Central Power Research Institute Electrical Maintenance Division
Monthly Progress Report for the month of May 2013
Friday, 31 May 2013 6:47:39 PM
Sl.No. Particulars Work progress Pending works
1. CCAR – Electrical works
Electrical wall conduit pipe groove cutting and metal box fixing is completed in double bed rooms and in Suit rooms.
Major electrical works are pending in double bed rooms and suit rooms due to delay of civil works.
2. LED test facility – Electrical works
Electrical works are completed, and Light fixing is in progress.
Page 2 of 5
3. GH 1 & 2 – Electrical works
GH – 1 and GH – 2 Electrical works are pending due to delay of civil works.
4. SC Lab – Electrical works
Compact substation (CSS) erection and test charging works are completed
Workshop building is not yet ready to carry out any electrical works.
5. LCM Project – Electrical
Electrical works are in progress
Major Electrical works are pending due to delay of Civil works
Page 3 of 5
6.
PQ Lab Project
Internal Electrification works
Electrical works are pending in Control room, Laboratory building, Snake coil room No.1 and No.2 due to delay of civil works.
External Electrification works
Transformer and VCB Erection works are completed including earthing work.
7.
LCM Lab Grounding system - Part – A
Part – A 95% grounding systems works are completed Part – B grounding systems works are completed Grounding Systems works are completed Part – C & Part – D
Concreting works are pending.
LCM Lab Grounding system - Part – B
PQ Lab Grounding system – Part – C
PQ Lab Grounding system – Part - D
Page 4 of 5
8. EMI/EMC – Internal and External Electrical works
Work orders are not yet issued due to non-availability of funds for Execution of Internal and External electrical works.
9. Erection of New Lift at LCM project building
Lift Machine room civil works are yet to be completed
10. Other works
i. Timely all Electrical, Telephone complaints are attended, and assistance provided for arranging PA systems for meetings, seminars and conferences, etc.
ii. 33 kV SS maintenance works and earth pit maintenance works are carried out.
Page 5 of 5
iii. Pre commissioning Test charges has been conducted for SC Lab and PQ Lab projects
iv. BESCOM CT and PT works are in progress at 220 kV Substation
v. Earth resistence checked for ID Laboratoroy
Engineering Officer Gr. IV
Officer In-charge, EMD JD, P & C Division