Central States Water Environmen t Associatio n 2009 Collection s Seminar June 11, 2009 Central States Water Environment Association Collection System Seminar

Upload: ilori

Post on 03-Feb-2016

38 views

Category:

Documents


0 download

DESCRIPTION

Central States Water Environment Association Collection System Seminar. Mark Bushnell P.E. Trotter and Associates Inc. Village of Port Barrington Low Pressure Sanitary Sewer System Phase I. Collection System Seminar. Low Pressure Sanitary Sewer System - Phase I Project Location - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Central States Water Environment Association

Collection System Seminar

Central States Water Environment Association

Collection System Seminar

Page 2: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Mark Bushnell P.E.Trotter and Associates Inc.

Village of Port Barrington Low Pressure Sanitary Sewer System

Phase I

Mark Bushnell P.E.Trotter and Associates Inc.

Village of Port Barrington Low Pressure Sanitary Sewer System

Phase I

Page 3: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Low Pressure Sanitary Sewer System - Phase I

Project Location Village Port Barrington

West-Il 59 South-ll 176 Adjacent to Fox River Within NMWRD FPA

Collection System SeminarCollection System Seminar

Page 4: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Team Village of Port Barrington

Village Engineer – Smith Engineering Consultants Inc. Village Attorney – Diamond and LeSueur Financial Consultant – Public Finance Resource Ltd

Contractor- Joel Kennedy Construction

Northern Moraine Wastewater Reclamation District District Engineer – Trotter and Associates Inc.

Page 5: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Goals Provide Reliable Sanitary Sewer Service to 117 Homes Abandon Failing Septic Systems Eliminate Septic Fields within Floodplain Increase Water Quality of Fox River

Project Scope Installation of Low Pressure Sanitary Sewer System Public Infrastructure

Forcemain and Grinder Pumps Serving all Existing Homes Connection into Existing NMWRD Gravity System

Private Improvements Sanitary Sewer Service Lateral Plumbing and Electrical

Page 6: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Infrastructure Owned by Village Maintained by NMWRD Grinder Pumps / Forcemain Air Release / Isolation Valves

Page 7: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Funding - Infrastructure Federal STAG Grant (U.S. Rep. Don Manzullo) - $ 482,100 Mc Henry County Community Block Grant - $ 61,101 IEPA Low Interest Loan (SSA) - $ 910,133 Village of Port Barrington- $ 209,299

Total Project Cost - $ 1,662,633

Page 8: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Funding – IEPA Loan / Special Service Area SSA approved by residents Each resident served pays an annual assessment Repays the IEPA Low Interest Loan This is assessment is added to the tax bill Annual repayment of less than $500 per resident

Project Funding – Grants Funded almost one-third of the project Required to make the project fiscally feasible

Page 9: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Construction – Infrastructure Completed During 2006- 07 Designed by SEC Group Inc. Completed by Joel Kennedy Construction

All Items lie within limited Right of Way or Easements Minimize Disturbance by

Directional Drilling of HDPE Main

Page 10: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Testing - Infrastructure Pressure Testing of Forcemain Flow Meter Testing Vacuum Testing of Manholes Manufacturer Test of Grinder Pumps

Upon successful testing residents were permitted to connect to the Low Pressure Sanitary Sewer System. The District required

residents to connected within one year.

Page 11: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Village Ownership Forcemain Air Release/ Manholes Grinder Pumps

Resident Ownership Service Lateral Control Panel Electrical Service Floodplain Vents

Page 12: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Procedure for Connection Coordination of Village of Port Barrington and NMWRD to streamline the

connection process Workshops Mailings and Notifications Open Houses

Private Improvements were funded by individual residents Residents hired their own contractors

Phases of Connection Interior Plumbing Sanitary Sewer Service Extension / Electrical Improvements Septic Abandonment

Page 13: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Procedure for Connection

Step 1 - Interior Plumbing Plumbing Inspection by Village Removal of Illicit Discharges Ensure that all drains are connected Check for Connections that my Surcharge Grinder Pump Possible Rerouting of Interior Plumbing

Page 14: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Procedure for Connection- Continued

Step 2A - Connection to Grinder Pump- NMWRD Paperwork and Forms Standard for any Sanitary Sewer Connection Certificate of Insurance and Permit Bond from Contractor Payment of Connection Fee to Sanitary District NMWRD provides Control Panel to Resident

Prevents Homeowners from running pumps or connecting prior to payment

Schedule an Inspection of Sewer Service

Page 15: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Procedure for Connection- Continued

Step 2B- Installation of Electrical Panel / Sanitary Service Electrical Panel Installed on Home Visible from Pump

Page 16: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Procedure for Connection- Continued

Step 2B- Installation of Service Lateral and Electrical Sanitary Lateral

Schedule 40 PVC Inspected by NMWRD

Page 17: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Low Pressure Sanitary Sewer System - Phase I

Procedure for Connection- Continued

Step 2B- Inspection of Grinder Pump Lid Lids must remain exposed Floodplain Lids properly vented

Transfer of Service Step 3-Abandonment of Septic System

Collection System SeminarCollection System Seminar

Page 18: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Procedure for Connection

Finished Product

Page 19: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Connection Issues Issue -Outstanding Connections

117 Total - Few have yet to connect Foreclosures and Fire

Results Grinder Pump equipment remaining idle Warranty expiring prior to use NMWRD- Loss of revenue

Page 20: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Connection Issues Resolution – Timely Connections

Public Notification Payment Plans Frozen Connection Fees Ultimately District reserves the right for legal proceedings

Resolution – Idle Equipment Extended warranties are offered

Page 21: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Connection Issues Resident Concern – Service Interruptions

Power Outages Equipment Malfunction

Resolution Residents are on Wells IEPA requires - 150 Gallon Storage NMWRD provides Emergency Response

Spare Pump Cores are kept at NMWRD Core can be replaced w/in hours

Page 22: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Connection Issues District Concern – Landscaping

Non- Floodplain Lids must be kept dry NMWRD must have access for maintenance

Resolution Coordination with Resident

Page 23: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Project Accomplishments Provided Sanitary Sewer Service to 117 Homes Abandon Failing Septic Systems Removed Septic Systems from Floodplain Enhanced Water Quality within Fox River Completed with Minimal Disruption to Sewer Service

Page 24: Central States  Water Environment Association Collection System Seminar

Central States Water

Environment Association

2009 Collections

Seminar

June 11, 2009

Collection System SeminarCollection System SeminarLow Pressure Sanitary Sewer System - Phase I

Next Steps by Village and NWMRD Implementation of Phase II

Provide Service ninety-three additional residential homes Construction scheduled for Fall of 2009 Funded through IEPA Loan and Stimulus Program

NMWRD working with other areas within their FPA to inform residents about Low Pressure Sanitary Sewer Systems

Questions?