Page 1 of 5 Central Power Research Institute Electrical Maintenance Division Monthly Progress Report for the month of May 2013 Friday, 31 May 2013 6:47:39 PM Sl.No. Particulars Work progress Pending works 1. CCAR – Electrical works Electrical wall conduit pipe groove cutting and metal box fixing is completed in double bed rooms and in Suit rooms. Major electrical works are pending in double bed rooms and suit rooms due to delay of civil works. 2. LED test facility – Electrical works Electrical works are completed, and Light fixing is in progress.

Upload: habao

Post on 14-Mar-2018

214 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Central Power Research Institute Electrical … 1 of 5 Central Power Research Institute Electrical Maintenance Division Monthly Progress Report for the month of May 2013 Friday, 31

Page 1 of 5

Central Power Research Institute Electrical Maintenance Division

Monthly Progress Report for the month of May 2013

Friday, 31 May 2013 6:47:39 PM

Sl.No. Particulars Work progress Pending works

1. CCAR – Electrical works

Electrical wall conduit pipe groove cutting and metal box fixing is completed in double bed rooms and in Suit rooms.

Major electrical works are pending in double bed rooms and suit rooms due to delay of civil works.

2. LED test facility – Electrical works

Electrical works are completed, and Light fixing is in progress.

Page 2: Central Power Research Institute Electrical … 1 of 5 Central Power Research Institute Electrical Maintenance Division Monthly Progress Report for the month of May 2013 Friday, 31

Page 2 of 5

3. GH 1 & 2 – Electrical works

GH – 1 and GH – 2 Electrical works are pending due to delay of civil works.

4. SC Lab – Electrical works

Compact substation (CSS) erection and test charging works are completed

Workshop building is not yet ready to carry out any electrical works.

5. LCM Project – Electrical

Electrical works are in progress

Major Electrical works are pending due to delay of Civil works

Page 3: Central Power Research Institute Electrical … 1 of 5 Central Power Research Institute Electrical Maintenance Division Monthly Progress Report for the month of May 2013 Friday, 31

Page 3 of 5

6.

PQ Lab Project

Internal Electrification works

Electrical works are pending in Control room, Laboratory building, Snake coil room No.1 and No.2 due to delay of civil works.

External Electrification works

Transformer and VCB Erection works are completed including earthing work.

7.

LCM Lab Grounding system - Part – A

Part – A 95% grounding systems works are completed Part – B grounding systems works are completed Grounding Systems works are completed Part – C & Part – D

Concreting works are pending.

LCM Lab Grounding system - Part – B

PQ Lab Grounding system – Part – C

PQ Lab Grounding system – Part - D

Page 4: Central Power Research Institute Electrical … 1 of 5 Central Power Research Institute Electrical Maintenance Division Monthly Progress Report for the month of May 2013 Friday, 31

Page 4 of 5

8. EMI/EMC – Internal and External Electrical works

Work orders are not yet issued due to non-availability of funds for Execution of Internal and External electrical works.

9. Erection of New Lift at LCM project building

Lift Machine room civil works are yet to be completed

10. Other works

i. Timely all Electrical, Telephone complaints are attended, and assistance provided for arranging PA systems for meetings, seminars and conferences, etc.

ii. 33 kV SS maintenance works and earth pit maintenance works are carried out.

Page 5: Central Power Research Institute Electrical … 1 of 5 Central Power Research Institute Electrical Maintenance Division Monthly Progress Report for the month of May 2013 Friday, 31

Page 5 of 5

iii. Pre commissioning Test charges has been conducted for SC Lab and PQ Lab projects

iv. BESCOM CT and PT works are in progress at 220 kV Substation

v. Earth resistence checked for ID Laboratoroy

Engineering Officer Gr. IV