management team meetings described above
o As a supplement these meetings can be used to resolve technical questions too complicated to be resolved at management team meetings
o As an alternative these meetings provide a vital forum for the exchange of information and ideas
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Caution all participants in such meetings that contract changes can only be accomplished through written contract modification Agreements at the meetings cannot change the contract terms
bull Caution Government personnel not to issue direction to the contractor that is outside their authority under the contract Remind them that they may be held personally responsible for any unauthorized commitment -- constructive change -- unless the commitment is ratified by the Government
bull Caution contractor personnel to notify the contracting officer immediately of any action by any Government personnel that they interpret as a change to the contract
Routine Observations by Government Personnel Even with all the available reports and management analyses the first indication of potential costschedule problems often comes from routine observations by Government technical personnel
bull Encourage Observation Routine observations by Government personnel could identify a variety of indicators of problems affecting timely and cost effective contract performance such as
o Selection of work methods that are not suited to the contract effort
o Problems in completing critical tasks or production processes
o Inadequate personnel training or experience o Labor unrest (ie dissatisfaction that could cause a
slowdown in operations) o Inadequate tooling or equipment o Excessive work in process inventory o Excessive scrap rates or o Comments about costschedule problems made by
contractor personnel bull Encourage Reporting The biggest problem with routine
observations as a source of information on potential overruns is that the observations are often not reported to the contracting officer To benefit from this source of information you must foster the team concept and make every effort to keep the lines of communication open between yourself the auditor and such Government technical personnel as the user Contracting Officer Representative (COR) Contracting Officer Technical Representative (COTR) Industrial Specialist or Quality Assurance Representative (QAR) These specialists form the
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
core of the acquisition team They approach the contract for different perspectives but with one goal effective and efficient contract performance
bull Foster Communication By fostering communication between Government Acquisition Team members you can benefit from the picture that is created when different pieces of the puzzle are brought together
o On a manufacturing contract a QAR notes a large number of rejects from a particular process At the same time the Industrial Specialist notes that a shop responsible for that process is not meeting schedule commitments Together these bits of information paint a picture of a contractor that has significant quality problems that are affecting production and contract cost
o On an engineering services contract the COTR feels that the Contractor Team Leader has only minimal experience in performing the type of work required by the contract A Government Project Engineer feels that the Team Leader is putting unreasonable constraints on contractor personnel and these constraints are hampering contract operations It may be that the contractors failure to hire a qualified Team Leader is putting the contract schedule and cost performance in jeopardy
42 Estimating Cost To Complete
Support for Estimating Cost to Complete the Contract Whenever you suspect a cost overrun remember that the contracting officer is ultimately responsible for monitoring contractor performance and estimated cost to complete the contract However the contracting officer should actively seek support from other members of the Government Acquisition Team
bull Assistance from Government technical personnel is essential in analyzing contract progress to date and estimating the amount of effort required to complete the contract
bull The auditor is the Government expert on contract cost Audit assistance can be invaluable in verifying the actual contract cost incurred and validating data offered by the contractor to support projections of the cost to complete the contract
bull The requiring activity can provide valuable insight to the analysis process As the organization responsible for
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
managing funds they must be involved in any decision to increase contract price or any decision to modify contract requirements to contain costs
Procedure for Estimating the Cost to Complete the Contract When developing an estimate of the cost to complete a contract
bull Determine the progress toward contract completion to date bull Determine the cost of the contract work completed to date bull Determine the reasons for variances from initial estimates bull Estimate the amount of work remaining to be completed bull Estimate the cost of the work remaining to be completed
Progress Toward Contract Completion Normally the most difficult element of developing an estimate to complete the contract is determining the amount of work completed to date It is relatively easy to determine the number of hours worked wages paid and material purchased but those are measures of input --not measures of progress toward contract completion It is not always easy to determine how these inputs have contributed to completing the work required by the contract
To determine the work completed to date you must rely on the sources and types of information identified in the previous section of this chapter
bull Contractually required costschedule analysis and reporting
bull Contractually required cost information bull Contractor production management reports and analyses bull Progress review meetings or bull Observation by Government personnel
Normally the more detailed the information provided by the data source the more valuable it is as a basis of estimating the cost to complete the contract For example detailed contractor CPR data would normally be more valuable than general contract production management reports because the BCWS BCWP and ACWP data presented in the CPR provide detailed information on the contractors costschedule performance Contract progress reports typically provide a general overview of contract performance and specific detail only on a limited number of special interest items
As you analyze available information you should request support from the using activity and Government technical personnel They are the experts on Government requirements and
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
contractor progress When you request analysis support establish an as of date for the analysis That date can then be used for the collection of data on both contract work completed and the cost for completing that work
Cost of Work Completed to Date (FAR 32503-4(b)) In determining the cost of work completed rely on contractor submissions and input from involved members of the Government Acquisition Team Normally the cognizant auditor plays a key role in evaluating cost information submitted by the contractor However others can play key roles particularly when the contractor has implemented a management system that complies with EVMS Guidelines
If the auditor has identified deficiencies in the contractors accounting system consult with the auditor to determine how those deficiencies may affect the contractors recording of contract costs
Determine Reasons for Variances From Initial Estimates Before you can estimate the cost to complete the contract you must determine the reason or reasons for the overrun
bull Gather Information Solicit opinions from the contractor and Government Acquisition Team experts concerning the reasons for the overrun Ask questions such as
o Why do actual costs differ from the original estimates
o Have circumstances outside the contract affected costs For example has a major reduction in business volume increased indirect cost rates and inflated contract costs
o Does the Government have any responsibility for the increased costs
o What can be done by the contractor andor the Government to bring costs back into line
bull Identify The Reason The overrun could result from many possible reasons including
o Conflicting interpretations of contract requirements o One or more specific contract performance problems or o Generally poor contractor management of contract
operations bull Evaluate Current Status Evaluate available information to
establish whether the situation that caused the overrun has been resolved
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
Estimate Amount of Work Remaining Once you have determined the amount of contract effort completed to date it is relatively easy to estimate the tasks that remain to be completed Again you should request support from other members of the Government Acquisition Team as you perform your analysis They can provide invaluable support in developing and evaluating both cost and schedule estimates for contract completion
If the reason for the overrun has been resolved you can be much more certain of your estimate of the work required to complete the contract If they have not been resolved you must consider possible solutions and related risks as you develop your estimate
Cost of Work Remaining to be Completed Once you have determined the amount of work remaining and the causes for cost growth you can estimate the cost to complete the contract Given this information estimating the cost to complete the contract is much like estimating the cost of a new contract
bull Select estimating methods and quantitative techniques based on the information available You can develop estimates using any appropriate method -- round-table comparison or detailed However as the contractor progresses toward contract completion you should expect more reliance on comparison and detailed estimates and less on round table estimates
bull Consider contract cost history along with other available data in estimate development For example where there has been a history of schedule delays and cost overruns it may not be reasonable to assume that future contract effort will be completed as projected
bull Where there has been a history of schedule delays or cost overruns it may not be reasonable to assume that future effort will be as projected
bull If there are cost or schedule constraints develop several cost estimates based on different completion scenarios such as
o Complete contract to original contract specification and schedule requirements
o Complete the contract to original specification requirements but allow additional time
o Complete the contract to original schedule requirements but reduce contract specification
o Adjust both the contract specification and schedule requirements
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
43 Resolving Potential Cost Overruns
Course of Action Once the actual cost of work completed and estimates to complete have been identified a course of action must be determined
Fixed-Price Contracts A cost overrun in a firm fixed-price contract fixed-price economic price adjustment contract (unless the adjustment is based on actual cost) or fixed-price contract with prospective price redetermination contract will not affect contract price A cost overrun on a fixed-price incentive contract or fixed-price contract with price redetermination may affect overall contract price but the Governments contract obligation will be limited by the contract ceiling price
While the effect on contract price will be limited a cost overrun may have a substantial effect on contract performance Additional costs will reduce profits and may result in a contract loss Contractor efforts to control costs may result in decisions that affect the quality of contract performance Accordingly with fixed-price contracts your primary efforts should generally be directed toward
bull Monitoring contract performance more closely to assure that all work is being accomplished in accordance with contract requirements and
bull Considering the need for adjustment in the liquidation rate for any progress payments based on cost
Cost-Reimbursement Contracts For cost-reimbursement contracts you must determine the most appropriate action considering that the Government is responsible for reimbursing the contractor for all allowable costs up to the cost and funding limits established in the contract The most common alternatives for action include
bull Withhold action until more information is available bull Provide additional fundstime to complete the contract as
is bull Redefine the contract effort to fit existing funds bull Allow the contract to continue without change bull Terminate the contract
As you determine the appropriate course of action you should consider contract cost and other factors including
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
contract schedule probable impact of not completing the contract alternatives to completing the contract (eg terminate and reprocure from another source) availability and sources of funding and many more
Withhold Action In situations where your analysis has identified cost or schedule variances you may wish to stand pat (ie take no action until you can obtain additional information)
bull Consider this course of action when o You are not sure that the contractor cannot recover
from current cost or schedule variances to complete the contract within the original cost and schedule
o You are awaiting additional information that may affect contract cost and schedule
o A major program management decision is in progress and the decision will affect the action you will take on the contract
o Funding is uncertain bull When you withhold action awaiting more information inform
the contractor Failure to put the contractor on notice can result in the Government assuming additional liability through constructive consent Consider the following general steps to put the contractor on notice that the Government intends to withhold action pending further fact-finding
o Acknowledge that the Government is considering whether to add funds or increase the estimated contract cost
o Point out that the contractor is entitled to stop work when the contract dollar limit has been reached
o Admonish the contractor that any work done beyond the dollar limit will be at the contractors own risk
Provide Extra FundsTime to Complete the Contract When additional funding is available the need exists and the increase in cost is justifiable the most logical course of action may be to continue contract performance following the original contract technical and schedule requirements
You should consider schedule relief with or without extra funding when contract problems have affected the contractors ability to complete the contract on time
Consider the following points when implementing a decision to add funds andor change the contract schedule
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Obtain necessary approvals for your proposed course of action
o If you are planning to increase contract cost establish the amount of additional funds required and obtain a funded purchase request from the requiring activity
o If you are planning to change the contract schedule obtain concurrence on any proposed delivery date changes from the requiring activity
bull Meet with the Contractor to review contract requirements and verify the remaining tasks then negotiate the costtime changes needed to complete the contract
bull Negotiate adequate consideration to the Government for increasing contract cost or revising the contract schedule (eg a reduction in potential contract fee)
bull Execute and distribute a bilateral contract modification
Redefine Contract Requirements to Fit Existing Funds Redefining contract effort to fit available funds -- sometimes called downscoping -- can be a viable option for research contracts as well as supply and service contracts with multiple line items This option is particularly attractive when additional funds are not available but it can also be employed when the requiring activity determines that marginal elements of the contract are not worth the additional money
To implement a decision to reduce contract scope use either a deductive contract modification of a partial termination for convenience As you decide which one to use consider the guidance presented in the paragraphs below However consult with your agency legal counsel before making a final decision on which approach is appropriate in your situation
bull Deductive Contract Modification In general you should use a deductive modification when the redefinition of contract requirements is within the scope of the original contract
o For example you can use a contract modification under the Changes clause to downsize requirements in a variety of ways including changes in
o Specifications drawings or designs for supplies o Description of services o Method of shipping or packing o Place of delivery or performance o However none of the Changes clauses available for
cost reimbursement contracts provide for changes in quantity Such changes are normally considered to change the scope of the contract
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
bull Partial Termination for Convenience In general a partial termination for convenience is appropriate when the redefinition of contract requirements will change the scope of the original contract You should use a partial termination when
o You are redefining contract requirements by eliminating items from the contract
o The redefinition of other requirements (eg the description of services) is so substantial as to change the scope of the contract
Allow the Contract to Continue Without Change If you select this alternative allow the contract to continue until funds expire
bull Consider this alternative when o Additional funds are not available but continued
contract performance will benefit the Government o Most of the vital elements of the contract will be
accomplished within current requirements and funding o The cost of contract redefinition or termination will
be greater than the cost of simply allowing the contractor to use available funds and then halting contract performance
bull If you select this alternative it is absolutely critical that you
o Advise the contractor that additional funds will not be added to the contract
o Advise the contractor that any contract performance beyond current contract dollar limits will be at the contractors expense
o Not suggest that the contractor perform beyond current contract dollar limits
Terminate the Contract If you believe that the Governments best interests will be served by ending the contract immediately terminate the entire contract for convenience
Appendix 4A Earned Value Management System Guidelines
Organization
1 Define the authorized work elements for the program A work breakdown structure (WBS) tailored for effective internal management control is commonly used in this process
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
2 Identify the program organizational structure including the major subcontractors responsible for accomplishing the authorized work and define the organizational elements in which work will be planned and controlled
3 Provide for the integration of the companys planning scheduling budgeting work authorization and cost accumulation processes with each other and as appropriate the program work breakdown structure and the program organizational structure
4 Identify the company organization or function responsible for controlling overhead (indirect costs)
5 Provide for integration of the program work breakdown structure and the program organizational structure in a manner that permits cost and schedule performance measurement by elements of either or both structures as needed
Planning Scheduling and Budgeting
6 Schedule the authorized work in a manner which describes the sequence of work and identifies significant task interdependencies required to meet the requirements of the program
7 Identify physical products milestones technical performance goals or other indicators that will be used to measure progress
8 Establish and maintain a time-phased budget baseline at the control account level against which program performance can be measured Budget for far-term efforts may be held in higher level accounts until an appropriate time for allocation at the control account level Initial budgets established for performance measurement will be based on either internal management goals or the external customer negotiated target cost including estimates for authorized but undefinitized work On government contracts if an over target baseline is used for performance measurement reporting purposes prior notification must be provided to the customer
9 Establish budgets for authorized work with identification of significant cost elements (labor material etc) as needed for internal management and for control of subcontractors
10 To the extent it is practical to identify the authorized work in discrete work packages establish budgets or his work in terms of dollars hours or other measurable units Where the entire control account is not subdivided into work packages identify the far term effort
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
in larger planning packages for budget and scheduling purposes
11 Provide that the sum of all work package budgets plus planning package budgets within a control account equals the control account budget
12 Identify and control level of effort activity by time-phased budgets established for this purpose Only that effort which is unmeasurable or for which measurement is impractical may be classified as level of effort
13 Establish overhead budgets for each significant organizational component of the company for expenses which will become indirect costs Reflect in the program budgets at the appropriate level the amounts in overhead pools that are planned to be allocated to the program as indirect costs
14 Identify management reserves and undistributed budget 15 Provide that the program target cost goal is
reconciled with the sum of all internal program budgets and management reserves
Accounting Considerations
16 Record direct costs in a manner consistent with the budgets in a formal system controlled by the general books of account
17 When a work breakdown structure is used summarize direct costs from control accounts into the work breakdown structure without allocation of a single control account to two or more work breakdown structure elements
18 Summarize direct costs from the control accounts into the contractors organizational elements without allocation of a single control account to two or more organizational elements
19 Record all indirect costs which will be allocated to the contract
20 Identify unit costs equivalent units costs or lot costs when needed
21 For EVMS the material accounting system will provide for
a Accurate cost accumulation and assignment of costs to control accounts in a manner consistent with the budgets using recognized acceptable costing techniques
b Cost performance measurement at the point in time most suitable for the category of material involved but no earlier than the time of progress payments or actual receipt of material
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
c Full accountability of all material purchased for the program including the residual inventory
Analysis and Management Reports
22 At least on a monthly basis generate the following information at the control account and other levels as necessary for management control using actual cost data from or reconcilable with the accounting system
a Comparison of the amount of planned budget and the amount of budget earned for work accomplished This comparison provides the schedule variance
b Comparison of the amount of the budget earned the actual (applied where appropriate) direct costs for the same work This comparison provides the cost variance
23 Identify at least monthly the significant differences between both planned and actual schedule performance and planned and actual cost performance and provide the reasons for the variances in the detail needed by program management
24 Identify budgeted and applied (or actual) indirect costs at the level and frequency needed by management for effective control along with the reasons for any significant variances
25 Summarize the data elements and associated variances through the program organization andor work breakdown structure to support management needs and any customer reporting specified in the contract
26 Implement managerial actions taken as the result of earned value information
27 Develop revised estimates of cost at completion based on performance to date commitment values for material and estimates of future conditions Compare this information with the performance measurement baseline to identify variances at completion important to company management and any applicable customer reporting requirements including statements of funding requirements
Revisions and Data Maintenance
28 Incorporate authorized changes in a timely manner recording the effects of such changes in budgets and schedules In the directed effort prior to negotiation of a change base such revisions on the amount estimated and budgeted to the program organizations
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline
29 Reconcile current budgets to prior budgets in terms of changes to the authorized work and internal replanning in the detail needed by management for effective control
30 Control retroactive changes to records pertaining to work performed that would change previously reported amounts for actual costs earned value or budgets Adjustments should be made only for correction of errors routine accounting adjustments effects of customer or management directed changes or to improve the baseline integrity and accuracy of performance measurement data
31 Prevent revisions to the program budget except for authorized changes
32 Document changes to the performance measurement baseline