1. CFBC THERMAL PLANT, BHEL – NLC SITE Tasks: I. Responsible for checking signals between Control System (DCS) to Full condensing Steam Turbine (120MW X 2 ) Boiler, cooling Water and Steam Cycle (HP AND LP Bypass System),FD and PA fan ,ID FAN and Balance of Plant devices II. Responsible for testing the functionality and protections, as well as tuning and optimizing the Full condensing Steam Turbine (120MW X 2 ) Boiler, cooling Water and Steam Cycle (HP AND LP Bypass System),FD and PA fan ,ID FAN ,Coal Feeder and Balance of Plant devices a) Studying vendor supplied logic diagrams. b) Developing Logic using MAX Tool. c) Developing HMI Screens using MAX Editor . d) IO downloads for IO panels . e) Making report for IO downloads . f) Forcing IO’s and checking the status in screens. g) Preparing documentation for logics and screens developed h) Reading of Process and Instrumentation Diagram. i) Review of Commissioning sequence and plan, development of detailed commissioning procedures for leak test, steam turbine solo run, gas turbine solo run, DCS loop checking, DCS, ESD and PLC logic test, test forms and Ready for Start-up for systems. In collaboration with others departments and vendor’s representatives, where necessary, convert vendors procedures, check list and forms for commissioning accordingly to company commissioning plan, submission to management for approval, j) Organize and supervise client assigned teams, of 4-6 persons, for carry out of commissioning test such as DCS&ESD logic test, dryers k) Support vendor’s representative to carry of commissioning test and during start-up. l) Review, update and develop detailed start-up sequence, procedures and operating manuals m) Advising and support client operation team for preparation of unit for start-up, during start-up and normal operation. Suggest for best practice and where necessary on job training, - Preparation and update of commissioning progress reports, minutes of meetings.

Upload: pawan-deep

Post on 25-Jan-2017

21 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CFBC THERMAL PLANT

1. CFBC THERMAL PLANT, BHEL – NLC SITE

Tasks:I. Responsible for checking signals between Control System

(DCS) to Full condensing Steam Turbine (120MW X 2 ) Boiler, cooling Water and Steam Cycle (HP AND LP Bypass System),FD and PA fan ,ID FAN and Balance of Plant devices

II. Responsible for testing the functionality and protections, as well as tuning and optimizing the Full condensing Steam Turbine (120MW X 2 ) Boiler, cooling Water and Steam Cycle (HP AND LP Bypass System),FD and PA fan ,ID FAN ,Coal Feeder and Balance of Plant devices

a) Studying vendor supplied logic diagrams.b) Developing Logic using MAX Tool. c) Developing HMI Screens using MAX Editor .d) IO downloads for IO panels .e) Making report for IO downloads .f) Forcing IO’s and checking the status in screens.g) Preparing documentation for logics and screens developedh) Reading of Process and Instrumentation Diagram.i) Review of Commissioning sequence and plan, development

of detailed commissioning procedures for leak test, steam turbine solo run, gas turbine solo run, DCS loop checking, DCS, ESD and PLC logic test, test forms and Ready for Start-up for systems. In collaboration with others departments and vendor’s representatives, where necessary, convert vendors procedures, check list and forms for commissioning accordingly to company commissioning plan, submission to management for approval,

j) Organize and supervise client assigned teams, of 4-6 persons, for carry out of commissioning test such as DCS&ESD logic test, dryers

k) Support vendor’s representative to carry of commissioning test and during start-up.

l) Review, update and develop detailed start-up sequence, procedures and operating manuals

m) Advising and support client operation team for preparation of unit for start-up, during start-up and normal operation. Suggest for best practice and where necessary on job training,- Preparation and update of commissioning progress reports, minutes of meetings.